CU Fortnightly Report - Aug'15 - Final

Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

Package Name: Central Utility

System

Fortnightly Status Update


15-Aug-2015

Jindal Steel and Power Limited


(JSPL)
18 Aug 2015
Central Utility
Index System

S. No. Description Page #

1 Fortnight Highlights 3

2 Executive Summary 5

3 Project Timeline and Delays 6

4 Key Project Issues 7

5 Engineering Status 8

6 Procurement Status 9

7 Sub-Package level Status 13

8 Progress Photographs 14

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 2
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Fortnight Highlights System

Physical Progress Major Highlights


Cum. Fortnight
Total Plan for (up-to 15-Aug-15)
 eNFA approved for Sewage treatment plant.
Area UOM Actual till
Scope Aug-15  159MT of erection completed till 16th Aug’15
15-Aug-15 Plan Actual Lag
ENGINEERING / DRAWINGS RELEASE in Central utilities area against the monthly
Civil (RCC) m3 12,551 6,632 1500 - 600 - plan of 611 MT.
Structural(MT) MT 6,874 3,679 500 - 45 -  UG Piping works started at Utilities area and
CONSTRUCTION / FABRICATION / ERECTION 1,512 INM of pipes erected till 16th Aug’15.
Civil (RCC) m3 12,551 3,436 749 - 140 -  Total piling of 365 no’s completed out of total
Structural Fabrication MT 6,874 2,566 450 - 14 - scope of 1053.
Structural Erection MT 6,874 501 611 - 159  140 cum concreting completed till 16th Aug
out of 749 cum target for the month.
UG Piping INM 8 Lac 1,512 28,000 - 1,512 -
 AG piping works in Bar mill area under
AG Piping(Bar mill) INM 75,000 12,964 21,600 - 9,460 - progress. A total of 12,964 INM piping
Activity to be started, TPL to start piping erection erected as on 16th Aug’15 out of which 9,460
AG Piping INM 17.25Lac
from Aug’15. INM is erected in the month.

Package Ordering - Planned for Aug 2015

Activity Pending Package Name Current Status


Gas Mixing Station - 2&3 eNFA under approval GPH
Consolidated Electrical Package eNFA under approval with GPH
NFA/PO
Consolidated Instrumentation Package eNFA under approval with ED Projects
MCC panel for Bar Mill chiller eNFA under approval with PD
Sewage treatment plant - Blowers/ pumps. eNFA approved on 18-Aug-15, PO to be placed.

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 3
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Fortnight Highlights System

Package Ordering - Planned for Aug 2015

Activity Pending Package Name Current Status

ZLD - Effluent treatment plant system TR is scheduled for 28-Aug-15.


Technical
Recommendation
Chilled water Automation Package (Bar Mill) TR is scheduled for 21-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 4
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Project Highlights: System
Executive Summary

As on 15-Aug-15, 6632 cum of civil drawings (53% of total civil scope) and 3,679 MT of structural drawings (approx. 54% of total structural
scope) are released. Approx. 32% of overall Concreting,37% of fabrication and 7% of erection has been achieved.

Progress Highlights for the month are:


 Civil Works: 365 no’s Piling out of 1053 completed out of which 46 piles are casted in this month. 140 cum completed out of 749
cum(RCC) planned for the month. The cumulative concrete quantity completed is 3,976 cum.
 Structural: 2,566 MT fabricated by SSD against a scope 6,874 MT. Structural erection under progress, 159 MT erection completed out
of 611 MT planned for the month. Total erected quantity is 501MT. UG and AG Piping works started in Utilities and Bar mill areas. A total
of 1,512 INM of UG and 12,964 INM of AG piping completed.
 Procurement:
 eNFA approved for Sewage treatment plant.

• Based on the current status update, there is a potential delay of 155 days & overall commissioning date is shifted to 19-Jun-16 against
the baseline plan of 15-Jan-16 due to envisaged Piling (1053 No’s) in Pipe Rack 1A,2A & 4A , delay in start of Cooling Tower Civil works,
straightening of road #2A & 7A, slow progress in Pipe rack erection works and delay in procurement of critical equipment's like Air
compressors, ZLD.
• It is assumed that for Commissioning of Iron Making Packages, Oxygen & Nitrogen requirement to be met from the existing 2 X 1200
TPD plants. However for continuous operation, ordering of 2200TPD oxygen plant to be expedited.

