Olyad Report
Olyad Report
INSTITUTE OF TECHNOLOGY
SCHOOL OF CIVIL ENGINEERING AND ARCHITECTURE
DEPARTMENT OF CIVIL ENGINEERING
ID: 1103544
DECLARATION
𝐼 Olyad Chala student of Dire Dawa University Institute of Technology, hereby declare that
this internship report is submitted by me under the guidance of my mentor Tesfaye and
supervision of Ermiyas Bayew. I assure that the report contains actual events and facts that
were observed and performed during my internship practice program. All the contents are my
own original work and have not been submitted (presented) earlier to any other institute
Olyad chala
APPROVED BY
MENTOR
Ins. Tesfaye W.
Signature Date
COMPANY SUPERVISOR
Mr. Ermiyas bayew
Signature Date
ACKNOWLEDGEMENT
First, I would like gratefully acknowledge the Almighty God for his great help. Second, I would
like to express my gratitude and deep appreciation to my advisor, Mr. Tesfaye & Supervisor,
Mr. Ermiyas Bayew for their valuable comment, suggestions and advice during internship
program and preparing the final internship report paper.
Next, I want to acknowledge the Dire Dawa University, Institute of Technology and Department
of Civil Engineering for financial assistance and industrial linkage office for setting up this
internship program so that we could gain practical skills and hence strengthen our theoretical
skills.
Finally I want to express my heartfelt gratitude to my family and friends all others who had
encouraged and given me suggestions, comments and the required assistance
Page | ii
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
EXCUTIVE SUMMARY
As a fourth year civil engineering student, the internship program representatives me on
showing the practical with the theoretical knowledge that I have learnt in the class. The main
objective is to pave the way to students on accumulating knowledge’s and skills on real
world and on how to ease the work, hence it will be great foundation to the future carriers of
mine before I immerse to it. In my belief I have got basic knowledge of how I will be
compatible with the work for the future on mixing the practical skills with the theoretical
one. It is 1/2B+ 2B+G+9 building. When I join the project the site was on the beginning of
Ground floors, so I didn’t get the chance to see foundation and earth work. The following
lists are the skills that I grasp basic acquaintance from them. Those are
Structural work
Re baring
Reading drawing
As a whole the internship program is very important and interesting that I took a good lesson
out of it both in practical and ethically. From many types of work ethics, punctuality,
transparency, and accountability are the main issues and I got to learn it.
It also gave me the chance to know different people with different type of knowledge and
skill, which in return helped me to improve my communication skill with a better team spirit.
Above all, it improved my self- confidence and self-esteem
Page | iii
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
ABBREVIATION
D.D.U…………………………………………………….……Dire Dawa university
Hr.………………………………………………………………hour
G.C………......…………………………………………………Gregorian calendar
M…….…..…….……………………………………………….Meter
CM…….…..…….…………………………………………….. Centimetre
R.C…….…..…….……………………………………………..reinforced concrete
Page | iv
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Contents
DECLARATION ....................................................................................................................... i
ACKNOWLEDGEMENT ........................................................................................................ ii
EXCUTIVE SUMMARY ........................................................................................................ iii
ABBREVIATION.................................................................................................................... iv
List of figures .......................................................................................................................... vii
List of Table ............................................................................................................................ vii
CHAPTER ONE ....................................................................................................................... 1
1. Company profile ................................................................................................................... 1
1.1 Introduction ..................................................................................................................... 1
1.2 Brief History ................................................................................................................... 1
1.3 Vision and Mission Statement ........................................................................................ 2
1.4 Services ........................................................................................................................... 3
1.5 Health and Safety Policy ................................................................................................. 3
1.6 Environmental Policy...................................................................................................... 5
1.7 Organization work flow .................................................................................................. 7
1.8 On-site Organizational Chart .......................................................................................... 8
CHAPTER 2 ........................................................................................................................... 12
2. Overall Internship Experience ............................................................................................ 12
2.1 How I get in to the company? ....................................................................................... 12
2.1.2 General description of the project .............................................................................. 12
2.2 Section of the company I have been working in ........................................................... 13
2.3 Work flow in the construction site ................................................................................ 13
2.4 Work Task I Have Been Executing .............................................................................. 15
2.4.1 Office Work ........................................................................................................... 15
2.4.1.1 The work task I have been executing in the office: ........................................ 15
2.4.2 Site work ................................................................................................................ 18
2.4.2.1 Structure work tasks ........................................................................................ 18
2.4.2.1.2 Substructure Work ................................................................................... 19
Page | v
