This document outlines the schedule for a proposed warehouse project from August 2023 to May 2024. It includes engineering and procurement activities from August 2023 to March 2024, followed by construction from September 2023 to May 2024. Key milestones include work commencement in September 2023 and project finish in May 2024. The schedule shows the timing of nomination, agreement, shop drawings, material procurement, and delivery for both pre-engineered structural items and precast concrete items.

Uploaded by

isunfocus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views8 pages

Program

This document outlines the schedule for a proposed warehouse project from August 2023 to May 2024. It includes engineering and procurement activities from August 2023 to March 2024, followed by construction from September 2023 to May 2024. Key milestones include work commencement in September 2023 and project finish in May 2024. The schedule shows the timing of nomination, agreement, shop drawings, material procurement, and delivery for both pre-engineered structural items and precast concrete items.

Uploaded by

isunfocus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Activity ID Activity Name Original Start Finish 2023 2024

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
PROPOSED WAREHOUSE GROUND + MEZZANINE FLOOR. 297 01-Aug-23 23-May-24

MILESTONE 297 01-Aug-23 23-May-24

A1260 Project Start 0 01-Aug-23

A1000 Work Commencement 0 23-Sep-23

A2000 Project Dura on 244 23-Sep-23 23-May-24

A1010 Project Finish 0 23-May-24

ENGINEERING AND PROCUREMENT 199 21-Aug-23 06-Mar-24

PS ITEMS 156 03-Oct-23 06-Mar-24

NOMINATION 33 03-Oct-23 09-Nov-23

A1020 Compound Wall Gate 7 03-Oct-23 10-Oct-23

A1040 Light Fi ngs 7 13-Oct-23 20-Oct-23

A1030 Aluminium Rolling Shu er(Motorized) 7 23-Oct-23 30-Oct-23

A1060 Low Current System 7 28-Oct-23 04-Nov-23

A1050 Sanitarty Wares 7 02-Nov-23 09-Nov-23

AGREEMENT /LPO 40 11-Oct-23 25-Nov-23

A1110 Compound Wall Gate 14 11-Oct-23 26-Oct-23

A1130 Light Fi ngs 14 21-Oct-23 06-Nov-23

A1120 Aluminium Rolling Shu er(Motorized) 14 31-Oct-23 15-Nov-23

A1150 Low Current System 14 06-Nov-23 21-Nov-23

A1140 Sanitarty Wares 14 10-Nov-23 25-Nov-23

SHOP DRAWING/MATERIAL SUBMITTAL AND APPROVAL 51 27-Oct-23 27-Dec-23

A1160 Compound Wall Gate 25 27-Oct-23 24-Nov-23

A1180 Light Fi ngs 25 07-Nov-23 07-Dec-23

A1170 Aluminium Rolling Shu er(Motorized) 25 16-Nov-23 16-Dec-23

A1200 Low Current System 25 22-Nov-23 22-Dec-23

A1190 Sanitarty Wares 25 27-Nov-23 27-Dec-23

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 1 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
MATERIAL PROCUREMENT AND DELIVERY 103 25-Nov-23 06-Mar-24

