Introduction Building Construction Practical Notes
Introduction Building Construction Practical Notes
Introduction Building Construction Practical Notes
A construction site is an area or piece of land where construction work is taking place. It is a dynamic
environment where many different activities are taking place at the same time. The site is usually divided
into zones for different activities such as material storage, offices, and worker accommodation
Engineering drawing
A structural/Engineering drawing is a type of engineering drawing that provides detailed information
about the structural members needed to support the structure, which is not normally given in architectural
drawings. It is a plan or set of plans and details for how a building or other structure will be built.
Structural drawings are generally prepared by registered professional engineers and based on information
provided by architectural drawings. The structural drawings are primarily concerned with the load-
carrying members of a structure. They outline the size and types of materials to be used, as well as the
general demands for connections. They do not address architectural details like surface finishes, partition
walls, or mechanical systems. This detail drawing helps to set out any building or structure and requires
clear understanding of structural concepts.
The process involves the positions and levels of building lines and road alignments shown on the
construction plans to be established on the ground by various techniques and instruments1.
Formwork construction
Formwork is a temporary structure that is used to support wet concrete until it hardens. It is molds into
which concrete or similar materials are either precast or cast-in-place. In the context of concrete
construction, the falsework supports the shuttering molds. In specialty applications formwork may be
permanently incorporated into the final structure, adding insulation or helping reinforce the finished
structure.
Requirements of Good Formwork
It should be strong enough to withstand all types of dead and live loads.
It should be rigidly constructed and efficiently propped and braced both horizontally and
vertically, to retain its shape.
The joints in the formwork should be tight against leakage of cement grout.
Construction of formwork should permit removal of various parts in desired sequences without
damage to the concrete.
The material of the formwork should be cheap, readily available, and should be suitable for reuse.
The formwork should be set accurately to the desired line, and levels should have a plane surface.
It should be as light as possible.
The material of the formwork should not warp or get distorted when exposed to the elements.
It should rest on a firm base.
2. Plywood Formwork
Resin-bonded plywood sheets are attached to timber frames to make up panels of the required sizes.
3. Steel Formwork
This consists of panels fabricated out of thin steel plates stiffened along the edges by small steel angles.
The panel units can be held together using suitable clamps or bolts and nuts.
Column formwork 3D
Stair formwork
Concrete wall formwork
Reinforcement work
Rebar, also known as reinforcement steel and reinforcing steel, is a steel bar or mesh of steel wires used
in reinforced concrete and masonry structures to strengthen and hold the concrete in tension. To improve
the quality of the bond with the concrete, the surface of rebar is often patterned.
Rebar is necessary to compensate for the fact that whilst concrete is strong in compression, it is relatively
weak in tension. By casting rebar into concrete, it is able to carry tensile loads and so increase overall
strength.
Different uses of rebar include:
Primary reinforcement: Used to provide resistance to support design loads.
Secondary reinforcement: Used for durability and aesthetic purposes by providing localised
resistance to limit cracking and temperature-induced stresses.
Provide resistance to concentrated loads, spreading it through a wider area.
Assist other steel bars in accommodating their loads by holding them in the correct position.
External steel tie bars to constrain and reinforce masonry structures, sometimes as a means of
building conservation.
Reinforced masonry: Some masonry blocks and bricks include voids to accommodate rebar to
carry tensile loads. The rebar is secured in place using grout.
Metric bar size Linear mass density Nominal diameter Cross-sectional area
(mm) (kg/m) (mm) (mm2)
6,0 0.222 6 28.3
8,0 0.395 8 50.3
10,0 0.617 10 78.5
12,0 0.888 12 113
14,0 1.21 14 154
16,0 1.58 16 201
20,0 2.47 20 314
25,0 3.85 25 491
28,0 4.83 28 616
32,0 6.31 32 804
40,0 9.86 40 1257
50,0 15.4 50 1963
STRUCTURE
Bar Bending Schedule [BBS] Estimate of Steel in Building Construction
For clear understanding, look at the below image for calculation of the total length of stirrup the
with two hooks at ends.
