0 ratings0% found this document useful (0 votes) 68 views6 pages2
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
PERGAMON Building and Environment 4 (1999) 43-48,
A method for estimating labour requirements and costs for
international construction projects at inception
D. G. Proverbs*, G. D. Holt, P. O. Olomolaiye
Schoo! of Engineer and the Bult Excironment, University of Wolverhampton, Walfruna Street, Wolterhampton, WY 1SB.U-K,
Received 2 September 1997; revised 8 October 1997; accepted 8 Oxtober 1997
Abstract
At project inception stage, a quick and reliable method of estimating labour resource requirements and cost, is desirable, This
paper presents a fresh approach in that ambition. During inception, while design information is at a premium, cost forecasts should
bbe within 20% of the final cost of the building. The method presented achieves this by utilising the productivity rates of contractors’
planning engineers for a ‘typical’ building type (in this instance, a concrete framed high-rise structure is featured). The estimated
labour resource requirements for such a building constructed in France. Germany and the UK sre calculated. Planned productivity
rates form the basis of the estimate, these being used 0 generate a “Labour Estimate Factor’. This Factor is defined as the man-hour
requirements per square metre of the building's gross floor area. Respective national all-in wage rates are then applied to forecast
estimated budget costs, for construction in each international location. The calculations are based on a “typical” design, hence, they
‘are applicable to other buildings of similar type and form. Armed with relevant data, resource estimates could similarly be generated
fr alternative international locations, and, for different classifications of “typical” building forms. The process will be of interest to
practitioners and clientsjeustomers of the international construction industry. «° 1998 Elsevier Science Ltd, All rights reserved
‘Kevwords: Cost planning: Labour resources Productivity rates International comparison; In sit conerete construction
1. Introduction
Knowledge of productivity rates is an essential part of
the construction management process {1], such knowl-
edge being necessary for any study of construction pro-
ductivity. One of the most important applications of
productivity rates is in the area of construction planning
and scheduling. Other uses include estimating, account-
ing and cost control. Indeed, Koehn and Brown (2] used
them to generate international labour productivity
factors, while also suggesting Ways in which they could
subsequently be applied to determine comparative inte
national construction costs, Perhaps the most important
application of accurate productivity rates is in the area
of resource management, Here, planning engineers often
maintain a ‘basic library’, such rates being adjusted for
each project taking into consideration specifi site factors
and conditions, that may impact the productivity of con-
struction operations.
In their recent study of productivity rates, Christian
* Corresponding author.
10197-0186/99/S—sce fromt matter © 1998 Elsevier S
PH:S0360-1323(97)00064-4
and Hachey [3] found ‘substantial agreement” between
the average rates measured in the field and those used by
planning engineers. Hence, the productivity rates used by
planning engineers can provide useful data on which to
assess the (past and therefore predicted future) per-
formance of construction contractors, both nationally
and internationally, They also provide a basis on which
estimates of construction (labour) times and costs can be
formed. This paper presents the findings of an inter-
national study of contractors’ productivity rates, from
which & novel approach to estimating labour require-
‘ments and costs at the inception stage is proposed, for
typical buildings in three different European locations,
During the inception and feasibility stages, (when only
the floor area and building ‘type’ might be known), cost
prediction must necessarily be “crude” [4]. It is usual to
anticipate that such estimates should be within +20% of
the final cost of the building. Application of the est
mating tool presented herein has indicated an accuracy
well within such constraints and could therefore be of
‘much use to quantity surveyors, estimators, and potential
clients of the (European) construction industry.
