Method Statement For Repairing of Existing Sewerage Network
Method Statement For Repairing of Existing Sewerage Network
00005
Al MERIEF
DEVELOPMENT ROADS Rev :01
REHABILITATION WORKS
Date: 11-Jul-2023
2nd Submission
11-Jul-2023 – Issued for
Approval
1st Submission
30-May-2023 – Issued for
Approval
AMENDMENT RECORD
CONTENTS
1.0 SCOPE
2.0 REFERENCE
3.0 DEFINITIONS
4.0 RESOURCES
6.0 METHODOLOGY
7.0 ATTACHMENTS
7.2 I.TP
1.0 SCOPE
2.0 REFERENCE
ADNOC Specification
ADM Specification Chapter 2- Earth work
ADSSC Standard specification
Approved Project Quality Plan
As built Drawings
3.0 DEFINITIONS
RA Risk Assessments
4.0 RESOURCES
Hand Shovels
Safety Cone
Warning Tape
Asphalt Cutter
Excavator
Plate Compactor
Hand Roller
Foreman
Ganger
Skilled Laborers
A regular inspection carried out daily by our Safety advisor to the site.
All the safety measure should be taken during the work following the
HSE plan, Method Statement & Risk assessment.
Ensure all workers aware of the hazards/ Risks associated with the
Task.
Set out the location for the repairing of sewerage line as per
Construction Drawing.
Existing geo textile, aggregate and pipe to be exposed for the repairing
work.
If the depth is more than 1.2m multi step excavation shall be carried
out depending on the depth of utilities / Shoring to the provided as per
site condition
After locating all the existing services, the excavation to be carried out
the required level for the repairing work.
7.0 ATTACHMENTS