Quantity Calculation

This document provides details of construction works executed for a multipurpose building project in Ambo, Ethiopia. It includes a summary of substructure works with item descriptions, quantities, unit rates, contract amounts and amounts executed to date. The total value of substructure works executed is 5,636,043.63 Birr.

Uploaded by

Eba Getachew
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views25 pages

Quantity Calculation

This document provides details of construction works executed for a multipurpose building project in Ambo, Ethiopia. It includes a summary of substructure works with item descriptions, quantities, unit rates, contract amounts and amounts executed to date. The total value of substructure works executed is 5,636,043.63 Birr.

Uploaded by

Eba Getachew
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 25

CERTIFICATE OF PAYMENT NO 01

Date of Signature of cont.:- Feb. 2nd/2015

Project:- WEST SHEWA OFFICE BUILDING


Main Contract 58,045,324.11
Location :- AMBO TOWN
Supplementary Contract
Investor :- WEST SHEWA ZONE INDUSTRY & URBAN DEV
Variation Order 815,287.74
Contractor:-MCG Con PLC .
Total Sum 58,860,611.85
Consultant :- OROMIYA INDUS & URBAN DEV'T B

Amount (Birr)
(As per the attached statement the value of work executed and or materials supplied to date is )
5,636,043.63

845,406.54
No. Date Amount(Birr) Vat 15%

Advance 6,481,450.17
Total

Deduction Amount (Birr)

1.Previous Payments -

2. Rebate

3.Retention 5% 324,072.51

4. Penalty

5.Advance Repayment 20 % 1,296,290.03

6. Other
ÉU`
Total 1,620,362.54

Net Sum Due to the Contractor 4,861,087.63

KY^ }s^ß w` ----------------- K=ŸõM S‰K<” “[ÒÓ×K”::

ÉU` We certify that the contractor is now entitled to the sum of Birr:- 3,859,774.76
Total - (Three milionTwo Hundred Fourteen Thousand Five Hundred Thirty six and
76/100 Birr)

x :-
Location :- Ambo
}[ÒÓ×DM çÉsM
Certified By Approved By
_________________ _________________
k” ------------------- k” --------------------
Date Date
Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.

DETAILS OF WORKS EXECUTED


sub Total/Birr/ Total/Birr/
Summary Contract Executed Contract Executed

A. SUBSTRUCTURE
01 Excavation & Earth WorkS 914,807.77 2,246,243.74
02 Concrete Work 3,756,993.38 2,707,964.99
03 masonry work 310,855.50
Total 4,982,656.65 4,954,208.74
Demolishing 815,287.74 681,834.90
Total 815,287.74 681,834.90
GRAND TOTAL 5,636,043.63

_______________ _____________.
contractors supervisors Rep
Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.

A.Substructure works Contract Quantity(m3) Amount(ETB)


Item Prevous
No
Description Unit Qty Unit Rate Amount This period period
Total todate This Period Previous Period Total Todate

1. SUBSTRUCTURE
1. EXCAVATION AND EARTH WORK
- - - -
1.1 clearing of the site to remove top soil
and other rubbish m2 1,840.77 6.00 11,044.62
1,705.10 1,705.10 10,230.60 - 10,230.60
1.2 Bulk excavation to reduce level in
ordinary soil to depth of 2.7m m3 2,992.42 50.00 149,621.00
3,770.68 3,770.68 188,534.25 - 188,534.25
1.3 Trench excavation for masonry wall
foundation m3 202.35 50.00 10,117.50 109.61 109.61 5,480.46 - 5,480.46
1.4 Excavation for isolatedfooting in
ordinary soil to depth of 1.5m m3 610.44 60.00 36,626.40 4,760.52 4,760.52 285,631.37 - 285,631.37
1.5 Fill under hardcore with borrowed
selected material m3 838.63 200.00 167,726.00 1,994.54 1,994.54 398,908.08 - 398,908.08
1.6 Ditto fill around foundation with
borrowed selected material m3 399.34 200.00 79,868.00 1,483.03 1,483.03 296,605.74 - 296,605.74
1.7 Ditto fill retaining wall with borrowed
selected material m3 280.00 200.00 56,000.00 2,100.74 2,100.74 420,148.41 - 420,148.41
1.80 cartaway surplus material to distance not
exceeding 5kms m2 4,128.01 45.00 185,760.45
9,123.60 9,123.60 410,562.00 - 410,562.00
1.90 250mm thick basaltic or equivalent
hardcore m2 838.63 260.00 218,043.80
885.16 885.16 230,142.84 - 230,142.84