Jonce Ltd, All rights reserved“ DG. Proverbs) Building and Environment 34 (1999) 43-48
11. Cost planning
In cost planning, an estimate, cost forecast, of cost
plan, is only as reliable as the data upon which it is
based. Numerous sources of data are available for such
purposes, and include contractors’ own (historical) cost-
ing data, For example, when reviewing the costs of a
project at final account stage, a contractor may divide
the total cost (£) by the gross floor area (gfa) in order to
determine the cost in £/m? as a unit cost for the project
under review. Other sources of cost planning information,
include the use of Elemental Cost Analyses such as those
provided by The Building Cost Information Service [5]
or the use of standard costs of functional units, such as
the ‘cost per bed’ for hospitals. or the ‘cost per room’ for
hotels, It is not until the subsequent (more detailed)
design stages, that detailed elemental costs perhaps
derived from price books such as Spon {6} or Laxton (7
can be accurately forecast. At inception, the client is
normally onty able to provide outline data on which the
project cost can be forecast. Typically, the building type
and approximate floor area is all that will be known,
and hence preliminary cost advice is unlikely to be more
accurate than within 20% of the final cost of the building
Unit rate estimating is generally « more analytical tech-
nique, and uses predetermined output rates for labour
and plant, in conjunction with a price per unit for
materials. to calculate a rate per unit (m, m?, m’,ctc.) for
any measured item of work. Such methods cannot be
applied until detailed design information is available, In
contrast to these “traditional” approaches, the meth-
odology presented here uses.a form of unit rateestimating
that could be utilised during the earliest stages in the
design process.
Unit rate estimating requires the estimator to consider
basic resources (i. quantities and costs of labour, plant,
and materials) that form part of pricing any construction
work. Labour cost represents a considerable proportion
of the final cost of a building, usually between 40 and
60% [8]. Obviously, therefore, a reasonably correct and
accurate assessment of the cost of labour is fundamental
to the accuracy of any estimate, However, it is generally
recognised that the labour element is probably the most
difficult component to estimate with any reasonable
degree of accuracy [9]. Ashworth and Skitmore [10]
referred to estimators’ standard labour productivity rates
as being contained in a “black book’, and suggested that,
such data were rarely amended or revised. It is therefore
apparent that the estimation of labour costs can be sub-
ject to considerable uncertainty
The examples of estimating labour requirements and
costs presented in this paper concentrate on in situ, high-
rise concrete frames, utilising productivity rates provided
by contractors’ planning engineers. It is intended that the
‘method be applicable for project inception; when all that
is needed in order to derive the estimate is an approxi-
mation of the gf
2. An overview of the research methodology
The investigation concentrates on productivity rates
used by planning engineers in France, Germany and the
UK, and provides an innovative methodology for pre~
dicting man-power resource requirements for high-rise
concrete buildings. A comprehensive description of the
research methodology may be found in Proverbs et al
[11, 12}, and therefore only an overview is now presented.
To standardise the study, a high-rise in situ concrete
framed model building was designed (refer to Proverbs
et al, [13] for details), This, the principal research instru-
ment, was complemented with a structured questionnaire
via which various planning considerations, including
resource utilisation, productivity rates and construction
methods could be analysed. These research documents
(model project drawings and questionnaire) were dis-
tributed to the planning engineers of contractors within
the countries concerned, who were asked to assume that,
the model was 4 potentially ‘live’ project. The ques-
tionnaire concentrated on productivity rates of in situ
concrete operations, namely: reinforcement fixing: for-
mwork erection; and placing concrete, These operations
were analysed with respect to three separate elements.
