Construction Site Layout Planning
Construction Site Layout Planning
Construction Site Layout Planning
1. Introduction
Most construction sites that run into trouble do so for reasons related to managerial factors rather
than because of technical problems. The site-based management can make significant
improvements in the cost and time savings during the construction process without involving a
mass of additional work. The role of site managers is to control and maintain work performance
and then taking actions to rectify situations where performance is unsatisfactory.
Site management, in general, involves many tasks, such as site investigation before
construction process starts, material delivery and procurement management, keeping better site
records, keeping good site communication and high level of information flow, monitoring
performance regularly, establishing a well co-ordination system among different parts, and
performing a good site layout planning.
Among the important tasks of site management is the site layout planning. Extensive time
loss and cost overruns could result in large projects, where the number of manpower,
subcontractors, and equipment involved are high, if there is no effective and systematic approach
to site planning. A detailed planning of the site layout and location of temporary facilities can
enable the management to make considerable improvement by minimizing travel time, waiting
time, and increasing worker morale by showing better and safer work environment. Due to its
importance, this research focuses on the site layout planning problem.
Construction site layout involves identifying, sizing, and placing temporary facilities (TFs)
within the boundaries of construction site. These temporary facilities range from simple lay-
down areas to warehouses, fabrication shops, maintenance shops, batch plant, and residence
facilities. Required temporary facilities and their areas are depending in many factors including
project type, scale, design, location, and organization of construction work.
Site planning in particular, has been the most neglected aspect in the construction industry
and the attitude of the engineers has been that it will be done as the project progress. It is
important to realize that the site planning will be the conditions that site personnel will live with
for the total duration of the construction period. Thus the careful pre-planning is imperative.
Also, since the labor cost on a large project constitute approximately 50 to 60 percent of the total
project cost, significant saving can be occurred if the labor force moved freely and quickly
within the site. In 1987, the Construction Industry Institute reported in its “Constructability
Concepts File” that temporary facilities are important elements that can either enhance or
adversely affect construction productivity.
Layout planning, in general, can be viewed as a complex optimization problem that has
many engineering applications ranging from the layout of manufacturing plants to the layout of
computer chips on a board. Since the early 1960's, the problem has been extensively analyzed in
the Industrial Engineering and Operational Research communities. However, it has not been
satisfactory analyzed in the construction domain.
The problem of site layout planning has been solved by researchers using two distinctly
techniques: optimization and heuristics. Mathematical optimization procedures have been
designed to produce the optimum solutions. The heuristic methods, on the other hand, used to
produce good but not optimal solutions. However, the first category can not be adopted for large
projects, and the second category is the only available mean for solving the complex real life
projects.
2. The Problem
Failure to plan the site layout in advance is a prime cause of operational inefficiency, and can
increase the overall cost of a project substantially. In the absence of a precise site layout plan, the
following problems may occur:
a. Material stacks wrongly located. Materials arriving on site are off-loaded into what
someone guesses to be the correct location. This problem may involve double or triple
handling of materials to another location. For example:
- They may stocked over a drainage line or near the edge of excavation;
- They are too far from the work area;
- They are too remote from the hoist or not within the radius of the crane;
- They impede the smooth flow of work traffic across the site;
- Their delivery was wrongly phased and they are not needed until much later in the
project;
- They are fragile.
c. Inadequate space allowed. Where inadequate space is allowed for the stacking of materials
or activities:
- Materials may be stacked to high or stacked on roadways causing hazards.
- Working areas may become too cramped or additional areas may have o be allocated
with the consequent waste of time caused by having to travel between them.
d. Site huts wrongly located in relation to their effective use, such as:
- Site office located too near noisy activities such as mixer, or located too near to site
roads in dusty conditions, or too remote with insufficient overview of the site.
3. Present Practice
In construction, field practitioners manually mark up a single site drawing to include major
temporary facilities needed on site throughout the duration of the project. They depend on
knowledge of years of experience, common sense, and adoption of past layouts in determining
positions of temporary facilities on site. But, they can not keep track of all factors that could
affect the selection, location, and interactions of all facilities to be positioned.