Total Carried to Summary 914,807.77 2,246,243.74 - 2,246,243.74

2. CONCRETE WORK -

__________________ ______________ .
contractor Rep. supervisors Rep .
1. SUBSTRUCTURE
2.01
-
C-5 lean concrete with minimum cement
content of 150kg/m3 under footing pad -

a) isolated footings & lift pad m2 443.00 90.00 39,870.00 443.79 443.79 39,940.69 - 39,940.69

b) under Grade beam m2 252.07 90.00 22,686.30 - - - -

c) under concrete retaining wall m2 110.08 90.00 9,907.38 - - - -


2.02 Reinforced concrete quality C-
25,minimum cement content of 360 kg - - - - -
of cement/m3 filled in to form work
and
a) In vibrated around rod reinforcement
isolated footing,combine footin & li m3 345.30 2,550.00 880,515.00 345.30 345.30 880,518.95 - 880,518.95

b) In footing columns m3 125.00 2,550.00 318,750.00 84.525 84.53 215,538.75 - 215,538.75

c) In grade beamns& ground floor beams m3 111.19 2,550.00 283,534.50 53.8524 53.85 137,323.62 - 137,323.62

d) 100mm thick basement floor m2 864.18 255.00 220,365.90 - - - -

e) in 150mm thick groend floor slab10cm m2 858.61 390.00 334,857.90 - - - -


Formwork
f)in shall
retaining be timbered
wall,strong roomorand
steel
liftor
a combination of two,sufficent to
core m3 16.20 2,550.00 41,310.00 - - - -
contain the wet concrete with out
g) in entrance
leakage. Enoughsteps and ramps
to support temporary
loading and pressure from placing m3 6.28 2,550.00 16,014.00 - - - -
2.03 compaction or vibration without
displacement or appreciable deflection. - - - - -
sufficient to contain the wet concrete
without leakage. - - - - -

a) In isolated footing,combine footin & li m2 443.17 150.00 66,475.50 443.17 443.17 66,474.90 - 66,474.90

b) In footing columns m2 265.20 170.00 45,084.00 591 591.00 100,470.00 - 100,470.00

c) In grade beamns& ground floor beams m2 741.34 150.00 111,201.00 359.016 359.02 53,852.40 - 53,852.40

d) 100mm thick basement floor m2 858.61 170.00 145,963.70 - - - -

e) in 150mm thick groend floor slab10cm m2 313.20 170.00 53,244.00 - - - -


f)in retaining wall,strong room and lift
core m2 17.30 170.00 2,941.00 - - - -
2.04 Steel bar reinforcement according to
structural drawings.)Reinforcement shall - - - - -
befree from dirt,oil, grease, paint,
retarders, etc and any other substances
a) Dia.6 Plain kg - - - - -
which may affect the reinforcement and
concrete bond (price include cutting,
b) Dia.8 deformed
bending, placing in position and tying kg 8,405.21 32.00 268,966.72 1,918.14 1,918.14 61,380.37 - 61,380.37
wires ) with required spacers.
c) Dia.10 deformed kg 9,375.62 32.00 300,019.84 6,751.86 6,751.86 216,059.58 - 216,059.58

d) Dia.12 deformed kg 2,588.64 32.00 82,836.48 609.85 609.85 19,515.28 - 19,515.28

e) Dia.14 deformed kg 6,528.65 32.00 208,916.80 7,976.85 7,976.85 255,259.16 - 255,259.16

f) Dia.16 deformed kg 2,516.69 32.00 80,534.08 9,627.67 9,627.67 308,085.36 - 308,085.36

g) Dia.20 deformed kg 5,836.83 32.00 186,778.56 11,048.31 11,048.31 353,545.92 - 353,545.92

h) Dia.24 deformed kg 526.32 32.00 16,842.24 - - - -


2.5
20mm thick asphalt impregnated chipwood expansi 601.28 32.00 19,240.96 - -

Total Carried to Summary 3,756,855.86 - 2,707,964.99 - 2,707,964.99


__________________ ______________ .
contractor Rep. supervisors Rep .
Demolishion of Main store constructed
1. SUBSTRUCTURE
from HCB Material having size of
26.1m x 10.2m and Average height of
DEMOLITION WORKS
5m, Floor Finish cement tile & cement
1.01 screed. Price shall includes demolishing
of foundation wall below NGL m2 1,331.10 259.50 345,420.45 1,331.10 1,331.10 345,420.45 - 345,420.45
1.02 Ditto as item No-1; office Type-1
Dimension (5.5m x 17.10m x 3m) m3 282.15 259.50 73,217.93 282.15 282.15 73,217.93 - 73,217.93
1.03 Ditto as item No-1; office Type-2
Dimension (9.9m x 11.10m x 3m) m3 329.67 259.50 85,549.37 334.48 334.48 86,796.52 - 86,796.52
1.04 Demolishion of existing Masonry Fence
which has a length of ----- ml 400.00 600.00 240,000.00 180.00 180.00 108,000.00 - 108,000.00
1.05 Cartaway surplus excavated material to
appropriate tip m3 1,580.00 45.00 71,100.00 1,520.00 1,520.00 68,400.00 - 68,400.00

