HFY3-3720-ELE-PD-0002 - 0 OHTL Installation and Test Procedure
HFY3-3720-ELE-PD-0002 - 0 OHTL Installation and Test Procedure
HFY3-3720-ELE-PD-0002 - 0 OHTL Installation and Test Procedure
CONTENTS
chains are supplied by contractor and the rest are supplied by contractor
3.2.1 calibration of rings and chains
1 lifting rings. contractor supplied rings are used with rated lifting weight of each ring is 2 Ton. They
should meet follow requirement:
2lifting chains. Based on the information, e.g. the chains can meet the lifting need. To ensure the
chains can meet erection need, The contractor has also supplied one set of steel wires, i.e. φ63、6*37+1
type. Steel wires calculation: two wires are used for lifting (four strands of wires are with stress). Based on
the equipment dimension and steel wire length, the stressed angle α of the steel wire is approximately
15°, set the safety coefficient K is 8, thus Tension fracture of each stand steel wire should be not less
withσb=170kg/mm2. Based on Steel Wire Load Rate Sheet, it is confirmed that the steel wire with
diameter ≮60.5mm (190.29t>2 t) can meet lifting requirement, i.e. steel wire (φ63, 6*37+1) will be
The process of installing the terminal tower is the same with 3.0
5.0 Installation of Conductor & Stringing
5.1 Conductor Grips There is a wide variety of conductor grip styles and tie-down products available in
the industry. Always consult with the grip manufacturer for the correct selection so that the grip type and
configuration is sized for the diameter and type of conductor being installed and is capable of holding the
conductor to the highest tension that is anticipated during the sagging operation. There are two basic types
of mechanical grips that are used to secure the conductor during the pulling, sagging or dead-ending
operation. The Klein (Chicago) and Crescent types of grip are open-sided rigid body with opposing jaws
and swing latch that pinchthe conductor between the jaws. The pocketbook type of grip, often referred to
as come-along, suitcase, or four bolt, incorporates a bail attached to the body of a clamp that folds to
completely surround and envelop the conductor. Bolts are then used to close the clamp and obtain a grip.
A woven wire grip (often referred to as a basket, wire mesh, or sock) sized to fit over the conductor and a
suitably sized swivel link should be used for tension stringing. To prevent the grip from accidentally
coming off the conductor, two punch-lock steel bands should be applied at the open end of the grip over
the woven wire grip and conductor. Tape applied over the bands will protect the bullwheel tensioners and
stringing sheave lining from the steel bands.
5.2 Bottom-End Conductor Attachment to Reel
The bottom end of the conductor on the reel must be secured to the reel to provide a stationary
attachment point during manufacture and payout of the conductor. The end attachment must never be
relied upon as an anchor point for the conductor. When paying out the conductor, the stringing operation
must be stopped before the reel completely empties, and any required back tension must be transferred
from the conductor on the reel to some other anchor point. The conductor end that is attached to the reel
must never be considered as a brake or end-stop, as it is not capable of withstanding a conductor “run
out” situation
The ratio of the distance to the first structure and the height to the first stringing sheave should be 3:1. The
pay-off reel must be positioned 50 -80 feet back from the start of the bullwheel tensioner (with brake set as
low as possible to maintain tension).
sheave to swing left or right of plumb, depending on the direction of the line change. Figure 8 includes
depictions of conductor tracking through a stringing sheave being pulled through an angle. When the line
tension is pulling the sheave to one side or the other, as pictured in the images on the left hand side of
Figure 8, it causes the conductor to ride up on the side of the sheave. The displacement from center
produces a torsional moment that causes the conductor to rotate clockwise or counter-clockwise,
depending on which side of the sheave the conductor is on. To ensure that the conductor tracks in the
middle of the sheave’s groove during stringing, General Cable recommends supporting the sheaves at
angles, as depicted in the images on the right hand side of Figure 8. This can be done with a simple rope or
a chain and hoist if the blocks are heavy. Pulling the sheave to the appropriate angle minimizes the
torsional forces placed on the conductor and the potential for damage. If tandem sheaves are used, they
must be properly secured together and supported in the same manner as single sheaves.
stringing sheave groove is a function of the pulling tension (T) applied to the conductor, the diameter of
the stringing sheave at the bottom of the groove (Ds ), and the diameter of the conductor itself (Dc ). The
pressure is independent of the length of radial contact around the sheave. For overhead conductors, the
side wall bearing pressure can be expressed by the following equation:
EPCC OF WATER INJECTION BOOSTING STATION UPGRADE
ELECTRICAL INSTALLATION AND TEST PROCEDURE
For stringing blocks, IEEE 524 suggests a limitation of 500-700 psi (3.4 – 4.8 MPa) maximum side wall
pressure between the conductor and the sheave to minimize the potential for damaging the conductor.
Example: Pulling Drake ACSR/GA2 over a stringing sheave with a 24” bottom of the groove diameter:
The calculated conductor side wall pressure force of 196 psi(1.35MPa) against the groove lining of the
stringing sheave indicates a pulling tension of 1734 lb (787Kg)should not harm the conductor. The
calculated value is below the suggested limitation of 500 -700 psi (3.45-4.83MPa)maximum for an ACSR
conductor.
5.10 Time in Stringing Sheaves
Conductors should never be left hanging in sheaves for long periods of time. IEEE Standard 524
suggests that the conductors be “sagged” within 24 hours of installation. Leaving the conductors sitting
in the sheaves can cause damage, as the conductor is not secured and can come out of the sheave during
high wind. Excessive sag at low tensions can have conductors clashing together. Tension should be kept as
low as possible when temporarily tied down (snubbed-off conductor). The tension should never approach
that of the sagging tension value. Keeping the holding tension low and working within the 24-hour
window avoids having to rely on short term creep correction curves for subsequent sagging. This is
because these curves use assumptions as to tension, temperature and time, and as such are less accurate as
time increases.
5.11 Pre-Tensioning
Although it is not a common practice, in some applications the conductor is pre-stretched prior to
sagging. Pre-tensioning is carried out when it is desirable to sag the conductor according to its final
condition. Usually the conductor is pulled to 50-60% of the rated strength and held for at least one hour.
The pre-tension value is specifically calculated for each installation and temperature. Afterwards, the
tension is backed off to the final sagging tension. Typically pre-tensioning is only done on a few spans.
EPCC OF WATER INJECTION BOOSTING STATION UPGRADE
ELECTRICAL INSTALLATION AND TEST PROCEDURE
Sheaves and support hardware must be capable of withholding the applied tension.
5.12 Sagging
The sagging of ACSR conductors can be done using any of the existing methods. Line tension or sag
may be set using: