Reply To The Plaint (Civil Court Time Extension)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

BEFORE THE COURT OF CIVIL JUDGE PESHAWAR.

M/S TECHNICON ENGINEERS & EPC CONTRACTOR GROUP


and others Applicants
V/S

The Provincial Government of Khyber Pakhtunkhwa


and others. Respondents

WRITTEN REPLY ON BEHALF


OF RESPONDENTS

RESPECTED SHEWETH.

Preliminary Objection.

1. That the Petitioners has got no cause of action to file the present suit against the

respondents.

2. That the Petitioners has not served the Notice to the Government U/S 80 C.P.C,

which is mandatory.

3. That this Court has got no jurisdiction to entertain this suit.

4. That the suit of the Petitioners is baseless frivolous and based on malafide

intention.

5. That the suit of the Petitioners is bed for misjoinder and non-joinder of the

necessary parties.

6. That the Petitioners may be stopped to file the present suit.

7. That the Petitioners wants to put pressure on the defendant.

8. That the Petitioners has not come to the court with clean hands.
1|Page
9. That material facts have been concealed by the Petitioners.

10. That the suit of the Petitioners is time barred.

11. That the Petitioners failed to fulfill the terms and conditions mentioned in the

contract agreement as per contract agreement as he had never given intent for

arbitration to the Engineer, hence, not liable for filing the present suit against the

respondents.

APPLICATION UNDER SECTION 28 OF THE ARBITRATION ACT 1940 FOR

ENLARGMENT OF TIME FOR MAKING THE AWARD

1 That the Para No. (1) is subject to proof.

2.1 That the Para No. (2.1) is subject to proof.

2.2 That the Para No. (2.1) is subject to proof.

2.3 That the Para No. (2.3) is correct.

2.4 That the Para No. (2.4) is incorrect and denied.

During Arbitration Proceedings dated 15-03-2021, (Order No.2) the

claims were not ready and proceedings postponed to 05/04/2021. No

proceeding could take place until 13/10/2021.

The learned Arbitrator submitted the Claims of the Claimant (1-5

Volumes) to respondent No.1 (Secretary to Government of Khyber

Pakhtunkhwa Irrigation Department) vide his letter No 815/MLA/481

dated 07-10-2021 (Copy Annexed as I). The same was forwarded to

Respondent No 2&3 vide letter No. SO/(Lit)/Irr:/3-11/2021 dated 14-10-

2021 (Copy Annexed as II) meaning that the claims of the Claimant were
2|Page
provided to the respondents after lapse of 08 Months from the date of

appointment of the learned Arbitrator. Therefore the stance that

respondents submitted replies to the claims after 12 months is not based

on facts.

2.5 That the Para No (2.5) is subject to proof. Furthermore the detail reflected

herein is quit silent about the letter No.815/MLA/481 dated 7-10-2021,

which determine the exact date of submission to respondent No.1

contrary to a general statement reflected against the order No.3, Para

No.4. (Copy annexed as III).

2.6 That the Para No (2.6) is incorrect and denied. As elaborated in 2.4

above, the claimant submitted his claim after lapse of 08 Months since

commencement of proceedings by the Arbitrator. It is pertinent to mention

that the claimant was not urged/stressed by the Arbitrator for early

submission of his claim.

2.7 That the Para No. (2.7) is subject to proof/irrelevant.

2.8 That the Para No. (2.8) is subject to proof/irrelevant.

2.9 That the Para No. (2.8) is correct.

2.10 That the Para No. (2.10) is subject to proof.

2.11 That the Para No. (2.11) is subject to proof.

2.12 That the Para No. (2.12) is subject to proof.

2.13 That the Para No. (2.13) is correct.

3|Page
2.14 That the Para No. (2.14) is subject to proof. The Arbitration Proceeding

was to be concluded within the allocated time period of 04 Months (From

22-02-2023 to 22-06-2023). However, the same could not be finalized

even up till 15-09-2023. (The last date of Proceeding)

2.15 That the Para No. (2.15) is correct as the Applicant/Arbitrator has

become functus officio and proceedings in the matter were void ab initio,

without jurisdiction and barred by Law.

2.16 That the Para No.(2.16) need clarification. The Arbitration could not be

completed within the stipulated time due to conduct of claimant and

Arbitrator.

2.17 That the Para No. (2.17) is correct.

2.18 That the Para No. (2.18) is correct.

2.19 That the Para No. (2.19) is correct.

2.20 That the Para No. (2.20) is correct.

2.21 That the Para No. (2.21) is correct. However, since the conduct of

Arbitrator/Applicant render him biased, hence not liable for further

extension. Furthermore the Arbitrator does not have any experience of

Irrigation/Hydraulic works and would not be able for making fair award.

2.22 That the submission under Para No. (2.22) may not be accepted on

grounds as per Para 2.21 above.

4
4|Page
PRAYER

In light of above it is respectfully prayed that the instant application may

kindly be dismissed and ……..

From Respondents (1 to 3)

THROUGH.

Jehanzeb Khan Muhammadzai


Advocate Supreme Court.

Affidavit

Verified that the Contents of written reply /


statement are correct to the best knowledge /
record and nothing has been concealed to this
Honorable Court.

5|Page

You might also like