Total Carried to Summary 815,287.74 - 3,647.73 681,834.90 - 681,834.90

__________________ ______________ .
contractor Rep. supervisors Rep .
Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.
T D R Description T D R Description
A. SUBSTRUCTURE
Demolishing works
1 26.10

10.20 1.01) Store


5.00
1,331.10 M3
1,331.10 Total volume
1 5.50
17.10 1.02) office
3.00
282.15 M3
282.15 Total volume
1 5.50
17.10 1.03) office
3.00
282.15 M3
1 1.02
17.10
3.00 office
52.33 M3
334.48 Total volume

1.04 Fence
2
60.00

120.00 m
2
30.00

60.00 m
180.00 Total length
1.05. cart away
95
16.00
1,520.00 m3
1,520.00 total volume
Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.

T D R Description T D R Description
1. excavation and earth work
1.1 Site clearing
1 59.00
28.90

1,705.10 M2
1,705.10 Total area

_____________ ______________
Contractor rep. Consultsnt rep.
T D R Description T D R Description

1. excavation and earth work 1.3 Trench excavation

1.2 Bulk excavaiton to reduced level


2 22.60
1 26.35 depth of 2.7m 0.90 Front and back
8.00 axis 1-2 0.85
2.70 34.58
569.16 M3 2 49.04
1 26.35 0.90 Two sides
5.00 axis 2-3 0.85
2.70 75.03
355.73 M3 109.61 Total volume
1 26.35
5.00 axis 3-4
2.70
355.73 M3
1 26.35
5.00 axis 4-5
2.70
355.73 M3
1 26.35
5.00 axis 5-6
2.70
355.73 M3
1 26.35
5.00 axis 6-7
2.70
355.73 M3
1 26.35
5.00 axis 7-8
2.70
355.73 M3
1 26.35
5.00 axis 8-9
2.70
355.73 M3
1 26.35
5.00 axis 9-10
2.70
355.73 M3
1 26.35
5.00 axis 10-11
2.70
355.73 M3

3,770.68 Total volume

_____________ ______________
Contractor rep. Consultsnt rep.
T D R Description T D R Description
1. excavation and earth work 1.5 fill under hardcore
1 49.03
1 26.35 1.4 Excavation for isolated footing 22.60
8.00 axis 1-2 1.80
3.50 1,994.54
738.33 M3 1,994.54 Total volume
1 26.35
5.00 axis 2-3
3.48 1 49.03 1.6 Fill around foundation
457.96 M3 22.60
1 26.35 1.65
5.00 axis 3-4 1,828.33 m3
3.45 -1 345.30
454.54 M3 1.00 Ddt footings volume
1 26.35 1.00
5.00 axis 4-5 345.30
3.42
450.59 M3 1483.0287 Total volume
1 26.35
5.00 axis 5-6 1 49.03 1.7 Fill around retaining wall
3.40 5.89 beyond axis A
447.42 M3 2.75
1 26.35 794.31 m3
5.00 axis 6-7 1 49.03
3.39 6.08 beyond axis E
446.63 M3 1.00
1 26.35 297.95 m3
5.00 axis 7-8 1 49.03
3.39 6.31 beyond axis 1
446.24 M3 2.75
1 26.35 850.12 m3
5.00 axis 8-9 1 26.35
3.38 6.01 beyond axis 10
444.79 M3 1.00
1 26.35 158.36 m3
5.00 axis 9-10
3.36 2,100.74 Total volume
442.28 M3
1 26.35
5.00 axis 10-11
3.28
431.74 M3

4,760.52 Total volume

_____________ ______________
Contractor rep. Consultsnt rep.
T D R Description T D R Description
1. excavation and earth work

1 1.8 Cartaway surplus material


1,705.10 From cart away material
0.20 cleared area=1,705.1m2
341.02 M3
1
3,770.68 from bulk excavation
Bulk excavation volume=3,770.69m3
3,770.68 M3
1
109.61 From trench excavation
trench excavation volume=109.61m3
109.61 M3
1
4,902.29 from excavation of isolated footing
excavation of isolated footing=4,902.29m3
4,902.29 M3

9,123.60 Total volume

_____________ ______________
Contractor rep. Consultsnt rep.
T D R Description T D R Description
1. Excavation and Earth work 1. Excavation and Earth work
1.9 . 250mm hardcore 1.9 .250mm hardcore