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | vi
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
List of figures
Figure 1.1 previous completed project.................................................................................... 11
Figure 2.1 column reinforcement ............................................................................................ 21
Figure 2.2 casted column ........................................................................................................ 21
Figure 2.3 Lap length .............................................................................................................. 22
Figure 2.4 Beam reinforcement .............................................................................................. 24
Figure 2.5 Stirrup .................................................................................................................... 25
Figure 2.6 Slab reinforcement................................................................................................. 26
Figure 2.7 Punching shear reinforcement ............................................................................... 26
Figure 2.8 Chair bar ................................................................................................................ 26
Figure 2.9 shear wall ............................................................................................................... 27
Figure 2.10 stair case reinforcement ....................................................................................... 29
Figure 2.11 casted stair case ................................................................................................... 29
Figure 2.14 column form work ............................................................................................... 36
Figure 2.15 shear wall form work ........................................................................................... 37
Figure 2.16 Stair case form work ............................................................................................ 37
Figure 2.20 Cross brace .......................................................................................................... 39
Figure 2.21 RHS ..................................................................................................................... 39
Figure 2.22 Spacer .................................................................................................................. 40
Figure 2.23 using of vibration during column casting ............................................................ 40
Figure 2.24 Surveying Equipment's ........................................................................................ 41
Figure 2.25 Pulley system ....................................................................................................... 41
List of Table
Table 1.1 Construction Experience ........................................................................................... 9
Table 2.1 – Take off sheet....................................................................................................... 17
Table 2.2 –Bar schedule format .............................................................................................. 18
Page | vii
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
CHAPTER ONE
1. Company profile
1.1 Introduction
BamaCon Engineering PLC is a share, privately owned construction firm with a reliable
record of accomplishments and a bright prospect that matches its high aspiration.
The following volume is an attempt to profile that track record, the prospect and the
aspiration from its effective operating system springs.
This profile includes:
Vision Statement, Mission statement and brief history of BamaCon Engineering
PLC
Its legal status
Its organizational structure and operating systems
Its existing capacity and experience
The inclusion of these elements in the profile, we presume, will give the concerned reader
an insight on the substance of BamaCon Engineering PLC.
In the Fifteen years of its growth, the firm has always believed that capacity depends
more on organizational and human resource development than on equipment and finance.
In this belief, the firm has invested a significant portion of its time and money on:
Retaining and developing a highly professional management team.
Training and motivating its technical staff, from the craftsmen to the senior
engineers, to achieve and maintain high standards.
Page | 1
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
And the result has been a firm with a work force that can take on any challenge in
the form of a construction job.
With respect to capacity in terms of equipment, while acquisition of major
machinery has been dictated by the need to satisfy the regulatory body’s (ministry
of infrastructures) capacity Requirements, special emphasis on equipment that are
specifically appropriate to BAMACON Engineering’s own method of
construction were also sought and acquired.
Hitherto, financial capacity has always been commensurate to the cash flow
requirements of the projects. This has been partly due to the firm’s good credit record
with clients, insurance companies, banks and construction material suppliers perhaps the
most important creditors to any construction firm.
Looking back, the path BamaCon Engineering PLC travelled over the last years seems
to be a path of initiation for the competitive challenges of the third millennium.
Page | 2
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
respectively.
Ensure the prolonged existence of our company through repeat and referral
business achieved by customer satisfaction in all areas including timeliness,
attention to detail and service‐minded attitudes.
1.4 Services
BAMACON Engineering PLC, through years of vast experience dealing with project
management and contract administration issues in different construction projects, has
specialized in construction of:
Residential Houses
Office Building Complexes
Hospitals
Hotels
Factories
Warehouses and Multi‐Purpose Buildings
1.5 Health and Safety Policy
This Health and Safety Policy Statement recognizes BAMACON ENGINEERING P.L.C
obligations under the Health and Safety at Work. This policy statement and the health and
safety documentation detailing the means of implementing the policy are in respect of
BAMACON ENGINEERING P.L.C and its operating businesses.
BAMACON ENGINEERING P.L.C has a moral and legal obligation to safeguard, the health,
safety and welfare of their employees and anyone who may be affected by the actions of the
Company, or as a result of BAMACON ENGINEERING P.L.C activities. BAMACON
ENGINEERING P.L.C fully accepts their obligations and responsibilities, which will be
achieved by:
Page | 3
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 4
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 5
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
options exist.
