User Manual - PM Process For Doffer
User Manual - PM Process For Doffer
User Manual - PM Process For Doffer
USER MANUAL
PLANT MAINTENANCE PROCESS-FLOW
The document acknowledges that the testing has been completed ”Sign Off on behalf of “Shree Durga Syntex Private
Limited”.
1
Project – PM Implementation
Key Activities performed for testing (Insert the test scenario list)
Task T-CODE
Create IP11
Display IP13
• Choose New entries
• You reach the detail screen for maintenance strategies.
• Enter the necessary data.
2
Project – PM Implementation
1.2. Call up the entry screen for maintenance packages in the overview tree by clicking twice on Packages
1.2.1.Choose New entries.
1.2.2.The system makes the fields ready for input.
1.2.3.Enter the necessary data.
1.2.4.Save the maintenance strategy.
3
Project – PM Implementation
2.2. To create General Maintenance task list – IA05, enter no data and click on Continue. You can enter an existing
group number and click Continue.
4
Project – PM Implementation
2.3. Once you click continue, you have to enter the header data in the task list.
2.4. Select operation tab and fill operation details and assign.
5
Project – PM Implementation
6
Project – PM Implementation
7
Project – PM Implementation
Task T-CODE
Create IP42
Change IP02
Display IP03
3.2. In the next window, enter the Maintenance plan category and Strategy then click Continue.
8
Project – PM Implementation
9
Project – PM Implementation
3.4. Next go to, Maintenance Plan Scheduling parameters and enter the relevant data scheduling period and the
start of the cycle then save it.
10
Project – PM Implementation
4.2. Then enter the maintenance plan number to schedule on the Schedule Maintenance Plan:
Initial screen. Press enter to continue.
4.3. After that, click on the Start icon on the menu bar to schedule the order as per the maintenance plan.
11
Project – PM Implementation
4.4. Next select the first row from the scheduling list and release it by clicking on the Release icon and click
save.
12
Project – PM Implementation
4.6. Now you can check the order number generated from T code IP24 /IW38 List display.
13
Project – PM Implementation
14
Project – PM Implementation
15
Project – PM Implementation
Task T-CODE
Individual Time Confirmation IW41
Overall Completion Confirmation IW42
Display PM order Confirmation IW43
6.2. On the initial screen of the transaction, enter the order numbers. Next, press enter button and the
following screen will appear.
6.3. here, you should enter the required details as explained below.
Personnel Number Employee who is assigned to perform the maintenance operation at a work
center in the respective plant.
Actual Work Time taken to complete the work and in which period it has occurred.
16
Project – PM Implementation
6.4. From here you can also post goods movement, process the material list can be entered.
6.5. Finally, press Save button. SAP PM completion confirmation will be saved for the order and operation.
Now, check the status for order, it will be set CNF
17
Project – PM Implementation
7.2. Now, check the maintenance order again. The system status will be set to TECO and NOCO
• T-code- IW32 for order.
18
Project – PM Implementation
19
Project – PM Implementation
20
Project – PM Implementation
Task T-CODE
Create IW21
Change IW22
Display IW23
1.2. Click Create Notification and you will be prompted to select a Notification type.
21
Project – PM Implementation
1.3. Next window, enter the notification description. To get the functional location, go to the functional location
field and search from the available list. Next is to select the Equipment. Select the Equipment number by
technical Id number and click the tick mark button to populate this.
22
Project – PM Implementation
1.5. Once a save the go to change notification screen and release the notification– IW22
23
Project – PM Implementation
2.2. Enter the notification number. Select the order type as BD01 Breakdown Maintenance Order Once you enter
the details, click the tick mark at the top.
24
Project – PM Implementation
2.4. Go to Operations tab and enter all the details. Add other operations as required.
2.5. Click the Component tab to assign components that are required for the operations.
25
Project – PM Implementation
26
Project – PM Implementation
Task T-CODE
Individual Time Confirmation IW41
Overall Completion Confirmation IW42
Display PM order Confirmation IW43
3.2. On the initial screen of the transaction, enter the order numbers. Next, press enter button and the
following screen will appear.
3.3. here, you should enter the required details as explained below.
Personnel Number Employee who is assigned to perform the maintenance operation at a work
center in the respective plant.
Actual Work Time taken to complete the work and in which period it has occurred.
27
Project – PM Implementation
3.4. From here you can also post goods movement, process the material list can be entered.
3.5. Finally, press Save button. SAP PM completion confirmation will be saved for the order and operation.
Now, check the status for order, it will be set CNF
28
Project – PM Implementation
4.2. Now, check the maintenance order again. The system status will be set to TECO and NOCO
• T-code- IW32 for order.
29
Project – PM Implementation
30
Project – PM Implementation
31
Project – PM Implementation
32