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 5
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Project Highlights: System
Project Timeline and Delays

Potential Delay
Project Start of 155 Days*

CENTRAL UTILITIES

*01-Mar-14
15-Jan-16 19-Jun-16
*Note: The schedule is made considering the availability of Steam & Oxygen in the existing Phase IA Plants. Only piping is considered in the scope.

*Start of Engineering considered as the Project Start Date.

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 6
(“KPMG International”), a Swiss entity. All rights reserved. Schedule update as on 31st Jul’15.
*Delay shown is not considering ZLD completion.
Central Utility
Key Project Issues System

Sr.
Description Mitigation Strategy Responsibility
No.
In place of 1000 TPD plant. Commercial negotiation is going on for 2200
1 Expedite ordering of Oxygen Plant Project Team
TPD Plant.

For ZLD:TR to be submitted by 28th Aug’15. Procurement and delivery to


be expedited. Project
2 Ordering of ZLD & Consolidated electrical package. Team/Managem
For Electrical pkg: eNFA under approval with GPH. Procurement and ent
delivery to be expedited.

Expedite the completion of straightening of road in 2A to ensure hand


3 Straightening of Road#2A & 7A Management
over of area for civil works to utilities team by sept’15.

Only 600 Cum Civil drawings is released against planned Drawing release to be expedited immediately to provide working fronts to
4 Project Team
quantity of 1500 Cum. CCD.

PO released on 30th of June. Delivery to be expedited and to be ensured


5 Delivery of Air Compressor.
latest by end of Dec’15.
Purchase

Priority wise Engineering drawing release from M/S Essar to


6 be expedited. (45 MT structural drawings are released against Adherence to submitted Look ahead plan for drawing release by Essar. Project Team
planned quantity of 500MT for the month).

Immediate corrective measure to be taken and painting works should be Project


7 Delay in painting of fabricated structures by SSD.
expedited to provide painted structures to M/s TPL for erection. Team/SSD

8 Slow rates of piling in Pipe rack 1A,2A & 4A. CCD to mobilize extra piling rig/Increase rate of piling works. CCD

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 7
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Engineering Status System

Plan Drwg /
Actual Plan for
Total TS Release Cumulative
Package UOM (01 Aug- Next Status Remarks
Scope for the Completion
15 Aug) Fortnight
Month

Civil Cum 12,551 1,500 600 6,632 -

Fabrication MT 6,874 500 45 3,679 -

Technical
- Packages
Specifications

- Long Lead Pkgs. Nos. 0 - - - -

- Medium Lead Pkgs. Nos. 8 0 0 8 0

- Short Lead Pkgs. Nos. 25 0 0 25 0

L Long Lead M Medium Lead S Short Lead


> 12 Months 6 – 12 Months < 6 Months

Corrective Measures required Delay and attention required On schedule


© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 8
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Procurement Status(1/4) System

Long Lead Packages (A) Medium Lead Packages (B) Short Lead Packages (C)

Total Packages: Nil No. of Packages: 8 No. of Packages: 25


Packages Ordered / LOI issued: Nil Packages Ordered / LOI issued: 6 Packages Ordered / LOI issued: 20

Procurement - Ordering Status


Enquiry Technical Commercial Note for
Category Total scope TS Issued Offers Receipt PO placed
Floated Recommendation Negotiation Approval
B (Medium Lead) 8 8 8 8 7 7 6 6
C (Short Lead) 25 25 25 25 24 24 20 20
Grand Total>> 33 33 33 33 31 31 26 26

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 9
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Procurement Status – Package Ordering in progress (2/4)

Actual / Expected Completion Dates


S MECHANICAL
Category Stream Enquiry Last Offer TR NFA PO
No Procurement Packages TS Receipt NFA Initiation
Floatation Receipt Submission Approval Release

1 Compressed Air - Air Compressor B M 30-Sep-14 30-Sep-14 10-Oct-14 23-Apr-15 18-May-15 22-Jun-15 30-Jun-15

2 Compressed Air - Dryer 1 B M 30-Sep-14 30-Sep-14 9-Oct-14 5-Nov-14 6-Dec-14 30-Jan-15 13-Feb-15

3 Compressed Air - Receivers C M 6-Oct-14 7-Oct-14 17-Oct-14 13-Nov-14 5-Dec-14 19-Dec-14 29-Dec-14
Chilled Water - Chilled Water System-
4 B M 25-Jun-14 21-Jul-14 11-Aug-14 02-Dec-14 31-Jan-15 31-Mar-15 07-Apr-15
VAM & VCM
Cooling Tower - Cooling Tower
5 B M 28-May-14 12-Jul-14 28-Jul-14 02-Dec-14 9-Jan-15 12-Jan-15 29-Jan-15
Equipment

