Guide For Final Exam
Guide For Final Exam
Part I
C. Suppliers
D. Budgets
B. Arbitrary
C. Real
D. With responsible
C. Plurality methods
B. The primary metric must be congruent with the problem and objectives.
C. The project charter should include the problem statement and objectives.
D. Scope and project boundaries are one of the main risk factors
B. Focus groups ok
C. Experimentation ok
D. Primary research
C. Champion is not responsible for keeping the project on time according to plan.
10. What is the key factor for a good deployment of the DMAIC methodology based on Six Sigma?
A. To have certified Black Belts.
D. Define requirements.
12. In which company did the Six Sigma methodology start?
A. Motorola
B. General Electric
C. Allied Sigma
D. Coca Cola
13. What are the two types of data that can be collected?
A. Ordinal and nominal.
C. The pilot test must have its own plan and timetable.
D. The pilot test requires the same effort and dedication as the DMAIC project itself.
B. Qualitatively assess the risk of all failures at each step of the process.
C. Ongoing meetings should be held to maintain the commitment of all those involved.
21. Which VOC tools would you not apply to get VOC information from a small group of people (less
than 5)?
A. Interviews
B. Focus groups
C. Survey
D. Customer visits
A. Zero defects
Which of the following is false regarding the Six Sigma initiative in the Motorola program?
A. I include the concept of Black Belt and Green Belt focused on projects.
D. Under his leadership, the Six Sigma Research Institute was instituted.
25. This tool helps to foresee the different failure modes and how to prevent them.
A. FTA
B. AMEF
C. XYZ
D. CDM
A. The FEA is used in the measurement stage and in the control stage.
27. An MEFA uses 3 estimates to calculate the risk priority number (RPN), which are?
A. Every project must have at least one primary and two secondary metrics.
B. Primary and secondary metrics should be selected to cover cost, time and quality.
A. Customer satisfaction
C. Perception of value
B. The scope of the project should include what is in and what is out of scope.
D. A good definition of the scope of the project should be agreed upon by everyone involved in the
project.
31. What are the three types of MEFAs that can be created?
General Electric contributed a lot to Six Sigma Which of the following is NOT a contribution of General
Electric? GE?
C. To promote the Six Sigma methodology and its benefits within the industry.
D. Process capability
C. To display and weigh those factors that are important to the client.
C. Correctly assessing the current situation is the key factor in the measurement stage.
D. Not having a well-designed experiment is the key risk factor for the improvement phase.
A. Failure analysis
B. Systematic analysis
C. 5 Whys Techniques
C- In every process there are costs that are not directly visible.
39. Which of the following is not part of the definition of objectives in Six Sigma?
A- The project objectives must be realistic.
40. What are the two types of definition statements used in Six Sigma?
When analyzing a survey design, how do you assess repeatability and redundancy?
a) That the sample means are the same for all groups
b) That population means are the same for all groups
c) At least one sample mean is different from the rest.
d) At least one half of the population is different from the rest.
Part II
6. What does the p-value in the Anderson-Darling test mean when selecting the best minitab
distribution?
a. The smallest value of P is the best distribution
b. The highest p value is the best distribution
c. Negative p value is the best distribution
d. The value of p is irrelevant
7. What is the purpose of the Turkey test?
a. To test the equivalence of the bipolar coordinates d Tukey
b. To prove that population means are different from each other.
c. To prove that Tukey's test works
d. To prove that averages are equal to each other
8. It helps to see the predominant factors affecting the process:
a. Scatter plot
b. Matrix plot
c. Box plot
d. Pareto Chart
9. What is the purpose of the residual plot in ANOVA analysis?
a. It is similar to a control chart
b. Allows to discard unrelated variables
c. Allows to identify the root cause
d. Evaluate ANOVA assumptions and look at interactions of variables.
10. Which method is used to test vias in a measuring device?
a. Perform measurement tests in different ranges of the process.
b. Perform measurement test of a part versus standard multiple times.
c. Perform measurement tests in different time periods.
d. Regression
11. What is the conclusion in an ANOVA analysis if the variance within groups is much smaller than
the variance between groups?
a. There is at least one significant variable
b. All variables are significant
c. There are no significant variables
d. It is not possible to conclude
12. In what type of distribution is it common to use the Z-transform?
a. Gumbel
b. Gamma
c. Binomial
d. Normal
13. What is the Anderson-Darling test used for?
a. To evaluate the interaction between different discrete variables
b. To discard those variables that are not significant
c. To assess normality in a sample
d. To evaluate if there are differences in the means of two populations.
