Assignment 5 - CH 15 - OM12E
Assignment 5 - CH 15 - OM12E
9) Forward scheduling:
A) begins with a delivery date, then offsets each operation one at a time, in
reverse order.
B) has the same meaning as "finite loading."
C) is often used in service environments such as catering a banquet or
scheduling surgery.
D) starts the schedule as soon as the job requirements are known.
E) produces a schedule only if it meets the due date.
12) A work center had actual input of 280 hours and actual output of 270
hours. What is the change in backlog?
2
Copyright © 2022 Pearson Education, Inc.
A) 10
B) -10
C) 0
D) 1.037
E) Unable to determine with the given information
13) A work center had planned outputs of 10, 15, 13, and 20 hours with
actual outputs of 12, 14, 13, and 18 hours. What is the cumulative
deviation in output?
A) 0
B) 1
C) -1
D) 58
E) Unable to determine with the given information
17) There are two jobs to be assigned to two workers. The profit for
worker A on job 1 is $5 and on job 2 is $8. The profit for worker B on job 1
is $10 and on job 2 is $12. How should the work be divided using the
assignment method?
A) worker A assigned to job 1 and worker B assigned to job 2
B) worker A assigned to job 2 and worker B assigned to job 1
C) worker A gets both jobs 1 and 2
3
Copyright © 2022 Pearson Education, Inc.
D) worker B gets both jobs 1 and 2
E) unable to determine
23) Three jobs are to be assigned to three machines. Cost for each job-
machine combination appears in the table below. Perform the first two
steps of the assignment method (subtract the smallest number in each
row and subtract the smallest number in each column; then cover with
straight lines). At this point in the problem-solving process:
4
Copyright © 2022 Pearson Education, Inc.
Machine Machine Machine
A B C
Job 1 11 14 6
Job 2 8 10 11
Job 3 9 12 7
24) The jobs listed below need to be completed. Assume that it is now day
140. If the jobs are sequenced according to the longest processing time
rule, what is the lateness of job A?
A) 0.0 days
B) 24.0 days
C) 7.4 days
D) 9.0 days
E) 11.6 days
25) The jobs listed below need to be completed. Assume that it is now day
140. If the jobs are sequenced according to the shortest processing time
rule, what is the average completion time?
A) 47.6 days
B) 60.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days
5
Copyright © 2022 Pearson Education, Inc.
26) EDD stands for what?
A) earliest due date
B) earliest design date
C) earliest detrimental date
D) earliest decision date
E) economic date determination
27) Using LPT priority would result in what sequence for Jobs A, B, C, and
D if their process times are 4, 6, 5, and 2 respectively?
A) ABCD
B) DCBA
C) DACB
D) DABC
E) BCAD
28) Orders are processed in the sequence in which they arrive if (the)
________ rule sequences the jobs.
A) earliest due date
B) slack time remaining
C) first come, first served
D) critical ratio
E) Johnson's
29) Which of the following dispatching rules ordinarily gives the best
results when the criterion is quickest time for completion of the full
sequence of jobs?
A) shortest processing time (SPT)
B) critical ratio (CR)
C) first in, first out (FIFO)
D) first come, first served (FCFS)
E) longest processing time (LPT)
30) Five jobs are waiting to be processed. Their processing times and due
dates are given below. Using the shortest processing time dispatching
rule, in which order should the jobs be processed?
A) A, B, C, D, E
B) C, E, A, D, B
C) B, D, A, E, C
6
Copyright © 2022 Pearson Education, Inc.
D) D, A, E, B, C
E) C, E, A, B, D
32) Five jobs are waiting to be processed. Their processing times and due
dates are given below. Using the earliest due date dispatching rule, in
which order should the jobs be processed?
7
Copyright © 2022 Pearson Education, Inc.
Processing Job due
Job Time (days) date (days)
A 4 7
B 2 4
C 8 11
D 3 5
E 5 8
A) C, E, A, D, B
B) A, B, C, D, E
C) B, D, A, E, C
D) C, B, A, E, D
E) B, D, A, C, E
34) Which of the following dispatching rules tends to minimize job flow
time?
A) FCFS: first come, first served
B) SPT: shortest processing time
C) EDD: earliest due date
D) LPT: longest processing time
E) FCLS: first come, last served
36) Eight jobs have been sequenced at a single work center. Total
processing time for the eight jobs is 34 hours, and total flow time for the
sequence is 85 hours. For this schedule, utilization is ________ and the
average number of jobs in the system is ________.
8
Copyright © 2022 Pearson Education, Inc.
A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized
37) Five welding jobs are waiting to be processed. Their processing times
and due dates are given below. Using the critical ratio dispatching rule, in
which order should the jobs be processed? All dates are specified as days
from today.
A) B, D, A, E, C
B) C, D, A, B, E
C) C, E, A, D, B
D) E, B, A, D, C
E) B, D, A, C, E
38) Which critical ratio value implies that a job is already late?
A) more than 100
B) 1
C) less than 1
D) 10
E) 3.4
39) What is the priority rule that sequences jobs using the smallest ratio
of due date from today to processing time?
A) critical ratio
B) earliest due date
C) first come, first served
D) longest processing time
E) shortest processing time
9
Copyright © 2022 Pearson Education, Inc.
41) What does the use of the shortest processing time sequencing rule
generally produce?
A) maximum average lateness
B) maximum utilization
C) maximum effectiveness
D) minimum average flow time
E) B and D
42) When a set of jobs must pass through two workstations whose
sequence is fixed, ________ is the sequencing rule most commonly applied.
A) critical ratio
B) earliest due date
C) first come, first served
D) slack time remaining
E) Johnson's rule
43) Five jobs are waiting for processing through two work centers. Their
processing time (in minutes) at each work center is contained in the table
below. Each job requires work center Alpha before work center Beta.
According to Johnson's rule, which job should be scheduled first in the
sequence?
A) R
B) S
C) T
D) U
E) V
44) Five jobs are waiting for processing through two work centers. Their
processing time (in minutes) at each work center is contained in the table
below. Each job requires work center Sigma before work center Delta.
According to Johnson's rule, what sequence of jobs will minimize the
completion time for all jobs?
10
Copyright © 2022 Pearson Education, Inc.
A) R-S-T-U-V
B) S-V-T-R-U
C) S-U-T-V-R
D) V-R-U-S-T
E) R-V-T-S-U
46) Five jobs are waiting for processing through two work centers. Their
processing time (in minutes) at each work center is contained in the table
below. Each job requires work center Alpha before work center Beta.
According to Johnson's rule, what is the optimum sequence of jobs and
the minimum time for completion of all jobs?
A) V-T-S-U-R; 225
B) U-R-T-S-V; 175
C) R-S-T-U-V; 240
D) U-S-V-T-R; 200
E) R-U-T-S-V; 175
11
Copyright © 2022 Pearson Education, Inc.
A) forward scheduling.
B) backward scheduling.
C) infinite scheduling.
D) finite capacity scheduling.
E) progressive scheduling.
50) Which of the following is NOT one of the risk mitigation tactics for the
supply chain risk category of suppliers failing to deliver?
A) use multiple suppliers
B) effective contracts with penalties
C) subcontractors on retainer
D) require overnight delivery
E) pre-planning
12
Copyright © 2022 Pearson Education, Inc.