6 Cooling Tower - Side Stream filter C M 26-Dec-14 31-Dec-14 03-Feb-15 23-Apr-15 14-May-15 20-May-15 25-May-15

7 Gas Mixing Station - 1 C M 20-Oct-14 20-Oct-14 2-Feb-15 22-Apr-15 30-Apr-15 28-Apr-15 05-May-15

8 Gas Mixing Station - 2&3 C M 6-Nov-14 3-Jun-15 30-Jun-15 8-Jul-15 29-Jul-15 20-Aug-15 27-Aug-15
Pipes-AG,UG,Bar Mill- Big Bore(1800
9 C M 22-Oct-14 3-Nov-14 13-Nov-14 24-Dec-14 21-Mar-15 04-Apr-15 23-Mar-15
Dia-2500Dia)
Pipes-AG,UG,Bar Mill- Big Bore(600
10 C M 21-Aug-14 1-Sep-14 15-Sep-14 11-Dec-14 23-Dec-14 6-Jan-15 2-Apr-15
Dia-1600Dia)
Pipe AG-UG- Bar Mill - Dia(150-500)
11 C M comp comp comp comp comp comp 28-Jan-15
ERW,CS
Pipe AG-UG- Bar Mill -
12 C M comp 6-Jun-15 8-Jun-15 9-Jun-15 25-Jun-15 9-Jul-15 20-Jul-15
Dia(80,100,200,350,400) ERW,CS
PIPE AG Dia 600 seamless oxygen
13 C M comp comp comp comp 26-May-15 22-Jun-15 21-Jul-15
service

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 10
(“KPMG International”), a Swiss entity. All rights reserved. Procurement Tracker updated on 19th Aug’15
Central Utilities
Procurement Status – Package Ordering in progress (3/4)

Actual / Expected Completion Dates


S MECHANICAL
Category Stream Enquiry Last Offer TR NFA PO
No Procurement Packages TS Receipt NFA Initiation
Floatation Receipt Submission Approval Release

Pipe AG Dia 450(Oxygen) & Dia


14 C M comp comp comp comp 24-May-15 22-Jun-15 8-Jul-15
500(steam)
15 Pipe Bar Mill Dia 15,50,80 C M comp 6-Jun-15 comp comp comp comp 9-Jun-15

16 Pipe Dia 25,200 seamless-Steam C M comp comp comp comp comp 8-Jun-15 9-Jun-15
Pipe AG Dia 150 Seamless
17 C M comp comp comp comp comp comp 27-Apr-15
Galvanised

18 Pipe UG Dia 150 Galvanized C M comp comp comp comp comp comp 26-Mar-15

19 Pipes-UG & AG- Fittings C M 21-Aug-14 1-Sep-14 24-Jan-15 11-Feb-15 27-May-15 29-May-15 20-Jun-15

20 Pipes-UG Valves C M 21-Aug-14 1-Sep-14 12-Dec-14 7-Jan-15 6-Feb-15 12-Feb-15 15-Feb-15

21 Pipes-AG Valves C M 12-Mar-15 21-Mar-15 16-Apr-15 28-Apr-15 1-Jun-15 21-Jun-15 22-Jun-15

22 Central Utilities- EOT Crane C M 26-Jun-14 14-Oct-14 29-Oct-14 10-Nov-14 25-Dec-14 7-Jan-15 31-Jan-15

HPS - Hydropneumatic
23 C M 18-Sep-14 18-Nov-14 3-Dec-14 15-Dec-14 25-Mar-15 4-Apr-15 7-Apr-15
System(Drinking water Skid)
Pumps for Chilled Water plant,
24 Cooling water, Firewater & Drinking B M 10-Oct-14 10-Oct-14 7-Nov-14 19-Nov-14 18-Mar-15 31-Mar-15 10-Apr-15
water