14. What method is normally used to test the stability of a measurement system?
a. X-bar graphs with lead parts (non-standard)
b. X-bar graphs with "gold" (standard) parts in different operating ranges
c. Individual graphs with "gold" (standard) parts at different times
d. EWMA Charts
15. What is the purpose of the Barlett & Levine test?
a. It tells us whether the population means are equal.
b. Tells us whether the variances of the populations are equal across the same
populations.
c. Tells us if the populations are similar
d. Tells us whether the populations are significantly different
16. Which of the following is false?
a. Repeatability is commonly called precision
b. Bias is sometimes referred to as precision
c. Reproducibility includes operators or machines
d. Linearity of the deviation that exists over time.
17. What discrimination rate would you expect with a system with a high percentage of
measurement error?
a. Less than 2
b. Equal to 6
c. Between 2 and 4
d. Greater than 4
18. What are the 2 most important menus in minitab?
a. Editing, statistics
b. Archive and help
c. Statistics and graphics
d. Tools and calculation
19. Analyze a survey design with respectability and redundancy are evaluated.
a. Through tukey's test and Chebycheff's theorem
b. By means of Levene's test and Bartlett's test
c. Through Anderson's test and Darling's index
d. Through the Cronbach's alpha coefficient and the discrimination index
20. Which of the following is a characteristic of a decision tree?
a. Not useful in six sigma
b. It is useful because it makes the decision for us
c. Weigh probability by project costs
d. Helps to structure information for better decision making
21. What is the purpose of a two-variance test?
a. Validate that both variances are equal to a constant
b. A test to identify whether the variances of two samples are different.
c. Validate the confidence interval of both samples
d. Validate that the means of both variances are within the ranges of the confidence
interval.
22. What does the central limit theorem say?
a. Of a set of means, this distribution will tend to be normal even if the population is not.
b. The trend of a normal distribution can be estimated from the Z-transform.
c. The outcome of a measurement study is altered because the operators feel they are
being evaluated
d. The capabilities of a system can be evaluated if the data are transformed
23. Why is the 2-sample t-test used?
a. To evaluate the interaction between different discrete variables
b. To discard those variables that are not significant
c. To assess normality in a sample
d. To evaluate whether there are differences in the means of two populations
24. What is a Run chart for? (Execution graph)
a. To see the variation of the data with respect to time
b. To evaluate clustering, mixing, trending and oscillation.
c. To assess clustering, trend, linearity and respectability
d. To assess reproducibility and respectability
Run Chart
34. In an ANOVA analysis, what can be concluded when a P lower than the risk alpha is obtained?
a. There are no significant variables
b. There is at least one significant variable
c. The null hypothesis could not be rejected
d. No conclusion
p-value is the probability that the calculated F0 value is given due to
randomness (the area under the curve, beyondF0). If theP-Value is less than the
alpha risk (example: 0.05) that you are willing to accept, then the effect is
"significant" at100(1-α)% confidence level and you have at least one variable
that significantly affects the response.
35. Theorem applicable to data of any standard distribution that allows to evaluate the set of
measurements within K deviations.
a. Tchebysheff
b. Anderson - Darling
c. Tukey
d. Gamma
This theorem is very useful if we want to quickly identify the % of data that fall
within a certain number of standard deviations (σ).
PART 3
Mean: the sum of the data value divided by the amount of data.
Median: the central value of a group of ordered data. For an odd number of
points, the median is the central value; for an even number of points, the
median is the average of the two central data.
Mode: the most frequent value in a set of data.
Stability can be defined in the graph as the degree of variation that exists in a process
over time. Some processes tend to perform excellently in the short term, but as time goes
by, they degrade and, therefore, present certain variations that cause erroneous
readings.
As shown in the figure, the process capability index ( Cp) shows the
relationship of the process to the specification limits set by the
customer.
11) It is the capability index that shows the relationship of the process with respect to the
specification limits:
Would you be able to solve the problem?
a. Cpk
b. Pp
c. Ppk
d. Cp
Process capability index Cpk:
In order to evaluate the centering variable with respect to the specification limits, the
process capability index (Cpk), which is shown in the following figure, is available
12) It is the long-term capacity of the process:
a. Cpk
b. Cp
c. Pp
d. Sigma
• Pp is the "long-term" capacity of the process.
14) This coefficient tells the percentage of variability of the predicted values explained by a
regression model:
a. r
b. r squared
c. Cp
d. Cpk
R-squared(coefficient of determination) tells the percentage of total variability of
the predicted values that you were able to explain in the model.
