0% found this document useful (0 votes)
163 views119 pages

NDT Penetrant Test Report

Uploaded by

sukandar tulus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
163 views119 pages

NDT Penetrant Test Report

Uploaded by

sukandar tulus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 119

NDT

NON DESTRUCTIVE TEST

PENETRANT TEST REPORT

PROJECT :
PURE DATA CENTER JKT01

LOCATION :

LOGOS METROLINK LOGISTIC HUB , BEKASI

SYSTEM :
HVAC

SUB SYSTEM :
BUFFER TANK 1
8500 LITER - Ø 1900 MM, H 3575 MM – 150 PSI
JOINT NUMBER :
ASNT NDT
Drawing Reference : -
Material Reference : JKT01-TAT-DC1-R2-TS-W-56005 R2
Joint Number NDT-Penetrant Test = 39 Joint Horisontal
Joint Number NDT-Penetrant Test = 6 Joint Vertical
EDY SETYAWAN
ASNT NDT Level II Joint Number NDT-Penetrant Test = 0 Joint Nozzle
Certificate:
026.R/SDIT/NDT-
Joint Number NDT-Penetrant Test = 0 Joint Support
PT/XII.2021 Total Joint Number NDT-Penetrant Test = 45 Joint

File:HVAC-Buffer Tank 1-Non Destructive Test-Penetrant Test


Document No.

NDT PENETRANT TEST REPORT


PDC-JKT01-NDT-PT
Rev. No : 0
Page : 2 of 150

TABLE OF CONTENT

1. DRAWING TANK PLAN……….…………………………………………….… 5

2. NDT-PENETRANT TEST REPORT…....................................................22


2.1 Joint Number: Ø 1900-BT1-J1.1
2.2 Joint Number: Ø 1900-BT1-J1.2
2.3 Joint Number: Ø 1900-BT1-J1.3
2.4 Joint Number: Ø 1900-BT1-J1.4
2.5 Joint Number: Ø 1900-BT1-J1.5
2.6 Joint Number: Ø 1900-BT1-J1.6
2.7 Joint Number: Ø 1900-BT1-J1.7
2.8 Joint Number: Ø 1900-BT1-J1.8
2.9 Joint Number: Ø 1900-BT1-J1.9
2.10 Joint Number: Ø 1900-BT1-J1.10
2.11 Joint Number: Tank 1-C.1
2.12 Joint Number: Tank 1-C.1A
2.13 Joint Number: Tank 1-C.1B
2.14 Joint Number: I 1500-BT1-J1.1
2.15 Joint Number: I 1500-BT1-J1.2
2.16 Joint Number: I 1500-BT1-J1.3
2.17 Joint Number: Ø 1900-BT1-J2.1

2.18 Joint Number: Ø 1900-BT1-J2.2

2.19 Joint Number: Ø 1900-BT1-J2.3

2.20 Joint Number: Ø 1900-BT1-J2.4

2.21 Joint Number: Ø 1900-BT1-J2.5

2.22 Joint Number: Ø 1900-BT1-J2.6

2.23 Joint Number: Ø 1900-BT1-J2.7


2.24 Joint Number: Ø 1900-BT1-J2.8
2.25 Joint Number: Ø 1900-BT1-J2.9
2.26 Joint Number: Ø 1900-BT1-J2.10
2.27 Joint Number: Tank 1-C.2
2.28 Joint Number: Tank 1-C.2A
2.29 Joint Number: Tank 1-C.2B
2.30 Joint Number: I 800-BT1-J2.1 (Tank 1-T1)

2.31 Joint Number: I 800-BT1-J2.2 (Tank 1-L1)

File:HVAC-Buffer Tank 1-Non Destructive Test-Penetrant Test


Document No.

NDT PENETRANT TEST REPORT


PDC-JKT01-NDT-PT
Rev. No : 0
Page : 3 of 150

2.32 Joint Number: I 800-BT1-J2.3 (Tank 1-T2)

2.33 Joint Number: Ø 1900-BT1-J3.1

2.34 Joint Number: Ø 1900-BT1-J3.2

2.35 Joint Number: Ø 1900-BT1-J3.3

2.36 Joint Number: Ø 1900-BT1-J3.4

2.37 Joint Number: Ø 1900-BT1-J3.5

2.38 Joint Number: Ø 1900-BT1-J3.6

2.39 Joint Number: Ø 1900-BT1-J3.7


2.40 Joint Number: Ø 1900-BT1-J3.8
2.41 Joint Number: Ø 1900-BT1-J3.9
2.42 Joint Number: Ø 1900-BT1-J3.10
2.43 Joint Number: Tank 1-C3
2.44 Joint Number: Tank 1-C.3A
2.45 Joint Number: Tank 1-C.3B

3. DOCUMENTATION.………………………………………………………….…104
3.1 Documentation Buffer Tank 1-NDT-Penetrant Test…………………....……… …..105

4. ATTACHMENT ………………………………………………………………....125
4.1 Certificate ASNT NDT Level II…………………………………………………..……....126
4.2 Certificate Welding Inspector ………………………………………………………....128

4.3 WPS……………………………………………………………………………………………….. 131


4.4 Certificate Welder W1 - Welder Fabricator………………………………………....144

4.5 Certificate Welder W5 - Welder Repair……………………………………………….145

4.6 Certificate Material…………………………………………………………………………….148

File : HVAC-Buffer Tank 1-NDT-Penetrant Test


Document No.