Minimize the storage and use of all articles and substances providing a substantial
environmental hazard, where appropriate.
Reduce the consumption of resources (energy, materials, packaging), where
feasible.
Minimize waste through a commitment to reuse, recover or recycle, where
feasible.
The Company will communicate the Environmental Policy to all BAMACON
ENGINEERING P.L.C employees, and it will be freely available to customers,
shareholders and the general public.
The Managing Director, Mr Girma Gelaw is personally responsible for the
environmental performance of the Company and signs this policy statement in
acknowledgement of this overall responsibility.
Page | 6
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 7
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 8
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
4 Ato Ayele G/medhin Azzeman Hotel Addis Ababa Bole around Atlas Hotel, Addis Ababa
7 Fisseha Abay Sapphire Hotel Addis Ababa Bole around Atlas Hotel, Addis Ababa
8 Tenkir Trading PLC Foyat Hotel Addis Ababa Bole Brass, Addis Ababa
9 Wro. Zenebech Tadesse LOUVER Hotel Addis Ababa Bole around Atlas Hotel, Addis Ababa
APARTMENT BUILDINGS
Mexico, behind Alsam Chelelek Bldg.,
1 AL SAM PLC (phase 2) 2B+G+19 Hotel Apartment Building
Addis Ababa.
2 AZ Real Estate Development Construction of Luxury Apartment Piassa, (Eri bekentu), Addis Ababa
Century Addis Real Estate Mixed Use
3 Century Addis Real Estate PLC (Atlas) Building Bole Atlas, Addis Ababa
Page | 9
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
MIXED-USE BULDINGS
1 Adika tour & Travel Adika Mixed Use Building Bole around Edna mall, Addis Ababa
Merkato, Behind Tana Shopping
2 Admas Zemenawi B+G+5 Shopping Complex Building
Center, Addis Ababa
3 Afework Int. Group AIG Shop and Office Building Bambis, Addis Ababa
4 Again‐bi Construction PLC Againbi Mixed Use Building Merkato, Addis Ababa
5 Ageca S.c B+G+4 Store and Office Building Akaki, Addis Ababa
6 AIA PLC AIA Business Center Lideta, Addis Ababa
4kilo Infront of Holy Trinity Church,
7 Ambassador Garment and Trade Plc G+4 Mixed Use Building/Shopping Mall
Addis Ababa
8 Atkilt Tera Mar. Center B+G+7 Shopping Mall Piassa (Atkilt Tera), Addis Ababa
Bole behind DH Geda Building, Addis
9 Ato Alemayehu Tameru Alex Mixed Use Building
Ababa
Bole road, around Dembel, Addis
10 Ato Bahiru Abraha 2B+G+10 Mixed Use Building
Ababa
11 Ato Estifanos Zeleke Mixed Use Building, Eliana Hotel Piassa, Addis Ababa
Extension
12 Ato Jonny Seifu G+10 Mixed Use Building Infron of Genet Hotel, Addis Ababa
13 Ato Mesfin Mengesha Park Plaza, B+G+7 Mixed Use Building Atlas Hotel, Addis Ababa
2B +G+7 Mixed use Building, AB ZONE
14 Beyene and Aman Business Center Urael, Addis Ababa
Business Center
PLC
15 BKMY Impex PLC 3B+G+15 Mixed Use Building 22 next to H&M Building, Addis Ababa
Bole Olympia (ShoaBakery), AddisAbaba
16 Dagi PLC B+G+14 Mixed Use Building
17 Emiru & Elizabeth Business Mixed Use Building Meskel Flower, Addis Ababa
18 Ethio ceramics PLC G+8 Mixed Use Building Kazanchis, Addis Ababa
Ethiopian Evangelical Church
19 Mekane 2B+G+7 Mixed Use Building Bambis, Addis Ababa
Yesus
20 Lemenh Emiru & Alemay Shita B+G+9 Mixed Use Building Global, Addis Ababa
21 Military Tera Merchants S.Co. 3B+G+7 Shopping Mall Merkato, around Militery Tera
2B+SB+G+M+12 Mixed Use Building, Gurd Shola Beside Daminaroff
22 NEHCO Trading PLC
Century Mall Building, Addis Ababa
Bole Olympia (Shoa Bakery), Addis
23 OMEDAD PLC OMEDAD PLC 2B+G+12 Mixed Use
Ababa
Building
Rakeb & Nahom Mixed Use Building,
24 RANG PLC Bole road, Addis Ababa
2B+G+13
Page | 10
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 11
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
CHAPTER 2
2. Overall Internship Experience
2.1 How I get in to the company?
When I received the letter from the department to go find an internship opportunity on a
construction company, my first choice was BAMACON Engineering PLC, and they accepted
my request. The acceptance was possible with the great effort of my father. Then they
assigned me on a construction site around piassa.
