Group 7 - Assignment Week 7
Group 7 - Assignment Week 7
Group 7 - Assignment Week 7
Diketahui :
Budget : $ 3.200.000
Time : 45 weeks
Jawaban
Activity Preceding Normal Time
A Design - 6
B Build Hull A 12
C Install Ballast Tanks B 2
D Order Mast A 8
E Order Sails A 6
F Order Accessories A 15
G Build Deck C 5
H Coat Hull D 3
I Install Accessories D,E,F,G 6
J Install Mast and Sails D,E,F 2
K Test I,J,H 5
L Sea Trials K,S 8
M Select Crew - 6
N Secure Housing - 3
O Select Crew Equipment M, N 2
P Order Crew Equipment O 5
Q Routine Sail/Maintenance M, N 15
R Crew Maintenance Training D,E,F,G,Q,P 10
S Initial Sail Training R 7
Total Direct Cost
Pembuatan Network
0 A 6
0 Design
0 6 6
0 M 6
4 Select Crew
4 6 10
0 N 3
7 Secure Housing
7 3 10
Dari penyusunan Network ini, diketahui bahwa :
Crash Time Crash Cost ($)
2 -
2 -
0 -
1 200
0 -
2 100
0 -
0 -
1 100
1 40
1 40
1 250
1 10
0 -
0 -
0 -
3 130
1 240
2 150
Per Minggu
Per Minggu
6 B 18 18
0 Build Hull 0
6 12 18 18
6 D 14
11 Order Mast
17 8 25
6 E 12
13 Order Sails
19 6 25
6 F 21
4 Order Accessories
10 15 25
6 Q 21
4 Routine Sail/Maintenance
10 15 25
6 O 8 8
12 Select Crew Equipment 12
18 2 20 20
/ (Normal time - Crash Time)
NORMAL TIME
C 20 20 G 25
Install Ballast Tanks 0 Build Deck
2 20 20 5 25
P 13
Order Crew Equipment
5 25
25 I 31
6 Install Accessories
31 6 37
25 J 27 31 K 36
10 Install Mast and Sails 6 Test
35 2 37 37 5 42
18 H 21
16 Coat Hull
34 3 37
25 R 35 35 S 42
0 Crew Maintenance Training 0 Initial Sail Training
25 10 35 35 7 42
42 L 50 =Waktu Proyek
0 Sea Trials
42 8 50