Total Cutting Length of stirrup or tie = Total length of Bar + 2 x Hook Length (Two hooks)
Total Cutting Length = L+2(9d)
Therefore Total Cutting length = L+18d (d is the Diameter of a bar)
Hope, now you are clear with the Hook length calculation.
2. Bend Length: -
The Bend length calculation is different for Cranked bars (bent up bars) and bends at corners.
The bars are usually cranked in Slabs and bars are bent at corners in Stirrups or ties.
(i) Bend Length calculation in Cranked Bars: -
As Shear stress is maximum at supports in Slab. To resist these stresses, we usually crank the bars at the
ends of supports in the slab. The below figure depicts the bent-up bar in Slab. To calculate the bend
length the below procedure is followed.
From the above figure as the bar is bent at an angle θ0 the additional length (la) is introduced.
Where, la = l1 – l2–(i)
Tanθ = D/l2 ; Sinθ = D/l1
Hence l1 = D/Sinθ and l2 = D/tanθ
Therefore from (i) :- la = D/Sinθ – D/tanθ
Giving different θ values as 300 , 450, 600 results different additional length la values as below.
θ0 D
/Sinθ D
/tanθ la =D/Sinθ – D/tanθ
300 D/0.500 D/ 0.27D
0.573
450 D/0.707 D/ 0.42D
1.000
600 D/0.866 D/ 0.58D
1.732
900 D/1 0 1D
1350 D/0.707 D/-1 2.42D
From above fig, There are 3 bends which are bent at an angle of 900 and two bends are bent at an angle of
1350
Total bend length = 3 x 900 Bend length + 2 x 1350 Bend length = 3 x 2d + 2 x 3d = 12d = 12 x 8 = 96mm
The standard length of Rebar is 12m. Suppose the height of the column is 20 m. To purvey this
requirement, two bars of length 12m and 8m are overlapped (joined) with overlap length.
The bars used in building should be grouped together for each structural unit and listed seperately
for each floor.
Bars are listed in numerical order.
To identify the bar in the bundle of bars, each bar is uniquely labelled with reference details
(Length of the bar, size of the bar, Shape of the bar)
The type of bar and shape of the bar should be in accordance with B8666.
It is essential that the bar mark reference on the label attached to a bundle of bars refers uniquely
to a particular group or set of bars of defined length, size, shape and type used on the job.
The cutting length and bending length calculations are separately calculated and not included in
the detailed list. Like I have listed the Bar Bending details in a table and calculations are done
separately.
BBS helps to estimate the total quantity of steel required for the construction of building or
structure. It helps to quote for tender the cost incurred by steel.
Finding the cutting length and bending length in reinforcement detailing improves the quality of
construction and minimize the wastage of steel, makes an economic construction
With the help of reinforcement drawings, cutting and bending can be done at the factory and
transported to the site. This increases faster construction and reduces the total construction cost.
For site engineers, It becomes easy to verify the cutting length and bending length of the
reinforcement before placing the concrete.
BBS of Column
Structural Member Column
(3mx0.3mx0.3m)
Bar Marking 1. Main Bars
2. Stirrups (Longitudinal bars)
Dia of Bar 1. Main Bars = 16mm;
2. Stirrups
(Longitudinal bars) = 8mm
No. of Bars used 1. Main bars = 4
2. Stirrups = 30
Cutting length 1. Main bars = 4m
2. Stirrups = 1.2m
Total Length of 1. Main bars = 16 m
bar 2. Stirrups = 36m
Weight of Steel 1. Main bars = 25.24Kgs
bar 2. Stirrups =14.22Kgs
Below is the standard format of BBS for the above table calculation
REBAR SCHEDULE
Payment No :-____
N Locat
Length (m)
o. Description ion D L N M
6 8 10 12 14 16 20 24
Columns C1
1 16 4 4 1 16
2 8 1.2 30 1 36
Total Length
(m) - 36 - - - 16 - -
Unit Weight
(Kg/m) 0.222 0.395 0.617 0.888 1.208 1.578 2.468 3.551
Supervisor Contractor
Bar placement
Practical Tips for Placement of Reinforcements in Concrete Members
1. The site engineer should examine clearance at stirrups and column ties that protrude beyond
other reinforcement.
