RMHS Monthly Report Aug'15
RMHS Monthly Report Aug'15
RMHS Monthly Report Aug'15
10 September 2015
# Contents
This monthly progress report is prepared by the Angul
Project’s PMO to report on the Raw Material Handling A Project Highlights:
System (‘RMHS’) package status. • Snapshot – Progress Overview
• Progress Dashboard
• Project Summery
The salient features of the project include: • Civil Works Status
• Structural Works Status
• Target Completion without Wagon Tippler revised to
• Schedule Analysis – Projected Delays
15-Jan-2016 from Oct-2015
• Analysis of Delays and Mitigation Measures
• Target Completion with Wagon Tippler revised to • Procurement Progress in Month
31-Mar-2016 from Dec-2015 • Progress Score-card
• Baseline L3 Schedule revised in Dec-2014 • Execution Plan for Next Month
• Monthly Look Ahead Projection
Raw Material Handling System: • Procurement Plan for Next Month
• JSPL Raipur Dispatch Status
Size: Stacking 3000 TPH
Reclaiming 2000 TPH B Progress Reports
• Engineering
Main Supplier: JSPL, Raipur • Procurement
• Construction
Engg. Consultant: Essar Projects (I) Ltd
C Variance / Gap Analysis and Mitigation Measures
Main Contractors:
D Area wise Detailed Progress
• Civil JSPL – CCD
E Contractor Evaluation
• Structural Fabrication JSPL – SSD
F Health & Safety Report Extract
• Structure Erection TPL, Hyderabad
G SAP Budget and Cashflow Extract
• Mechanical Erection TPL, Hyderabad H Progress Photographs
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 2
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (1/13): Handling System
Snapshot – Progress Overview
1) JH105 39) Coal Blending Bin
56 55 40) JH207
57 2) JH106
3) J102C3/C4 41) JH208
4) J101C4/C5 42) PCIC1
59
19 2 1
58 5) JH102 43) PCI Building
6) J101C6/C7 & J102C1/C2 44) J209RC1
60
36 18 7) JH101A/B 45) JH209
35 46) SH1C1
8) J101C1/C2/C3
45 46 9) Wagon Tippler 47) JH204
21 20 15
34 16 48) JH214
44
17 10) J104C1/C2/C3
52 51 54
11) JH104 49) SH1C4
50 48
33 37 49 47 12) J206C1/C2 50) J214C1
32 41 53 42
43 3 4 13) JH206 51) JH215
30 31 22 14) J401C1/PBC1 52) J215C1
29
15) JH401 53) J216C1
14
16) CSC1/C2 54) J216C2
28
17) Sinter Plant Crushing Station 55) JH201
40 56) J202C1
18) PBC1/C2
27 19) PBJH01 57) JH202
20) J401C4/C5 58) J204C1
26 21) JH216 59) J203TC1
25
22) JH213 60) JH203
23) J302C1/C2/C3
23 24
24) JH302
39 25) J303C1/ J304C1/ J305C1
6 5 26) JH303
38 10 7 27) J304C1/ J305C1/ J306C1
12 11
13 28) JH304
29) J305C1/ J306C1/ J307C1
8 30) JH305
31) J213C1
32) J306C1/ J307C1
33) JH306
9 34) J307C1
35) JH307
36) SH1C2
37) SH1C3 Under
38) 805AC1 HOLD
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 3
Construction Drawing Available but Engineering/
independent member firms affiliated with KPMG International Cooperative (“KPMG Deferred
International”), a Swiss entity. All rights reserved. in Progress construction not started Drawing Awaited
Raw Material
Project Highlights (2/13): Handling System
Progress Dashboard
Concrete-RCC Cum 27,664 24,167 10,487 2,933 2,026 69% Nov-15 1,491 4,751
o Structural Erection commenced by
Without Wagon
TPL at – Concrete-PCC Cum 3,725 2,412 1761 283 270 95% Oct-15 344 437
Tippler
o Conveyor trestle between
JH207 to JH 208 Str Fabrication MT 10,890 8,407 3,588 1210 472 38% Dec-15 510 1,528
o JH105 & JH106 Structural MT 10,890 N/A 267 873 201 23% Jan-16 65 1,217
With Wagon Tippler Erection
o E-NFA initiated by purchase for - Concrete-RCC Cum 57,064 24,119 8,474 2,933 1,991 65% Mar-16 1,491 4,751
o Automaton &
Concrete-PCC Cum 3,725 2,412 1491 283 277 65% Oct-15 344 437
Instrumentation
o Cables Package Str Fabrication MT 11,360 7,462 3,588b 1210 462 38% Mar-16 510 935
o Vibro-feeder for Ground
Structural MT
Hopper 11,360 N/A 267 873 201 23% Apr-16 65 919
Erection
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 4
independent member firms affiliated with KPMG International Cooperative (“KPMG # Excluding finishing works
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (3/13): Handling System
Project Summary
In the period 01-Aug-15 to 31-Aug-15, 48 m3 of civil drawings (RCC) and 945 MT of structural drawings were released, and 2026 Cum of
Concrete, 472 MT of structural fabrication and 201 MT of Structural Erection work was done.
