Method Statement For UPS System Testing and Commissioning
Method Statement For UPS System Testing and Commissioning
Method Statement For UPS System Testing and Commissioning
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages
are hereby superseded and are to be destroyed.
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 4 of 15
1.0 PURPOSE
The purpose of generating this method statement is to define the procedure step by step to implement the
correct practices for UPS System Testing and Commissioning through the guidelines contained herein so
as to ensure that the job execution complies with specification and serves the intended function to
satisfactory level where applicable in the building of the project.
2.0 SCOPE
This method statement covers the Commissioning & Testing of the Uninterruptable Power Supply.
3.0 REFERENCE
4.0 DEFINITIONS:
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
- Project Manager is the overall responsible for the project in terms of work execution, safety, planning
& quality. The Project Manager will maintain the planning progress and coordination of works with
the main contractor.
- The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
- Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
5.2 Construction Manager
- The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
- Provision of all necessary information and distribution of responsibilities to his Construction team.
- The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
- The constant coordination with the Safety Engineer to ensure that the works are carried out in safe
working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by the Consultant.
- Efficient daily progress shall be obtained for all the equipment and manpower.
- He will engage in the work and check the same against the daily report received from the
Foremen.
- The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 6 of 15
- The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
- Check and insure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available resources in coordination
with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
- The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working environment on the
work activity.
- Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
- Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material delivery to the site
and keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and
concerned Engineer.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 7 of 15
6.0 EQUIPMENTS
7.0 PROCEDURE
7.1 Safety
- Ensure only trained/ Authorised & licensed persons only shall operate the power tools and do the
Testing job.
- Necessary PPE to be worn while working in energized to be worn while working in energized
circuits.
- Ensure adequate lighting is provided in the working area at night time and if inside the building
area to be well illuminated.
- Ensure service area/work area openings are provided with barricade, tape, safety nets and warning
signage to be provided.
- Ensure LOTO procedure to be followed and implement comprehensive logout & tag out during
execution of work.
- Emergency evacuation plan and procedure to be developed prior to start of testing.
- PTW to be applied and obtained to start work on the required area.
- Calibrated Instruments only to be used.
- All works in progress should be constantly monitored by Supervisors / QA/QC Engineers / Project
managers, etc. for quality workmanship / cost saving methods / professionalism / Production /
Work Safety procedures and all works should be as per approved drawings and method statements
for UPS and Accessories Installation
- Ensure that all tools, devices and equipment needed to complete the test. Site test requiring a load
bank shall be performed. The load bank shall be furnished by the supplier, if required. Refer to
the attached Procedure for the Load bank testing on Section 8.2 in Attachments.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 8 of 15
Functional tests on all equipment to demonstrate the system constructed are fully in
compliance with the specification section 263354 clause 8.D. and manufacturer
recommendation;
Simulation tests to simulate all alarms and faults;
System bypass, mains failure simulation test; and
Full load test to verify the battery capacity.
Noise level test;
A- Visual Inspection:
C- Testing
Functional test:
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 10 of 15
- UPS System is working without any alarms or any fault and the switches in correct position and two
units are working.
- 'Normal Operation': Rectifier is charging the batteries and supplying the inverter which provides a pure
sinusoid wave with stabilized O/P voltage& frequency.
(Egymatec will calibrate the Units by checking the UPS setting & configuration using Expert software).
Load Test:
Provide a load. 'customer Load'
A- System Load Test (_______% load) 'Provide this test between 10 to 15min'.
- Putting _____Kwatt. 'by connect the load '.
- Take measurement.
- Fill format no. (1).
- Due to several UPS rating, Supplier will testing them using a different rating/model of dummy
load to be suitable with the UPS rating.
- After connecting the dummy load to the UPS, we are going to take measurement with Zero load
then increase the load to reach 25% of the UPS rating then take measurement for 25%, then
increase the load to reach 50% of the UPS rating then take measurement for 50%, then increase
the load to reach 75% of the UPS rating then take measurement for 75%, then increase the load to
reach 100% of the UPS rating then take measurement for 100%.
- For test the backup time:
a) The batteries shall be fully charged without any power interruption for at least 8 hours.
b) the dummy load will be adjustable to reach the same current load 'as per battery calculation'.
c) cut off the power and take measurement.
Format 1
L3 400 V+ 1%
O/P Current: I1 Depend on load
I2 Depend on load
I3 Depend on load
O/P Frequency 50 Hz + 0.1%
O/P Power
Comments:
Approved / Retest :
Sign:
Approved / retest :
Sign:
Approved / retest :
Sign:
- Practically the noise level test is usually done in the factory due to special requirement which may
affect the result of it.
- The test of the noise level can be done only after providing us a special room with shall be:
Then we will measure the noise level without UPS and with UPS carrying the full load then
muses these values to get the real value of the noise level.
8.0 ATTACHMENTS