2. A clear cover between the top of the slab and the top of reinforcements must be maintained,
especially if exposed to an aggressive environment as in the bridge deck slab.
3. In the case of double mat reinforcement, it is advised to align steel bars vertically above each
other in horizontal directions to facilitate concrete pouring and consolidation.
4. Provide openings in the top mat reinforcement to place fresh concrete easily and prevent
scattering and concrete segregation.
5. In case of extremely congested reinforcement, create an opening by moving congested steel
bars to each side to make way for concrete placement. Move the steel bars to the previous
position after concrete pouring is completed. Sometimes, the displaced bars can be left at their
place if the designer approves them.
6. The nominal coarse aggregate size in the concrete mixture should not be greater than three-
quarters of the spacing between bars to ensure the flow of concrete through steel bars and
avoid honeycombing.
7. The head of vibrators should fit between steel bars to consolidate concrete adequately. If a
small vibrator head is used, reduce the spacing between vibration points and increase
vibration time. All vibrators should be functional and prevent concrete placement unless spare
vibrators are available.
8. Stagger bar splices to ease the concrete placement.
9. Ensure that the splice of column ties is staggered around the corners of the column. It is not
recommended to place splice of column ties above each other.
10. When splices are welded, make sure that the weld is of the required size and length. The bars
should not be burned, or their cross-section should not be reduced due to welding.
11. The use of tack welding is prohibited because it weakens the bars at the tack location. If
contract documents allow tack welding, it should be done by professionals. It is recommended
to carry out weld tests if many welds are made.
12. It is common to use splicing sleeves for large bars.
13. The mechanical splices should be approved by the designer otherwise it is not permitted to
use.
14. Anchor steel bars, whenever required, by bending it around another bar, by extending it to the
point of zero stress, or by bending it to 90 degrees or semicircular hook of specified minimum
radius.
Construction Management
Construction management refers to the processes needed to successfully complete a construction
project. Construction project managers ensure that all elements of a construction project are supported
and executed efficiently throughout the project lifecycle. At its most fundamental level, construction
project management handles the coordination, execution, and planning of a construction project,
whether it’s agricultural, residential, commercial, institutional, industrial, heavy civil, or
environmental.
Construction management typically includes complicated tasks that can shift wildly depending on the
work at hand and requires strong skills in communication, deep knowledge of the building process,
and the ability to problem-solve.
Here we are going to cover two basic concepts which are practical on every construction project
Construction cost estimating using unit rate analysis
Construction works scheduling using duration estimating
Construction cost estimating using unit rate analysis
Unit price construction cost estimating is a method of estimating the cost of a project by dividing the
work into the smallest possible work increments and establishing a unit price for each piece. The unit
price is based on the cost of materials, equipment, and labor for each component or element of the
project. The unit price is then multiplied by the required quantity to find the cost for the increment of
work
Cost breakdown technique/Unit rate analysis is a method of estimating the cost of a project by
dividing it into smaller components or elements and estimating the cost of each component or
element. This technique is used to provide a detailed estimate of the cost of a project and to identify
areas where costs can be reduced.
A cost breakdown is a detailed list of all the costs associated with a project. It includes all the costs of
materials, labor, equipment, and other expenses. A sample cost breakdown
Standard output rates of construction works are predetermined labor output rates and plant output
rates used to calculate the cost per unit of the measured works. These rates can be found from actual
site measurements or standards like “General formula”.
The general formula to calculate the output of construction workers we can use any of the following
formulas.
Output = (Total number of workers) x (Total hours worked) x (Efficiency factor)
Output = Item of work actual executed/Number of persons who did the job
Output = Item of work actual done/Unit price of item
The efficiency factor is a measure of how much work is done in each amount of time. It takes into
account factors such as the skill level of the workers, the quality of the tools and equipment used, and
the working conditions.
