ABSTRACTO OF COST FOR

CONSRTUCTION OF INTERMEDIATE LANE BRIDGE OVER NALLAH


SUKHNAG AT TAKIBAL TO KANIGUND BUDGAM

S. No. Particulars Amount


1 Construction of 138m Truss Girder Bridge at Kanigund
a. Sub structure 374.00
b. Superstructure 408.80
c. Protection Works 330.82
d. Approaches 337.89
Total 1451.52
Add 3% for contingencies 43.55
Grand Total 1495.07
Say 1495.00

ASSISTANT Ex. ENGINEER EXECUTIVE ENGINEER


R&B SUB DIVISION BEERWAH MUFASSIL R&B DIVISION BUDGAM

SUPERINTENDING ENGINEER CHIEF ENGINEER


R&B CIRCLE SRINAGAR/BUDGAM R&B DEPARTMENT KASHMIR
DETAILED ESTIMATE FOR PROPOSED
CONSRTUCTION OF INTERMEDIATE LANE BRIDGE OVER NALLAH SUKHNAG
AT TAKIBAL TO KANIGUND BUDGAM
S.NO LENGTH WIDTH HEIGH
Description of item UNIT NO. QUANTITY Rate Amount
(M) (M) T(M)
A-FOUNDATION AND SUBSTRUCTURE
1 Surface dressing of the ground including
removing vegetation and in-equalities
not exceeding 15 cm deep and disposal of LS 1.0 30000 30000
rubbish, lead upto 50 m and lift upto
1.5 m in -All kinds of soil.

1.01 Dismantling of existing foot bridge by


manual/mechanical means including disposal
of unserviceable material and stacking of LS 1.0 100000 100000
serviceable material as directed

2 Earth work in bulk excavation by manual


means over areas (exceeding 30 cm in depth,
1.5 m in width as well as 10 m2 on plan)
including disposal of excavated earth lead
upto 50 meters and lift upto 1.5 m, as directed
by Engineer-in-Charge. Ordinary Rock

2.01
Abuts (10.0x10.0) Cum 2 17 17 4.5 2601.0

2.02 Piers (10.0x10.0) Cum 2 17 17 9.3 5375.4

Total 7976.4 378.35 3017871

3 Dewatering of trenches during execution of


LS 4 50000 200000
work incl. diversion of Nallah
4 Providing and laying of hand packed stone
soling including all carriages

4.01
Abuts Cum 2 12.2 12.2 0.2 59.5

4.02
Piers Cum 2 12.2 12.2 0.2 59.5

Total 119.07 1200 142886

5 Providing and laying in position cement


concrete of specified grade including curing
but excluding the cost of centring and
shuttering. All work upto plinth level with:
1:4:8 (1 cement : 4 coarse sand : 8 graded
stone aggregate 40 mm nominal size)

5.01 Abuts Cum 2 12.2 12.2 0.1 29.8


5.02 Piers Cum 2 12.2 12.2 0.1 29.8
Total 59.54 4419.85 263140
6 Providing and laying of Controlled cement
concrete of M-25 grade using 40mm down
aggregates in Abutment, Pier Shaft and return
walls and other Sub-Structure elements
including approaches ; consolidated and cured
complete but excluding cost of necessary
formwork /shuttering and cost of
reinforcement Incl. all carriages complete.
6 Providing and laying of Controlled cement
concrete of M-25 grade using 40mm down
aggregates in Abutment, Pier Shaft and return
walls and other Sub-Structure elements
including approaches ; consolidated and cured
complete but excluding cost of necessary
formwork /shuttering and cost of
reinforcement Incl. all carriages complete.

6.1 Abut Foundation Cum 2 16.730 sqm 12.00 401.520


6.2 Pier Foundation Cum 2 14.550 sqm 12.00 349.200
6.3 Abut Shaft Cum 2 9.000 0.7 6.12 77.049
6.4 CF1 Cum 4 40.382 sqm 0.50 80.764
6.5 CF2 Cum 4 18.707 sqm 0.40 29.931
6.6 Tie Beans Cum 12 2.400 0.5 0.50 14.400
6.7 Pier Shaft Cum 2 7.200 sqm 10.52 151.416
6.8 Abut Cap Cum 2 9.000 1.395 0.75 18.833
6.9 Pier Cap Cum 2 12.400 sqm 2.20 54.560
6.1 Dirt Wall Cum 2 9.000 0.3 1.25 6.750
6.11 Corbel Cum 2 9.000 0.45 0.30 2.430

Total 1186.85 8457.25 10037510


7 Providing and laying of Controlled cement
concrete of M-40 grade using 20mm down
aggregate in Pier and abutment Pedestals,
consolidated and cured complete but excluding
cost of necessary formwork /shuttering and cost
of reinforcement Incl. all carriages complete.

