Start Up & Commissioning of Sump Pumps
Start Up & Commissioning of Sump Pumps
Start Up & Commissioning of Sump Pumps
ETA
MEP
Client :- Emaar Properties Contractor
M&E Division
MEP Consultant
Roberts & Partners
Page 1 of 5
Nasa Multiplex
Burj Dubai - The Residences
ETA
MEP
Client :- Emaar Properties Contractor
M&E Division
1.0 Scope
The scope of this Method Statement is to define the method of Start-up and
Commissioning of Sump Pumps installed within the Burj Dubai – The Residences, in
accordance with the Specification Sections 15440 manufacturer’s instructions
attached.
Note
2.0 Material
Note
The calibration certificates of testing instruments shall be verified prior to usage and
copies shall be included in the test reports.
4.1 Mechanical
4.1.1 Check and inspect the installation of Sump Pump is complete, verify
the installation as per approved drawings.
Page 2 of 5
Nasa Multiplex
Burj Dubai - The Residences
ETA
MEP
Client :- Emaar Properties Contractor
M&E Division
4.1.4 Check and ensure adequate clearance available for service and
maintenance of pumps and motors.
4.1.7 Check all nuts, bolts, screws, fasteners etc., are fixed and tightened as
required.
4.1.9 Check and ensure the safety guards are in place and secure.
4.1.10 Rotate the pump manually and ensure free and smooth rotation.
4.1.11 Ensure the pumps are cleaned prior to start-up and all identification
labels and tags are in place.
4.2 Electrical
4.2.1 Check all power cabling and control wiring is completed and dressed
neatly.
4.2.2 Check the power isolator is fixed close to the pump motor for
emergency stop and power isolation.
4.2.5 Ensure the overload protections are set correctly as per the pump motor
load current.
4.2.6 Ensure all identification tags and labeling works are complete.
Page 3 of 5
Nasa Multiplex
Burj Dubai - The Residences
ETA
MEP
Client :- Emaar Properties Contractor
M&E Division
5.1 Check the line voltage and phase rotation before energizing the power.
5.2 Switch ON the power and start the pump and check the rotation is in the
correct direction.
5.3 Immediately on start-up, check for any abnormal noise and vibration. Rectify
as / if required Consult manufacturer if required.
5.4 Observe for the correct operation of motor, pump and drive system.
5.5. Measure the current drawn (amperage) by the pump motor and record the
same.
5.6 Record all pump and motor nameplate data in the commissioning format.
6.0 Safety
6.1 Only experienced and skilled personnel shall be engaged for start-up and
commissioning of Sump pumps.
6.3 Warning signs and tapes shall be placed during start-up and commissioning as
required.
6.4 All safety procedures shall be followed in accordance with the project health
and safety plan.
6.5 Safety Officer shall check and ensure all safety precautions are followed.
Page 4 of 5
Nasa Multiplex
Burj Dubai - The Residences
ETA
MEP
Client :- Emaar Properties Contractor
M&E Division
7.0 Records
7.1 Inspection request (for Witness of start-up and commissioning) duly signed by
NMX and Consultants
8.0 References
9.0 Attachments