NDT PENETRANT TEST REPORT


PDC-JKT01-NDT-PT
Rev. No : 0
Page : 3 of 150

CHAPTER 1

DRAWING TANK PLAN

File : HVAC-Buffer Tank 1-NDT-Penetrant Test


final pressure drop at
design flow rate shall be
proided

provide summary of total


empty weight
update to English
Document No.

NDT PENETRANT TEST REPORT


PDC-JKT01-NDT-PT
Rev. No : 0
Page : 3 of 150

CHAPTER 2

NDT-PENETRANT TEST REPORT

File : HVAC-Buffer Tank 1-NDT-Penetrant Test


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.1.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 01/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.1.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 01/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.2.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 02/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.2.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 02/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.3.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 03/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.3.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 03/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.4.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 04/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.4.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 03/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.5.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 05/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.5.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 05/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.6.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 06/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.6.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 06/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.7.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 07/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.7.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 07/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.8.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 08/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.8.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 08/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.9.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 09/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.9.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 09/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.10.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 10/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1.................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900-BT1-J1.10.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 10/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C1.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 11/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair IF-Incomplete Fussion No Defect Indication

Capping W5 Accepted , After Repair Repair WH-Worm Hole No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : TANK 1-C1.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 11/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C1.A.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 12/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair IF - Incomplete Fussion , Repair No Defect Indication

Capping W5 Accepted , After Repair WH - Worm Hole , Repair No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C1.A.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 12/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C1.B.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 13/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W5 Accepted , After Repair IF - Incomplete Fussion , Repair No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C1.B.................................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 13/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : I 1500 - BT1 - J1.1................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 14/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : I 1500 - BT1 - J1.1................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 14/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : I 1500 - BT1 - J1.2................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 15/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : I 1500 - BT1 - J1.2................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 15/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 13-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : I 1500 - BT1 - J1.3................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 16/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : I 1500 - BT1 - J1.3................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 16/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.1................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 17/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.1................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 17/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.2................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 18/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair C - Crack No Defect Indication

Capping W5 Accepted , After Repair Repair C - Crack No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.2................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 18/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.3................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 19/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair UC - Undercut No Defect Indication

Capping W5 Accepted , After Repair Repair UC - Undercut No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.3................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 19/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.4................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 20/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 .................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.4................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 20/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Satiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.5................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 21/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair UC - Undercut No Defect Indication

Capping W5 Accepted , After Repair Repair UC - Undercut No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Satiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.5................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 21/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Satiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.6................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 22/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5...........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair UC - Undercut No Defect Indication

Capping W5 Accepted , After Repair Repair UC - Undercut No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Satiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.6................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 22/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.7................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 23/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.7................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 23/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.8................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 24/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.8................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 24/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.9................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 25/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.9................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 25/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.10................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 26/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ................................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900 - BT1 - J2.10................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 26/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C2......................................... Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 27/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair SI - Slag Inclusion No Defect Indication

Capping W5 Accepted , After Repair Repair SI - Slag Inclusion No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C2......................................... Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 27/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C2.A......................................... Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 28/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W5 Accepted , After Repair Repair 1P- Incomplete Penetration No Defect Indication

Filler W5 Accepted , After Repair Repair 1F- Incomplete Fusion No Defect Indication

Capping W5 Accepted , After Repair Repair 1F- Incomplete Fusion No Defect Indication
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C2.A......................................... Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 28/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C2.B......................................... Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 29/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted No Defect Indication

Filler W1` Accepted No Defect Indication

Capping W5 Accepted , After Repair Repair POR- Porosity No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT.............................. Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1-C2.B......................................... Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 29/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : I 800- BT1 -J2.1 ( TANK 1.T1 ).................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 30/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted No Defect Indication

Filler W5 Accepted , After Repair Repair IF - Incomplete Fussion No Defect Indication

Capping W5 Accepted , After Repair Repair POR- Porosity No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : I 800- BT1 -J2.1 ( TANK 1.T1 ).................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 30/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : I 800- BT1 -J2.2 ( TANK 1.L1 ).................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 31/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W5 Accepted , After Repair Repair SI- Slag Inclusion No Defect Indication
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : I 800- BT1 -J2.2 ( TANK 1.L1 ).................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 31/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : I 800- BT1 -J2.3 ( TANK 1.T2 ).................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 32/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair IF - Incomplete Fussion No Defect Indication

