Substation Inspection Report - Khali
Substation Inspection Report - Khali
Yes
vii Whether oil in conservator is adequate.
Yes
viii. Whether oil in OLTC conservator adequate.
ix. Last oil BDV checked Date Not Checked
x BDV Value Nill
xi Last oil filteration Date Nill
xii. Earthing intact Neutral Nill
xiii Earthing intact Body Nill
3) Breaker
a) 33 KV side
i. No. of breakers provided :- 1 No
ii. Type :- VCB
iii. Capacity :- 33 KV
iv. No of breakers in service :- 1 NO
v. Problems observed :- Nill
(Attach separate sheet if reqd.) :-
vi. Addl. Breakers reqd :- Yes
Purpose :- Backfeeding Supply 33 kv ashwi line
b) 11 KV side
i. No. of breakers provided :- 4 no
ii. Type :- VCB
iii. Capacity :- 11 KV
iv. No of breakers in service :- 4 No
v. Problems observed :- yes
11 kv side -
i. No of CTs provided 09 nos :- 4 Set
CTR :- 400-200-100/5-5A
4) P.T.-
33kv side-
i. No of PTs provided :- 1 Set
ii. No of PTs in Service :- 1 Set
iii. No of PT required :- No
11 kv side-
i. No of PTs provided :- 1 Set
ii. No of PTs in Service :- 1 Set
iii. No of PT required :- No
5) Relaying & metering –
i. Whether metering provided 33 kv side :- No
11 kv side :- No
ii. Meters not in service 33 kv side :- Nill
11 kv side :- Nill
iii. Reasons for not in service 33 kv side :- NA
11 kv side :- NA
iv. Relays provided Type :- Digital
v. Relays not in service :- Nill
vi. Relays to be upgraded :- No
6) Battery & Charger
i. Battery Charger :- Fail
ii. Battery Condition :- New
iii. Cells to be replaced :- No
7) Sub Stn Capacitor bank
i. Whether equipped with S/Stn. capacitor bank
If yes a) Capacity :- 2.4 MVAR
b) Working :- 1.2 MVAR
If no, a) Dt.of failure :- 24/04/2023
b) Reasons for non working :- Sell Damaged
Cells damaged. :- 1 Nos
NDCT/RVT Faulty. :- No
Breaker /Relay Faulty. :- No
Cable Faulty. :- No
Others specify :- No
8) TESTING HISTORY:-
i Substation last checked by testing DIV :- 21/07/2023
All SDT Bypassed, OLTC Motor Burnt, OLTC
:- Panal Wiring Burnt, Re Erthing of all SDT
ii Remarks therein Requierd
iii Whether complied :-