these being: beams, columns, and floor slabs. The esti-
mating methodology presented is bused on this data
2.1. The research survey
In the UK, questionnaires were distributed amongst
the top 40 contractors as listed in Building [14] and 110
other companies selected from the Register of British
Industrv and Commerce {15}. From this total of 150 firms,
positive responses were reveived from 31 contractors:
representing & 21% response rate. The same (but trans-
lated) documentation was distributed to 75 contractors
in France, chosen trom the Syndicat Natinal duu Béton
Armé, des Techniques Industrialisées et de I’ Entreprise
Générale list of members [16]. Completed questionnaires
were received from 14 contractors (19% response). Simi-
larly, translated questionnaires were dispatched to 5S
German contractors, identified with the assistance of the
major contractors’ federation in Germany, Hauptterband
der Deutschen Bauindustrie e.V., and yielded 10 (18%)
positive response
In view of the international nature of the research, and
the exaggerated difficulties in securing participation from,
foreign companies, (ie. French and German planning
engineers are even less likely to respond to an inves-
tigation which originates from another country), the
research team considered the response to provide a rep-
resentative sample of contractors, sufficient in size
experience and resources to undertake such a project
represented by the model, Table | provides an indication
of the size and diversity of the participating companies
from each countryDG. Proverbs Building and Environment 34 (1999) 43-48 45
Table 1
Size of participating firms
Number and percentage of contractors
uk France Germany
Companysizet No. & No. No. %
Small 38 S387 00
Medium 44520 S 3872 no
Large 9 0 4 e700
Total Tn a )
Small: Annual turnover <£50 million (sterling): Medium: Annual
turnover >£50-< £450 million (sterling): Large: Annual turnover
> £450 milion (sterling)
3. Analysis of the survey data
The following analysis is based on the aggregated sur-
vey response (ie, 55 European contractors). It sum-
marises the findings for each of the three concrete
‘operation elements and focuses on the method by which
such data is utilised to estimate labour resource require-
ments and costs for three international locations. Plan-
ning engineers were requested to provide their
productivity rates for three operations (formwork erec~
tion, reinforcement fixing and placing concrete), each of
which was split into three elements (columns, floor slabs
and beams), as defined by the model drawing. By deter-
mining a mean productivity rate for each element of
construction, for each country, the necessary labour
requirements for the project in each international
location can be estimated. There now follows a detailed
example of the proposed method for one particular coun-
try, followed by a succinct presentation of results for the
two remaining locations.
3.1. Labour resource estimate
Productivity rates for the three main operations (plac-
ing concrete, reinforcement fixing and formwork erec
tion}, comprised three elements (beams, columns and
floor slabs). Therefore, a combined total of nine pro-
ductivity rates was determined. For each of these nine
elements a ‘mean’ productivity rate (MPR) was cal-
culated to represent each nationality’s productivity for
that particular element of work, e.g. a mean productivity
rate for placing concrete to beams in the UK.
For each country the three elements of each operation
were then combined (o yield an ‘overall mean’ MPR
(designated MMPR). This represented the nation’s mean,
productivity rate for that operation, e.g. placing concrete
in the UK. Hence for Germany, the MPRs for each
element, and the MMPR for each operation are presented
in Table 2
Table 2
MPR and MMPRs for German conttactors
MPR:
Floorshibs MMPR
Beums Columns
Placing Conerste = 105.28 O88. Lan
tmanchourim’)
Fining Reinforcement 18.02 18.51 1498 nr
{man housjtoane)
Erecting Formwork 1321098 Lor
(enan-hourim’)
Therefore, it can be seen that the MPRs indicate pro-
ductivity levels for each ‘element’, whilst the MMPRs,
indicate productivity levels for each “operation”. So for
German contractors involved in high- rise in situ concrete
construction, a rate of 2.48 man-hour per m’ is the MPR
for placing concrete to columns, whilst a rate of 1.47 man-
hour perm’ (MMPR) represents the average production
output for placing concrete to buildings of this type.
In that the model building is a “generic” example of
high-rise conerete frame construction, labour require-
ments can be estimated based on MMPRs, and nor-
malised proportions (see below) of the three operations
Since the gfa is likely to be known at inception stage, it
is assumed that it will provide the basis on which to
evaluate the labour (cost) estimate, However, the method
presented could quite easily be adapted for other known,
‘quantities, such as reinforcement, formwork, or indeed.
for net floor areas, if so desired.
The first step is to normalise the quantities of each
operation for the given gfa. Hence, extracted from the
model, total quantities of the three operations are as
follows:
848.69 m°
6616.40 m*
94.50 tonnes
Placing conere
Erecting formwork
Fixing reinforcement
Ifthe total of each operation is divided by the total gfa
contained in the model (4037.88 m’): e.g. for formwork:
(6616.40 m*/4037.88 m?
= 1,639 m’ of formwork per m? of gfa,
and this is repeated for cach operation, then the nor-
malised values are as Follows:
Placing concrete
Erecting formwork
Fixing reinforcement
0.21 mm?
1.639 mm?
0.0234 tonne/m?
