VTU Exam Question Paper With Solution of 15CV82 Design of Prestressed Concrete Structural Elements July-2021-Sreelakshmi Gopalakrishnan
VTU Exam Question Paper With Solution of 15CV82 Design of Prestressed Concrete Structural Elements July-2021-Sreelakshmi Gopalakrishnan
VTU Exam Question Paper With Solution of 15CV82 Design of Prestressed Concrete Structural Elements July-2021-Sreelakshmi Gopalakrishnan
SOLUTIONS
Solutions ( Diagram should be drawn using the data from the given question )
25 kN 25 kN
𝑃𝑖 𝑃𝑖 𝑒 5.22 × 106
− + = -1
46400 4.52 × 106 4.52 × 106
𝑃𝑖 𝑃𝑖 𝑒
− = -2.153……..(1)
46400 4.52 × 106
1c
Eff span = 16 m
ft = 0, fb = 12 MPa
A = 1200×200 + 1000 × 240 = 480000mm2
𝟏𝟐𝟎𝟎 ×𝟐𝟎𝟎 ×𝟏𝟎𝟎+𝟏𝟎𝟎𝟎 ×𝟐𝟒𝟎 ×( 𝟐𝟎𝟎+𝟓𝟎𝟎)
yt = = 400 mm , yb = 800 mm
𝟒𝟖𝟎𝟎𝟎𝟎
𝟏𝟐𝟎𝟎× 𝟐𝟎𝟎𝟑 𝟐𝟒𝟎 × 𝟏𝟎𝟎𝟎𝟑
Ixx = + (𝟏𝟐𝟎𝟎 × 𝟐𝟎𝟎) × ((𝟒𝟎𝟎 − 𝟏𝟎𝟎)𝟐 ) + + (𝟐𝟒𝟎 × 𝟏𝟎𝟎𝟎) ×
𝟏𝟐 𝟏𝟐
((𝟕𝟎𝟎 − 𝟒𝟎𝟎)𝟐 )
=6.4 × 𝟏𝟎𝟏𝟎 mm4
𝐼𝑥𝑥 𝟔.𝟒 × 𝟏𝟎𝟏𝟎
Zt = = = 160 × 106 mm3
𝑦𝑡 400
• Straight concentric cables induce only horizontal reactions or pure axial forces at the
ends.
• A straight eccentric cable induces axial force plus external moment causing a hogging
moment
• Triangular profiles induce inclined forces at the ends and vertical upward reaction at
the centre (2Psin θ)
• A trapezoidal profile induced inclined forces at the end and two vertical upward
reaction at the point of change in the angle
• A parabolic profile induces inclined forces at the end and an upward UDL
2b
In above the problem, if effective PSF is required to balance the external load, Pe e =
M , Pe = 445.3125 × 106 / 275×1000 = 1619.32kN
Case 2 To balance a total load of 50kN/m on the beam,
P × e = M , Here M = 50 × 102/8 = 625kNm, P = 625/0.275 = 2272.73 kN
2c
Ra = Rb = 300kN
BM @ supports Ms = 40 x 2.52/2 = 125kNm
BM @ centre Mc = 300 x 5 – 40 x 7.52/2 = 375 kNm
Eccentricity at 1) supports , e = Ms / P = 100 mm 2) centre = e = Mc / P = 300 mm
3a
The various reductions of the prestressing force are termed as the losses in prestress. The
losses are broadly classified into two groups, immediate and time-dependent. The
immediate losses occur during prestressing of the tendons and the transfer of prestress to the
concrete member. The time-dependent losses occur during the service life of the prestressed
member.