2 5.70
1 5.69 axis 5-7 & C-D
1 4.64 64.91 M2
1 5.70 axis 1-2 &A-A'
26.47 M2 1 4.70
1 5.69 axis 8-9 & C''-D
4 4.70 26.76 M2
1 5.70 axis 2-5,7-8 & A-A'
107.16 M2 1 5.69 axis 9-10 &C''-D INCLUDING
1 6.40 CANTILEVER
2 5.70 36.44 M2
1 4.70 axis 5-7 &A-A'
53.58 M2 1 4.36
1 4.64 axis 1-2 &D-E with cantiliver
1 4.64 20.22 M2
1 4.70 axis 1-2 & B-B'
21.82 M2 4 4.70
1 4.36 axis 2-5,7-8 & D-E With cantiliver
4 4.70 81.89 M2
1 4.70 axis 2-5,7-8 & B-B'
88.36 M2 2 5.70
1 4.36 axis 5-7 & D-E with cantiliver
2 4.70 49.66 M2
1 4.70 axis 5-7 & B-B'
44.18 M2 1 4.36
1 6.62 axis 8-9 & D-E including cantiliver
1 4.70 28.85 M2
1 6.62 axis 8-9 & A'-C''
31.10 M2 1 4.36 axis 9-10 & D-E INCLUDING
1 6.40 CANTILEVER
1 6.62 axis 9-10 & A'-C'' INCLUDING 27.90 M2
1 6.40 CANTILEVER
42.37 M2

1 4.64 885.16 M2 total area


1 5.69 axis 1-2 & C-D
26.44 M2

4 4.70
1 5.69 axis 2-5,7-8 & B-B'
107.05 M2

_____________ ______________
Contractor rep. Consultant rep.
Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.
T D R Description T D R Description
2. Concrete works
2.1 Concrete C-5 under
a.Isolated footing and lift pad

1
10 3.50
3.50 F1
122.50 M2

1
12 3.00
3.00 F2
108.00 M2

1
17 2.75
2.75 F3
128.56 M2

1
4 2.30
2.30 F4
21.16 M2

1
3 1.90
1.90 F5
10.83 M2

1
1 3.00
3.50 F6
10.50 M2

1
1 3.10
3.25 CF1
10.08 M2

1
1 2.10
2.78 CF2
5.84 M2

1
1 4.70
5.60 MATF
26.32 M2

443.79 M2 ,Total

Contractor Rep Consultant Rep


T D R Description T D R Description
2. Concrete Work
2.2 Rc. Substructure Concrete C-25
b . In Foundation Column
a .In isolated,combined and lift pad footing
Up to -2.70

1
10 3.50 1
3.50 F1 16 0.60
0.85 0.60
104.13 M3 2.60 C1
1 14.98 M3
12 3.00 1
3.00 15 0.60
0.75 F2 0.60
81.00 M3 2.60 C2
1 14.04 M3
17 2.75 1
2.75 3 0.60
0.70 F3 0.60
89.99 M3 2.60 C3
1 2.81 M3
4 2.30 1
2.30 2 0.40
0.60 F4 0.40
12.70 M3 2.60 C4
1 0.83 M3
3 1.90
1.90 1
0.50 F5 4 0.50
5.41 M3 0.50
1 2.60 C5
1 3.00 2.60 M3
3.50 1
0.85 F6 5 0.30
8.92 M3 0.30
1 2.60 C6
1 3.10 1.17 M3
3.25 1
0.80 CF1 2 0.60
8.06 M3
0.60
1 2.60 C7
1 2.10 1.87 M3
2.78 1
0.60 CF2 7 0.60
3.50 M3 0.60
2.60 C8
1 4.70 6.55 M3
5.60

1.20 MF
31.58 M3 44.85 M3,Total

345.30 M3 ,Total

Contractor Rep Consultant Rep


T D R Description T D R Description
2. Concrete Work
2.2 Rc. Substructure Concrete C-25
Foundation column from -2.75- 0+00

1 0.60
16 0.60
2.30 C1
13.25 M3

1 0.60
15 0.60
2.30 C2
12.42 M3

1 0.60
3 0.60
2.30 C3
2.48 M3

1 0.40
2 0.40
2.30 C4
0.74 M3

1 0.50
4 0.50
2.30 C5
2.30 M3

1 0.30
5 0.30
2.30 C6
1.04 M3

1 0.60
2 0.60
2.30 C7
1.66 M3

1 0.60
7 0.60
2.30 C8
5.80 M3

39.68 M3,Total
84.53 M3,Total for foundation column

Contractor Rep Consultant Rep


T D R Description T D R Description
2.2 . Concrete Work
RC. SubstructureIn situ Concrete
Concrete C-25