15. A portfolio management goal that tells us that many organizations will seek to allocate
resources to maximize the value of the portfolio in terms of some company objective such
as long-term profitability or return on investment:
a. Stability
b. Strategic direction
c. Value maximization
d. Increases in product value
16) Portfolio management goal that tells us that some organizations seek to achieve some desired
portfolio stability in terms of long-term vs. short-term projects, high-risk vs. low-risk projects,
market mixes, diverse technologies, or types of projects:
a. Increase in the value of the product
b. Value maximization
c. Stability
d. Strategic direction
17) Portfolio management goal that tells us that the final portfolio must be truly aligned with the
organization's strategic plan:
a. Stability
b. Increased product value
c. Strategic direction
d. Value maximization
Strategic direction: the final portfolio must be truly aligned with the
organization's strategic plan.
18) It is a very effective tool in the generation of ideas. It helps to find and identify a large
number of possible ideas.
a. Pugh matrix
b. Brainstorming
c. Ranking process
d. Pros and cons matrix
20) Its purpose is to make an adequate selection of the best concept according to an established
methodology.
a. Pugh matrix
b. Cause and effect matrix
c. Pros and cons matrix
d. Priority matrix
The purpose of the Pugh matrix concept is to make an appropriate selection of
the best concept according to an established methodology.
Income
Margins
ROI
22) Measurement of performance against the standard, assuming that the standard was set based
on the desired performance.
a. Capacity
b. Efficiency
c. Effectiveness
d. Of cost
Effectiveness
Measure of performance against the standard, assuming that the
standard was set based on the desired performance.
23) A measure that uses statistical performance characteristics to estimate the probability of
conformance to the standard (or some equivalent metric).
a. Capacity
b. Effectiveness
c. Efficiency
d. Of cost
Capacity
A measure that uses statistical performance characteristics to estimate the
probability of conformance to the standard (or some equivalent metric).
24) Measure that estimates operating costs, resource utilization, cycle times.
a. Capacity
b. Effectiveness
c. Of cost
d. Efficiency
Efficiency
A measure that estimates operating costs, resource utilization and cycle times.
26) Graph establishing control limits at +/- three standard deviations from the sample mean.
a. Shewart
b. XS
c. Cusum
d. XR
Recall that the generalShewhart chart model sets the control limitsat +/-
three standard deviations from the sample mean.
Xbar -R Graphics
Application: univariate monitoring process.
Data:
o Continuous.
o Approximately normal.
o No correlation.
Sample size:
For setting:K >= 25 subgroups of sizen
a. I-MR
b. XR
c. X - bar
d. X bar - S
Xbar -R Graphics
Application: univariate monitoring process.
Data:
o Continuous.
o Approximately normal.
o No correlation.
Sample size:
For setting:K >= 25 subgroups of sizen
In operation:2 ≤ n ≤ 10
a. X bar
b. XR
c. I-MR
d. X bar -S
30) Control chart which has the following characteristics: Application: univariate process
monitoring.
Data: Discrete No correlation
Sample size: k > 25 subgroups for the set size n
a. np
b. P
c. U
d. X bar
a. P
b. np
c. U
d. C
NP
a. np
b. p
c. c
d. u
Graph C
33) Control chart which has the following characteristics: Application: Monitoring of a variable.
Data: Discrete No correlation
Sample size: K > 25 subgroups for start-up.
a. np
b. p
c. c
d. u
Graph U
DO NOT COME
a) Xbar Graph
b) Graph R
c) Individual charts (IMR)
d) Graph np
a) Job Descriptions
b) Work instructions
c) Workers' compensation
d) Process controls
What is one of the key factors for a good deployment of the DMAIC methodology?
What is the null hypothesis when testing a simple regression coefficient in the regression table?
a) That the coefficient is zero
b) That the p Value is low
c) That the sum of squares is zero
d) That the t-statistic is zero
If a p-chart has been calculated, p bar is 0.8 and the subgroup sample is 20, then what are the upper
control limits (UCL) and lower control limits (LCL)?
a) The natural variation of an estimated process plus minus two standard errors.
b) The natural variation of a process estimated by its median plus minus interquartile range
median.
c) The natural variation of a process estimated by the mean plus minus three standard errors.
d) The natural variation of a process estimated by the mean plus minus three standard ranges.
Six Sigma projects should be evaluated by the process owner, the green belt and finance:
How many subgroups are necessary to have any certainty that the process is in control?
a) 5
b) 10
c) 25
d) Infinitely
a) The acceptable quality level (AQL) is the largest proportion of defect in a good lot.
b) Sampling plans are generally designed to minimize alpha risk.
c) The tolerance percent defective for a lot (LTPD) is the smallest percentage of defects in a bad
lot.
d) Alpha risk is the most important metric for the client.