Case Study Report Project Management Analysis in The Internet Forecasting Industry
Case Study Report Project Management Analysis in The Internet Forecasting Industry
Sachin Kadam
Activity Task:
1. What is the estimated completion time of this project under normal conditions?
2. What is the probability that the project could be completed within the deadline of 35
weeks (normal conditions)?
Case Study Report - Project Management Analysis in the Internet Forecasting Industry
Completion Time:
The critical path, once all the weeks have been calculated, total to a budgeted completion time of
A+C+D+E+H+J+K= 3 + 6.33 + 8.33 + 8.83+ 4.17 + 5.5 + 3= 39.16 weeks.
Estimated Budget:
Case Study Report - Project Management Analysis in the Internet Forecasting Industry
Z= (36-39.16) / sqr
Case Study Report - Project Management Analysis in the Internet Forecasting Industry
7.64= -1.51
Additional Cost to reduce the Project time to 35 weeks: $41,214.29. The specific tasks to crash to
achieve this milestone are: C – 0.67 weeks; D – 2.33 weeks; F – 1 week; H – 0.17 weeks; K – 1 week
No Impact - Because of how high the slack time is for task B (see table below), increasing the
expected time from seven weeks to nine weeks will have no impact on the crashing solution.