7.1 Pedestals Cum 12 0.9 0.6 0.225 1.46


7.2 RB1 Cum 12 1.095 0.69 1 9.07
7.3 RB2 Cum 12 1 0.4 0.8 3.84

14.36 8762.3 125867


8 Providing and fixing in position HYSD bar
reinforcement of grade Fe-500D conforming
to IS:1786 as per technical drawing including
fabrication, spot welding if required, laying
and binding with 18gauge annealed steel wire,
in foundations, abutments, pier, caps,
pedestals, return walls, dirt walls, approach
slabs, approach walls etc.

8.1 Foundations/Shafts KG 1104.3 x 130 143556.4


8.2 Caps/dirt walls/corbels KG 82.57 x 110 9083.0
8.3 Pedestals KG 1.46 x 610 889.4
8.4 Reaction Blocks KG 12.91 x 325 4194.6

Total TOTAL 157723.4 79.25 12499582


9 Centering and shuttering including strutting,
propping etc. and removal of form for:
9a Foundations, footings, bases of columns etc.
for mass concrete.
Abut Foundation Sm 4 16.73 sqm 66.9
Sm 4 12 sqm 0.5 24.0
Pier Foundation Sm 4 14.55 sqm 58.2
Sm 4 12 sqm 0.5 24.0
TOTAL 173.1 262.3 45409
9b Columns, pillars, piers, abutments, posts and
struts.
Abut Shaft Sm 4 9 sqm 6.115 220.1
Sm 4 0.7 sqm 6.115 17.1
CF1 Sm 8 40.382 sqm 323.1
Sm 4 8.865 sqm 0.5 17.7
CF2 Sm 8 18.707 sqm 149.7
Sm 4 8.865 sqm 0.5 17.7
Pier Shaft Sm 2 11.355 sqm 11.765 267.2
Pedestals Sm 12 3 sqm 0.225 8.1

TOTAL 1020.7 680.15 694241


9c Lintel, beams, plinth beams, girders,
bressumers and cantilevers.
Tie Beams Sm 12 2.4 sqm 1.5 43.2
Abut Cap Sm 2 9 sqm 2.195 39.5
Pier Cap Sm 4 12.4 sqm 49.6
Sm 4 2.2 sqm 0.75 6.6
Sm 4 1.69 sqm 2.2 14.9
TOTAL 138.9 502.85 69851
9d Walls (any thickness) including attached
pilasters, buttresses, plinth and
string courses etc.
Dirt Wall Sm 4 9 sqm 1.25 45.0
Corbel Sm 2 9 sqm 0.45 8.1
RB1 Sm 12 3.572 sqm 1 42.9
RB2 Sm 12 2.8 sqm 0.8 26.9
Total TOTAL 122.8 573.85 70494
10 Backfilling and comapction in layers behind
abutment,approaches to the level of approach
slabs with approved selected boulders/
Granular material brought from approved
source incl. all carriages of materials involved
the site of work incl. spreading in layers not
exceeding 200mm thickness,
watering ,consolidating with vibrating
compactors, incl. provision of filter media of Cum 6.00 2.40 5.00 9.615 692.28 1250 865350
not less than 600mm width as per techinical
specification clause 2504.22 of MORTH
specification and all incidentals complete
pletion of raft to form embankment, slope, etc.

11 Providing and fixing in postion weep holes in


abutment walls with 100 mm dia PVC pipes
cut to required length and profile and installed mtr 350.0 250 87500
in concrete.
12
Test boring up to 30m or appropriate depth at
abutment and pier locations consisting of
collecting required number of disturbed and
undisturbed soil samples for laboratory tests
samples to be collected at 1.5m intervals or at
every change of soil strata whichever is
earlier, carrying out dynamic and standard
mtr 60.0 4000 240000
penetration test as required based on type of
soil encountered as per IRC-78-1983,
including field vane shear test if called for and
conducting soil tests as per appendix 2 of IRC
78, for evaluation of soil properties and
relating with field test.