A1210 Compound Wall Gate 30 25-Nov-23 24-Dec-23

A1230 Light Fi ngs 90 08-Dec-23 06-Mar-24

A1220 Aluminium Rolling Shu er(Motorized) 60 17-Dec-23 14-Feb-24

A1250 Low Current System 40 23-Dec-23 31-Jan-24

A1240 Sanitarty Wares 60 28-Dec-23 25-Feb-24

PC ITEM 102 07-Nov-23 16-Feb-24

NOMINATION 20 07-Nov-23 29-Nov-23

A1070 Ceramic Floor le 7 07-Nov-23 14-Nov-23

A1080 Ceramic Wall Tile 7 07-Nov-23 14-Nov-23

A1090 Marble Threshold 7 07-Nov-23 14-Nov-23

A1100 Interlock and kerbstone 7 22-Nov-23 29-Nov-23

AGREEMENT /LPO 27 15-Nov-23 18-Dec-23

A1270 Ceramic Floor le 14 15-Nov-23 30-Nov-23

A1280 Ceramic Wall Tile 14 15-Nov-23 30-Nov-23

A1290 Marble Threshold 14 15-Nov-23 30-Nov-23

A1300 Interlock and kerbstone 14 30-Nov-23 18-Dec-23

SHOP DRAWING/MATERIAL SUBMITTAL AND APPROVAL 38 04-Dec-23 17-Jan-24

A1310 Ceramic Floor le 25 04-Dec-23 02-Jan-24

A1320 Ceramic Wall Tile 25 04-Dec-23 02-Jan-24

A1330 Marble Threshold 25 04-Dec-23 02-Jan-24

A1340 Interlock and kerbstone 25 19-Dec-23 17-Jan-24

MATERIAL PROCUREMENT AND DELIVERY 45 03-Jan-24 16-Feb-24

A1350 Ceramic Floor le 45 03-Jan-24 16-Feb-24

A1360 Ceramic Wall Tile 45 03-Jan-24 16-Feb-24

A1370 Marble Threshold 45 03-Jan-24 16-Feb-24

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 2 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
A1380 Interlock and kerbstone 30 18-Jan-24 16-Feb-24

DOMESTIC SUBCONTRACTOR /SUPPLIER 194 21-Aug-23 01-Mar-24

SUBCONTRACTOR /SUPPLIER PQ SUBMISSION 101 21-Aug-23 19-Dec-23

A1390 Anitermite 7 21-Aug-23 28-Aug-23

A1400 Steel 7 21-Aug-23 28-Aug-23

A1410 Concrete 7 21-Aug-23 28-Aug-23

A1420 Water proofing 7 23-Sep-23 02-Oct-23

A1430 Blocks 7 23-Sep-23 02-Oct-23

A1440 Steel Structure 3 23-Sep-23 26-Sep-23

A1450 Electrical and Plumbing 7 23-Sep-23 02-Oct-23

A1460 HVAC 7 23-Sep-23 02-Oct-23

A1470 Fire alarm and fire figh ng 7 23-Sep-23 02-Oct-23

A1520 Metal works ( AC Louver, Steel Staircase) 7 13-Oct-23 20-Oct-23

A1500 Aluminium and Glazing 7 28-Oct-23 04-Nov-23

A1480 Pain ng 7 07-Nov-23 14-Nov-23

A1490 Epoxy Flooring 7 07-Nov-23 14-Nov-23

A1510 Steel Door 7 22-Nov-23 29-Nov-23

A1530 False Ceiling 7 12-Dec-23 19-Dec-23

SUBCONTRACTOR /SUPPLIER PQ APPROVAL 115 29-Aug-23 13-Jan-24

A1540 Anitermite 7 29-Aug-23 05-Sep-23

A1550 Steel 7 29-Aug-23 05-Sep-23

A1560 Concrete 7 29-Aug-23 05-Sep-23

A1590 Steel Structure 7 28-Sep-23 05-Oct-23

A1570 Water proofing 7 03-Oct-23 10-Oct-23

A1580 Blocks 7 03-Oct-23 10-Oct-23

A1600 Electrical and Plumbing 14 03-Oct-23 18-Oct-23

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 3 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
A1610 HVAC 21 03-Oct-23 26-Oct-23

A1620 Fire alarm and fire figh ng 21 03-Oct-23 26-Oct-23

A1670 Metal works ( AC Louver, Steel Staircase) 21 21-Oct-23 14-Nov-23

A1650 Aluminium and Glazing 21 06-Nov-23 29-Nov-23

A1630 Pain ng 21 15-Nov-23 11-Dec-23

A1640 Epoxy Flooring 21 15-Nov-23 11-Dec-23

A1660 Steel Door 21 30-Nov-23 26-Dec-23

A1680 False Ceiling 21 20-Dec-23 13-Jan-24

SHOP DRAWING/MATERIAL SUBMITTAL AND APPROVAL 129 06-Sep-23 07-Feb-24

A1690 Anitermite 7 06-Sep-23 13-Sep-23

A1700 Steel 7 06-Sep-23 13-Sep-23

A1710 Concrete 7 06-Sep-23 13-Sep-23

A1740 Steel Structure 7 06-Oct-23 13-Oct-23

A1720 Water proofing 7 11-Oct-23 18-Oct-23

A1730 Blocks 7 11-Oct-23 18-Oct-23

A1750 Electrical and Plumbing 7 19-Oct-23 26-Oct-23

A1760 HVAC 45 27-Oct-23 20-Dec-23

A1770 Fire alarm and fire figh ng 45 27-Oct-23 20-Dec-23

A1820 Metal works ( AC Louver, Steel Staircase) 30 15-Nov-23 21-Dec-23

A1800 Aluminium and Glazing 30 30-Nov-23 06-Jan-24

A1780 Pain ng 21 12-Dec-23 05-Jan-24

A1790 Epoxy Flooring 21 12-Dec-23 05-Jan-24

A1810 Steel Door 30 27-Dec-23 31-Jan-24

A1830 False Ceiling 21 15-Jan-24 07-Feb-24

MATERIAL PROCUREMENT AND DELIVERY 170 14-Sep-23 01-Mar-24

A1840 Anitermite 1 14-Sep-23 14-Sep-23

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 4 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
A1850 Steel 2 14-Sep-23 15-Sep-23