Here is an example of an efficiency factor table for different types of construction work:
Excavation 0.60
Material unit cost 575.00 Manpower unit cost 260.00 Equipment unit cost
As you can see in this critical path diagram, project activities are represented by letters and the
critical path is highlighted in green. Tasks F, G and H are non-critical activities with float or
slack. We can also identify task dependencies between the critical path activities, and also
between activities (A, F and G) or (A, H and E), which are parallel tasks.
Critical Path Method (CPM) Formula
Before we learn how to use the CPM formula, we need to understand some key CPM
concepts.
Earliest start time (ES): This is simply the earliest time that a task can be started in your
project. You cannot determine this without first knowing if there are any task dependencies
Latest start time (LS): This is the very last minute in which you can start a task before it
threatens to delay your project timeline
Earliest finish time (EF): The earliest an activity can be completed, based on its duration and
its earliest start time
Latest finish time (LF): The latest an activity can be completed, based on its duration and its
latest start time
Float: Also known as slack, float is a term that describes how long you can delay a task before
it impacts its task sequence and the project schedule. The tasks on the critical path have zero
float because they can’t be delayed
The critical path method formula has two parts; a forward pass and a backward pass.
Use the CPM diagram and the estimated duration of each activity to determine their earliest
start (ES) and earliest finish (EF). The ES of an activity is equal to the EF of its predecessor,
and its EF is determined by the CPM formula EF = ES + t (t is the activity duration). The EF
of the last activity identifies the expected time required to complete the entire project.
Begins by assigning the last activity’s earliest finish as its latest finish. Then the CPM
formula to find the LS is LS = LF – t (t is the activity duration). For the previous activities,
the LF is the smallest of the start times for the activity that immediately follows.
Let’s take a look at a critical path example to better understand how the critical path method
is used in project management. Although it’s high-level, it can help you visualize the
meaning of a CPM schedule.
We will use this critical path diagram to explain the elements that make up the critical path
analysis process. To keep things simple, we’ve already done the calculations for this example
using the CPM formula.
The above critical path method example shows the critical path for getting a website online.
All the tasks that are scheduled to build and launch the website are shown in the rectangular
nodes.
Some of the tasks are being done at the same time as others. For example, the work on
defining a target market is being done as the design is being done and the content for the site
is being drafted.
However, not all these tasks are equally important. Some aren’t critical to getting the site live
by the deadline. That’s where the critical path comes in. It has identified by the colored
arrows all the tasks that must be done in order to complete the project plan on time.
Now that you know the key concepts of the critical path method, here’s how to calculate the
critical path in 8 steps.
Use a work breakdown structure to collect all the project activities that lead to the final
deliverable.
Determine which tasks are dependent on other tasks before they can begin. Use your
judgment and your team members’ feedback. Failing to define task dependencies correctly
makes the critical path method useless.
To use the critical path method, you’ll need to estimate the duration of each task. Use data
from past projects and other sources of information such as subject matter experts.
The critical path uses an algorithm, also referred to as the CPM formula. That algorithm has
two parts, the forward pass and the backward pass. The forward pass is determined by using
the earliest start for each activity (ES) and the earliest finish (EF). The ES of an activity
equals the EF of the one before it. The EF is calculated by EF = ES + t (the duration of an
activity).
The backward pass assigns the last activity’s EF as its latest finish. Then use the CPM
formula to find the LS, which is LF – t. For the activities before that, LF is the smallest of the
start times for the next activity.
The activities with 0 float make up the critical path. All of these critical path activities are
dependent tasks except for the first task in your CPM schedule. All project tasks with positive
slack are parallel tasks to the critical path activities.
Continue to update the critical path diagram as you go through the project execution phase.
These critical path analysis steps determine what tasks are critical and which can float,
meaning they can be delayed without negatively impacting the project schedule. Now you
have the information you need to plan the critical path schedule more accurately and have
more of a guarantee you’ll meet your project deadline.
You also need to consider other changes or constraints that might change the project
schedule. The more you can account for these unexpected events or risks, the more accurate
your critical path schedule will be. If time is added to the project because of these constraints,
that’s called a critical path drag, which is how much longer a project will take because of the
task and constraint.