Weekly Project-W HSE Report RPCO 26th Mar To 1st Apr
Weekly Project-W HSE Report RPCO 26th Mar To 1st Apr
Weekly Project-W HSE Report RPCO 26th Mar To 1st Apr
Date: 01/04/2023
AGENDA
HS&E STATISTICS
INCIDENT SUMMARY
KEY ISSUES
PROJECT RELATED UPDATES
WELFARE FACILITY
HSE BEST PRACTISE
ENVIRONMENTAL BEST PRACTISE
HSE MILESTONES & ACHIEVEMENTS
1 Week Look Ahead
5. NO. OF INCIDENT/ACCIDENT 0 1 1
Lagging Indicators
1.2
0.8
0.6
0.4
0.2
0
15-Feb
PACKAGE CONTRACTOR INCIDENT INCIDENT BRIEF DECRIPTION ROOT CAUSE ACTION STATUS
CLASSIFICATION DATE
A RPCO Property damage 15-02-23 Electric pole hit by unknown vehicle Poor Illumination
at incident
Hard
barriers
Close
PHOTO PHOTO
RPCO - Segregated vehicle movement area, workplace and pedestrian way by RPCO – Assigned flagman at all working point for equipment’s and intersection
points
erecting soft barricades at both sides of service road from 00 to END
PHOTO PHOTO
RPCO – Transfer of General waste to main skip bin on daily basis and RPCO – Spray water at access road for dust Control on daily basis
bulk skip bin removed as per requirement by local contractor.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 26th to Apr 1st, 2023
PROJECT MILESTONES/ACHIEVEMENTS
SN DESCRIPTION
RPCO –
Up to
• R2: Up to Station 1+200 26% Excavation done.
• R3 15+200 top of embankment backfill 30CM 1st layer of Subgrade
1. Material done.
• Fence 2 All pots concreted.
• Fence-1A: Up to station 2+000 and from 4+000 to 7+500 Posts Installed.
BENAN –
• Continue drilling in BH M 104 at monolith (total depth 52) from 19.5 m to 28 m
• Continue drilling in BH M111 at monolith (total depth 27.0 M) from 12.m to 17 m
2.
BH M 118 at monolith (total depth 28) stuck at 25m.
• Continue drilling on Wadi secondary route O- BH-1 from 20.0 to 27.0 m Lifting
12 water tanks