A1860 Concrete 2 14-Sep-23 15-Sep-23

A1890 Steel Structure 60 14-Oct-23 12-Dec-23

A1870 Water proofing 10 19-Oct-23 28-Oct-23

A1880 Blocks 3 19-Oct-23 21-Oct-23

A1900 Electrical and Plumbing 60 27-Oct-23 25-Dec-23

A1910 HVAC 60 21-Dec-23 18-Feb-24

A1920 Fire alarm and fire figh ng 60 21-Dec-23 18-Feb-24

A1970 Metal works ( AC Louver, Steel Staircase) 30 22-Dec-23 20-Jan-24

A1930 Pain ng 21 06-Jan-24 26-Jan-24

A1940 Epoxy Flooring 21 06-Jan-24 26-Jan-24

A1950 Aluminium and Glazing 45 07-Jan-24 20-Feb-24

A1960 Steel Door 30 01-Feb-24 01-Mar-24

A1980 False Ceiling 10 08-Feb-24 17-Feb-24

CONSTRUCTION AND INSTALLATION 297 01-Aug-23 23-May-24

SUBSTRUCTURE 134 01-Aug-23 12-Dec-23

ENABLING WORKS 53 01-Aug-23 22-Sep-23

A1990 Founda on Excava on For Proposed 20 01-Aug-23 23-Aug-23


Warehouse others
A2590 Stone Piling Works by others 30 24-Aug-23 22-Sep-23

FOOTING 81 23-Sep-23 12-Dec-23

A2010 An termite Treatment PCC Works 4 23-Sep-23 28-Sep-23

A2020 Foo ng Reinformcent works 10 29-Sep-23 10-Oct-23

A2030 Foo ng shu ering works 7 11-Oct-23 18-Oct-23

A2040 Authority inspec on and Concrete 4 19-Oct-23 23-Oct-23

A2050 Foo ng Deshu ering and Curing 4 24-Oct-23 27-Oct-23

A2190 Solid Block Works and Pedestal Column RCC 7 28-Oct-23 03-Nov-23
Works

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 5 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
A2200 Bitumen Applica on For Foo ngs, Solid 4 04-Nov-23 07-Nov-23
Blocks And Pedestal Column
A2210 Earth Backfilling And Compac on Works For 10 08-Nov-23 17-Nov-23
Solid Block Level
A2220 Tie Beam RCC Works 5 18-Nov-23 22-Nov-23

A2230 Ground Floor Backfilling, Levelling And 7 23-Nov-23 29-Nov-23


Compac on Works For Proposed
A2240 Under Ground MEP Works 6 30-Nov-23 05-Dec-23

A2250 Grade Slab Works 7 06-Dec-23 12-Dec-23

WATER TANK ADN PUMP ROOM 37 24-Oct-23 29-Nov-23

A2060 Excava on For Proposed Under Ground 4 24-Oct-23 27-Oct-23


Water Tank And Pump Room Ra
A2070 Earth Leveling and Compac on 3 28-Oct-23 30-Oct-23

A2080 Road Base Laying, Levelling & Compac on 2 31-Oct-23 01-Nov-23


Works
A2090 Pcc For Proposed Under Ground Water Tank 1 02-Nov-23 02-Nov-23
And Pump Room
A2095 Water Proofing over PCC 1 03-Nov-23 03-Nov-23

A2100 Founda on Reinforcement works for Water 4 04-Nov-23 07-Nov-23


Tank and Pump Room
A2110 Authority inspec on and founda on 1 08-Nov-23 08-Nov-23
Concrete
A2120 Founda on De Shu er and Curing 2 09-Nov-23 10-Nov-23

