CU Fortnightly Report - Aug'15 - Final
CU Fortnightly Report - Aug'15 - Final
CU Fortnightly Report - Aug'15 - Final
System
1 Fortnight Highlights 3
2 Executive Summary 5
5 Engineering Status 8
6 Procurement Status 9
8 Progress Photographs 14
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 2
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Fortnight Highlights System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 3
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Fortnight Highlights System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 4
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Project Highlights: System
Executive Summary
As on 15-Aug-15, 6632 cum of civil drawings (53% of total civil scope) and 3,679 MT of structural drawings (approx. 54% of total structural
scope) are released. Approx. 32% of overall Concreting,37% of fabrication and 7% of erection has been achieved.
• Based on the current status update, there is a potential delay of 155 days & overall commissioning date is shifted to 19-Jun-16 against
the baseline plan of 15-Jan-16 due to envisaged Piling (1053 No’s) in Pipe Rack 1A,2A & 4A , delay in start of Cooling Tower Civil works,
straightening of road #2A & 7A, slow progress in Pipe rack erection works and delay in procurement of critical equipment's like Air
compressors, ZLD.
• It is assumed that for Commissioning of Iron Making Packages, Oxygen & Nitrogen requirement to be met from the existing 2 X 1200
TPD plants. However for continuous operation, ordering of 2200TPD oxygen plant to be expedited.
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 5
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Project Highlights: System
Project Timeline and Delays
Potential Delay
Project Start of 155 Days*
CENTRAL UTILITIES
*01-Mar-14
15-Jan-16 19-Jun-16
*Note: The schedule is made considering the availability of Steam & Oxygen in the existing Phase IA Plants. Only piping is considered in the scope.
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 6
(“KPMG International”), a Swiss entity. All rights reserved. Schedule update as on 31st Jul’15.
*Delay shown is not considering ZLD completion.
Central Utility
Key Project Issues System
Sr.
Description Mitigation Strategy Responsibility
No.
In place of 1000 TPD plant. Commercial negotiation is going on for 2200
1 Expedite ordering of Oxygen Plant Project Team
TPD Plant.
Only 600 Cum Civil drawings is released against planned Drawing release to be expedited immediately to provide working fronts to
4 Project Team
quantity of 1500 Cum. CCD.
8 Slow rates of piling in Pipe rack 1A,2A & 4A. CCD to mobilize extra piling rig/Increase rate of piling works. CCD
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 7
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utility
Engineering Status System
Plan Drwg /
Actual Plan for
Total TS Release Cumulative
Package UOM (01 Aug- Next Status Remarks
Scope for the Completion
15 Aug) Fortnight
Month
Technical
- Packages
Specifications
Long Lead Packages (A) Medium Lead Packages (B) Short Lead Packages (C)
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 9
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Procurement Status – Package Ordering in progress (2/4)
1 Compressed Air - Air Compressor B M 30-Sep-14 30-Sep-14 10-Oct-14 23-Apr-15 18-May-15 22-Jun-15 30-Jun-15
2 Compressed Air - Dryer 1 B M 30-Sep-14 30-Sep-14 9-Oct-14 5-Nov-14 6-Dec-14 30-Jan-15 13-Feb-15
3 Compressed Air - Receivers C M 6-Oct-14 7-Oct-14 17-Oct-14 13-Nov-14 5-Dec-14 19-Dec-14 29-Dec-14
Chilled Water - Chilled Water System-
4 B M 25-Jun-14 21-Jul-14 11-Aug-14 02-Dec-14 31-Jan-15 31-Mar-15 07-Apr-15
VAM & VCM
Cooling Tower - Cooling Tower
5 B M 28-May-14 12-Jul-14 28-Jul-14 02-Dec-14 9-Jan-15 12-Jan-15 29-Jan-15
Equipment
6 Cooling Tower - Side Stream filter C M 26-Dec-14 31-Dec-14 03-Feb-15 23-Apr-15 14-May-15 20-May-15 25-May-15
7 Gas Mixing Station - 1 C M 20-Oct-14 20-Oct-14 2-Feb-15 22-Apr-15 30-Apr-15 28-Apr-15 05-May-15
8 Gas Mixing Station - 2&3 C M 6-Nov-14 3-Jun-15 30-Jun-15 8-Jul-15 29-Jul-15 20-Aug-15 27-Aug-15
Pipes-AG,UG,Bar Mill- Big Bore(1800
9 C M 22-Oct-14 3-Nov-14 13-Nov-14 24-Dec-14 21-Mar-15 04-Apr-15 23-Mar-15