When I first arrived on site I introduced myself to the project manager, office engineer and
site engineer. Then I told them that the company assigned me in there site for an internship
experience and then they accepted me.
Before I started working at the site, site engineer gave me orientation about the building
project and that I should put safety first before executing any activities in the site.
When I started this internship program, already Ground floor were started so I did not have
the chance to see setting out, earth work, concrete work for footing and grade beam .
Page | 12
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
In general, the project manager acts as a leader who guides as to have an efficient work to be
done on the site in accordance with the scheduled time and as a decision maker representing
the entire site management.
Page | 13
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Site engineer
Site engineer controls all the activities in the site and is responsible for the whole
construction work. He/she makes sure that the works executed are according to the
specifications and drawings. Some of the activities performed by the site engineer are:-
Setting out of the project site.
Check the construction of all structural and finishing works.
Gives support to site workers.
Prepare all necessary progress reports to the office engineers.
Follow up the general foreman
Office engineer
The office engineer controls all the construction activities of the office starting from the
beginning and follow construction sites according to the schedules of the project which is
planned by the project manager. Some of the activities performed by the office engineer are:-
Prepare take off, bar schedules etc. based on the plan.
Prepare all necessary progress reports to the project manager and head office.
Preparation of cross sectional and detail drawings, payment certificates.
Sub-contractors
In building work there has been a long trend to pass the majority of work to sub-contractors,
who specialize in various trades, where many operations are packaged up and sub-let to
them. Thus sub-contractors may be let for excavation, formworks, reinforcement making and
erecting, plastering masonry work etc.
General Forman
Forman manages and supervise manual works. The Forman controls distribution of masons,
carpenters, and daily labours. He also gives guidance on how the work is to be done and
gives correction if there is any mistake done
Data collector
A data collectors that records the amount of the accomplished task, the materials used, the
number of labours involved on a specified work in accordance with the time within which
Page | 14
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
they completed that particular task as well as the type of equipment and machineries they
used.
Store keeper
Store keeper controls the amount and type of material of the construction entering and
leaving from the store by preparing some forms.
Page | 15
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
a. Structural drawing:
This drawing shows the structural aspect of the building. This includes:
Detail of columns
Detail of beams
Detail of foundation
Detail of slab
These structural drawings has a detailed information of number, diameter and spacing of
reinforcing bars and stirrups
b. Architectural drawing:
These drawings show the architectural aspect of the building. This Includes:
Site plan
Floor plans
2.4.1.1.2 Take off sheet
Take off is prepared by office engineers and submitted to the supervisor from the consultant
side. It always common in construction sites but different table format can be used. Take off
sheet expresses the amount of formwork, concrete (cement, sand and aggregate), and hard
core. The unit for formwork, hard core and lean concrete was m2 (area) and for concrete was
m3 (volume).
Take off sheet is a tabular standard format in which dimensions of items from working
drawing are transferred for further calculations. It consists of four columns, namely;
Page | 16
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
T D S DESCRIPTION T D S DESCRIPTION
Page | 17
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
a
ΣL for each diameter
Diameter
Location
member
Length
No in
8 10 12 14 16 18 20 24
Shape
Mark
Total
W/m
ΣW
Page | 18
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 19
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
To resist tensile stress caused in the column due to eccentric load and
moment.
To impart certain ductility to the column
To reduce the effects of creep and shrinkage due to sustained loading.
Transverse re – bars
Are used:-
To prevent longitudinal buckling of longitudinal re – bars
To resist diagonal tension caused due to transverse shear due to
moment (transverseload).
To hold the longitudinal re – bars in position at the time of concreting.
To impart ductility to the column.
To prevent sudden brittle failure of the column.
Finally after 24 hrs. The formworks are removed to form the required column.
In my site the column types used are rectangular and square column, there dimension
is:
60*60cm for square column.
70*70cm for square column.
80*80cm for square column.
90*90cm for square column.
60*30cm for rectangular column.
90*35cm for rectangular column.
70*30cm for rectangular column.
Page | 20
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Some cross sectional dimension of elevation columns was decreased as the number of
stories increase because the load coming from the super structure decrease as we go
up to the top.