Capping W5 Accepted , After Repair Repair POR- Porosity No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : I 800- BT1 -J2.3 ( TANK 1.T2 ).................. Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 32/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.1................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 33/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5 ..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.1................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 33/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.2................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 34/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.2................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 34/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.3................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 35/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.3................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 35/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.4................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 36/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.4................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 36/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.5................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 37/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.5................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 37/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.6................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 38/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.6................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 38/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.7................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 39/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.7................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 39/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.8................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 40/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 , W5..........................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W5 Accepted , After Repair Repair UC - Undercut No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.8................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 40/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.9................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 41/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.9................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 41/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.10................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 42/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : Ø 1900- BT1 -J3.10................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 42/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1 - C3........................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 43/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W5 Accepted , After Repair Repair IF - Incomplete Fussion No Defect Indication

Capping W5 Accepted , After Repair Repair IF - Incomplete Fussion No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki , Suhadi Sastiawan
Date : 01-04-2022................................................................................. Joint No : TANK 1 - C3........................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 43/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : TANK 1 - C3.A........................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 44/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : TANK 1 - C3.A........................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 44/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : TANK 1 - C3.B........................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

WELDING SCHEMATIC
Report No. : 45/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 1 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
SKETCH

Figure 2
PT Procedure : ASME Section V..............
Acc. Standard : ASME Section IX..............
Welder Stamp No. : W1 ..............................
Welder Type : Double V Groove.............
Material Thk : 10 mm........................
Material Spec. : ASTM A36...........
Weld Process : SMAW...........................

STAGE EXAMINATION SURFACE PREPARATION

Applicable Mat. ˅ Grinding Machining Brushing


After Machining After Pressure Test
PENETRANT
˅ As Welded Casting Type:
Application Color Contrast Flourecent
After PWHT Hard Chrome Plating Brushing ˅ Spraying : Magnaflux SKL SP2…

DEVELOPER CLEANER/REMOVER
Type:
Type: Water : …..................................................................................................
˅ Drying : Magnaflux SKD-S2…………. Wet Post : ……...............................................................................................
˅ Solven : Magnaflux SKC-S............................................................................

Part of Weld Number Welder Code Accepted Rejected Remarks


Root W1 Accepted - No Defect Indication

Hot Pass W1 Accepted - No Defect Indication

Filler W1 Accepted - No Defect Indication

Capping W1 Accepted - No Defect Indication


Project Package : PURE Data Centre JKT01-Bekasi....................................................... Document No. : PDC-JKT01-NDT-PT............................ Description :
…............................................................................................... Revision No. : R0...................................................... Appicable Mat. : ASME Section IX
Location : LOGOS Metrolink Logistic Hub Bekasi............................................... Issued Date : 21-03-2022........................................... Welder Name : Basuki
Date : 01-04-2022................................................................................. Joint No : TANK 1 - C3.B........................................ Position of Groove : 6G

NDT-PENETRANT TEST REPORT


PT DWIMITRA EKATAMA MANDIRI

Report No. : 45/PDC/JKT01/HVAC/BT1/NDT/PT Location : Warehouse DME Tangerang Date : 14-10-2022 Run Pipe Spec. : N/A Tank Size : Ø 1900 MM
Client : PT TATAMULIA NUSANTARA Page : 2 of 2 WPS No. : 001/WPS/DEM/ASME/20 Split Tee Spec. : N/A Weld Process : SMAW
Part of Weld Number Welder Code Accepted Rejected Remarks

Remarks :

Prepared Checked & Reviewed Acknowledge Witnessed and/or Inspected


PT DWIMITRA EKATAMA MANDIRI PT. TATAMULIA NUSANTARA INDAH PT. JAYA KARYA INTEGRASI PT. LANTERA SEJAHTERA INDONESIA Welding Inspector

EDY SETYAWAN
ASNT NDT PT MT Level II
Document No.

NDT PENETRANT TEST REPORT


PDC-JKT01-NDT-PT
Rev. No : 0
Page : 3 of 150

CHAPTER 3

DOCUMENTATION

File : HVAC-Buffer Tank 1-NDT-Penetrant Test


PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear
PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear
PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear
PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear
PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear
PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear

Repair Rejected Repair Rejected

Repair Rejected Repair Rejected

Repair Rejected Repair Rejected


PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear

Visual Inspection Visual Inspection

Visual Inspection Visual Inspection

Surface Preparation Surface Preparation

NDT Penetrant Test NDT Penetrant Test


PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear

Tool Box Meeting Tool Box Meeting

Tool Box Meeting Surface Preparation

Surface Preparation NDT Radiograpy Test

NDT Radiograpy Test NDT Radiograpy Test


PURE DATA CENTER
JKT01-BEKASI
DOCUMENTATION
Subject : HVAC-Buffer Tank 1 Date : 13/10/2022
Location : Warehouse DME , Tangerang Weather : Clear
Document No.

NDT PENETRANT TEST REPORT


PDC-JKT01-NDT-PT
Rev. No : 0
Page : 3 of 150

CHAPTER 4

ATTACHMENT

File : HVAC-Buffer Tank 1-NDT-Penetrant Test