PROJECT-W

WEEKLY HSE REPORT


Prepared by: Abhinav.D.J

Date: 01/04/2023
AGENDA

HS&E STATISTICS
INCIDENT SUMMARY
KEY ISSUES
PROJECT RELATED UPDATES
WELFARE FACILITY
HSE BEST PRACTISE
ENVIRONMENTAL BEST PRACTISE
HSE MILESTONES & ACHIEVEMENTS
1 Week Look Ahead

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
HS&E Statistics
SL.NO FIGURES WEEK PROJECT TO DATE (PTD) YEAR TO DATE (YTD)

1. TOTAL MANPOWER 1375 8523 8523

2. TOTAL MAN-HOUR 13750 85230 85230

3. SAFE MAN-HOURS WORKED WITHOUT LTI 13750 85230 85230

4. NO. OF NEAR MISS REPORTED 2 17 17

5. NO. OF INCIDENT/ACCIDENT 0 1 1

6. TOTAL NO. OF LOST TIME INJURY (LTI) REPORTED 0 0 0

7. NO. OF SAFETY TRAINING CONDUCTED 0 6 6

8. NO. OF SAFETY OBSERVATION REPORTED 6 46 46

9. NO OF HSE INSPECTION CONDUCTED 2 13 13

10. NO. OF SAFETY MEETING’S CONDUCTED 1 11 11

11. NO. OF EMERGENCY DRILL 0 1 1

12. NO. OF MANAGEMENT WALKTHROUGH 1 13 13

13. NO. OF SAFETY AUDIT 0 1 1


PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HS&E Statistics
SL.NO FIGURES WEEK PROJECT TO DATE (PTD) YEAR TO DATE (YTD)

14. NO. OF WEEKLY TOOLBOX SESSION 2 11 11

15. NO. OF ENVIRONMENTAL INCIDENT/ACCIDENT 0 0 0

16. NO. OF ENVIRONMENTAL INSPECTION 0 4 4

17. NO. OF ENVIRONMENTAL OBSERVATION 0 2 2

Lagging Indicators
1.2

0.8

0.6

0.4

0.2

0
15-Feb

LTI Motor Vehicle Incident LTI Motor Vehicle Incident


Property Damage Fire Property Damage Fire
Total Recordable Incident Rate Total Recordable Incident Rate

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
KEY ISSUES

SN CONTRACTOR KEY ISSUES ACTION TAKEN

• Interference from Local residence & over speeding, camels wanderings


on workplace/project area.
1 RPCO • Mosque to be provided at offices area.
In Progress of rectification

2 BENAN • Internet not established


• Medical items as per checklist is missing (Need to be provided)
In Progress of rectification

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
INCIDENT SUMMARY

PACKAGE CONTRACTOR INCIDENT INCIDENT BRIEF DECRIPTION ROOT CAUSE ACTION STATUS
CLASSIFICATION DATE

A RPCO Property damage 15-02-23 Electric pole hit by unknown vehicle Poor Illumination
at incident
Hard
barriers
Close

location/ Lack of installed


protection barriers Assigned
security
guard/
flagman
at
entrance

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS

RPCO completed below task:


1. • Fence-2: (7+250 to 6+750) Installing Mesh. PHOTO
• Fence-2: (4+100 to 4+400) Installing Barbed Wires.
• R1: (0+000 to 1+400) lowering access for 4x4 vehicles to reach St 1+400.
• Station (2+000 to 3+000) spreading, grading, levelling and compacting 2nd
layer of Subgrade Material.
• Station (11+200 to 11+300) spreading, grading, levelling and compacting 1st
BACKFILL 30CM layer of Subgrade Material.
• Station (11+300 to 11+800) spreading, grading, levelling and compacting 1st
BACKFILL 30CM layer of Subgrade Material (READY FOR FDT).
• Station (11+800 to 12+000) spreading, grading, levelling and compacting
3rd BACKFILL 30CM layer of Subgrade Material.
• Station (15+500 to 15+750) spreading, grading, levelling and compacting 1st
BACKFILL 30CM layer of Subgrade Material.
• Importing Subgrade Material to Site using 12 Dump Trucks: (qty = 31 trips =
744 CUM).
• R2: (0+800 to 1+200) Excavation and lowering access.
• R2: (0+125 to 0+250) spreading, grading, levelling and compacting 2nd
BACKFILL 30CM layer
• R2: (0+450 to 0+550) spreading, grading, levelling and compacting 2nd
BACKFILL 30CM layer.
• 7 days concrete cylinder testing for Fence 1A at Sta.4+320 to 4+395 & Sta.
5+165 to 5+875