A well planned site including all temporary facilities and utilities lead to: 1) increasing
productivity and safety, 2) reducing area(s) needed for temporary construction, and 3)
maximizing utilization. The following points should be considered in good site layout.
1. Safety
- Fire prevention: Fire is a major cause of damage on construction sites. So that, fire
extinguishers are basic requirements on a construction project.
- Medical services: On construction project a first aid kit is a must. In remote projects a
well-equipped medical room with a doctor and nurse is important.
- Construction safety clothing: Basic safety supplies like safety shoes, hard hats, gloves, and
goggles must be used by workers.
2. Site Accessibility
Easy accessibility will keep the morale of the equipment and vehicle drivers high, minimize
the chance of accidents, and save time in maneuvering to arrive at and leave the project. In
case of large projects, proper planning is required to layout the roads leading from the nearest
highway. Internal roads are necessary for easy flow of work. Also, Parking Lots are provided
for the owner, office, and craft personnel, but this facility must be planned where space does
exist.
- Site map: It should locate details of the project, and displayed in the office of the site
superintendent or project manager and posted at the entrance gate.
- Traffic regulatory signs: For large projects, traffic regulatory signs help in guiding the
traffic on the site and avoid accidents to a considerable extent.
- Display of labor relations’ policy and safety rules: This will help in eliminating disputes
between labor and management.
- Emergency routes and underground services: It is important to display the emergency
escape routes on every floor as the building progresses. Locations of underground services
should be marked to prevent its damage.
4. Security
- Entrance: It is necessary to have a proper guard entrance to the site provided by a booth.
Also, it is necessary to keep track of all visitors to the project.
- Lighting: It is necessary to have a standby generator to maintain site lighting.
- Fencing: The boundary should be fenced off from a security point of view.
5. Accommodation
On large construction projects, it is necessary to provide camp accommodation for all type of
staff involved in the project.
6. Offices
The offices should be close together, close to the site, and in a safe area. Also, provide the
offices with proper office equipment. The offices at the site may include job office, general
contractor office, and sub-contractors and consultants Offices.
It is necessary to have water and toilet facilities in convenient locations to accommodate the
work force.
8. Material Handling
One third or more of all construction operations can be classified as material handling. The
use of proper equipment for material handling and advance planning for minimizing multiple
handling will result in direct cost and time savings.
It is necessary to plan and reserve storage areas for materials so that multiple movement of
material is avoided.
Craft change-houses provide sheltered space for craft personnel to change and store clothes,
wash, and rest during waiting periods.
Batch plants are provided on projects where it is more economical to produce concrete on site
than to buy a ready mix. Aggregate storage piles, cement silos and admixture tanks will
accompany an on-site batch plant. Shops are used where materials and equipment are
fabricated on site. This includes electrical, mechanical, carpentry, and paint shops. Also,
testing shops used to house the necessary testing equipment and personnel for the project.
It is important to understand the characteristics of the temporary facilities before planning the
site layout. Six generic temporary facility characteristics are discussed in this section.
1. Satisfying environmental and safety regulations: All temporary facilities should satisfy
environmental and safety regulations. Special attention should be paid to temporary
facilities like batch plants, which have high pollution potential. Planners have to make
proper arrangements to control the air, water, and noise pollution from such facilities.
2. Availability of diverse solutions for the same problem: There are many arrangements that
can be made to establish a temporary facility. For example, if a warehouse is required, the
planner can build a warehouse on the site, use existing facilities on the site, rent a building
near the site, or plan a just in time delivery. Based on the usage of the warehouses, each
alternative can be further divided into several sub items. For example, the material of
building the facility can vary from wood, bricks, to a steel structure.
3. Relatively short life span of a specific location: The life span of temporary facility depends
on the duration of the project. In general, it must be removed as soon as the project is
completed.
