Method Statement For UPS System Testing and Commissioning

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

PROJECT NAME

TITLE Ref. No. :


METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 1 of 15

METHOD STATEMENT FOR

UPS SYSTEM TESTING & COMMISSIONING


PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 2 of 15

REVISION RECORD

This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages
are hereby superseded and are to be destroyed.

Rev. No. By Chkd. Approvals Description and Page Numbers of Revisions


Date
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 3 of 15

CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENT

7.0 PROCEDURE

8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 4 of 15

1.0 PURPOSE

The purpose of generating this method statement is to define the procedure step by step to implement the
correct practices for UPS System Testing and Commissioning through the guidelines contained herein so
as to ensure that the job execution complies with specification and serves the intended function to
satisfactory level where applicable in the building of the project.

2.0 SCOPE

This method statement covers the Commissioning & Testing of the Uninterruptable Power Supply.

3.0 REFERENCE

 Approved Shop drawings for power distribution.


 Specifications
 Project Quality Plan
 Project HSE plan
 Manfacturer’s Data sheets & Manufacturer recommendations.
 Regulation of the local Electrical Authority,
 Requirements of Civil Defense Department,
 Approved Material submittal

4.0 DEFINITIONS:

PQP : Project Quality Plan


PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
SK : Store Keeper.
WIR : Inspection and Test Request
MIR : Material Verification Record.
MAR : Material Approval Request
UPS : Uninterruptible Power Supply.
I/P : Input.
O/P : Output.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 5 of 15

5.0 RESPONSIBILITIES:

Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK

5.1 Project Manager

- Project Manager is the overall responsible for the project in terms of work execution, safety, planning
& quality. The Project Manager will maintain the planning progress and coordination of works with
the main contractor.

- The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.

- Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
5.2 Construction Manager

- Construction Manager is responsible to supervise and control the work on site.


- Coordinating with QA/QC Engineer and site Team and foremen for all activities on site.
- Control and sign all WIR’s before issuing to Consultant approval.

5.3 Site Engineer

- The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
- Provision of all necessary information and distribution of responsibilities to his Construction team.
- The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
- The constant coordination with the Safety Engineer to ensure that the works are carried out in safe
working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by the Consultant.
- Efficient daily progress shall be obtained for all the equipment and manpower.
- He will engage in the work and check the same against the daily report received from the
Foremen.
- The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 6 of 15

5.4 QA/QC Engineer (MEP):

- The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
- Check and insure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.

5.5 Site Foreman

- The carrying-out of work and the proper distribution of all the available resources in coordination
with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.

5.6 Safety Officer

- The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working environment on the
work activity.
- Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
- Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
- Ensure safe access to site work at all times.

5.7 Store Keeper (SK)

- Responsible for overall Store operations in making sure to store the material delivery to the site
and keep it in suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and
concerned Engineer.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 7 of 15

6.0 EQUIPMENTS

6.1 Tool box.


6.2 UPS and accessories.
6.3 Battery Cabinets.
6.4 Dry Contact.
6.5 Multimeter.
6.6 Tester.
6.7 Load Bank.
6.8 Netvision card. “SNMP Card”.
6.9 Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and
safety gloves to insure maximum ability of safe work and dust mask when required.

7.0 PROCEDURE

7.1 Safety

- Ensure only trained/ Authorised & licensed persons only shall operate the power tools and do the
Testing job.
- Necessary PPE to be worn while working in energized to be worn while working in energized
circuits.
- Ensure adequate lighting is provided in the working area at night time and if inside the building
area to be well illuminated.
- Ensure service area/work area openings are provided with barricade, tape, safety nets and warning
signage to be provided.
- Ensure LOTO procedure to be followed and implement comprehensive logout & tag out during
execution of work.
- Emergency evacuation plan and procedure to be developed prior to start of testing.
- PTW to be applied and obtained to start work on the required area.
- Calibrated Instruments only to be used.

7.2 Testing and Commissioning procedure:

7.2.1 Pre-commisioning procedure:

- All works in progress should be constantly monitored by Supervisors / QA/QC Engineers / Project
managers, etc. for quality workmanship / cost saving methods / professionalism / Production /
Work Safety procedures and all works should be as per approved drawings and method statements
for UPS and Accessories Installation

- Ensure that all tools, devices and equipment needed to complete the test. Site test requiring a load
bank shall be performed. The load bank shall be furnished by the supplier, if required. Refer to
the attached Procedure for the Load bank testing on Section 8.2 in Attachments.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 8 of 15

- To follow manufacturer recommendations attached for the requirements from Electrical


Contractor – Sub-Contractor- before start the testing and commissioning of the system.
- Start-up and Site Test: On-site inspection and testing of the UPS system after installation shall be
provided by the Sub-contractor and included in the Contract.
- The site acceptance test shall be detailed and performed to ensure that the equipment will perform
with the actual load as installed.
- All inspection and testing shall be performed and conformed by manufacture in the presence of
Consultant.
- All works shall be inspected for conformance to specification and Authority Regulations

Requirement from Electrical Contractor before Commissioning & testing:

Description OK/ Not OK


 UPS room must be large enough.
 UPS location should have a non-flammable floor.
 UPS Location should be dry, clean and dust-free.
 UPS Location should be with Air condition 20-25C. AC air circulation
in the room should be sufficient to ensure a constant temperature to the
UPS and to the batteries.
 All Power & Network Cables are tested.
 Installation of I/P & O/P Power Cables.
 For netvision, Each UPS System IP to connect it to the Local Network.
'if Applicable'
Comment:

7.2.2 Site Commissioning and Testing:

- Site Acceptance Test


- The site acceptance test shall include:
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 9 of 15

 Functional tests on all equipment to demonstrate the system constructed are fully in
compliance with the specification section 263354 clause 8.D. and manufacturer
recommendation;
 Simulation tests to simulate all alarms and faults;
 System bypass, mains failure simulation test; and
 Full load test to verify the battery capacity.
 Noise level test;

7.2.3 Procedures / Method:

A- Visual Inspection:

Description OK/ Not OK


Carry out a visual inspection of outside & inside System.
Visually check Central PC to ensure that all equipment is installed
in line with Approved Construction drawing & Approved Material
Submittal.
Check AC Connection. 'I/P & O/P'
Check DC connection if external Battery available.
Check UPS component 'i.e. rectifier, inverter and static switches'
are secure and that no damage has occurred.
o Record Results on commissioning.

B- Start Up & Commissioning

Description OK/ Not OK


Re - Check UPS component 'i.e. rectifier, inverter and static
switches' are secure and that no damage has occurred during
transit or installation. Check that all connections are tight
(including flat cables). Verify that all PCB switch positions are
correct.
Check that all external connections have been made in accordance
with supplied drawings.
Check that installation cables are correctly sized and that
fuses/circuit breakers are suitable rated.
Check phasing and polarity of all connection and phase rotation.
Check that all UPS associated equipment is fully earthed.
Check the input voltage and the input frequency.
Check Alarms.
Check the general system operation is satisfactory
Check load connections for testing.

C- Testing

Functional test:
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 10 of 15

- UPS System is working without any alarms or any fault and the switches in correct position and two
units are working.

- 'Normal Operation': Rectifier is charging the batteries and supplying the inverter which provides a pure
sinusoid wave with stabilized O/P voltage& frequency.

(Egymatec will calibrate the Units by checking the UPS setting & configuration using Expert software).

No load test (provide this test between 5 to 10min).


- Putting '0' Zero load.
- Take measurement.
- Fill format no. (1).

Load Test:
Provide a load. 'customer Load'

A- System Load Test (_______% load) 'Provide this test between 10 to 15min'.
- Putting _____Kwatt. 'by connect the load '.
- Take measurement.
- Fill format no. (1).

- Due to several UPS rating, Supplier will testing them using a different rating/model of dummy
load to be suitable with the UPS rating.
- After connecting the dummy load to the UPS, we are going to take measurement with Zero load
then increase the load to reach 25% of the UPS rating then take measurement for 25%, then
increase the load to reach 50% of the UPS rating then take measurement for 50%, then increase
the load to reach 75% of the UPS rating then take measurement for 75%, then increase the load to
reach 100% of the UPS rating then take measurement for 100%.
- For test the backup time:
a) The batteries shall be fully charged without any power interruption for at least 8 hours.
b) the dummy load will be adjustable to reach the same current load 'as per battery calculation'.
c) cut off the power and take measurement.

Format 1

Load Test: Excepting Value Reading


Load rating Existing Load
I/P Voltage: Ph-Ph 400 +15% / + 20%
I/P Voltage: L1 Depend on mains
L2 Depend on mains
L3 Depend on mains
I/P Current: I1 Depend on load
I2 Depend on load
I3 Depend on load
I/P Frequency 45Hz – 65Hz
I/P Power
O/P Voltage: L1 400 V + 1%
L2 400 V+ 1%
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 11 of 15

L3 400 V+ 1%
O/P Current: I1 Depend on load
I2 Depend on load
I3 Depend on load
O/P Frequency 50 Hz + 0.1%
O/P Power
Comments:

Approved / Retest :

Sign:

B- Battery discharge test:


- With same load and same position.
- Cut off the Input mains from UPS.
- Take measurement.
- Fill format no. (2).
Format 2

Battery Discharge test at_____% load:

Measurement 0 min 10min 20min 30min 40min 50min 60min


Battery capacity:
Active power output:
O/P Voltage: L1
L2
L3
O/P Frequency:
O/P current: I1
I2
I3
Temperature:
Comments:

Approved / retest :

Sign:

D- Return to Normal Operation:

- Return the Input mains to UPS.

Transfer Test Describe OK/ Not OK


Automatic Load transfer to bypass Circuit.
Manual Load transfer to Manual bypass.
Normal Load transfer from Manual bypass
to Normal.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
UPS System Testing and Commissioning
Page 12 of 15

Approved / retest :

Sign:

E- Noise Level Test:

- Practically the noise level test is usually done in the factory due to special requirement which may
affect the result of it.
- The test of the noise level can be done only after providing us a special room with shall be:

1. Isolated from noise.


2. one meter length space from each direction around the UPS also one meter from the top.

Then we will measure the noise level without UPS and with UPS carrying the full load then
muses these values to get the real value of the noise level.

Noise Level Test Value Measurement 'dBA'


- UPS with 100% load. '1'
Measure the noise level @ 1meter
- UPS with 0% load. '2'
Measure the noise level @ 1meter
UPS Noise level = '1' - '2' = '3'

8.0 ATTACHMENTS

- Inspection and Testing Plan


- Check List for pre commissioning
- Checklist for testing & commissioning
- Risk Assessment