13 Diversion of Nallah during execution of job at


No 4.0 30000 120000
different abutment or Pier locations
14 CARRIAGE OF MATERIALS By
Mechanical Transport including loading,
unloading and stacking
14a
Sand Avg lead of 30km cum 567.3 436.22 247485

14b
Stone aggregates Avg lead of 12 km cum 1134.7 265.34 301075

TOTAL 29158261

ADD 30% ABOVE ON ALL ITEMS EXCEPT ITEM NO 1, 3,


8241757
4, 10, 11, 12 & 13

GRAND TOTAL
37400019
''A''

Assistant Ex. Engineer Executive Engineer


R&B Sub Division Beerwah Mufassil R&B Division Budgam
DETAILED ESTIMATE FOR PROPOSED
CONSRTUCTION OF INTERMEDIATE LANE BRIDGE OVER NALLAH SUKHNAG
AT TAKIBAL TO KANIGUND BUDGAM
S.NO LENGTH WIDTH HEIGH
Description of item UNIT NO. QUANTITY Rate Amount
(M) (M) T(M)
B- SUPERSTRUCTURE
1 "Bearings
Providing and installing in position of POT -
PTFE bearings at free ends of Truss girder
over abutments and pier locations as per
drawings which shall include the following:
a) Cost of bearing assembly, transportation,
erection and installation to level and position,
provision for necessary pockets in pedestals
lugs inserts as required and grouting of same
as directed after installation.
b) All necessary labour and material required
for temporary supports and structure locking
bearing in position during construction and Nos 12.00 12.00 50000.00 600000
releasing of the same on completion of units
as required in the drawings.
c) Providing of epoxy mortar for leveling and
seating including application of two or more
coats of protective anti-corrosive epoxy based
paint on exposed steel sections of bearings
assembly, greasing/lubrication of moving
parts etc as required on completion of
installation.

2 Providing and fixing of Elastomeric Bearings


over reaction blocks, complete job. Nos 24.00 24.00 40000.00 960000

3 Steel Girders, Deck Slab etc.


Structural Steel
Providing and fixing structural steel of grade-250
in Steel truss girders/plate girders, cross beams MT 105 1 1 2.5 262.50 92850 24373125
stringers, and bracing etc., as per structural details
complete including welding.

4 Providing and laying in position cement


concrete of specified grade including curing
but excluding the cost of centring and
shuttering. All work upto plinth level with:
Cum 2 9 5 0.1 9.00 4419.85 39779
1:4:8 (1 cement : 4 coarse sand : 8 graded
stone aggregate 40 mm nominal size)

5 "Providing and laying of controlled cement


concrete of M-30 Grade using 20 mm down
aggregate in two end spans and Deck Slab for
remaining length consolidated and cured complete
but excluding cost of necessary formwork
/shuttering and cost of reinforcement.Incl. all
carriages complete.

"
5.1 Deck Slab Cum 1 108.44 6.1 0.225 148.83
5.2 Approach Slab Cum 2 9 5 0.3 27.00
5.3 Crash Barriers Cum 2 108.44 sqm 0.26 56.39
Total 232.22 8660.6 2011188
6 Reinforcement for RCC works including
straightening, cutting, bending, binding &
placing in position all complete. HYSD
reinforcement of gra"Reinforcing Steel
Providing and fixing in position HYSD
reinforcement of grade Fe-500 including Kg 232.22 1 1 150 34833.41 79.25 2760547
fabrication, laying and binding with 18 gauge
annealed steel wire, in Deck Slab and wheel
guard/Kerbs. Fe-500D steel bars at all levels.

7 Centering and shuttering including strutting,


propping etc. and removal of form
forSuspendedProviding and fixing exposed
quality shuttering in Deck slab, wheel guards
etc.
floors, roofs, landings, balconies and access
platforms

7.1 Deck Slab Sqm 1.00 108.44 sqm 6.1 661.5


7.2 Crash Barriers Sqm 4.00 108.44 sqm 1.1 477.1
7.3 Edges Sqm 2.00 114.54 sqm 0.2 45.8
Total 1184.4 635.6 752828
8 Providing and fixing in position of rain water
collection boxes with pipe outlets (RWCB
Type 2) partly in MS sections and cast iron
complete as per details (MS angle frame with
Nos 38.00 38.0 1000 38000
anchors to be cast in position along with deck
slab for seating and fixing of RWCB)