C . In Grade Beam and ground floor Beam

1 37.39
1 0.30
0.40 B-1
4.49 M3

1 12.10
1 0.40
0.30 B-2
1.45 M3

1 32.49
1 0.40
0.30 B-3
3.90 M3

1 32.44
1 0.40
0.30 B-4
3.89 M3

1 12.15
1 0.40
0.30 B-5
1.46 M3

1 49.14
1 0.40
0.30 B-6
5.90 M3

1 49.14
1 0.40
0.30 B-7
5.90 M3

1 22.29
7 0.40
0.30 B-8
18.72 M3

1 22.19
1 0.40
0.30 B-9
2.66 M3

1 18.20
2 0.40
0.30 B-10
4.37

1 4.65
2 0.40
0.30 LB-1
1.12 M3

53.85 M3 , Total in grade beam

Contractor Rep Consultant Rep


Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.
T D R Description T D R Description
2.Concrete work
2.3 Form work b . In foundation column
a . In isolated footings, combined footing and below -2.70
lift pad
10 0.85
4 3.50 F1
119.00 M2 16 2.60
12 0.75 4 0.60 C1
4 3.00 F2 99.84 M2
108.00 M2
17 0.70 15 2.60
4 2.75 F3 4 0.60 C2
130.90 M2 93.60 M2
4 0.60
4 2.30 F4 3 2.60
22.08 M2 4 0.60 C3
3 0.50 18.72 M2
4 1.900 F5
11.40 M2 2 2.60
1 0.85 4 0.40 C4
2 3.000 F6 8.32 M2
5.10 M2
1 0.85 3 2.60
2 3.50 F6 4 0.50 C5
5.95 M2 15.60 M2
1 0.80
2 3.100 CF1 5 2.60
4.96 M2 4 0.30 C6
1 0.80 15.60 M2
2 3.25 CF1
5.20 M2 3 2.60
1 0.60 4 0.60 C7
2 2.100 CF2 18.72 M2
2.52 M2
1 0.60 7 2.60
2 2.78 CF2 4 0.60 C8
3.34 M2 43.68 M2
1 1.20
2 4.700 MATF
11.28 M2 314.08 M2,Total
1 1.20
2 5.600 MATF
13.44 M2

443.17 M2,Total

Contractor Rep Consultant Rep


T D R Description T D R Description
2. Concrete Work
2.3 Formwork

Foundation column from -2.75- 0+00

16 2.30
4 0.60 C1
88.32 M2

15 2.30
4 0.60 C2
82.80 M2

3 2.30
4 0.60
16.56 M2

2 2.30
4 0.40 C4
7.36 M2

4 2.30
4 0.50 C5
18.40 M2
.

5 2.30
4 0.30 C6
13.80 M2

2 2.30
4 0.60 C7
11.04 M2

7 2.30
4 0.60 C8
38.64 M2

276.92 M2,Total
591.00 M2,Total for foundation column

Contractor Rep Consultant Rep


T D R Description T D R Description
2.Concrete work
2.3 Form work
a . In Grade beams and ground floor beams

1 37.39
2 0.40 B-1
29.91 M2

1 12.10
2 0.40 B-2
9.68 M2

1 32.49
2 0.40 B-3
25.99 M2

1 32.44
2 0.40 B-4
25.95 M2

1 12.15
2 0.40 B-5
9.72 M2

1 49.14
2 0.40 B-6
39.31 M2

1 49.14
2 0.40 B-7
39.31 M2

2 22.29
7 0.40 B-8
124.82 M2

1 22.19
2 0.40 B-9
17.75 M2

2 18.20
2 0.40 B-10
29.12 M2

2 4.65
2 0.40 LB-1
7.44 M2

359.02 M2, Total in grade beam

Contractor Rep Consultant Rep


Project:- B+G+5 multipurpose building
Location:- Ambo
Consultant:- OBON voyage architechts and engineers
Contractor:- MCG Construction plc.
Rebar For Foundation Pad