Lap length
Lap length is a lap columns immediately above the casted. A reinforced concrete column
is extended by having the steel reinforcing bars extend a few centimetre in our site
according to our drawing we use (50* Φ mm of bar). if not given on drawing commonly
(40*Φ mm of bar) used above the top of the concrete, then placing the next level of
reinforcing bars to overlap, and pouring the concrete of the next level.
Page | 21
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
2.4.2.1.3.2 Beam
A beam is a horizontal structural element of the building that is capable of withstanding
vertical loads, shear forces and bending moment. The bending force induced into the material
of the beam as a result of the external loads, own weight, span and external reactions to these
loads is called a bending moment. Beams transfer loads imposed along their length to their
end points to walls, column, foundations, etc.
When a beam is subjected to loading it develops tension zone, so it has to be reinforced.
Beams are also subjected to shear stresses. It is difficult to overcome the shear stresses that
occurred in beams by increasing the depth of the beam, because it is impractical to make
beams deep due to architectural and other reasons. So we provide stirrups to overcome the
shear stresses developed at beams.
As that of grade beam and basement beam, superstructure beams are subjected to moments
and shear loads. Superstructure beams have the same reinforcement and detail provision as
that of grade beam and basement beam. But the difference is that it does not have contact
with the ground and in the construction needs bottom formwork (soffit).
Page | 22
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Moment
Transversal load
Page | 23
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
2.4.2.1.3.3 Stirrups
Stirrups are rounded steel bars used to tie the top and bottom reinforcement bars
together.
Stirrups has also the following functions:-
To hold the top and bottom reinforcement bars in position at
the time of concreting(casting) and to make the shape required for
beams, shear walls and columns.
In our site we use the diameter ∅8 & ∅10 of bar for the stirrups and
its more casual in other site also.
The stirrups has their own angle (hook) of 1350 or what is called 450 hook.
Why do we provide hook in stirrups
To prevent column from buckling
To resist seismic movement
To prevent concrete from splitting outward
To prevent slippage of steel from the concrete
To keep longitudinal steel bars in position and hold steel tightly
Page | 24
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 25
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Chair bar
Chair bar or as referred to on site as ‘Kebeleto’, is provided in between bottom and top
rebar’s ensuring that spacing is kept when concrete is being poured. Once the setting of bars
in both directions is finished they are tied with wires at joints of random spacing for
stiffening, than concrete is ready to be cast
Page | 26
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 27
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Main bars are placed parallel to the direction of flight to take the tensile stress in the
inclined slab
Distribution bars are placed across the flight perpendicular to main bars.
Negative bars are placed at the whole landing and at beginning and end of the flight
with length equals one third of flight length for each
Step bars are placed in each step to take the shear stress as in the case of stirrups in
beams.
Page | 28
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Cement:
It is one of row material used to produce concrete. It forms a paste which hardens and binds
the aggregate to make hard and durable concrete.
Aggregates:
Since aggregate occupies about three-quarters of the volume of concrete, it contributes
significantly to the structural performance of concrete, especially strength, durability and
volume stability. In general, aggregates in concrete have been grouped according to their
sizes into fine and coarse aggregates
Aggregate is classed into the following two sizes:
Coarse aggregate—gravel or crushed rock 5 mm or larger in size
Fine aggregate—sand less than 5 mm in size
It is common to refer to fine aggregate as sand and coarse aggregate as stone. Traditionally,
aggregates are derived from natural sources in the form of river gravel or crushed rocks and
Page | 29
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
river sand. Aggregates should be free from excess amount of clay, silt, dust and organic
matter.
Water:
The strength and durability of concrete depends on the amount of water mixed with it. Too
much or too little water can adversely affect the strength of concrete.
After concrete cast, water is used to cure it so that the temperature is controlled and concrete
matures slowly.
It is very important to use clean, potable water in quality concrete production. Contaminated
water will produce concrete mortars with lower durability erratic set characteristics and
inconsistent colour.
It is an important ingredient of concrete as it actively participates in the chemical reaction
with cement and all other materials and makes the concrete workable. Since it helps for the
strength of cement paste, the quality & quality of water is required to be looked very
carefully
Admixtures:
Admixtures are added to the batch immediately before use or during mixing. These day
concrete is being used for so many purposes in different condition. In these conditions
ordinary concrete may fail to exhibit the required quality or durability or workability. In most
cases admixture is used to modify the property of the ordinary concrete so as to make it
suitable to any condition.
