Ms Drainages

The document provides a method statement for the construction of drainage systems including catchpits, U-channels, and stepped channels as part of a landslip prevention project. It outlines the drawings, materials, plant, and construction procedures to be used. Procedures include setting out locations, excavation, formwork erection, reinforcement installation, concreting, curing, installation of gratings and covers, and safety measures. Junctions between channels will follow standard drawings and expansion joints will be provided at maximum 10m intervals.

Uploaded by

deanico
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views3 pages

Ms Drainages

The document provides a method statement for the construction of drainage systems including catchpits, U-channels, and stepped channels as part of a landslip prevention project. It outlines the drawings, materials, plant, and construction procedures to be used. Procedures include setting out locations, excavation, formwork erection, reinforcement installation, concreting, curing, installation of gratings and covers, and safety measures. Junctions between channels will follow standard drawings and expansion joints will be provided at maximum 10m intervals.

Uploaded by

deanico
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Ming Hing Waterworks Engineering Co., Ltd.

Civil Engineering Development DEPARTMENT – Contract No. GE/2017/07

Landslip Prevention and Mitigation Programme 2014, Package I,


Landslip Prevention and Mitigation Works

Method Statement for Construction of Drainage system

a. Drawings

 Catchpit drawings
a. Works Order drawing for the features
b. Standard drawing : C2405/1-C2450/5, C2406/1, C2406/2A

 U-Channel drawings
a. Works Order drawing for the features
b. Standard drawing : C2409H, C2410G, C2412E, C2413D

 Stepped Channel drawings


a. Works Order drawing for the features
b. Standard drawing : C2411G, C2413D

b. Materials
a. Concrete : Grade 20
b. Reinforcement : A252 Mesh

c. Plant
a. Concrete vibrator

d. Construction Procedures

 Catchpit

a. Setting out for the location of the Catchpit according to the Works Order
drawing
b. Removal the top soil and soft spots
c. Excavate to formation according to the Standard drawing C2405/1-C2450/5.
d. Erection for formwork according to the Standard drawing C2405/1-C2450/5
and Works order drawing
e. Fixing the A252 mesh reinforcement according to the Standard drawing
C2405/1-C2450/5.
f. Concreting to catchpit.
g. Removal of formwork (12 hrs after concreting) and curing (at Least 4 days)
h. Installation of Steel Grating or precast concrete cover for the catchpit
according to the Standard drawing C2405/1-C2450/5 or installation of precast
concrete covers/ grating according to the Standard drawing C2406/1,
C2406/2A

 U-Channel

a. Setting out for the alignment of the U-Channel according to the Works Order
drawing
b. Removal the top soil and soft spots
c. Excavate to formation level according the Standard drawing C2409H,
C2410G.
d. Erection for formwork according to the Standard drawing C2409H, C2410G
and Works order drawing
e. Concreting to U-Channel.
f. Removal of formwork (12 hrs after concreting) and curing (at Least 4 days)
g. Installation of Cover slab and cast iron grating for u-channel according to the
Standard drawing C2412E.

 Stepped Channel

a. Setting out for the alinement of the Stepped Channel according to the Works
Order drawing
b. Removal the top soil and soft spots
c. Excavate the keys according to the Standard drawing C2411G.
d. Erection for formwork according to the Standard drawing C2411G and Works
order drawing
e. Concreting to Stepped Channel.
f. Removal of formwork (12 hrs after concreting) and curing (at Least 4 days)

e. Concreting/Shotcreting
a. Concrete trucks will be parked at the nearest accessible location. The fresh
concrete will be delivered manually by means of trolley or by concrete pump.
b. Fresh concrete will be compacted by means of vibratory poker.
c. Shotcreting method shall be adopted according the separated submitted
shotcreting method statement.

f. Method and procedures of curing concrete after concreting


a. Wet the concrete surface by water.
b. Cover the concrete surface by a plastic sheet or the like.
c. Check the condition of plastic sheet every day and add water to keep them
wet.
d. The concrete structure shall be cured at least 4 days.
g. Junction of U-channels and Step-channels
a. The junction of U-channels and Stepped channel should be following the
details according to the Standard drawing C2413D.
b. Expansion joints shall be provided at intervals of 10m Max.

h. Safety Measures
a. Workers shall wear safety harness and attach it to an independent lifeline
during working. Anchor points for lifeline shall be tested.
b. All workers shall wear appropriate PPE while carrying out the boulder
removal works.