No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24

1 F1 Main 16.00 4.90 44.00 10.00 2,156.00


2 F2 Main 14.00 4.20 48.00 12.00 2,419.20
3 F3 Main 14.00 3.85 38.00 17.00 2,487.10
4 F4 Main 12.00 3.20 34.00 4.00 435.20
5 F5 Main 12.00 2.60 26.00 3.00 202.80
Longer d/n 14.00 4.90 23.00 1.00 112.70
6 F6
shorter d/n 14.00 4.40 26.00 1.00 114.40
Top along longer
d/n 16.00 4.55 22.00 1.00 100.10
Top along
shorter d/n 16.00 4.44 23.00 1.00 102.12
7 CF1
Bottom along
longer d/n 16.00 4.55 22.00 1.00 100.10
Bottom along
shorter d/n 16.00 4.44 23 1.00 102.12
Top along longer
d/n 14.00 3.68 14 1.00 51.98
Top along
shorter d/n 14.00 3.00 18 1.00 55.13
8 CF2
Bottom along
longer d/n 14.00 3.00 18 1.00 54.00
Bottom along
shorter d/n 14.00 3.68 14 1.00 51.52
Top along
shorter d/n 16.00 6.80 48 1.00 324.13
Top along longer
d/n 16.00 7.70 40 1.00 309.28
9 MATF
Bottom along
shorter d/n 16.00 6.80 48 1.00 324.13
Bottom along
longer d/n 16.00 7.70 40 1.00 309.28
Total length(m) - - 638.00 5,346.03 3,827.27 - -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total Weight (Kg) - - 566.54 6,468.69 6,047.09 - -

Contractor Rep Supervisors Rep. -


Rebar For foundation Column of Basement

No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24

Main 20.00 5.20 12 16.00 998.40


1 C1 stirrup 10.00 2.35 14 16.00 526.40
stirrup 10.00 1.95 28 16.00 873.60
Main 20.00 5.20 12 15.00 936.00
2 C2 stirrup 10.00 2.35 14 15.00 493.50
stirrup 10.00 1.95 28 15.00 819.00
Main 20.00 5.10 10 3.00 153.00
3 C3 stirrup 10.00 2.35 14 3.00 98.70
stirrup 10.00 1.95 28 3.00 163.80
Main 16.00 5.00 8 2.00 80.00
4 C4 stirrup 10.00 1.55 14 2.00 43.40
stirrup 10.00 1.55 14 2.00 43.40
Main 20.00 5.10 8 4.00 163.20
5 C5 stirrup 10.00 1.95 14 4.00 109.20
stirrup 10.00 1.95 14 4.00 109.20
Main 16.00 5.20 8 5.00 208.00
6 C6 stirrup 10.00 1.15 14 5.00 80.50
stirrup 10.00 1.15 28 5.00 161.00
Main 20.00 5.10 12 2.00 122.40
7 C7 stirrup 10.00 2.35 14 2.00 65.80
stirrup 10.00 1.95 28 2.00 109.20
Main 20.00 5.10 10 7.00 357.00
8 C8 stirrup 10.00 2.35 14 7.00 230.30
stirrup 10.00 1.95 28 7.00 382.20
Total Length (m) - 4,309.20 - - 288.00 2,730.00 -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total Weight (Kg) - 2,658.78 - - 455.04 6,743.10 -

Contractor Rep Supervisors Rep. -


Rebar For Beam @ Basement floor

No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24
Top 14.00 8.15 2 1.00 16.30
Top 14.00 10.56 2 1.00 21.12
Top 14.00 6.06 2 1.00 12.12
Top & bottom 14.00 6.56 4 1.00 26.24
Top 14.00 8.73 2 1.00 17.46
Top 14.00 1.59 2 1.00 3.17
Top 14.00 3.32 2 1.00 6.63
1 B1 Top 14.00 3.33 4 1.00 13.32
Top 14.00 3.67 4 1.00 14.66
Top 14.00 4.00 2 1.00 8.00
Top 14.00 1.60 2 1.00 3.20
bottom 14.00 5.65 2 1.00 11.30
bottom 14.00 5.56 8 1.00 44.48
bottom 14.00 5.73 2 1.00 11.46
Stirrup 8.00 1.30 276 1.00 358.80
Top 14.00 8.15 2 1.00 16.30
Top 14.00 5.01 2 1.00 10.01
Top 14.00 1.59 2 1.00 3.17
Top 14.00 3.33 2 1.00 6.66
2 B2
Top 14.00 3.89 2 1.00 7.78
bottom 14.00 5.65 2 1.00 11.30
bottom 14.00 7.51 2 1.00 15.01
Stirrup 8.00 1.30 92 1.00 119.60
Top 14.00 8.19 3 1.00 24.56
Top 16.00 10.64 3 1.00 31.92
Top 16.00 6.14 3 1.00 18.42
Top 16.00 6.60 3 1.00 19.80
Top 14.00 6.56 3 1.00 19.68
Top 16.00 8.77 3 1.00 26.31
Top 16.00 1.59 1 1.00 1.59
Top 16.00 3.33 2 1.00 6.66
3 B3 Top 16.00 3.67 2 1.00 7.33
Top 16.00 4.00 1 1.00 4.00
Top 16.00 1.60 1 1.00 1.60
bottom 16.00 5.65 2 1.00 11.30
bottom 16.00 5.56 3 1.00 16.68
bottom 14.00 5.56 4 1.00 22.24
bottom 16.00 6.64 2 1.00 13.28
bottom 16.00 5.77 2 1.00 11.54
Stirrup 8.00 1.30 276 1.00 358.80
Total Length (m) 837.20 - - 346.16 170.42 - -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total Weight (Kg) 330.69 - - 418.85 269.27 - -