Page | 30
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Is to maintain desired water content within the concrete for the required time.
We should start curing of concrete as quickly as possible after finishing of
concrete.
Page | 31
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
The formwork should be removed after the concrete attain its first strength. All structure has
their own detaching (removing time) according to the decision made by the site engineer by
considering the weather condition and the type of construction.
Considering shapes, formwork types can be classified as;
Column formwork
Beam formwork
slab formwork
shear wall formwork
2.5.2.1.1 Concrete batching plant process
Pumping cement from cement bulk carrier (kokosh) in to cement silo.
Adding aggregates (sand & gravel) in to the bin by a wheel loader.
Transport aggregate in to storage bin by conveyer belt.
Storage bin have 4 parts of storage on it. It stores 3 types of coarse
aggregate and 1type fine aggregate.
Coarse aggregate types :-
Page | 32
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 33
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Discharge
chute
Page | 34
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
tied, and fastened in its position in the forms. The materials for the concrete have
been prepared, and the mixed concrete has been arrived. We are now ready to
place the concrete in the forms. The concrete should be placed and vibrated before
its setting starts.
Following precautions should be taken while placing the concrete:-
Page | 35
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
The purpose of compaction is to get rid of the air voids that are trapped in loose concrete.
Compaction of concrete is used to:-
Air voids increase concrete's permeability. That in turn reduces its durability. If
the concrete is not dense and impermeable, it will not be watertight. It will be less
able to withstand aggression and its exposed surfaces will weather badly.
Page | 36
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 37
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
The reason behind it is that the plywood formwork provides smooth finish when
compared to normal timber and steel formwork. Hence, finishing cost may reduce
by the use of plywood. Plywood are bonded with strong adhesive to make it
watertight. The plywood boards are available in thicknesses from 7mm to 32mm.
In general, plywood of size 1220 x 2440 and 18mm thick boards are
Disadvantages
Thin plywood sheets cannot sustain the weight of concrete they may
bow out; if properthickness is not provided.
If not properly greased or oiled has capacity of water absorption
making it to be out of useat early stage.
2.6.1.1 Scaffolding
It is any temporary structure used to support the forms for concrete. Scaffolding supports the
forms until the concrete can support it self it is essential that scaffolding be strong enough to
support the weight of three things: the forms, the fresh concrete and any construction
equipment and workers. It also must be capable of maintaining the correct elevation.
Scaffolding may be prepared by a wooden or steel structure. In our site mostly steel
scaffolding used.
Page | 38
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Spacer
Spacers had been put on the bottom and in the interface of four sides of the bar and the panel.
Spacers are materials (either reinforcement bars or wire imbedded concrete) which provide
space for the concrete to cover the reinforcement bars in columns, beams, slabs, foundations,
etc…
Concrete cover is the least distance between the surface of embedded reinforcement bars and
the outer surface of the concrete. The cover to reinforcement is required for the following
reasons:
To protect the steel against corrosion.
To provide sufficient bond or adhesion between steel and concrete.
To ensure sufficient protection of the steel in a fire
Page | 39
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Concrete spacer was used in our site on concrete casting for column, staircase, slab ……
Page | 40
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Plumb bob (thumb):- it’s very important equipment in order to check the alignments of
column and to get the centre point and corner points during placing of a column.
Truck crane: - is a type of machine generally equipped with a hoist rope, wire rope or
chains that can be used both to lift and lower materials and to move them horizontally.
Mainly in
our site it’s used to fill concretes for elevation columns
Surveying equipment’s used in check level of every structure.
Pulley system
This system is used to transport construction materials to the upper floors
Page | 41
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Communication problem with workers in the office and at the site due
to terms used in siteare not used with scientific names.
Weather condition of the site.
Shortage of knowledge in some portion of the work at the site.
Underestimation by workers such as engineers, Foreman.
Page | 42
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 43
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
CHAPTER THREE
3. Overall Benefit I Gained from the Internship
Internship is a duration that is held at site to provide an enhanced understanding of the
outside working environment before we graduate. The main aim of this practice (internship)
is to let us have communication with different workers or employees, to improve the
practical skills beyond what we have learned theoretically in classrooms, in addition letting
us upgrade the theoretical knowledge to improve our leadership skill, team playing skill,
entrepreneur skill and etc.