4. Reutilization with a minimum loss for the same or modified function at another location:
Due to the shorter life span of temporary facility on site, planners consider reutilization of
the temporary facilities. This can result in saving the cost of construction. With appropriate
5. Easy of assembly, dismantling, and exploitation: temporary facilities structures which are
easy to assemble and dismantle will reduce both assembly and disassembly time. As
mentioned above, temporary facilities will need to be removed in a very short period of
time after project completion. Thus, temporary facilities structures should be easy to
assemble and dismantle without any damage to the structure components. Prefabricated
modules are ideal for constructing temporary facilities and they are usually easy to
assemble and dismantle.
Identifying the required temporary facilities for a specific project and determining their areas are
difficult decisions that require thorough consideration of the project conditions and local
regulations. In current practice, layout planning is often done in a speedy manner by adjusting
previous plans based mainly on the project manager's experience and common sense. In many
situations, some facilities, which are required by local by-laws, such as a site first-aid office or a
fire route may be omitted. Accommodating these facilities later can be costly and can cause loss
of site productivity. While some information related to facility identification and sizing have
been documented in the literature, this information however is scattered and is not readily usable.
In order to develop the knowledge base for the facility identification and area determination, the
knowledge were acquired and compiled from different sources, including construction safety and
health manuals, company handbooks, published dissertations, technical articles, and interviews
with some experts in the construction industry.
One of the characteristics of temporary facilities is the availability of diverse solutions for the
same function. This section describes some of the considerations when selecting the required
temporary facilities for a specific project.
- Construction type: The construction of an industrial plant, such as power plant, requires
more storage and fabrication area for process mechanical and electrical work than other
projects such as a highway project.
- Project size: A relatively small project can be managed from a trailer or portable structure.
While a five to ten year project may need temporary facilities of a more permanent nature.
- Project location: Projects located in uninhabited regions or in places where skilled labor is
scarce require additional facilities for eating and living. Project far from industrial centers
require more on site services such as batch plant, equipment maintenance shops, long term
storage area, and even some other recreational centers for the families.
Also, the selection of some of the temporary facilities depends on the manpower permanent
resident from the site. The work force breaked down into three categories as shown in Figure 1:
L3 L2 L1 Site
5 km
60 km
The type and number of temporary facilities needed for a specific project must be
determined prior to their sizing and location. Table 1 gives a list of common temporary facilities
that can be used in a project. While some temporary facilities are to be selected from this list for
a specific project, taking into account the factors cited above, as well as other temporary
facilities justified by the uniqueness of the project.
1 Job office
2 Owner representatives office
3 Subcontractors office
4 First aid office
5 Information and guard house
6 Toilet on site
7 Staff/Engineer dormitory
8 Staff/Engineer family dormitory
9 Labor dormitory
10 Labor family dormitory
11 Dinning room for labor
12 Bathroom for labor
13 Restroom for labor
14 Equipment maintenance shop
15 Parking lot for mechanics
16 Prefabricated rebar storage yard
17 Rebar fabrication yard
18 Fabricated rebar storage yard
19 Carpentry shop
20 Storage yard for lumber
21 Storage yard for formed lumber
22 Cement warehouse
23 Batch-plant and aggregate storage
24 Craft change-house
25 Sampling / Testing lab
26 Pipe jointing yard
27 Pipe storage yard
28 Welding shop
29 Parking lot
30 Tank
31 Long term laydown storage
32 Machine room
33 Electrical shop
34 Steel fabrication shop
35 Sandblast shop
36 Painting shop
37 Scaffold storage yard
38 Material warehouse
After selecting the temporary facilities that are needed on the site, the size required for them
must be estimated. The size of temporary facilities is mainly based on the manpower
requirements, estimated quantity of work, production rate of resources, availability of site space,
and cost considerations. Some of the rules of thumb, safety regulations, and other criteria for
sizing temporary facilities are described below.
According to survey among 36 construction Company of various sizes, the size of temporary
facilities are based on manpower requirements, project size, duration or costs. Ignoring the large
variations of the numeric values, his rules show that the companies have similar practices.
However, some adjustments have to be made when they are applied to a unique project. Tables
2, 3, and 4 illustrate the results of the survey. The values presented in Table 4 for projects ranges
from $200 million to $4.5 billion, with average values around $2 billion.