3b
Es = 210 kN/mm2, P = 800 × 1200 = 960 kN, μ = 0.5, k = 0.0015/m, l = 8000 mm, δL = 2
1
mm, θ = change in slope = 2 × = 0.1
20
Solution
a) Loss due to friction = 𝑃𝑜 (𝜇𝜃 + 𝑘𝐿) =1200 × (0.5 × 0.1 + 0.0015 × 8) = 74.4
N/mm2
𝛿𝐿 2
b) Loss due to anchorage slip = × 𝐸𝑆 = × 2 × 103 = 52.5 N/mm2
𝐿 8000
126.9
% loss = × 100 = 10.54 %
1200
3c
4a
iii) Long term deflection- ( creep effects) – Use Formula by Lin
𝑷𝒕
𝜶𝒇 = [+𝜶𝒊𝒍 − 𝜶𝒊𝒑 × ]×(𝟏+ 𝜱)
𝑷𝒊
𝑷𝒕
or Loss ratio = 0.8 or 80 % , Creep coefficient , 𝜱 = 1.8 , Then
𝑷𝒊
Check it with IS: 1343 code limit of span/ 250 = 6000/250 = 24 mm . It is safe against
deflection since 13.54 mm < 24 mm
4b
5 5
Downward deflection due to self-weight = 𝑤𝑑 𝑙4 = ×
384 𝐸𝑐 𝐼 384 ×33541.02×337.4802×106
1.08 × 95004
= 10.12 mm
5 𝑃 𝑒 𝑙2 5 × 336.7 × 60 ×95002
Upward deflection due to prestressing force = = = 16.78 mm
48𝐸𝑐 𝐼 48×33541.02×337.4802×106
5 5
Downward deflection due to live load = 𝑤𝑙 𝑙4 = ×4 ×
384 𝐸𝑐 𝐼 384 ×33541.02×337.4802×106
95004
= 37.48 mm
5a
Given data: 𝑓𝑐𝑘 = 40 N/mm2 , b = 400 mm, d = 800 mm , l = 16 m, Aps = 2840 mm2,
Effective prestress in the steel 𝑓𝑝𝑒 = 800 N/mm2
𝑓𝑝𝑒 = 0.45 × 𝑓𝑝𝑢 , 800 = 0.45 × 𝑓𝑝𝑢 , 𝑓𝑝𝑢 = 800/ 0.45 = 1777.7 N/mm2
• STEP 1
• STEP 2
𝐴𝑝𝑠 × 𝑓𝑝𝑢
From Table 11, take values of the ratios corresponding to ≈
𝑏 ×𝑑×𝑓𝑐𝑘
𝑓𝑝𝑏 𝑥𝑢
= 0.75 , 𝑓𝑝𝑏 = 0.75 ×0.87 × 1600 =1160 N/mm2 and = 0.653 , 𝑥𝑢 = 0.653
0.87×𝑓𝑝𝑢 𝑑
× 800= 520mm
• STEP 3
5b
𝑓𝑐𝑘 = 40 N/mm2 and 𝑓𝑝 = 1600 N/mm2, 𝐴 𝑝 = 𝐴𝑝𝑠 = 4700 mm2 , Effective prestress in steel
𝑙
𝑓𝑝𝑒 = 1000N/mm2 , =20 m, d = 1600mm, 𝐷𝑓 = 50 mm, 𝑊𝑒𝑏 𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 , 𝑏𝑤 = 300 mm, 𝒃𝒇
𝑑
=1200 mm
𝟓𝟎
= 𝟎. 𝟒𝟓 × 𝟒𝟎 × ( 𝟏𝟐𝟎𝟎 − 𝟑𝟎𝟎) × = 506.25 mm2
𝟏𝟔𝟎𝟎
𝑓𝑝𝑢
• Table 12 , IS 1343 -1980, Then interpolate to get the ratios = 1.16 , 𝑓𝑝𝑢 = 1.16
𝑓𝑝𝑒
𝑥𝑢 𝐴𝑝𝑤 × 𝑓𝑝𝑒
× 𝟏𝟎𝟎𝟎 = 𝟏𝟏𝟔𝟎 and = 0.58 , 𝑥𝑢 = 0.58 × 1600 = mm based on ≈
𝑑 𝑏𝑤 ×𝑑×𝑓𝑐𝑘
= 7163 kNm
Effective span = 15 m, Live load = 12 kN/m, 𝑓𝑐𝑘 = 50 N/mm2 , 𝑓𝑐𝑡 = 41 N/mm2, Loss ratio 𝜂
𝜋
= 0.85, 𝑓𝑝 = 1500 N/mm2, 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑜𝑛𝑒 𝑐𝑎𝑏𝑙𝑒, 𝐴𝑝 = 12 × × 72 = 461.58 mm2 , Area of the
4
concrete section, A = b × d
• Step 1
Assume breadth of the section as b = 250 mm = 0.25 m , let ‘d’ be the depth of the section in
metres
6.25× d ×202
Moment due to self-weight/ gravity, 𝑀𝑔 = = 312.5 × 𝑑 kNm
8
12.0 ×202
Moment due to live load, 𝑀𝑞 = = 600 kNm
8
𝐿𝑜𝑠𝑠 𝑟𝑎𝑡𝑖𝑜 𝜂 = 0. 85