During our Three months duration with BAMACON Construction PLC with the site engineer
and other we have acquired much knowledge in different tasks as explained below in
different section. This different knowledge got us a good performance in the internship
period and we have gained experience that would help us after the graduation in the
upcoming working era of us.
Page | 44
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
This Three month internship program have given us different improvement and experience in
terms of different skills, the skills that we have gained during the internship program are
listed below:-
I would like to list the practical skills I gained from the internship program as the following:
Page | 45
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
work in good way, I just try to have good communicative skills with people around. As I
tried to know some things that are strange to me on the site, I would ask those nearby to me
and whom I supposed they know. This program is definitely helped me by improving my
communication skill.
Communication is good to;
Handle information;
To convince people;
To improve relationship with others.
Improve productivity
Share ideas, suggestions and complaints
Page | 46
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Responsible
Punctual
Respect others
Effective and mature problem solver
Ability to motivate co- workers
Active listener and problem solver
Self-confidential
3.1.6 Understanding work ethics
Ethical conduct of workers is very important for creating healthy working environment and
increasing productivity. Someone needs to have ethical conduct to be fruitful in working
environment and in his or her social life.
Some of the work ethics include:
Punctuality: - means the characteristic of being able to complete a required task or
fulfil an obligation before or at a previously designated time. In other words,
punctuality means getting to work on time and completing a given task within the
given period.
Office disciplines: - The worker should never disturb the working atmosphere. The
office should remain quiet and undisturbed.
Reliability: - The worker should be qualified for the part he/she is supposed to
be performing . He/she must have appropriate skill and knowledge for the task
assigned .
Page | 47
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Honesty: - Regarding this value each worker regardless of its status should
abstain from bad behaviour such as cheating , bias , corruption etc..
Cooperation: - Each worker should interact and cooperate with each other while
working. That is because it is through such system problems could be easily solved.
Page | 48
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
CHAPTER FOUR
4. CONCLUSION AND RECOMMENDATION
4.1 Conclusion
The internship is a bridge between the theoretical knowledge and the practical or the reality
work at the field of construction or civil engineering work. We all who have taken the
internship program went to companies which were already working either as a consultant or a
contractor. The responsibilities of the hosting company are to teach and shape us in the Three
months duration as real site workers.
Our hosting company was a contractor and they helped us take the internship session in their
company in acquiring different knowledge in different activities performed at the site. This
program played an important role, that field works can be only implemented by people who
have an experience in building construction. We were able to acquire a high level of
confidence to deal with problems that arise in a building construction.
Since we took our internship session in the contractor side We got opportunity to work in
the different positions of the construction work which helped us to gain more knowledge by
seeing what they work in office and in site to realize what responsibilities they had to the
client and to the consultant.
BAMACON Construction PLC is a grade 1 general contractor (GC1) which is working in
different construction projects and operate in the fields of road, bridge, building construction,
waterworks and infrastructure development.
Since we were working with the side of this construction company, we have understood
The overall organization of the company and the work flow
The tasks of the engineers and other employees.
The challenges of the works in the site and their solutions.
Management of resources and the overall site and project activity.
More over working with skilled and experienced engineers and foreman gave us great quality
and increased our level of confidence. Working with the contractor led us acquire more
knowledge than that of the consultation work since it includes the duties on site.
Page | 49
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
The contractor played important role for us to improve our practical knowledge status in the
field and also the made us more familiar with site works by letting us understand ways of
communication, handling different site works, usage of equipment ,manpower controlling
and structure of work flows.
The hugeness of the project, the machineries, equipment, experienced engineers and other
situations has led us to be confidential, well experienced and skilled.
Generally speaking the benefits that we gained during the internship program can be
summarized with the following core points:
Practical skills
Upgrading of theoretical knowledge and able to use it for practical work.
Developing of communication skill.
Developing skill of team work.
Improving personal ethics and knowing work ethics.
Being able to do different tasks.
Knowing the local construction terms.
Summarizing, the internship program laid sound foundation for us to start our future career.
4.2 Recommendations
4.2.1 Recommendation to the hosting company
During my Three months of internship experience period I have seen some positive and
negative sides about the internship hosting company. In this part of my report I will try to
suggest some ideas. I have some recommendation for my hosting company:
The weakness of the company is that, they have no enough safety material especially
for daily workers, they didn’t give any attention for safety but it is very necessary for
any construction company because nothing is better than human’s life.
The project has delay problem due to construction material shortage so the company
have to supply material on time.
Page | 50
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Some of the daily labours didn’t follow the structural order given the site engineers,
and to overcome these defects there should be a high degree of supervision of
workmanship.