- Project Manager 12 – 25
- Construction Manager 9 – 14
- Mechanical/ Electrical/ Civil Engineer per Engineer 9 – 11
- Purchasing (total) 46 – 84
- Schedule & Cost Control (total) 28 – 93
- Accounting (total) 37 – 80
- First Aid & Safety per Office 17 – 19
- Clerical (total) 28 – 74
- Estimator 11
The size of sanitary facilities depended on the manpower requirements and it can be entirely
temporary or permanent. If portable toilets are used, a minimum of one toilet per twenty persons
must be provided. Space required for some facilities as fabrication shops dependent on the
amount of on-site fabrication work as well as rate of fabrication dictated by construction
schedule. Also, the size of the equipment maintenance shop depends on the amount of
construction equipment on the site.
An = ( Q max / I m ) / q n (1)
Table 6 shows the rules of thumb developed by Obayashi Corporation of Japan. The areas
given in Table 6 are based on the following assumptions:
- For each facility, the unit area includes areas for corridors, closets and aisles.
- The area of the bathroom should be adequate for simultaneous use by 10% of the
residents, and one toilet for 15 labors.
- The number of labors is the peak number of labors required.
Some safety rules were also compiled from safety and health manual (ILO 1992), safety and
health administration (OSHA 1987), building codes (UBC 1985; SBC 1985). Some of these
regulations are listed below.
Example 1
Figure 2 illustrates the layout of building materials and access roads for the purposes of servicing
two hoists for the erection of a low-rise building. Comment on and criticize the present layout in
relation to the positioning of both the materials and hoists.
scaffold
waste materials
timber
scaffold store
reinforcement
stockpile
Joiners
shop
building
concrete hoists
batch plant
material
mat. stockpile stockpile access
morter road
stores
cement silo mixer canteen
temporary road laboratory check point
waste materials
scaffold
Reinf..
building stock
hoists canteen
stockpile
Scaffold
materials
compound Joiners
shop
stores
concrete batch
plant
temporary road
laboratory morter mixer
check point
Figure 4 shows the construction site for the construction of a radio transmitter station on a
remote site in open location. The site involves the construction of a transmitting tower and
transmitter building along with some access roads.
generator
transmitter building house
The contractor prepared the site layout plan as shown in Figure 5. In developing this given plan,
the contractor collected the following information to layout the site:
- All equipment was delivered before building foundations were complete. All
other fitting also delivered (doors, sanitary, etc.).
- Generator house completed. Hoist was not available at commencement and has
only just delivered.
- Nearest pure water is in the town 20-km away. Water delivered by tanker and
stored in 6 200-litre drums.
- Pylon bases and sewer/septic tank not yet started.
- Agents' office is sited on a privileged place and to satisfy the best view for site.
Criticize the layout given in Figure 5 and prepare another layout to correct the criticism.
to major temporary
highway access road
nearest town 20
km distant
- In general, the working area is too spread out, making control more difficult and
increasing travelling time about the site which will lead to reducing
productivity.
- Site latrines and canteen are too far away, causing loss of time due to
unnecessary travelling. There is no apparent supply of drinking water on site.
- No security fencing is shown.
- Temporary access road should follow the line of the proposed station access
road to avoid duplication of work.
- Surplus excavation should have been led directly to the erosion site to avoid
double handling.
- Pylon girders have been stacked over foundation bases, necessitating double
handling.
Figure 6 shows the suggested improved site layout planning to offset the drawbacks recorded
from the previous site plan given in Figure 5.
to
quarry
gener.
mason transmitter building house
site access
road
The project shown in the following figure is for the construction of water treatment plant located
at Elmansoura City on the east bank of the Nile River (Domiatte branch) near Mansoura
University. Access to the site is provided by an adjacent road, which joins the project site with
the nearby highways. The project involves the construction of reservoirs and basins needed for
the treatment operations and an operation building. The construction site area is about 53,000 m2
(13 acre). The following figure shows the general layout plan of the construction site of the
project prepared by the contractor. Comment and criticize the given layout.