• Step 2
𝑀𝑞 + (1−𝜂 )𝑀𝑔
Use expression for 𝑍𝑏 = (𝜂 𝑓𝑐𝑡 − 𝑓𝑡𝑤 )
… (1)
Equate (1) = (2) , put 𝑓𝑐𝑡 = 41000 kN/m2, tensile stress at working load, 𝑓𝑡𝑤 = 0 since it is
Type 1 members, all tensile stresses are zero
• Step 3
• Step 4
𝑀𝑔 312.5×0.7
𝑓𝑡 = 𝑓𝑡𝑡 - = 0- = - 10937 kN/m2 = -10.9 N/mm2
𝑍𝑡 0.02
• Step 5
Calculate Stress at bottom fibre 𝑓𝑏
1 𝑀𝑔 𝑀𝑞 1 312.5×0.7 600
𝑓𝑏 = (𝑓𝑡𝑤 + + )= (0 + + ) = 48161 kN/m2 = 48.16 N/mm2
𝜂 𝑍𝑏 𝑍𝑏 0.85 0.02 0.02
• Step 6
𝑨 ×(𝒁𝒕 𝒇𝒕 + 𝒁𝒃 𝒇𝒃 )
𝑷𝒓𝒆𝒔𝒕𝒓𝒆𝒔𝒔𝒊𝒏𝒈 𝑭𝒐𝒓𝒄𝒆 , 𝑷 = (𝒁𝒕 + 𝒁𝒃 )
, A = 0. 𝟐𝟓 × 𝟎. 𝟕 = , 𝑍𝑏 = 𝑍𝑡 = 0.02 , 𝑓𝑡 =
P = 3257.12 kN
• Step 8
No of cables required =
3257000
Total 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑎𝑏𝑙𝑒𝑠 = = 2171.41
1500
Number of cables =Total 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑎𝑏𝑙𝑒𝑠 / Area of one cable = 2171.41/ 461
Design is over
7a
In the case of RCC members when subjected to super imposed loads, shear forces are developed
at the loaded member. Due to these shear force and stresses are developed in the member. Shear
stress will be at the neutral axis and is minimum at the extreme fibres. The shear stress at any
depth in the cross section is calculated using the equation.
𝐹 ×𝐴× 𝑦̅
τ=
𝐼 ×𝑏
F is the shear force in KN
𝐴 × 𝑦̅ moment of area above the level at which shear stress is required about the neutral axis
I is Moment of inertia
The effect of this shear stress is to induce the principal tensile stress on the diagonal planes.
Due to diagonal tensile stress, diagonal cracks are developed at the support section. To reduce
the diagonal cracks, the diagonal tension can be made compressive by following 3 ways
In general, there are three ways of improving the shear resistance of structural concrete
members by prestressing techniques:
1. Horizontal or axial prestressing
2. Prestressing by inclined or sloping cables
3. Vertical or transverse prestressing
Axial prestressing reduces the principal stresses considerably when compared with the
members without prestressing. Furher inaddition to axial prestressing, transverse or vertical
prestressing is used it is possible to nullify the principal tension itself. In case the cables are
placed as per the profile obtianed bya load balancing approach it results in the most desirable
system of forces in concrte ie entire section of concrete will be subjected to uniform
compressive state of stress at support.