9 Finishing with Deluxe multi surface paint


system for interiors and exteriors using primer
as per manufacturers’ specifications:Painting
steel work with deluxe multi surface paint of
required shade to give an even shade. Two or
more coats applied @ 0.90litre/10sqm over an Sqm 6.00 157 sqm 942.0 125.6 118315
under coat of primer applied @
0.80litre/10sqm of approved brand and
manufacture

10 Providing and fixing in position expansion


joints complete with U-strip made from 24
gauge copper strip. MS angles with welded
anchors and MS top plate bolts/nuts etc. Rm 4.00 6.1 1 1 24.4 2000 48800
complete as per MOST standard drawing.

11 Providing and filling of approved quality


bitumen mastic sealant in expansion joints
wherever necessary, prepared and applied as Rm 4.00 6.1 1 1 24.4 1000 24400
directed Including all incidental work
complete.

12 CARRIAGE OF MATERIALS By
Mechanical Transport including loading,
unloading and stacking
12a Sand Avg lead of 30km cum 108.6
436.22 47352
12b Stone aggregates Avg lead of 12 km cum 217.1
265.34 57605
TOTAL 31831939
ADD 30% ABOVE ON ALL ITEMS EXCEPT ITEM NO 1, 2, 8, 10 &11, 9048222
GRAND TOTAL ''B'' 40880160

Assistant Ex. Engineer Executive Engineer


R&B Sub Division Beerwah Mufassil R&B Division Budgam
DETAILED ESTIMATE FOR PROPOSED
CONSRTUCTION OF INTERMEDIATE LANE BRIDGE OVER NALLAH SUKHNAG
AT TAKIBAL TO KANIGUND BUDGAM
LENGT WIDTH HEIGH
S.NO Description of item UNIT NO. QUANTITY Rate Amount
H (M) (M) T(M)

C -PROTECTION WORKS
Earth work in excavation by mechanical
means (hydraulic excavator) for approachs
upto concrete level . including dressing of
sides and ramming of bottoms lift upto 1.5 m,
including getting out excavated earth and Cum 0.50 115 4.2 3.2 772.80
disposal of surplus excavated earth as
directed, within a lead of 50 metres:
1 All kinds of soil : Cum 0.50 115 7.2 12.2 5050.80

Cum 0.50 115 6.65 5.5 2103.06

Total 7926.66 188.75 1496158

Providing and laying in position cement


concrete of specified grade including curing
but excluding the cost of centring and
2 Cum 1.00 115 11 0.15 189.75 4419.85 838667
shuttering. All work upto plinth level with:
1:4:8 (1 cement : 4 coarse sand : 8 graded
stone aggregate 40 mm nominal size)

Providing and laying in position machine


batched and machine mixed design mix M-30
grade cement concrete for reinforced cement
concrete work, using cemet content as per
approved design mix, including pumping of
concrete to site of laying but excluding the
cost of centering, shuttering, finishing and
3
reinforcement, including admixtures in
recommended proportions as per IS: 9103 to
accelerate, retard setting of concrete, improve
workability without impairing strength and
durability as per direction of Engineer-
incharge. All works above plinth level upto
floor V level

3.1 Cum 1.00 115 0.6 3.2 220.80


3.2 Cum 1.00 115 0.6 4.3 296.70
3.3 Cum 1.00 115 11 0.3 379.50
Total 897.00 8660.6 7768558
Reinforcement for RCC works including
straightening, cutting, bending, binding &
4 placing in position all complete. HYSD Kg 1.00 897.00 x 125 112125.00 79.25 8885906
reinforcement of grade Fe-500D steel bars at
all levels.

Providing and fixing of 150mm thick flat


5 stone masonary in cement mortor 1:3 Sqm 1.00 115 sqm 11 1265.00 600 759000
including flush pointing of joints
Providing & making Gabion structure with
Mechanically Woven Double Twisted
Hexagonal Shaped Wire mesh Gabion Boxes
as per IS 16014:2012,MORTH Clause 2500,
of required size, Mesh Type 10x12(D=100
mm with tolerance of ±2%), Zinic+10% Al
alloy+PVC
coated, Mesh wire diameter 2.7/3.7mm
6 (ID/OD), mechanically edged/ selvedged with Cum 9.00 1 1 115 1035.00 3325.05 3441427
partitions at every 1m interval and shall have
minimum 10 numbers of openings per meter
of mesh perpendicular to twist, tying with
lacing wire of diameter 2.2/3.2mm(ID/OD),
supplied @3% by weight of Gabion boxes,
filled with boulders with least dimension of
200 mm, as per drawing, all complete as per
directions of Engineer-in-charge.

