4 - Unit Warm Start-Up (CNK 12 M Ove Oi 112C)
4 - Unit Warm Start-Up (CNK 12 M Ove Oi 112C)
4 - Unit Warm Start-Up (CNK 12 M Ove Oi 112C)
03) FUS
B 08/07/03 Jp Mo Bad Reviewed further to Client’s letter n°1886(21.05.03) FUS
A 21/03/03 Jp Ch Bad First issue PRE
REV DATE AUTH. CHECK. APPR. BY MODIFICATIONS STATUS
BY
TEAS
TÜRKIYE ELEKTRIK ÜRETIM - ILETIM A. S.
SANTRALLAR PROJE VE TESIS DAIRESI BASKANLIGI
TURKISH ELECTRICITY GENERATION - TRANSMISSION Co.
CONSORTIUM
PROJECT DWG. N° :
DESIGN SUBCONT.
SCALE : - Rev. No
Drawing N° CNK 1 2 M - - - OV EO I 11 2
SIZE : C
ALSTOM Power
ALL RIGHT PERTAINING TO THE REPRODUCTION, TRANSFORMATION AND USE OF THIS DOCUMENT
IN ANY FORM OR MANNER REMAIN THE EXCLUSIVE PROPERTY OF ALSTOM POWER
abcd
Power
Plant Segment
Engineering
SUMMARY
_____
1 PURPOSE
3 INITIAL STATE
4 UNIT START-UP
Reference documents :
- Boiler and steam turbine start-up curve CNK 00 M --- --- SC 020
- General system design manual CNK 00 M OVE --- DM 001
- Master block control CNK 01 M KCA --- DM 001
This document is a general guidance for experienced and authorised operators. It lists the main
operations to be carried out for the warm start-up of the unit, with auxiliary-steam not available from
the other unit.
To start the different equipment, the operator refers to the system operating instructions of the
relevant systems.
This procedure is arranged to use with DCS in an specific page preview. When will notified in the
Operating Instructions form to start or to put or to select or to adjust or to open or to close or to check
any plant or system or equipment the operator would perform as following :
Future conditions may dictate the requirement to implement changes to this document.
All the unit load figures indicated in the loading up phase are for guidance only. Specific figures will
be determined under actual operating conditions.
The unit warm start-up is applied if one or until all of the following conditions exist :
- when the unit has been shutdown for more than 8 hours up to less 40 hours,
- when the lower bed boiler temperature is between 100 and 650 °C.
The turbine is run up and synchronised using steam flow through the IP and LP turbines only, with
the HP turbine isolated, bypassed and under vacuum. HP steam flow is established at nominally
24 MW load.
If need, the HP turbine and valve chests are pre-warmed by pressuring with cold reheat steam
towards a value of 20 to 22 bar a. to reduce thermal stresses when normal steam flow is introduced
to the HP turbine. Turbine speed is limited to 1000 rpm until pre-warming is completed.
Run up rates are automatically limited with IP governing valves controlling the steam admission
depending on initial the IP cylinder metal reference temperature. If need, run-up rates are limited to :
The operator, depending on the HP cylinder metal reference temperature sets loading rates.
The turbine then operates in a conventional manner with steam admission being controlled by the
HP governing valves.
If need, the turbine load is held at block load nominally 24 MW to allow the IP turbine thermal stress
to decay before the loading is resumed.
The entire auxiliaries, boiler, turbine, balance of plant systems have been pre-start checked as
indicated in the documents :
- CNK 12 M OVE OI 101
- CNK 12 M OVE OI 104
- CNK 12 M OVE OI 105
- CNK 12 M OVE OI 106
and are ready to operate or in operation.
4 UNIT START-UP
500
REHEATER OUTLET TEMPERATURE°C
450
350
300
MINIMUM STEAM TEMPERATURE
AT REHEATER OUTLET
250
200
0 50 100 150 200 250 300 350 400 450 500 550
IP INNER CASING REFERENCE TEMPERATURE BEFORE START UP °C FROM AVERAGE OF MAB30CT605XV1 & MAB30CT610XV1
450
MAXIMUM STEAM TEMPERATURE
AT SUPERHEATER OUTLET
400
300
250
0 50 100 150 200 250 300 350 400 450 500 550
HP CASING REFERENCE TEMPERATURE BEFORE HP CYLINDER INTRODUCTION °C FROM AVERAGE OF MAA30CT605XV1 & MAA30CT610 XV1
stop
t/h bar °C %
oil
oil
600
100
200
500
ST-load
Synchronisatio
Turbine start
Coal feeding
550
180
450
90
n
+
500
160
400
80
450
SH-Temp.
140
350
70
5,3 bar/min
400
Steam-flow
120
300
60
350
Steam-pressure
2°C/min
Temperature
Steam-flow
RH-Temp.
300
100
250
50
SH-Pressure
250
200
80
40
200
3000 rpm
150
60
30
150
ST-speed
100
40
HP bypass
20
100
Fuel-rate
20
50
RH-Pressure
10
50
LP bypass
0
0
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220
Time (min)
CAN - 2 x 160 MW Appr. Bdj
COAL FIRED THERMAL PLANT Check Pm
Power WARM START-UP CURVE ( 08 to 40h shutdown ) Author Sb
Steam Power Plant N° CNK 00 M --- SC 020 D 04/03/02