7b
Calculation of slope of the cable
4 ×𝑒
Calculation of slope at support y = (𝐿𝑥 − 𝑥 2 )
𝐿2
𝑑𝑦 4 ×𝑒
= (𝐿 − 2𝑥 )
𝑑𝑥 𝐿2
𝑑𝑦 4 ×𝑒 4 ×100 1
At support x =0, θ = = = = , ( for small angle and zero shear let us take directly
𝑑𝑥 𝐿 8000 20
1
sin θ = )
20
8a
450 × 10003 300 × 7003
𝐼= − = 2.8975 × 1010 𝑚𝑚4
12 12
4 ×𝑒
Calculation of slope at support y = (𝐿𝑥 − 𝑥 2 )
𝐿2
𝑑𝑦 4 ×𝑒
= (𝐿 − 2𝑥 )
𝑑𝑥 𝐿2
𝑑𝑦 4 ×𝑒 4 ×300
At support x =0, θ = = = = 0.06 radians
𝑑𝑥 𝐿 20000
180
θ in degrees = 0.06 × = 3.42o
𝜋
= 1.594 N/mm2
• At junction of the web
150
𝐹 ×𝐴× 𝑦̅ 182640 ×( 450 × 150 ×(500− 2 )
τ= = , ( taking b = bw)
𝐼 ×𝑏 2.8975 ×1010 ×150
= 1.207 N/mm2
• At junction of the flange
150
𝐹 ×𝐴× 𝑦̅ 182640 ×( 450 × 150 ×(500− 2 )
τ= = , ( taking b = bf)
𝐼 ×𝑏 2.8975 ×1010 ×450
= 0.402 N/mm2
1250000
𝑓𝑥 = = 5.21 N/mm2
240 x 1000
5.21 1
𝑓𝑚𝑎𝑥,𝑚𝑖𝑛 = ± √(5.212 + 4 × 1.5492 )
2 2
= 2.605 ± 3.504
𝑓𝑚𝑎𝑥 = 2.605 + 3.504 = + 5.6 N/mm2 ( compression)
𝑓𝑚𝑖𝑛 = 2.605 − 3.504 = - 0.449 N/mm2 ( tension)
1250000
𝑓𝑥 = = 5.21 N/mm2
240 x 1000
5.21 1
𝑓𝑚𝑎𝑥,𝑚𝑖𝑛 = ± √(5.212 + 4 × 0.402 2 )
2 2
= 2.605 ± 2.63
𝑓𝑚𝑎𝑥 = 2.605 + 2.63 = + 5.24 N/mm2 ( compression)
𝑓𝑚𝑖𝑛 = 2.605 – 2.63 = - 0.031 N/mm2 ( tension)
1250000
𝑓𝑥 = = 5.21 N/mm2
240 x 1000
5.21 1
𝑓𝑚𝑎𝑥,𝑚𝑖𝑛 = ± √(5.212 + 4 × 1.207 2 )
2 2
= 2.605 ± 2.87
𝑓𝑚𝑎𝑥 = 2.605 + 2.87 = + 5.47 N/mm2 ( compression)
𝑓𝑚𝑖𝑛 = 2.605 – 2.87 = - 0.266 N/mm2 ( tension)
8b
bw = 200 mm,D = 2000 mm,L =40 m,e = 750 mm @ centre,A = 0.88 x 10 6 mm2, P = 1200
kN, Loss ratio = 0.8 , fy = 415, Peff = 0.8 x 1200 = 9600 kN, 𝑓𝑐𝑘 = 60 MPa
V = 2850 kN
𝑓𝑡 = 0.24 √ fck = 1.86 N/mm2
𝑃𝑒𝑓𝑓 9600000
𝑓𝑐𝑝 = = = 10.91 𝑁/𝑚𝑚2
𝐴 0.888 ×10 6
𝑑𝑦 4 ×𝑒 4 ×750
θ= = = = 0.075 radians ≈ sinθ
𝑑𝑥 𝐿 40000
= 0.676 × 200 × 2000 × √(1.862 + 0.8 × 10.91 × 1.86 ) + 9600 × 0.075 = 1909.32
kN < 2850kN
Let us assume 12 mm Φ and two legged stirrups and effective cover 100 mm
𝐴𝑠𝑣 = 2 x π / 4 x 122 = 226.19 mm2
0.87 ×226.19 ×415×1900
𝑆𝑣 = (2850−1909.32)×1000
= 164.95 mm < 0.75 × d = 1425
Hence Ok
Use 12 mm Φ # two legged stirrups @ 150 mm c/c
9a
Prestressed concrete contains tendons which are typically stressed to about 1000 MPa. These
tendons need to be anchored at their ends in order to transfer (compressive) force to the
concrete. In pretensioned concrete, the anchorage consists of a bonded length of tendon, in
direct contact with the concrete. In post-tensioned concrete, an achorage plate is used, which
bears onto the concrete over a relatively small area.The tendon is connnected to the plate either
through wedges, button-heads or other methods. The plate itself then bears on the concrete.