Supply and filling of well compacted River


Bed Material including ramming dressing and
7 Cum 1.00 115 sqm 17.035 1959.03 1250 2448781
consolidating in 20cm layers all leads,lifts and
carriages upto the site of work

Dewatering of trenches and diversion of


8 no 1.00 - - - 1.00 100000 100000
nallah during execution of job
CARRIAGE OF MATERIALS By
9 Mechanical Transport including loading,
unloading and stacking
9a Sand Avg lead of 30km cum 489.0 436.22 213328
9b Stone aggregates Avg lead of 12 km cum 978.1 265.34 259522

T OTAL 26211347

ADD 30% ABOVE ON ALL ITEMS EXCEPT ITEM NO 5,7&8 6871070


GRAND TOTAL
33082417
''C''

Assistant Ex. Engineer Executive Engineer


R&B Sub Division Beerwah Mufassil R&B Division Budgam
DETAILED ESTIMATE FOR PROPOSED
CONSRTUCTION OF INTERMEDIATE LANE BRIDGE OVER NALLAH SUKHNAG
AT TAKIBAL TO KANIGUND BUDGAM
S.NO LENGTH WIDTH HEIGH
Description of item UNIT NO. QUANTITY Rate Amount
(M) (M) T(M)
D- APPROACHES
1 Earth work in excavation by manual means in
trenches for foundations, drains, pipes, cables
etc. (not exceeding 1.5 m in width) and for
shafts, wells, cesspits and the like not
exceeding 10 sqm on plan, including dressing
of sides and ramming of bottoms lift upto 1.5
m, including getting out excavated earth and Cum 4.00 100 1.25 0.75 375.00 612.75 229781
disposal of surplus excavated earth as
directed all types of soils adn lead beyond
50m form the cutting edge.

2 Total Stone work Cum 4.00 100 0.925 2.5 925.00


Random Rubble masonry with hard stone in
foundation and plinth including leveling up
with cement concrete 1:6:12 (1 Cement : 6
coarse sand : 12 graded stone aggregate cum 65 % of Total qty 601.25 4400.50 2645801
20mm nominal size) upto plinth level and
curing complete with Cement mortar 1:6 (1
Cement : 6 coarse sand) Quarry stones

Dry random rubble masonry with hard stone


in foundation and plinth with bond stone. Cum 35 % of Total qty 323.75 2497.50 808566

3 Providing and laying in position cement


concrete of specified grade including curing
but excluding the cost of centring and
shuttering. All work upto plinth level with:
Cum 4.00 100 0.6 0.1 24.00 4943.40 118642
1:3:6 (1 cement : 3 coarse sand : 6 graded
stone aggregate 20 mm nominal size)

4 Back filling behind abutment, wing wall and


return wall complete as per drawing and Cum 4.00 100 0.75 2.25 675.00 500.00 337500
Technical Specification.

5 Construction of embankment with approved


materials deposited at site from cutting and
excavation from drain and foundation of other
structures graded and compacted to meet Cum 2.00 950 5.5 1.5 15675.00 550 8621250
requirement of table 300-2.Material from
borrow pits

6 Construction of granular sub-base by


providing close graded Material conforming
to specifications, mixing in a mechanical mix
plant at OMC, carriage of mixed material by
tippers to work site, for all leads & lifts,
spreading in uniform layers of specified
thickness with motor grader on prepared
surface and compacting with vibratory power Cum 2.00 950 5.5 0.3 3135.00 1086.80 3407118
roller to achieve the desired density, complete
as per specifications and directions of
Engineer-in-Charge. With material
conforming to Grade-III (size range 26.5 mm
to 0.075 mm ) having CBR Value-20
7 Laying, spreading and compacting stone
aggregate of specified sizes to WBM
specifications in uniform thickness, hand
picking, rolling with 3 wheeled road /
vibratory roller 8-10 tonne capacity in stages
to proper grade and camber, applying and Cum 2.00 950 5.5 0.075 783.75 710.85 557129
brooming requisite type of screening /binding
material to fill up interstices of coarse
aggregate, watering and compacting to the
required density