Dia-2500Dia)
Pipes-AG,UG,Bar Mill- Big Bore(600
10 C M 21-Aug-14 1-Sep-14 15-Sep-14 11-Dec-14 23-Dec-14 6-Jan-15 2-Apr-15
Dia-1600Dia)
Pipe AG-UG- Bar Mill - Dia(150-500)
11 C M comp comp comp comp comp comp 28-Jan-15
ERW,CS
Pipe AG-UG- Bar Mill -
12 C M comp 6-Jun-15 8-Jun-15 9-Jun-15 25-Jun-15 9-Jul-15 20-Jul-15
Dia(80,100,200,350,400) ERW,CS
PIPE AG Dia 600 seamless oxygen
13 C M comp comp comp comp 26-May-15 22-Jun-15 21-Jul-15
service
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 10
(“KPMG International”), a Swiss entity. All rights reserved. Procurement Tracker updated on 19th Aug’15
Central Utilities
Procurement Status – Package Ordering in progress (3/4)
16 Pipe Dia 25,200 seamless-Steam C M comp comp comp comp comp 8-Jun-15 9-Jun-15
Pipe AG Dia 150 Seamless
17 C M comp comp comp comp comp comp 27-Apr-15
Galvanised
18 Pipe UG Dia 150 Galvanized C M comp comp comp comp comp comp 26-Mar-15
19 Pipes-UG & AG- Fittings C M 21-Aug-14 1-Sep-14 24-Jan-15 11-Feb-15 27-May-15 29-May-15 20-Jun-15
22 Central Utilities- EOT Crane C M 26-Jun-14 14-Oct-14 29-Oct-14 10-Nov-14 25-Dec-14 7-Jan-15 31-Jan-15
HPS - Hydropneumatic
23 C M 18-Sep-14 18-Nov-14 3-Dec-14 15-Dec-14 25-Mar-15 4-Apr-15 7-Apr-15
System(Drinking water Skid)
Pumps for Chilled Water plant,
24 Cooling water, Firewater & Drinking B M 10-Oct-14 10-Oct-14 7-Nov-14 19-Nov-14 18-Mar-15 31-Mar-15 10-Apr-15
water
25 Consolidated Electrical Package B E&I 15-Jan-15 30-Mar-15 16-Apr-15 13-Jul-15 24-Jul-15 20-Aug-15 27-Aug-15
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 11
(“KPMG International”), a Swiss entity. All rights reserved. Procurement Tracker updated on 19th Aug’15
Central Utilities
Procurement Status – Package Ordering in progress (4/4)
Consolidated Instrumentation
26 C E&I 27-Mar-15 3-Apr-15 22-Jun-15 15-Jul-15 4-Aug-15 21-Aug-15 28-Aug-15
Package
27 Mcc panel for Bar Mill chiller C E&I 10-Apr-15 18-Apr-15 2-Jun-15 8-Jul-15 10-Aug-15 24-Aug-15 31-Aug-15
Sewage treatment plant - Blowers/
28 pumps, Clarifier Eqpts, Filter Press, C M 6-Nov-14 28-Jun-15 1-Jul-15 16-Jul-15 31-Jul-15 18-Aug-15 22-Aug-15
Filters
29 ZLD - Effluent treatment plant system B M 27-Nov-14 1-Dec-14 20-Jun-15 28-Aug-15 12-Sep-15 22-Sep-15 29-Sep-15
30 Cooling Tower (Bar Mill) B M 20-Dec-14 5-Jan-15 18-Feb-15 2-Mar-15 17-Mar-15 12-May-15 19-May-15
32 Valves (Bar Mill) C M 5-Mar-15 14-Mar-15 9-Apr-15 21-Apr-15 28-May-15 8-Jun-15 25-Jun-15
Chilled water Automation Package
33 C E&I 6-Jun-15 9-Jun-15 18-Jul-15 21-Aug-15 05-Sep-15 15-Sep-15 22-Sep-15
(BarMill)
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 12
(“KPMG International”), a Swiss entity. All rights reserved. Procurement Tracker updated on 19th Aug’15
Central Utility
Sub Package Level Status System
Progress Corrective Measures required Delay and attention required On Schedule To be started
%age of Completion Not Started 0-50% 50 -100% Completed
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 13
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 14
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System
Pipe Rack
31-Jul-15 15-Aug-15
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 15
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 16
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 17
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 18
(“KPMG International”), a Swiss entity. All rights reserved.
Central Utilities
Progress Photographs System
HTSS Area
31-Jul-15 15-Aug-15
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of independent member firms affiliated with KPMG International Cooperative 19
(“KPMG International”), a Swiss entity. All rights reserved.
Document Audit Trail
# Event Event Owner Date
1 Release of Draft Report
KPMG 18-Aug-15
2 Discussion of draft
Fortnightly Status
KPMG
Update with Project
team
3 Circulation of Fortnightly
KPMG
Status Update
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network
of independent member firms affiliated with KPMG International Cooperative
(“KPMG International”), a Swiss entity. All rights reserved.
The KPMG name, logo and "cutting through complexity" are registered
trademarks or trademarks of KPMG International Cooperative ("KPMG
International").