The plates employed for this are very much smaller than the area of concrete which is to be
compressed. Therefore, a redistribution of stress occurs behind the anchorage plate as the
compression trajectories spread out to form uniform stress patterns some distance into the
concrete, according to St Venant's Principle. It is the distance over which this redistribution
occurs that is of interest to the Engineer. This disturbed region is known as the Anchorage
Zone. The state of stress in the anchorage zone is extremely complex. It consists of severely
curved trajectories, perhaps interfering with 'secondary' stresses due to bearing supports.
Therefore, it is in the Engineer's interest to ensure two things in this zone.
1. The zone must not crack at the serviceability limit state (this would allow the ingress of
water, leading to possible corrosion problems), and
10 a
In a composite construction, precast prestressed members are used in conjunction with the
concrete cast in situ, so that the members behave as monolithic unit under service loads.
Generally, the high-strength prestressed units are used in the tension zone while the concrete,
which is cast in situ of relatively lower compressive strength, is used in the compression zone
of the composite members. The composite action between the two components is achieved by
roughening the surface of the prestressed unit on to which the concrete is cast in situ, thus
giving a better frictional resistance, or by stirrups protruding from the prestressed unit into the
added concrete, or by castellations on the surface of the prestressed unit adjoining the concrete
which is cast in situ.
The phenomenon of differential shrinkage between the concrete cast in situ and the prestressed
units also contributes to the monolithic action of the composite member.
The advantages in using precast prestressed units in association with the in situ concrete are:
1. Appreciable saving in the cost of steel in a composite member compared with a reinforced
or prestressed concrete member.
2. Sizes of precast prestressed units can be reduced due to the effect of composite action.
3. Low ratio of size of the precast unit to that of the whole composite member.
4. In many cases, precast prestressed units serve as supports and dispense with the form work
for placement of in situ concrete.
5. Composite members are ideally suited for constructing bridge decks without the disruption
of normal traffic.
10 b
1. Section properties of the pretensioned beam
P = 150 kN
2×𝑃 2 × 150000
Thus, stresses due to prestressing force becomes = + = = 15 N/mm2 at the bottom
𝐴 20000
Live load on the composite section = 0.4 × 1.0 × 8000 = 3200 N/m
3200 × 52
Maximum live load moment = = 10000 × 103 Nmm
8
𝑀𝐿 10000 × 103
At bottom = = = 7.85 N/mm2 ( tension)
𝑍𝑏 128× 104
If the pretensioned beam is propped, the self-weight of the slab acts on the composite
section
Moment due to slab weight = 1200 Nm
Stress due to this moment in the composite section
𝑀𝑑 1200 × 103
At top = = = 0.53 N/mm2 ( compression)
𝑍𝑡 225× 104
𝑀𝑑 1200 × 103
At bottom = = = 0.94 N/mm2 ( tension)
𝑍𝑏 128× 104
The distribution of stresses for the various stages of loading for the propped and
unpropped construction is shown in the figure below