Exercises 4 Program
Exercises 4 Program
4. For the printing project, the optimistic, pessimistic and most probable duration times
have been estimated, which are presented in the following table
PROGRAMMING OF WORKS
NATIONAL UNIVERSITY OF CENTRAL PERU
FACULTY OF CIVIL ENGINEERING
The duration time obtained from the PERT diagram found above is 21.4 weeks.
ACTIVIDAD a m b VARIANZA
A 1 2 4 0.250
C 2 5 9 1.361
F 4 6 12 1.778
I 6 7 10 0.444
3.833
[ ]
2
1
v 2=σ 2= ( b−a )
6
PROGRAMMING OF WORKS
NATIONAL UNIVERSITY OF CENTRAL PERU
FACULTY OF CIVIL ENGINEERING
DESVIACION
ESTANDAR
1.958
Data:
PROBABILIDAD
μ=T= 21.4
X= 20
S= 1.958
X−T 20−21.4
Z= Z= =−0.750
S 1.958
X−T
Z= and with tables or using Excel
S
PROGRAMMING OF WORKS
NATIONAL UNIVERSITY OF CENTRAL PERU
FACULTY OF CIVIL ENGINEERING
PROGRAMMING OF WORKS
NATIONAL UNIVERSITY OF CENTRAL PERU
FACULTY OF CIVIL ENGINEERING
700
600
500
400
300
200
100
0
0 5 10 15 20 25 30 35
SEMANAS
PROGRAMMING OF WORKS