Given the current progress, RMHS is expected to get commissioned with a delayed of 115 days and is expected to feed sinter plant by
08-May-2016, coke oven & byproduct plant by 07-Jun-2016 and blast furnace by 13-Jun-2016 through connection with existing yard
conveyors. Further commissioning of RMHS with Stacker cum Reclaimer is delayed by 238 days and is expected to feed sinter plant
by 25-Aug-2016, coke oven and byproduct plant by 09-Sep-2016 and blast furnace by 24-Sep-2016. Tandem Wagon Tippler is
expected to get commissioned by 15-Dec-2016.
Based on the quantity based “S” curve for Raw Material handling packages, project is 30% completed against plan of 79.4%.
Till date, Rs 39 cr has been spent against planned expenditure of Rs 274 cr.
Major delay is attributable to the delayed order placement of major packages such as Stacker cum Reclaimer & Wagon Tippler package
which has delayed the engineering of the same. Further delay in start of civil work has also delayed the construction activity.
The forecasted dates can be reduced with additional efforts on following fronts:
• Expediting the Construction work at Receipt and Storage area (Zone -1)
• Expediting detailed engineering for –
(a) inter connection of existing and proposed yard conveyor (b) Stacker cum Reclaimer (c) Tandem Wagon Tippler.
Activities on the critical path include:
(a) Structural Fabrication of Conveyor and Junction House
(b) Detailed Engineering of JH 101 & Civil work at Receipt & Storage Area (Zone 1).
(c) Ordering of Bought-out for Conveyor and Stacker Cum Reclaimer Package by JSPL Raipur
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 5
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (4/13): Handling System
Civil Work Progress
Drawing Release in
Scope of Drawing Civil Civil Execution in Aug’15 Plan for Sep’15
Aug’15
Area Concrete Released till Execution till
Drawing Civil
(RCC) 31-Aug-15 31-Jul-15 Plan Actual Plan Actual
Release Execution
1 Electrical Substation - HTSS 1,300 176 79 - 0 79 - -
Wagon Tippler & Truck Tippler (Including
2 29,400 - - - - - -
Tunnel)
Zone 1 Tunnels (Excluding from Wagon
3 7,345 7,111 4,132 - 1309 624
Tippler)
4 Stacker Cum Reclaimer 11,437 11,438 3,210 - 758 718
5 Zone 1 Junction Houses 1,406 732 577 - 148 249
6 Zone 2 Junction Houses 860 0 - - 0 0
7 Zone 3 Junction Houses 1,495 1,521 787 - 56 63
8 Zone 2 Conveyors 915 85 22 - 85 22
9 Zone 3 Conveyors 2,906 2,505 1,680 - 577 271
Total (RCC) 57,064 24,167 10,487 5,000* 48 2,933 2,026 14,952* 2,811*
42% of 69% of
% Achieved (RCC) 18% of Scope 1% of Month Plan
Scope Month Plan
Total (PCC) 3,725** 2,412 1,761 NA NA 283 270 NA 245
Total (RCC+PCC) 57,064 26,531 1,2248 3,022 437 3,216 2,296 14,952 3,056
47% of 71% of
% Achieved (RCC+PCC) Included 18% of Scope 15% of Month Plan
Scope Month Plan
11 Others 32 -
Total 11,360 8,407 3,588* 267 1,0001 945 1,210 472 8731 2011 NA 10201 1133
74% of 32% of 3% of 94.5% of 39% of Month
% Achieved 23% of Plan
Scope Scope Scope Month Plan Plan
* Total Painted till 31-Aug-15: Not Available 1 Structure wise breakup not available
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 7
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (6/13): Handling System
Schedule Analysis – Projected Delays
Start of Planned
Engineering BL – 1 Commissioning #
30-Oct-15
Potential Delay
RAW MATERIAL Planned Completion (79 %) of 115 Days
HANDLING SYSTEM Actual Completion (30 %)
Dec-13 30-Jan-15 15-Jan-16 08-May-16
Potential Delay
of 238 Days
Progress S-Curve #
100
Reasons for Delay:
% Complete (Plan) o Delay in start of engineering of long lead
% Complete (Actual) packages – Stacker cum Reclaimer, Tandem
80 79.4%
Wagon Tippler
o Delay in commencement of Civil works
60
o Hold on Tunnel drawings from Emergency
Gap hopper provision of JH 101B to JH 103B
Analysis
40
30% Mitigation Actions Planned / Underway:
Expedite civil works of critical areas – JH101 and
20
associated tunnels
Expedite pilling work at Storage and Receipt area
0
Expedite the structural fabrication based on erection
priority
Expedite the rate of Structural Erection by TPL to 1200
Management Support Required: MT/Month
Expedite engineering of Connection between existing and proposed Availability of equipments such for Structural erection
yard conveyors & JH 101 Engineering to be completed for existing and proposed
yard conveyors
Expedite to increase the rate of fabrication by SSD
Expedite detailed engineering & manufacturing of
Ordering of Conveyor related packages by JSPL Raipur
Stacker cum Reclaimer & Wagon Tippler
# The S-Curve is based on weighted average percentages derived from the proportion of physical quantity engineering, procurement, construction and commissioning quantities for
the project. This cure is revised based on revised delivery schedule of equipment.
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 9
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (8/13): Handling System
Procurement Progress in Month
TS Issue TR Submission NFA Initiation NFA Approval PO Release
Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual
4 2 2 1 7 3 7 2 5 2
High Pressure Single Fluid Fog High Pressure Single Fluid Fog Consolidated Electrical
EOT Crane Underslung Crane
System System Package
Plain Water Spraying System Cable
Underslung Crane Ventilation System Hoist
at Storage/ Dispatch Area
Automation &
Automation &
Sump Pump Underslung Crane Instrumentation
Instrumentation
6 Vibro feeder for Ground
PA & Telephone System, 6 Vibrofeeder for Ground
Hoist Hopper
CCTV Hopper
Dust Extraction System
Cable Dust Extraction System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 10
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Complete Could Not Be Done
Raw Material
Project Highlights (9/13): Handling System
Progress Scorecard
Package Scorecard
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 11
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (10/13): Handling System
Execution Plan for Next Month – Sep 2015
Civil Execution Plan: 3,056m3 Structural Fabrication Plan: 1020 MT Structural Erection Plan: 1133 MT
SSD Angul: 1020 MT
Asking Rate as per Catchup 4,751 m3 Asking Rate as per Catchup Plan 1,217MT
Plan Asking Rate as per Catchup Plan 1,528 MT
Maximum Erection achieved 201
Maximum RCC achieved 2,026 m3 Maximum fabrication achieved 905 MT
Average Erection achieved 65
Average RCC achieved 1491 m3 Average fabrication achieved 510 MT
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of
independent member firms affiliated with KPMG International Cooperative (“KPMG Some Resource Available but Resource Not Available. This 12
International”), a Swiss entity. All rights reserved. Resource Available
Additional Effort required should be dealt on priority
Raw Material
Project Highlights (11/13): Handling System
Monthly Look Ahead Projection
May’16
Aug’16
Nov’15
Nov’16
Sep’15
Dec’15
Sep’16
Dec’16
Mar’16
Feb’16
Jun’16
Jan’16
Achieved Balance
Oct’15
Apr’16
Oct’16
Jul’16
Total
Discipline till to
Scope
31-Aug-15 Achieve
Engineering-Civil
57,064 24,167 32,897 14,952 10,000 5,300 2,645
Concrete (CuM)
Engineering-
11,360 8,407 2,953 1,000 1,000 898
Structural (MT)
Civil Execution –
57,064 12,248 44,816 3,056 3,685 3,204 2,695 3,240 3,250 3,250 3,021 3,000 3,000 3,000 3,000 2,500 2,000 1,500 1,415
Concrete (CuM)
Structural
Fabrication-Total 11,360 3,588 7,772 1,020 1,485 1,600 1,600 1,200 500 367
(MT)
Structural Erection
11,360 267 11,093 1,133 1,259 1,500 1,500 1,600 1,500 1200 900 501
(MT)
Equipment Erection
13,355 - 13,355 128 200 1,200 1,500 1,600 1,800 1,400 1,400 1,100 1,000 1,000 100 250 250 250 177
(MT)
Above projections are made based on high level discussion with project team.
