Voltage Band Limitations: Dominik - Geibel@iwes - Fraunhofer.de Thorsten - Buelo@sma - de Jdacosta@uni-Kassel - de
Voltage Band Limitations: Dominik - Geibel@iwes - Fraunhofer.de Thorsten - Buelo@sma - de Jdacosta@uni-Kassel - de
Paper 0234
Figure 1: Voltage profiles in the distribution network (MV+LV) for different load and feed-in cases.
Electronic Voltage Controller (EVC) a factor of 1.5 up to 2. This underlines the importance of
Another approach for influencing the voltage profile of a reactive power capability for PV-inverters.
LV network is to use power electronic units which are able In long feeders however the voltage regulation by reactive
to inject an additional series voltage into a feeder. As power provision is relatively limited. In this case
described in [5], such an EVC can be based e.g. on the controllable MV/LV transformers are preferred. Herewith,
concept of the Unified Power Flow Controller. EVCs are an increase by a factor of about 2.7 is reached. This factor
able to control the voltage of a feeder steplessly and can is dependent on the dimensioning of the transformer taps
be integrated into a network either as part of the substation but nearly independent of the network data at the network
or as distributed equipment in LV feeders. Therefore, one connection point as long as constraints of the network
advantage of this approach is the possibility to install an assets do not apply.
EVC in a specific feeder without necessarily affecting the LV network Case-Study
whole network. This can be more favourable than a smart
Figure 3 shows a simplified network diagram of the
substation in case of networks where some feeders exhibit
studied LV network with currently already 236 kW of PV-
a high penetration of DG while others are dominated by
systems installed. Within this LV network a case study is
loads.
carried out, in order to examine the potential for additional
PV-systems applying afore mentioned voltage regulation
ASSESSMENT OF VOLTAGE REGULATION strategies. At first additional PV-systems are distributed
METHODS randomly within the network area. In a second case study
The different voltage regulation methods are evaluated the application of an EVC in a long branch of the network
with regard to the possible increase of the hosting capacity with a high feed-in at the end of the feeder is evaluated.
of the LV network. At first generic networks are being Sk“ = 250 MVA
Psik = 69,2°
used. In a next step, the methods are applied to a real PV 18,8 kW PV 34,0 kW
Generic networks
Bus 3
EVC
A homogeneous 4-feeder network with NAYY 4x150mm² PV 16 kW
Bus 2
Existing PV-systems
feeder. By varying the length of the feeder the short circuit PV 19,4 kW
EVC
50
switchable MW/LV transformer
An even higher share of PV-systems can be reached with a
Factor 2.7
40
P_PV > SrT transformer controllable MV/LV transformer; an increase of up to
30 160% becomes possible. As the potential for new PV-
Factor 1.5 - 2
systems has been limited by the voltage rise in the case of
20
cosM = 1 reactive power, now the limitation is reached due to the
10 power ratings of the network components.
45 40 35 30 25 20 15
Network impedace angle in °
Furthermore it is found that a combination of controllable
MV/LV transformer and reactive power provision does
Figure 2: Maximum permissible installed capacity.
not increase the hosting capacity, since the additional
Indicated points refer to feeder length 100m, 300m,
loading through the reactive power reduces the capacity
600, 900m. Sk and <k refer to the weakest point in the
for active power injection.
network.
3.5 1.03
Voltage [p.u.]
Hosting capacity restricted by limits of the network components
Hosting capacity of LV network in relation to
bus 4
already installed active power in kW/kW
3
1.02 bus 2 Additional
Hosting capacity limited by voltage rise (3%) 617 kW 595 kW 588 kW PV 34kW
2.5
Existing PV-systems 1.01
2 434 kW
1.5 1.00
294 kW
270 kW
236
1
0.99
0.5
0.98
0 bus 3
Existing PV- New PV-systems New PV-systems All PV-systems Active substation Active substation Active substation
EVC (Du= -4%)
systems
with cos φ = 1
with cos φ = 1 with cos φ = 0.90 with cos φ = 0.90 with dU = 10% with dU = 7.5% with dU = 5.0%
0.97
All PV-systems New PV-systems New PV-systems 0 200 400 600 800
with cos φ = 1 with cos φ = 0.90 with cos φ = 0.90 Distance from the substation [m]
Figure 4: Increase of hosting capacity using different voltage Figure 5: Voltage profile of long feeder with
regulation methods in a real LV network EVC installed at bus bar 3