Contractors rep. :___________________ Supervisors rep. : ________________


No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24
Top 14.00 8.15 3 1.00 24.44
Top 14.00 10.56 3 1.00 31.68
Top 16.00 6.06 3 1.00 18.18
Top 14.00 6.56 3 1.00 19.68
Top 16.00 1.59 1 1.00 1.59
Top 16.00 3.32 1 1.00 3.32
Top 16.00 3.33 2 1.00 6.67
Top 14.00 3.67 1 1.00 3.67
Top 16.00 4.00 1 1.00 4.00
4 B4 Top 16.00 1.85 1 1.00 1.85
bottom 14.00 5.65 3 1.00 16.94
bottom 12.00 5.65 1 1.00 5.65
bottom 14.00 5.56 9 1.00 50.04
bottom 12.00 5.56 3 1.00 16.68
bottom 14.00 6.56 3 1.00 19.68
bottom 12.00 6.56 1 1.00 6.56
bottom 14.00 6.73 3 1.00 20.19
bottom 12.00 6.73 1 1.00 6.73
Stirrup 8.00 1.30 236 1.00 306.80
Top 14.00 8.15 3 1.00 24.44
Top 14.00 5.01 3 1.00 15.02
Top 16.00 1.59 1 1.00 1.59
Top 16.00 3.33 1 1.00 3.33
Top 16.00 3.89 1 1.00 3.89
5 B5
bottom 14.00 5.65 3 1.00 16.94
bottom 14.00 7.51 3 1.00 22.52
bottom 12.00 5.65 1 1.00 5.65
bottom 12.00 7.51 1 1.00 7.51
Stirrup 8.00 1.30 92 1.00 119.60
Top 14.00 8.15 3 1.00 24.44
Top 16.00 10.56 3 1.00 31.68
Top 16.00 6.06 6 1.00 36.36
Top 16.00 6.56 3 1.00 19.68
Top 16.00 5.56 3 1.00 16.68
Top 16.00 10.01 3 1.00 30.02
Top 16.00 1.59 1 1.00 1.59
Top 16.00 3.30 4 1.00 13.20
Top 16.00 3.67 2 1.00 7.33
6 B6
Top 16.00 4.00 1 1.00 4.00
Top 16.00 3.89 1 1.00 3.89
bottom 16.00 5.65 2 1.00 11.30
bottom 16.00 5.56 3 1.00 16.68
bottom 14.00 5.56 4 1.00 22.24
bottom 16.00 6.64 4 1.00 26.56
bottom 16.00 5.64 4 1.00 22.56
bottom 16.00 7.55 2 1.00 15.09
Stirrup 8.00 1.30 324 1.00 421.20
Total Length (m) 847.60 - 48.77 311.93 301.01 - -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total Weight (Kg) 334.80 - 43.31 377.43 475.59 - -

Contractors rep. :___________________ Supervisors rep. : ________________


No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24
Top 14.00 8.15 2 1.00 16.30
Top 14.00 10.56 2 1.00 21.12
Top 14.00 6.06 2 1.00 12.12
Top 14.00 6.56 2 1.00 13.12
Top 14.00 8.73 2 1.00 17.46
Top 14.00 10.05 2 1.00 20.10
Top 14.00 1.59 2 1.00 3.17
Top 14.00 3.32 2 1.00 6.63
Top 14.00 3.33 8 1.00 26.64
7 B7 Top 14.00 3.67 2 1.00 7.33
Top 14.00 4.00 2 1.00 8.00
Top 14.00 3.67 2 1.00 7.33
Top 14.00 3.89 2 1.00 7.78
bottom 14.00 5.65 2 1.00 11.30
bottom 14.00 5.56 8 1.00 44.48
bottom 14.00 6.56 4 1.00 26.24
bottom 14.00 5.56 2 1.00 11.12
bottom 14.00 7.51 2 1.00 15.01
Stirrup 8.00 1.30 324 1.00 421.20
Top 14.00 8.61 3 7.00 180.77
Top 16.00 6.06 3 7.00 127.18
Top 16.00 9.23 3 7.00 193.83
Top 16.00 3.22 1 7.00 22.51
Top 16.00 2.73 1 7.00 19.08
Top 16.00 3.33 1 7.00 23.31
8 B8 Top 16.00 3.67 1 7.00 25.66
Top 16.00 1.85 1 7.00 12.95
bottom 16.00 5.65 3 7.00 118.65
bottom 16.00 6.63 3 7.00 139.29
bottom 16.00 5.64 3 7.00 118.44
bottom 16.00 6.77 3 7.00 142.17
Stirrup 8.00 1.30 210 7.00 1,911.00
Top 14.00 6.89 3 1.00 20.67
Top 16.00 8.93 3 1.00 26.78
Top 16.00 8.08 3 1.00 24.24
Top 16.00 3.22 1 1.00 3.22
Top 16.00 2.73 1 1.00 2.73
Top 16.00 3.33 1 1.00 3.33
9 B9 Top 16.00 3.67 1 1.00 3.67
Top 16.00 1.85 1 1.00 1.85
bottom 16.00 5.65 3 1.00 16.95
bottom 16.00 6.66 3 1.00 19.99
bottom 16.00 5.64 3 1.00 16.92
bottom 16.00 6.77 3 1.00 20.31
Stirrup 8.00 1.30 210 1.00 273.00
Total Length (m) 2,605.20 - - 476.68 1,083.02 - -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total Weight (Kg) 1,029.05 - - 576.78 1,711.18 - -