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 13
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Project Highlights (12/13): Handling System
Procurement Plan for Next Month – Sep 2015
TS Issue TR Submission NFA Initiation NFA Approval PO Release
Plan: 2 Plan: 2 Plan: 5 Plan: 5 Plan: 5
High Pressure Single Consolidated Electrical
High Pressure Single
EOT Crane 10-Sep Sump Pump 17-Sep 15-Sep Fluid Fog System 29-Sep Package 12-Sep
Fluid Fog System
Plain Water Spraying
Ventilation System Cable
System at Storage/ 10-Sep Underslung Crane 5-Sep Ventilation System 15-Sep 29-Sep 9-Sep
Dispatch Area
Automation &
Underslung Crane
Underslung Crane 20-Sep 30-Sep Instrumentation 12-Sep
Cable 2-Sep
1 April’15 100 0 0%
5 Aug’15 NA 44.95
Total for Zone 3 1000 280.31 28%
Total (Zone1 & 3) 1600 611.62 38%
Above projections are made based on high level discussion with project team.
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 15
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
B. Progress Report:
Engineering, Procurement and
Construction
Raw Material
Engineering Handling System
Activity UOM Total Drawing Release for Aug’15 Cumulative Key Reasons for Shortfall in Month
Scope Plan Actual % of Monthly Drawing
Plan Released till
31-Aug-15
Major drawings included in the plan was of wagon
Civil (RCC+PCC) Cum 57,064 5,000 48 1% 24,167 tippler which required more time to be completed
and is considered in the plan of Sep’15
Design changes in junction houses and conveyors
Structural (Building +
MT 11,360 1000 945 95 % 8,407 associated with material flow from sinter plant to
Technological)
blast furnace stock house
Cumulative Civil Drawing Release (Cum) Cumulative Structural Drawing Release (MT)
60,000 14,000
50,000 12,000
10,000
40,000
8,000
30,000
Potential Delay 6,000
Potential Delay
of 2 Months of 3 Months
20,000
4,000
10,000
2,000
0 0
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 17
independent member firms affiliated with KPMG International Cooperative (“KPMG
Baseline Drawing Actual Drawing Project at Current Catchup
International”), a Swiss entity. All rights reserved. Release Plan Released Drawing Release Rate Plan
Raw Material
Handling System
Construction
Activity UOM Total Drawings Execution in Aug-15 Cumulative Key Reasons for Shortfall in Month
Scope Released till Plan Actual % of Execution till
31-Aug-15 Monthly 31-Aug-15
Plan
Concrete (RCC+PCC) Cum 57,064 26,168 3,216 2,296 71% 10,487 Due to rain and also due to front not available
Manpower shortage in painting
Structural Fabrication MT 11,360 7,462 1,210 462 38% 3,588
Space constraint in fabrication & painting yard
Manpower shortage, small structures not
Structural Erection MT 11,360 N/A 873 201 23% 267 available in sequence ,shortage of
equipments
Cumulative Civil Execution (Cum) Cumulative Structural Fabrication (MT) Cumulative Structural Erection (MT)
60,000 14,000 14,000
12,000 12,000
50,000
10,000 10,000
40,000
8,000 8,000
30,000
6,000 6,000
0 0 0
Jun-14
Aug-14
Dec-14
Jun-15
Oct-14
Aug-15
Dec-15
Jun-16
Apr-15
Oct-15
Aug-16
Apr-16
Oct-16
Feb-15
Feb-16
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 18
independent member firms affiliated with KPMG International Cooperative (“KPMG
Baseline Actual Project at Current Catchup
International”), a Swiss entity. All rights reserved. Execution Plan Execution Execution Rate Plan
Raw Material
Procurement Status – Package Ordering (1/3) Handling System
01-Nov-
6 Hoist C 15-Nov-14 19-Jan-15 05-Feb-15 18-Jul-15 28-Aug-15 8-Sep-15 30-Aug-15 25-sep-15 Purchase