If cach of these values is then multiplied by it’s cor-46 DG. Proverbs) Building and Eniromnent 34 (1999) 43-48,
responding MMPR, and the resulting indices totalled, an
overall Labour Estimate Factor (based on gfa) is gener-
ated. This ‘Labour Estimate Factor’ can then be used to
estimate man-hour requirements for any concrete framed
building (of a similar nature) if the gfa is known. Hence,
for Germany, the ‘Labour Estimate Factor’ (based on
sgfa) for the model project is presented in Table 3
Therefore, German contractors require 2.465 man-
hours to complete a m? of the gfa (including all associated
reinforcement, formwork and concrete placing) for high-
rise buildings of this type. Hence for the model building,
adopting this ‘Labour Estimate Factor’, an estimated
(2465 hx4037.88 m? gfa) 9953.37 man-hours are
required to complete all aspects of concrete work con-
tained in the structural frame.
AS a means of validating this overall labour estimate,
the “actual” total man-hour for German contractors can
be calculated using the MPRs for each element and mul-
tiplying these by the corresponding quantity contained
in the model. The sum of each of the nine elements will
provide the predicted number of man-hours as estimated
by the planning engineers themselves. Hence, based on,
the MPR's presented in Table 2, and extracting the quan-
tities from the model for each element, the actual pre-
dicted total of man-hours (assuming average productivity
for German contractors) is given in Table 4
‘Actual total man-hours for construction in Germany
(8808.97 man-hour) is comparable to the estimated figure
(9953.37 man-hour) calculated using the “Labour Esti-
mate Factor’ (of 2.465 man-hour/m? of gfa) previously
presented. The difference between these figures is 11
Table 3
Labour estimate factor for German contractors
Column
‘Nosmalised values
Pacing conerete
Erecting formwork
Fixing reinforcement
0.21 m'im?
1,639 mim"
0.0234 tonne im?
Table 4
Actual predicted man-hour for the ‘average’ German Contractor
Beams Columns
Quantity
Placing conerete 169.68 i416 na
Erecting formwork 160075 2113.00, 97176
Fining reinforcement 939 17281 616
and therefore well within the original parameter of
20%. Hence, based on the productivity of labour in
each country, an estimate of total man-hour requirements
is obtained, using only the gfa as a means of calculation
{n Germany, this ‘Labour Estimate Factor’ is calculated
as 2.465 man-hours/m? of gfa, whilst in France and the
UK itis 2.396 and 3.636 man-hours/m’, respectively. One
can elicit therefore, that contractors in France are the
‘most productive at high-rise concrete construction (ie.
demand fewer man-hours to complete one m” of gfa)
compared to those in Germany and the UK.
Indicative of high-rise concrete construction, the ‘Lab-
our Estimate Factors’ could be reasonably applied to
other, similar structures in each country. Indeed, if the
research process was repeated for other building forms,
“Labour Estimate Factors’ for each of the main building
types (eg. structural steel, masonry construction etc.)
could be generated
3.2. Labour cost estimate
Having established an estimate of the likely man-hour
requirements for each country, it is desirable to obtain
an approximation of the associated costs. This then facili-
tates an international comparison of construction (lab-
our) costs, which could, for some clients/customers help
to decide on the whereabouts of further international
projects. Furthermore, quantity surveyors and estimators,
need to establish reasonably accurate budget costs as
early as possible in a project’s inception, this quick cost
estimating procedure could be used as soon as the gf of
Column 2 Labour Estimates Indices
MMPRs (column txcolun 2)
var (0.309 man-hour
07 1.754 man-hour
0.402 man-hour
Labour Estimate Factor: 2.465 man-hourim? of aft
a
Floor slabs
Man brs Quantity Man brs Total
sie 603.68 ss.00 393.02
1065.76 088 27068 49.44
n1g.02 77S 119.68 1466.31
Acti overall total man-hou
808 97DG. Proverbs Building and Environment 34 (1099) 43-48 0
the building has been decided (normally established very
early on in the development process).
Considering the three main operations involved in in
situ conetete construction, namely fixing reinforcement.
erecting formwork and placing concrete, and utilising
national all in-rates for skilled and semi skilled labour
recently published {7}, an all-in-rate per m’ of gfa can be
determined. This should therefore represent construction
(akasesscants in euch intestatienah tection,
Adopting national *skilled” labour rates for reinforce-
ment and formwork operations, and semi-skilled” rates
for concrete placing, the findings for Germany are now
presented, Using the labour estimate indices previously
determined, an alin rate per my of gfa area can be ges
crated as shown in Table 5.