Contractors rep. :___________________ Supervisors rep. : ________________


No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24
Top 14.00 8.61 3 2.00 51.65
Top 16.00 6.06 3 2.00 36.34
Top 16.00 9.23 3 2.00 55.38
Top 16.00 3.22 1 2.00 6.43
Top 16.00 2.73 1 2.00 5.45
Top 16.00 3.33 1 2.00 6.66
10 B10
Top 16.00 2.37 1 2.00 4.73
Top 16.00 0.85 1 2.00 1.70
bottom 16.00 5.65 3 2.00 33.90
bottom 16.00 6.66 3 2.00 39.98
bottom 16.00 7.69 3 2.00 46.13
Stirrup 8.00 1.30 183 2.00 475.80
Top & Bottom 14.00 5.90 4 2.00 47.20
11 LB1 Top 14.00 1.60 4 2.00 12.80
Stirrup 8.00 1.30 35 2.00 90.24
Total Length (m) 566.04 - - 111.65 236.69 - -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total
Total Weight
Weight (Kg) @
for beam 223.59 - - 135.09 373.98 - -
basement (kg) 1,918.14 - 43.31 1,508.16 2,830.01 - -

Contractors rep. :___________________ Supervisors rep. : ________________


Rebar For found.column from -2.75 to +0.00
No of No of
SR.1 Item BarDesignation Ф Length Remark
bars member Ф8 Ф10 Ф12 Ф14 Ф16 Ф20 Ф24
Main 20.00 3.50 12 16.00 672.00
1 C1 stirrup 10.00 2.35 21 16.00 770.80
stirrup 10.00 1.95 42 16.00 1,310.40
Main 20.00 3.50 10 15.00 525.00
2 C2 stirrup 10.00 2.35 21 15.00 722.63
stirrup 10.00 1.95 42 15.00 1,228.50
Main 20.00 3.50 10 3.00 105.00
3 C3 stirrup 10.00 2.35 21 3.00 144.53
stirrup 10.00 1.95 42 3.00 245.70
Main 16.00 3.34 8 2.00 53.44
4 C4 stirrup 10.00 1.55 21 2.00 63.55
stirrup 10.00 1.55 42 2.00 130.20
Main 20.00 3.50 8 4.00 112.00
5 C5 stirrup 10.00 1.95 21 4.00 159.90
stirrup 10.00 1.95 42 4.00 327.60
Main 16.00 3.34 8 5.00 133.60
6 C6 stirrup 10.00 1.15 21 5.00 117.88
stirrup 10.00 1.15 42 5.00 241.50
Main 20.00 3.50 12 2.00 84.00
7 C7 stirrup 10.00 2.35 21 2.00 96.35
stirrup 10.00 1.95 42 2.00 163.80
Main 20.00 3.50 10 7.00 245.00
8 C8 stirrup 10.00 2.35 21 7.00 337.23
stirrup 10.00 1.95 42 7.00 573.30
Total Length (m) - 6,633.85 - - 187.04 1,743.00 -
Wt/Lm(Kg/m) 0.395 0.617 0.888 1.210 1.580 2.470 3.552
Total Weight (Kg) - 4,093.09 - - 295.52 4,305.21 -
Grand total (kg) 1,918.14 6,751.86 609.85 7,976.85 9,627.67 11,048.31 -

Contractors rep. :___________________ Supervisors rep. : ________________