14
18-Dec-
10 Sump Pumps C TS to be received Essar
14
Corrective Measures required Delay and attention required On schedule Activity Completed
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of TS – Technical Specification LOI – Letter of Intent 19
independent member firms affiliated with KPMG International Cooperative (“KPMG NFA – Note for Approval
International”), a Swiss entity. All rights reserved.
TR – Technical Recommendation
PO – Purchase Order
Raw Material
Procurement Status – Package Ordering (2/3) Handling System
13 Cable B 10-Nov-14 - 15-Apr-15 05-May-15 15-Jul-15 25-Jul-15 2-Sep-15 27-Jul-15 9-Sep-15 Purchase
* Consolidated Electrical Package includes: Distribution Transformer (6.6kV/0.433kV), 415V Switchboard, LT Busduct (415V), Battery Charger & DCDB, UPS & ACDB,
Battery for Charger & UPS, LDB/ Aux Panel, LV Power & Control Cable, Cable Termination & Straight Through Joining Kit, Cable Tray, Lighting Fixtures, Welding Socket,
Junction Box/LCS, Earthing & Lightning Protection Material, MV Motor, LV Motor
6 Electrical Works C 24-Feb-15 01-Sep-14 03-Apr-15 6-Jun-15 13-Jul-15 23-Jul-15 5-Sep-15 25-Jul-15 12-Sep-15 Purchase
Corrective Measures required Delay and attention required On schedule Activity Completed
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of TS – Technical Specification LOI – Letter of Intent 20
independent member firms affiliated with KPMG International Cooperative (“KPMG NFA – Note for Approval
International”), a Swiss entity. All rights reserved.
TR – Technical Recommendation
PO – Purchase Order
Raw Material
Procurement Status – Package Delivery Handling System
GA received: 14May15.
Tandem Wagon 14 Months from Mfg 2.5% advance paid
3 L&T 10-Feb-15 21-Mar-15 Sent to Essar for
Tippler Clearance on 21-Mar-15
approval
Hydraulic Truck
5 JP Engineering 23-Feb-15 Sep-15 NA 5% Advance done
Tippler
GA received:
6 Vibrating Feeder Electromag 09-Feb-15 Sep-15 NA Payment done 10May15. Sent to
Essar for approval
BG submitted by
7 Belt Weigh Scale Acme 21-Feb-15 Sep-15 NA GA approved
vendor
Payment done
8 Metal Detector Electro Zavod 24-Mar-15 Sep-15 NA GA approved
Activity Finish Date Potential Delay Reasons for Delay Mitigation Plan Responsibility
(Days)
Baseline Expected Activity Project
Detailed Engineering
Delay in ordering of Stacker cum JSPL, Raipur to expedite
of Stacker cum 16-Jan-15 14-Nov-15 302 238 JSPL, Raipur
Reclaimer detailed engineering
Reclaimer
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 23
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Delays – Construction Handling System
Activity Finish Date Potential Delay Reasons for Delay Mitigation Plan Responsibility
(Days)
Baseline Expected Activity Project
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 24
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
D. Area wise Detailed Progress
Raw Material
Construction Status Handling System
Zone 1 – Receipt & Storage Area
Junction Houses *Target completion dates given by CCD
5 JH106 Civil handover complete Monorail Fabrication Pending Structural Erection in Progress
Conveyors
Sno. Conveyor Civil Works* Structural Fabrication Structural Erection
Wagon Tippler to JH101 Tunnel Drawings on hold due to pending inputs Drawings on hold due to pending
1 Not Started
(J101C1/C2/C3) from Wagon Tippler inputs from Wagon Tippler
JH101 to JH102
Excavation, RCC in Progress
2 Tunnel (J101C6/C7) Work in Progress (Angul) Not Started
Issue: Hard Rock drilling and breaking in
Footing (J102C1/C2)
progress.