Therefore, labour costs per m? of gfa, are £6.53 for
placing concrete, £39.17 for erecting formwork and so
on. The total of these three labour rates will provide a
‘gross estimate of the labour costs for constructing the
frame, per m’ of floor area; in the case of Germany £54.67,
Pex sn of gfe, Then, dy sailing this rake with the,
gross floor area (4037.88 m’) a total estimated budget,
labour cost for the entire project is obtained. Hence, in
Germany, labour costs equate to £220,763.01; this based
‘on the productivity of an ‘average’ contractor.
Asa means of testing this estimate for accuracy, a more
detailed ueceutn can te obra, taeed on he MPRS
and quantities of each construction element contained
in the model. The results for German contractors are
presented in Table 6, Note that the quantities and MPRs
foreach element have been presented earlier, and are now
omitted for clarity.
Tae s
German labour coss perm’ of gfe For each operation
Labour estimate indices
Pacing conerete
Erecting formwork
Fining reinforcement
(0.309 man-hourim pa
1.754 man-hourim gl
0.402 man-hourim? fa
Tate's
Actus} labour cos (in Germany) For each operation and projec overall
Beams Columns
Placing concrete £3764.52 3842.70
Erecting formwork 3658.85 £2546007
Fixing reinforcement £47, 183.29 £23,798.42
Foreach element (ie. beams, columns and floor-slabs)
the cost has been derived from multiplying the MPR by
the quantity in the model and the relevant wage rate
(ic. either for semi-skilled or skilled labour). Here again,
actual labour costs as predicted by the planning engineers
are comparable to that using the quick method previousy
Gescribed. Sn fact, the difference represemis a divergence
of just 11%, which is well within the limits of accuracy
sens emesis 1h he inception KAGE K-RSKGR.
If the quick estimate procedure is repeated for France
and the UK, gross costs for labour are estimated at £31.70
and £45.97 per m? of gfa, respectively. This, therefore
facilitates a comparison of construction (labour) costs,
for che model building in each focation. Hemioe, costs are
estimated at: Germany £220,763.01; France £128,000.00;
and the UK at £185,621.34, Assuming the model building
to be typical of high-rise concrete framed structures, these
budget labour costs could be reasonably adopted for
obtaining estimates of similar structures. As soon as the
afa ofa planned project is identified an estimate of labour
‘wosts cole quite sinnply be deternvines.
‘The methods presented herein have been utilised 10
estimate labour and cost requirements based on ‘average’
productivity. However, by adopting judicious contractor
selection procedures clients and developers may be able
to secure contractors who achieve superior performance
U8), The quick estimating, wah cole wate easly te
adapted to reflect any anticipated changes in contractor
performance. In such instances, the labour indices would
need t0 be recalculated. but on this occasion, instead of
using the MMER values, the values representing the most
productive rates for each operation would need to be
[National all in wage
Labour costim?
rates per of git
Semi skilled as £21.13 £653
Skilled £22.32 9.17
Skilled «@ £22.38 £8.98
Total labour costs of gla = £54.67
Floor slabs Total labour cost
£11.26229 £18,869.51
£26.34225 £32.747.19
73034 28 £144.015 99
Actual overall labour costs = £195,632.6748 D.G. Proverbs Balding and Environment 34 (1999) 43-48
substituted. The subsequent “Labour Estimate Factor’,
would then be representative of high productivity, and
labour requirements and costs could be derived indicative
of such improved performance. Werea more conservative
estimate required, them similarly the least productive
MPRs could be utilised.