25 Consolidated Electrical Package B E&I 15-Jan-15 30-Mar-15 16-Apr-15 13-Jul-15 24-Jul-15 20-Aug-15 27-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 11
(“KPMG International”), a Swiss entity. All rights reserved. Procurement Tracker updated on 19th Aug’15
Central Utilities
Procurement Status – Package Ordering in progress (4/4)

Actual / Expected Completion Dates


S MECHANICAL
Category Stream Enquiry Last Offer TR NFA PO
No Procurement Packages TS Receipt NFA Initiation
Floatation Receipt Submission Approval Release

Consolidated Instrumentation
26 C E&I 27-Mar-15 3-Apr-15 22-Jun-15 15-Jul-15 4-Aug-15 21-Aug-15 28-Aug-15
Package
27 Mcc panel for Bar Mill chiller C E&I 10-Apr-15 18-Apr-15 2-Jun-15 8-Jul-15 10-Aug-15 24-Aug-15 31-Aug-15
Sewage treatment plant - Blowers/
28 pumps, Clarifier Eqpts, Filter Press, C M 6-Nov-14 28-Jun-15 1-Jul-15 16-Jul-15 31-Jul-15 18-Aug-15 22-Aug-15
Filters
29 ZLD - Effluent treatment plant system B M 27-Nov-14 1-Dec-14 20-Jun-15 28-Aug-15 12-Sep-15 22-Sep-15 29-Sep-15

30 Cooling Tower (Bar Mill) B M 20-Dec-14 5-Jan-15 18-Feb-15 2-Mar-15 17-Mar-15 12-May-15 19-May-15

31 PRS C M 20-Dec-14 22-Dec-14 4-Feb-15 16-Feb-15 18-May-15 20-May-15 23-May-15

32 Valves (Bar Mill) C M 5-Mar-15 14-Mar-15 9-Apr-15 21-Apr-15 28-May-15 8-Jun-15 25-Jun-15
Chilled water Automation Package
33 C E&I 6-Jun-15 9-Jun-15 18-Jul-15 21-Aug-15 05-Sep-15 15-Sep-15 22-Sep-15
(BarMill)

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 12
(“KPMG International”), a Swiss entity. All rights reserved. Procurement Tracker updated on 19th Aug’15
Central Utility
Sub Package Level Status System

Estimated Expected Percentage Completion


Sr. Baseline Baseline
Project Activities Date of Progress Delay in
No. Start Date Finish Date
Completion Days
NS 0-50 60-100 Finish

1 Chilled Water System 01-Mar-14 30-Dec-15 4-Apr-16 95 Days 

2 Gas Mixing Station 01-Mar-14 14-Jan-16 17-Feb-16 33 Days 

3 Plant Water System 01-Mar-14 26-Dec-15 15-May-16 140 Days 

4 Gas Distribution System 01-Mar-14 15-Jan-16 19-Jun-16 155 Days 

5 Compressed Air System 01-Mar-14 10-Jan-16 05-Apr-16 85 Days 

6 Sewage Treatment Plant 01-Mar-14 30-Dec-15 13-Feb-16 44 Days 

7 Zero Liquid Discharge 01-Mar-14 11-Jan-16 27-Jun-16 167 Days 

8 Sub-station 01-Mar-14 15-Jan-16 08-May-16 113 Days 

Progress Corrective Measures required Delay and attention required On Schedule To be started
%age of Completion Not Started 0-50% 50 -100% Completed

# Estimated Date for Completion

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 13
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System

Chilled Water Plant Area


31-Jul-15 15-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 14
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System

Pipe Rack
31-Jul-15 15-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 15
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System

Fire Water Pump house Area


31-Jul-15 15-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 16
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System

Compressed Air Station Area


31-Jul-15 15-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 17
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System

Drinking Water Pump House Area


31-Jul-15 15-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 18
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System

HTSS Area
31-Jul-15 15-Aug-15

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 19
(“KPMG International”), a Swiss entity. All rights reserved.
Document Audit Trail
# Event Event Owner Date
1 Release of Draft Report
KPMG 18-Aug-15

2 Discussion of draft
Fortnightly Status
KPMG
Update with Project
team
3 Circulation of Fortnightly
KPMG
Status Update

© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network
of independent member firms affiliated with KPMG International Cooperative
(“KPMG International”), a Swiss entity. All rights reserved.

The KPMG name, logo and "cutting through complexity" are registered
trademarks or trademarks of KPMG International Cooperative ("KPMG
International").

You might also like