2019 Exam - Moed A - Computer Science - (Solution)
2019 Exam - Moed A - Computer Science - (Solution)
: ____________________________
July, 2019
Please Read:
1. IDC Honor Code applies in the exam.
2. Do not go beyond this page until you are instructed to begin.
3. You are allowed up to 3 hours to complete this exam.
4. When you are instructed to stop writing, please stop writing immediately.
5. Please write your student identification number.
6. You should write your answers on this exam. There should be plenty of space to show your
work. Extra space is on page 11.
7. Please do not unstaple your exam booklet.
8. Please show all work required to obtain each answer. Answers without justification will
receive no credits, unless otherwise instructed in the question.
9. There are 5 questions. The points for each part of each question are indicated. There are a total
of 100 possible points.
10. This exam is close book, close notes but you may use two sheets of writings (on both sides,
total 4 pages). You may use a calculator in the exam.
11. If you make any additional assumptions, state them clearly.
12. Good luck!
• The feasible research is a sunk cost. This leads to overassessment of the NPV
• The initial investment cost of the project ($15 million) is depreciated incorrectly for two
reasons:
(1) It is depreciated over 5 years instead of 3.
(2) The depreciation should be added back to get net cash flow.
This is an understatement of NPV due to discounting
• Interest expenses should be ignored
• Synergy (the profit from the other project) was ignored. This leads to underestimation of the
NPV
• Cash from selling the machine – the tax on capital gains was not taken into consideration
• Working Capital:
o The change in working capital should start at year 0 (the working capital in the amount of
the following year’s revenues).
o The working capital was not recovered
This overestimate the NPV
𝑃𝑃𝑃𝑃 = 10,000
𝑛𝑛 = 2
APR = 7%
0.07
𝑟𝑟𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 = = 3.5%
2
𝑃𝑃𝑃𝑃𝑃𝑃 𝑃𝑃𝑃𝑃𝑃𝑃
10,000 = + => PMT = 5,264.00
(1 + 3.5%)1 (1 + 3.5%)2
𝑃𝑃𝑃𝑃 = 10,250 note, in this case you need 10,250 in order to get 10,000
𝑛𝑛 = 2
APR = 6%
0.06
𝑟𝑟𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 = = 3%
2
𝑃𝑃𝑃𝑃𝑃𝑃 𝑃𝑃𝑃𝑃𝑃𝑃
10,250 = + => PMT = 5,356.76
(1 + 3%)1 (1 + 3%)2
d. What is the effective annual interest rate (EAR) of the loan offered by bank B?
Answer: The EAR of the loan offered by bank B is: $ _______
5,356.76 5,356.76
10,250 = +
(1 + 𝑟𝑟𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 )1 (1 + 𝑟𝑟𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 )2
𝑟𝑟𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 = 4.72%
𝐸𝐸𝐸𝐸𝐸𝐸 = 9.66%
𝐹𝐹𝐹𝐹 = 1,000
𝑛𝑛 = 170 × 2 = 20
𝑌𝑌𝑌𝑌𝑌𝑌𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛 = %
𝟎𝟎.𝟎𝟎𝟎𝟎
The semi-annual coupon payment = = 𝟏𝟏. 𝟓𝟓%
𝟒𝟒
𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 = 𝐹𝐹𝐹𝐹 × 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 = 1,000 × 2.5% = 25
The real time line
0 1 2 … 39 40
Coupon 15 15 15 15
Face Value 1,000
total CF: 15 15 15 1,015
𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎
𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎
1 + 𝑌𝑌𝑌𝑌𝑌𝑌𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛 1.07
𝑌𝑌𝑌𝑌𝑌𝑌𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 = −1= − 1 = 4.90%
1 + 𝐸𝐸(𝐼𝐼𝐼𝐼𝐼𝐼) 1.02
1
𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠
𝑌𝑌𝑌𝑌𝑌𝑌𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 = (1 + 4.90%)4 − 1 = 1.2%
The price of the bond:
15 1 1,000
𝑃𝑃𝑃𝑃0 = �1 − �+ = 1,093.66
1.2% (1 + 1.2%) 40 (1 + 1.2%)40
b. Suppose that 6 months after the bond was issued, the YTM on similar nominal bonds remained
7%, however, the expected inflation increased to 2.5%. What is the price of the bond now (6
months after it was issued) if the actual inflation in the last 6 months was 1.5% ?
Answer: The price of the bond is $ .
𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎
𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎
1 + 𝑌𝑌𝑌𝑌𝑌𝑌𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛𝑛 1.07
𝑌𝑌𝑌𝑌𝑌𝑌𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 = −1= − 1 = 4.39%
1 + 𝐸𝐸(𝐼𝐼𝐼𝐼𝐼𝐼) 1.025
1
𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠
𝑌𝑌𝑌𝑌𝑌𝑌𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 = (1 + 4.39%)4 − 1 = 1.08%
Calculate the price of the bond:
40 1 1,000
𝑃𝑃𝑃𝑃𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 = �1 − � + = 1,130.36
1.08% (1 + 1.08%)38 (1 + 1.08%)38
𝑃𝑃𝑃𝑃 = 𝑃𝑃𝑃𝑃𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 × (1 + 𝑖𝑖𝑖𝑖𝑖𝑖𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 )
𝑃𝑃𝑃𝑃 = 1,130.36 × (1 + 1.5%) = 1,147.31
Calculation:
b. Which of the two companies will have a higher specific risk? Explain your logic
Answer: the specific risk of Fun Station Inc. / Simple Bread Inc. is higher today (circle one).
(Hint: this question requires more thinking than number crunching)
Since, Fun Station Inc has a higher beta (see a) and both firms have the same standard deviation
The specific risk of Fun Station Inc. is lower
c. Assuming that we can only choose one of the projects, which one should we choose?
Answer: we should choose project ____________