JH101 to JH104 Tunnel Excavation, RCC in Progress
3 Work in Progress (Angul) Not Started
(J104C1/C2/C3) Piling not started
New method for civil foundation has been
JH105 to JH102 Stacker
4 implemented. Target completion by No Structural Fabrication Not Started
Foundation (J102C3/C4)
31-Dec-15
New method for civil foundation has been
JH106 to JH101
5 implemented. Target completion by No Structural Fabrication Not Started
Stacker Foundation (J101C4/C5)
01-Jan-16
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 26
independent member firms affiliated with KPMG International Cooperative (“KPMG Work Not Started Work in Progress Complete
International”), a Swiss entity. All rights reserved.
Raw Material
Construction Status Handling System
Zone 2 – Sinter Plant Area
Junction Houses
Sno. Junction House Civil Works Structural Fabrication Structural Erection
Conveyors
Sno. Conveyor Civil Works Structural Fabrication Structural Erection
2 JH104 to Crushing Plant Drawings not received Drawings not received Not Started
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 27
independent member firms affiliated with KPMG International Cooperative (“KPMG Work Not Started Work in Progress Complete
International”), a Swiss entity. All rights reserved.
Raw Material
Construction Status Handling System
Zone 3 – Blast Furnace Area (1/2)
Junction Houses *Target completion dates given by CCD
Sno. Junction Civil Works* Structural Fabrication Structural Erection
House
1 JH201 Removed from Scope Removed from Scope Removed from Scope
2 JH204 Removed from scope Removed from Scope Not Started
3 JH206 Work on hold due to railway track shifting Work in Progress (Angul) Not Started
4 JH207 Civil handover complete Structural Fabrication Completed Work in Progress
5 JH208 Civil handover complete Complete (Punjipathra) Not Started
6 JH209 On hold due to design changes Complete (Punjipathra) Not Started
7 JH213 Civil handover complete Complete(Punjipathra) Not Started
8 JH214 Front available work not started Complete (Punjipathra) Not Started
9 JH215 Front available work not started Complete (Punjipathra) Not Started
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 28
independent member firms affiliated with KPMG International Cooperative (“KPMG Work Not Started Work in Progress Complete
International”), a Swiss entity. All rights reserved.
Raw Material
Construction Status Handling System
Zone 3 – Blast Furnace Area (2/2)
Sno. Conveyor Civil Works* Structural Fabrication Structural Erection
1 JH104 to JH206 (J206C1/C2) Piling work in progress Work in Progress (Angul) Not Started
2 JH206 to JH207 (J207C1,J208C1) Civil Handover Complete Work in Progress (Angul) Not Started
3 JH207 to JH209 (J209RC1,J208C1) On hold due to design changes Work in Progress (Angul) Work in Progress
4 JH201 to JH204 (J204C1) Removed from Scope Removed from Scope Not Started
5 JH208 to PCI (PCIC1) Drawing Not Received Not Started Not Started
6 JH209 to Stockhouse (SH1C1) Onhold due to design changes Not Started Not Started
7 JH307 to Stockhouse (SH1C2) RCC in progress Work in Progress (Angul) Not Started
8 JH306 to Stockhouse (SH1C3) Front not available due to Blast Furnace material Work in Progress (Angul) Not Started
9 JH204 to Stockhouse (SH1C4) Removed from Scope Removed from Scope Not Started
10 JH305 to JH213 (J213C1) Civil handover complete Work in Progress (Angul) Not Started
11 Stockhouse to JH214 (J214C1) No Civil Work Not Started Not Started
12 Stockhouse to JH215 (J215C1) No Civil Work Not Started Not Started
13 JH213 to JH216 (J216C1/C2) On hold due to design changes Not Started Not Started
15 Coke Screen to J302 (J302C1/C2) RCC in progress Drawing Not Received Not Started
16 JH206 to Coal Blending (805AC1) Drawing Not Received Not Started Not Started
17 Coke Screen to JH302 (J302C3) Drawing Not Received Not Started Not Started
18 JH303 to JH306 (J306C1) RCC in progress Work in Progress (Angul) Not Started
19 JH302 to JH304 (J304C1) RCC in progress Work in Progress (Angul) Not Started
20 JH302 to JH305 (J305C1) RCC in progress Work in Progress (Angul) Not Started
21 JH302 to JH303 (J303C1) RCC in Progress Not Started Not Started
22 JH304 to JH307 (J307C1) Civil handover complete Work in Progress (Angul) Not Started
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 29
independent member firms affiliated with KPMG International Cooperative (“KPMG Work Not Started Work in Progress Complete
International”), a Swiss entity. All rights reserved.