4. Summary
Based on the MPRs provided by contractors’ planning,
engineers for a typical conerete framed structure, labour
resource requirements and anticipated construction costs,
in three European countries have been calculated. Based
on information likely to be available at inception, (ie. an,
approximation of the gft of a building) this estimate
was found to be within the level of accuracy normally
expected at this stage. Initially, the quantities of each
operation were normalised to be representative of the gfa
of the model building, Multiplying the MMPRS (for each
operation) by the normalised quantities of each oper-
ation, labour estimate indices were derived. The sum total
of these three indices (referred to as a ‘Labour Estimate
Factor’), then represents the total number of man-hours
required to complete one m’ of gf, and the relative
proportions of reinforcement, formwork and concrete
work, therein. For German contractors, of average” pro-
ductivity, this ‘Labour Estimate Factor’ was 2.465 man-
hour/m? of gfa. By applying this factor to the model
project, German contractors were estimated to require
9953.37 man-hours to complete construction of the
frame. This compared favourably (ie. a disparity of just
11.5%) with the projected figure derived using a more
accurate elemental break-down of the structure.
Taking the process a step further, estimated (labour)
cost per m’ of gfa were also determined. Utilising respec-
tive national all-in wage rates for skilled and semi-skilled
workersin each country. comparable estimates forlabour
costs were derived for each international location. These
estimates were also found to be acceptable in terms of
desired degree of accuracy at inception.
The procedure described herein for in situ conerete
frame construction in France, Germany and the UK,
could conceivably be developed in a number of ways,
Estimates could be determined to represent highly pro-
ductive contractors from each country, or if desired, the
most inefficient firms. There is also scope to extend the
research to other countries, enabling a wider inter-
national comparison to be achieved. Another possibility.
is the development of further design models to represent
other “typical” forms of construction (such as domestic
masonry, high-rise structural steel frames, etc.) then, if
the original research process was repeated using models
of each building form, standard Labour Estimate Factors
and costs per m’ of gfa, could also be developed, rep-
resenting each major construction form in any chosen
international location
References
[1] Herbsmnan Z, Elis R. Research of factors influencing construction
productivity. Construction Management und Economics
1990384961
[2] Koehn E, Brown G. International labour productivity Factors,
Journal of Construction and Management 1986;112(2)299 3
[3] Christian J, Hachey D. Effet of delay times on production rates
in construction, Journal of Construction Enginesring and Man
agement 1995121(1)20 6
[8] Franks 5, Building Contract Administration and Practice, Bats:
Ford, London, 1991.
[5] Royal Institute of Chartered Surveyors, The Building Cost Infor
mation Servie, RICS, Kingston-upon-Thames, Surtey, 1991
[6] Davis Langdon and Everest. Spon’s Architect’sand Builder's Price
Book, 12st edn. Eand FN Spon, London, 1996
[7] Johnson VB. Laxton’s Building Price Book. 168thedn, Reed Infor
Imation Servies, West Susex, 1996,
{8} Buchan RD. Fleming FW. Kelly JR, Estimating for Builders und
Quantity Surveyors. Butlerworth-Heinemann, Oxford, 1993
[9] Smith AJ, Escimating, Tendering and Bidding for Construction,
Macmillan Press Lid, Basingstoke, 1995,
[10] Ashworth A, Skitmore RM. Accuricy in Estimating. Occasional
Paper No, 27, The Chartered Institute of Building, London, 1983,
[11] Proverbs D, Olomolaye. P. Haris F, An evaluation of trans:
portation syatems for high-rse concrete construction, Buildingand
Environment 1996:31(4) 363 74
112] Proverbs D, Olomolaiye P, Harris F. Planned construction times
and labour uiisation—A comparison of UK and French Con
tractors. Engineering, Constroction and Architectural, Man
gement 1996:83) 219-32,
113] Proverbs DG, Holt GD, Olomoluiye PO. Productivity rates and
construction methods for high-rise conerete construction: com-
parative evaluation of UK, German and French contractors. Con
struetion Management and Economics. 1997. in pees.
(14) The Builder Group, ABI Top 40. Building, 1994
[15] Kompass. Register of British Industry and Commeree, Kompass
Publishing Lid. 1994
(16) S.E.R-P., Syndicat National du Béton Arm, des Techniques Ind
stralsées et de TEntrepise Générale (SNBATH), Paris, France
1994,
17] The Builder Group, European Costings. Buildings 1994
4e45
[18] Holt GD. A methodology for predicting the performance of com
sicuetion contractors. Ph.D. thesis, University of Wolverhampton.
UK. 1995,
March,