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS
BENAN completed below task:
• Continue drilling in BH M 104 at monolith (total depth 52) from 19.5 m to
28 m
2. • Remove the Stuck in BH M 121 at monolith (total depth 31) at depth
25.0 m and the rig was Stuck ( total water loss due to the fracture)
• Continue drilling in BH M111 at monolith (total depth 27.0 M) from 12.m
to 17 m BH M 118 at monolith (total depth 28) stuck at 25m.
• Continue drilling on Wadi secondary route O- BH-1 from 20.0 to 27.0 m
Lifting 12 water tanks

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
WELFARE FACILITY
CONTRACTOR TOTAL EMPLOYEE’S HSE TOILET RESTING SHELTER PRAYER AREA
NAME AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED

RPCO 164 3/4 6/8 6/8 1/3


BENAN 39 2/3 8/3 0/3 2/2

• RPCO – To provide prayer Rooms & Toilets at Wadi area


• BENAN – Need to work on provision of Welfare facility & Waste Skips due to multiple location of work at Plateau , Wadi & Fence 2 area.

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE

PHOTO PHOTO

RPCO - Segregated vehicle movement area, workplace and pedestrian way by RPCO – Assigned flagman at all working point for equipment’s and intersection
points
erecting soft barricades at both sides of service road from 00 to END

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
ENVIRONMENTAL BEST PRACTISE

ENVIRONMENTAL BEST PRACTISE ENVIRONMENTAL BEST PRACTISE

PHOTO PHOTO

RPCO – Transfer of General waste to main skip bin on daily basis and RPCO – Spray water at access road for dust Control on daily basis
bulk skip bin removed as per requirement by local contractor.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 26th to Apr 1st, 2023
PROJECT MILESTONES/ACHIEVEMENTS

SN DESCRIPTION

RPCO –
Up to
• R2: Up to Station 1+200 26% Excavation done.
• R3 15+200 top of embankment backfill 30CM 1st layer of Subgrade
1. Material done.
• Fence 2 All pots concreted.
• Fence-1A: Up to station 2+000 and from 4+000 to 7+500 Posts Installed.

BENAN –
• Continue drilling in BH M 104 at monolith (total depth 52) from 19.5 m to 28 m
• Continue drilling in BH M111 at monolith (total depth 27.0 M) from 12.m to 17 m
2.
BH M 118 at monolith (total depth 28) stuck at 25m.
• Continue drilling on Wadi secondary route O- BH-1 from 20.0 to 27.0 m Lifting
12 water tanks

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
ONE WEEKS LOOK AHEAD

CONTRACTOR NAME ONE WEEKS LOOK AHEAD


RPCO • R2 – 30% Excavation and Starting the delivery of back fill material.
• R3- Shall be 30% of back fill up to Station 16+000.
• R3- From station 11+000 to 12+000 back fill shall be done.
• Fence 2- Chain link 50% shall be complete.

BENAN • Finish the first 10 BH at Monolith


• Start the benchmarks
• Continue drilling on secondary wadi route
• submit the preliminary geological survey

HSE Data - From March 26th to Apr 1st, 2023


PROJECT-W ADVANCE WORK PACKAGE-A
END OF REPORT