*Target completion dates given by CCD
E. Contractor Evaluation
Report
Raw Material
Contractor / Vendor Scorecard Handling System
Score
100
90
80
70 64
60 59
60
50 45 42
40
30
20
10
0
Essar CCD-Civil TPL SSD - Angul SSD- Punjipatra
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 31
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
F. Health & Safety Report
Extract
Raw Material
Environment, Health and Safety Handling System
Water Pollution
Noise Pollution
No incidents reported
Solid Waste disposal
Disposal of Hazardous
waste
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 33
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Quality Handling System
Sno. Description of Non-Conformance Raised By Date of Vendor Finish Date Status Preventive
Reporting Responsible Action
Target Actual
No non-compliances reported
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 34
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
G. SAP Budget & Cash-flow
Extract
Raw Material
Budget Update Handling System
Approved Budget
Activity
(in crore INR)
Structural 161.50
Equipment 408.10
Piping 0.70
Utilities 17.07
Electrical 64.16
These figures have been sourced from the project team based on inputs from project team. The
above figures are to be updated in SAP
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 36
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Cash Flow Projection Handling System
Cumulative Planned 113.62 136 162 192 233 274 323 372 413 450 488 488 488
Actual Cost in SAP to be reconciled by Project team. To be reported post confirmation from the team.
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 37
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
H. Progress Photographs
Raw Material
Progress Photographs – (1/10) Handling System
Date: 01-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 39
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (2/10) Handling System
Date: 01-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 40
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (3/10) Handling System
Date: 01-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 41
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (4/10) Handling System
Date: 01-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 42
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (5/10) Handling System
Conveyor between JH207 to JH208 Foundation for Conveyor J213C1 (JH305 to JH213)
Date: 1-Aug-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 43
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (6/10) Handling System
Date: 1-Aug-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 44
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (7/10) Handling System
Date: 1-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 45
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (8/10) Handling System
Date: 1-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 46
independent member firms affiliated with KPMG International Cooperative (“KPMG
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (9/10) Handling System
Date: 1-Sep-2015
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 47
independent member firms affiliated with KPMG International Cooperative (“KPMG NA: Breakup not available
International”), a Swiss entity. All rights reserved.
Raw Material
Progress Photographs – (10/10) Handling System
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network of 48
independent member firms affiliated with KPMG International Cooperative (“KPMG NA: Breakup not available
International”), a Swiss entity. All rights reserved.
Document Audit Trail
# Event Event Owner Date
1 Circulation of draft Monthly KPMG 09-Sep-2015
Progress Report to PMG,
Package Owner, Project
Manager and team
2 Discussion of draft Monthly KPMG 10-Sep-2015
Progress Report with
Package Owner & team
© 2015 KPMG, an Indian Partnership and a member firm of the KPMG network
of independent member firms affiliated with KPMG International Cooperative
(“KPMG International”), a Swiss entity. All rights reserved.
The KPMG name, logo and "cutting through complexity" are registered
trademarks or trademarks of KPMG International Cooperative ("KPMG
International").