8 Providing, laying, spreading and compacting


graded stone aggregate (size range 53 mm to
0.075 mm ) to wet mix macadam (WMM)
specification including premixing the material
with water at OMC in mechanical mix plant,
carriage of mixed material by tipper to site,
for all leads & lifts, laying in uniform layers
with mechanical paver finisher in sub- base /
base course on well prepared surface and Cum 2.00 950 5.5 0.10 1045.00 1041.50 1088368
compacting with vibratory roller of 8 to 10
tonne capacity to achieve the desired density,
complete as per specifications and directions
of Engineer-in-Charge

9 Providing and applying tack coat using hot


straight run bitumen of grade VG-10,
including heating the bitumen, spraying the
bitumen with mechanically operated spray
unit fitted on bitumen boiler, cleaning and sqm 2.00 950 5.5 10450.00 55.45 579453
preparing the existing road surface as per
specifications.On Granular surfaces treated
with primer

10 Providing and laying bituminous macadam


using crushed stone aggregates of specified
grading premixed with bituminous binder,
transported to site by tippers, laid over a
previously prepared surface with paver
finisher equipped with electronic sensor to the
required grade, level and alignment and
rolling with smooth wheeled, vibratory and
tandem rollers as per specifications to achieve
the desired compaction and density, complete
as per specifications and directions of cum 2.00 950 5.5 0.05 522.50 5996.55 3133197
Engineer-in-Charge. 50 to 100 mm average
compacted thickness with bitumen of grade
VG-30 @ 3.5% (percentage by weight of total
mix) prepared in Batch Type Hot Mix Plant of
100-120 TPH capacity.
11 Providing and laying semi- dense Bituminous
concrete using crushed stone aggregates of
specified grading, premixed with bituminous
binder and filler, transporting the hot mix to
work site by tippers, laying with paver
finisher equipped with electronic sensor to the
required grade, level and alignment and
rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired
compaction and density as per specification,
complete and as per directions of Engineer-in- sqm 2.00 950 5.5 10450.00 205.95 2152178
Charge. 25 mm compacted thickness with
bitumen of grade VG- 10 @5% (percentage
by weight of total mix) and lime filler @ 2%
(percentage by weight of Aggregate) prepared
in Batch Type Hot Mix Plant of 100-120 TPH
capacity.

12 Construction of shoulder by providing close


graded Material conforming to specifications,
mixing in a mechanical mix plant at OMC,
carriage of mixed material by tippers to work
site, for all leads & lifts, spreading in uniform
layers of specified thickness with motor
grader on prepared surface and compacting
with vibratory power roller to achieve the
desired density, complete as per specifications cum 2.00 950 5.5 0.25 2612.50 1086.80 2839265
and directions of Engineer-in-Charge. With
material conforming to Grade-III (size range
26.5 mm to 0.075 mm ) having CBR Value-
20

13 Providing & laying bitumen mastic wearing


course (as per specifications)
with industrial bitumen of grade 85/25
conforming to IS : 702, prepared
by using mastic cooker & laid to required
level and slope, including providing antiskid
surface with bitumen pre-coated fine grained
hard stone chipping of approved size at the
rate of 0.005 cum per 10 sqm& at sqm 1.00 140 5.5 770.00 618.80 476476
approximate spacing of 10 cm centre to centre
in both directions, pressed into surface
protruding 1 mm to 4 mm over mastic surface,
including
cleaning the surface, removal of debris etc. all
complete. (considering
bitumen using 10.2% as per MORTH
specification) 25mm thick
14 CARRIAGE OF MATERIALS By
Mechanical Transport including loading,
unloading and stacking
14a Sand Avg lead of 30km cum 10.8 436.22 4711
14b Stone aggregates Avg lead of 12 km cum 1850.4 265.34 490972
14c Stone Avg lead of 45 km cum 925.0 615.01 568884
TOTAL 28059289
ADD 30% ABOVE ON ALL ITEMS EXCEPT ITEM NO 4&5 5730162
GRAND TOTAL
33789451
''D''

Assistant Ex. Engineer Executive Engineer


R&B Sub Division Beerwah Mufassil R&B Division Budgam