A2130 Wall Reinforcement works (inc, MEP Works) 4 11-Nov-23 14-Nov-23

A2140 Wall Shu ering Works 4 15-Nov-23 18-Nov-23

A2150 Wall Concre ng 2 19-Nov-23 20-Nov-23

A2160 Water tanka and Pump Room Slab 4 21-Nov-23 24-Nov-23


Shu ering works
A2170 Water tanka and Pump Room Slab Rebar 4 25-Nov-23 28-Nov-23
and MEP Works
A2180 Water tanka and Pump Room Slab Authority 1 29-Nov-23 29-Nov-23
Inspec on and Concrete works
SUPER STRUCTURE 52 13-Dec-23 12-Feb-24

A2260 Steel Structure Erec on Shee ng Works 50 13-Dec-23 09-Feb-24

A2270 Mezzanine Floor Cas ng Works 20 27-Dec-23 19-Jan-24

A2570 Steel Structure Shee ng Works 20 20-Jan-24 12-Feb-24

INTERNAL FINISHES 132 03-Jan-24 13-May-24

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 6 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
WAREHOUSE 110 03-Jan-24 13-May-24

A2280 Block work 35 03-Jan-24 12-Feb-24

A2290 MEP 1st Fix in walls(GI Back Box, 30 22-Jan-24 24-Feb-24


Condui ng)
A2295 Intrnal Plastering Works 30 02-Feb-24 07-Mar-24

A2285 Installa on of Metal Staircase 35 13-Feb-24 23-Mar-24

A2300 MEP High Level (Fire piping, Cable tray, 30 26-Feb-24 30-Mar-24
Cable Pulling, HVAC Ducts, Low Current
A2350 Paint 1st Coat (Inc, Primer and Stucco) 30 08-Mar-24 15-Apr-24

A2360 Alumnium and Glazing works 30 16-Mar-24 23-Apr-24

A2310 Wet area Wall le 10 20-Mar-24 30-Mar-24

A2380 Installa on of MEP Final Fix 30 25-Mar-24 01-May-24

A2320 Wet area Water Proofing 10 26-Mar-24 05-Apr-24

A2370 Installa on of Rolling shu er 20 28-Mar-24 23-Apr-24

A2330 Wet area Floor Tile 10 01-Apr-24 15-Apr-24

A2390 Floor Epoxy Coa ng and Paint Final Coat 30 05-Apr-24 13-May-24

A2340 False ceiling works 10 06-Apr-24 20-Apr-24

WATER TANK AND PUMP ROOM 78 13-Feb-24 30-Apr-24

A2500 Surface Prepara on 7 13-Feb-24 20-Feb-24

A2510 GRP Lining inside the wate tank 7 21-Feb-24 28-Feb-24

A2520 Pump Founda on 4 29-Feb-24 04-Mar-24

A2515 Epoxy Flooring 5 05-Mar-24 09-Mar-24

A2530 Installa on of Pumps and its connce ons 30 11-Mar-24 17-Apr-24

A2550 Steel Door Installa on 4 18-Apr-24 22-Apr-24

A2560 MEP Final Fix 4 23-Apr-24 26-Apr-24

A2600 Paint Final Coat 4 27-Apr-24 30-Apr-24

EXTERNAL FINISHES 70 13-Feb-24 07-May-24

A2400 External Plastering 50 13-Feb-24 13-Apr-24

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 7 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23
Activity ID Activity Name Original Start Finish 2023 2024
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Duration -1 1 2 3 4 5 6 7 8 9 10 11 12
A2410 External Pain ng Works 50 07-Mar-24 07-May-24

EXTERNAL WORKS 139 25-Dec-23 11-May-24

A2470 Boundry wall works (Inc, Gate Installa on) 90 25-Dec-23 08-Apr-24

A2420 MEP Under Ground Services 30 13-Feb-24 18-Mar-24

A2430 Interlock and kerb stone Works 20 19-Mar-24 13-Apr-24

A2460 Installa on of Meter cabinet and Breaching 7 15-Apr-24 22-Apr-24


Inlet
A2610 External MEP Final Fix 19 23-Apr-24 11-May-24

AUTHORITY PROCEDURES AND PROJECT CLOSE OUT 16 08-May-24 23-May-24

A2450 DEWA Water Inspec on 5 08-May-24 14-May-24

A2480 DCD Inspec on 5 08-May-24 14-May-24

A2440 DEWA Electrical inspec on 5 12-May-24 16-May-24

A2580 Snag and De Snag 10 14-May-24 23-May-24

A2490 DDA Building comple on Inspec on 7 15-May-24 23-May-24

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Summary Page 8 of 8
16-Aug-23 PROGRAM PM
Actual Level of Effort Critical Remaining Work
% comp Milestone
Data Date: 01-Aug-23