4.2.2 Recommendation to the University
The teaching learning method shall be more practical other than theoretical, for
that to make the study.
The supervision and assistant from the department was not sufficient.
Therefore I suggest the department to arrange more frequent contact time
between the university advisors and the intern student.
Giving courses that are appropriate for the site work before the internship class,
like quantity surveying which was a big challenge for all of us
Budget adjustment for internship program since the inflation in our county is at
higher level.
Page | 51
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
References
Company website.
Company’s document, contract document and company profile document.
Final internship document from previous year.
http://www.mekaconcreteplants.com
http://www.dailycivil.com
http://www.scholar.google.com/
http://www.wikipidia.com
http://www.civilread.com
Page | 51
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Appendix
Sponda-side formwork used to retain concrete for beam and slab.
Concrete - ‘armata’
Reinforcement - ‘fero’
Plumbing bob ( Tumbi) -leveling instrument used to check a vertical alignment of
member
Stirrup - ‘stafa’
Slab : - Soleta
Berga: - 12m length bar.
Soffit: - bottom form work of beam.
Ready Mix: concrete that is specifically manufactured for customers'
construction projects, andsupplied to the customer on site as a single product
Flat Slab: reinforced-concrete floor construction not requiring beams and girders
to transmit the floor load to supporting columns.
Page | 52
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Takeoff Sheet
Project :- B+G+9 Building
Location :- Addis Ababa
Client:- St-Tsehay insurance
Contractor :- Bamacon Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
A. SUB STRACTURE
1.Excavation and
Earth work
32.00
1 1.1. Site Clearing
38.00 1,216.00 m²
Total
1.2. Bulk
Excavation
1 31.00 depth =50cm
37.00
0.50 m³
573.50 Total
1.3. Pit
1.3. Pit Excavation T.G L*W*H Squ Unit Excavation
+4.5 +1.5
4 4.30 2 3.50
4.30 3.50
1.20 88.75 m³ F1-c1 1.00 24.50 m³ F3-c3
2 3.90 4 3.50
3.90 3.50
1.20 36.50 m³ 1.00 49.00
F2-c2 m³ F3-c4
2 3.50 2 2.90
3.50 2.90
1.00 24.50 m³ F3-c3 0.80 13.46 m³ F4-c3
2 3.50 2 2.90
3.50 2.90
1.00 24.50 m³ F3-c4 0.80 13.46 m³ F4-c6
2 3.50 2 2.50
3.50 2.50
1.00 24.50 m³ F3-c5 0.60 7.50 m³ F5-c7
2 2.50 2 3.90
Page | 53
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
2.50 3.90
0.60 3.75 m³ F5-c7 1.00 30.42 m³ CF-1
1
10.50
202.51 m³ Total
6.50
1.00 68.25 m³ CF-2
206.58 m³ Total
Total pit excavation
=
409.09
m³
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
2.concrete work 2.concrete
+4.5 work + 1.5
2.1 lean
2.1 lean concrete concrete
A. under
4 3.8 A. under footing pad 2 3 footing pad
3.8 57.76 m² F1-c1 3 18 m² F3-c3
2 3.4 4 3
3.4 23.12 m² F2-c2 3 36 m² F3-c4
2 3 2 2.4
3 18 m² F3-c3 2.4 11.52 m² F4-c3
2 3 2 2.4
3 18 m² F3-c4 2.4 11.52 m² F4-c6
2 3 2 2
3 18 m² F3-c5 2 8 m² F5-c7
2 2 2 3.4
2 8 m² F5-c7 3.4 23.12 m² CF-1
10
142.88 m² Total 1
6 60.00 m² CF-2
168.16 m² Total
Total lean concrete
=
311.04
m²
Page | 54
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
2.2 C-30
2.2 C-30concrete concrete +
+ 4.5 1.5
164.59 m³ Total
Total C-30 concrete
for pad =
323.65
m³
B) for
B) for foundation foundation
column +4.5 column +1.5
4 0.90 2 0.70
0.90 0.70
0.80 2.59 m³ F1-c1 1.00 0.98 m³ F3-c3
2 0.80 4 0.60
0.80 0.60
Page | 55
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
6.45 m³ Total
Total C-30 concret for foundetion column =
12.98
m³
Page | 56
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 57
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 58
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 59
By Olyad chala
FINAL INTERNSHIP REPORT DDUIoT-SCEA
Page | 60
By Olyad chala