Mep Manual
Mep Manual
Mep Manual
2
PREFACE
This tiny effort has been made in the direction to appreciate the
importance of electro-mechanical and plumbing work in the
construction industry.
This book clearly defines the roll and responsibility of each one
involved in the execution of the project.
It is hoped that this small effort will bring a big change in the
professionals’ approach engaged in the construction industry.
Sincerely,
Dr. S.L.Sharma
Date: 10-09-2007
3
Contents
Pages
Preface 3
Abbreviation 106-107
4
REFERENCE STANDARD&
DOCUMENTS
5
3- Source of Documents
The philosophy of the electro mechanical project management is drawn from ISO
9001 (2000) and British standards.
However, every particular project is guided by its own project contract and
supervised by quality manual.
6
PROJECT COORDINATION
7
4- Co-ordination
4.1 The project co-ordination is the main operational and management tool to
Execute the project smoothly and timely.
Co-ordination among all agencies such as client, consultant, main contractor
and other subcontractor are most essential to have proper reporting system
to Over look and supervise all activities in progress at site.
Generally the following chain is maintained:
Client(Management)
Consultant
Main Contractor
8
4.2 Co-ordination between client and consultant
4.2.1 It is the main obligation of the consultant to appraise the progress of the
Project to the client periodically.
4.2.2 Where Specified with in the tender documents or in contract documents,
specific client reporting templates (formats) and coordination procedures will
Be implemented. In other cases the formats published/distributed by
Consultant will be utilized and followed.
4.2.3 Should client need any direct reporting on specific formats the same will be
Distributed to all concern by consultant.
4.2.4 Generally all reporting to the client or his representative will be followed or
routed through consultant. However client as the owner of the project can
direct any agency involved in the project to submit specific reports. All
agencies are requiring submitting the desired report to client under intimation
to consultant if not directed to do so by the client.
9
4.3 Coordination between consultant and main contractor
10
4.4 Co ordination between main contractor and sub contractor
4.4.1 All sub contractors will work under the supervision of main contractor.
4.4.2 All sub contractors are compulsorily registered with local government.
4.4.3 All submittals submitted by sub contractor should be routed through main
contractor.
4.4.4 Main contractor should act as intermediate agency between consultant and
sub contractor.
4.4.5 All the periodic report submitted by sub contractor should be forwarded to
engineer by main contractor.
4.4.6 It is mandatory for main contractor to take the approval of all sub contractors
engaged for project activities.
4.4.7 Main contractor is required to pass on all standard formats of engineer to sub
contractor.
4.4.8 It is the sole authority of engineer to deal directly with any of the sub
contractor wherever required or desired so by engineer.
11
MEP ORGANIZATION
12
Index Page no.
5. 01 Introduction 14-14
13
5.01 - INTRODUCTION
Comply with local Government guide lines with clear defined responsibilities especially in
the area of quality assurance, site management, testing &commissioning and finally handing
over the completed project to the client.
MANAGING DIRECTOR
Director
14
It is desired that the final goal of organization will be reached together with company’s
growth and development of all functions.
The function of general affairs include: Human Resources, Computer systems, Legal affairs,
Public relations etc.
However, targeted structure of Operational organization is outlined separately and not in the
scope of this manual.
15
5.03- (MEP) ORAGONOGRAM
The MEP organization structure, which is a good transitional solution adequate to the current
company’s size, needs and resources.
Consultant
Managing Resident Engineer
HEAD OF MEP
Department
16
5.04 Key personnel’s Job descriptions
5.04.01- Head MEP Division
Job code:
Job holder:
Managing Director /RE
Reports to:
Job description: This is key position for ensuring Proper design with quality &
safety. Development and control of quality program, technologies,
products and system evaluation and highest adherence of all local
and international standards.
Responsibility: SEE IN STAFF RESPONSIBILTIES
Authority: Can hire or fire staff with the approval of MD
Can suspend staff notifying MD
Approves revenue items within budget
Approves capital expenditure against budget
Agrees and approves product changes.
Recruitment and training of MEP staff.
Re location and realignment of MEP staff as per
project requirements.
All Project heads
All senior management
internal All other personnel deem fit.
Communication
Regulatory authorities
external Professional bodies
Customers
Suppliers
Requirements: Graduated in Mechanical / Electrical engineering.
Minimum 15 years experience out of which 10 years
in Middle East. UAE experience preferred.
Leadership & Management abilities
Excellent oral and written English
17
In depth understanding of local government rules and
requirement.
Familiar with computers
A postgraduate qualification would be an advantage
Managing Director’s Review
18
5.04.01 Assist. Resident Engineer
Job holder:
19
Communication Regulatory authorities
external Professional bodies
Customers
Suppliers
20
5.04.03 Sr. Engineers/Engineers
Job holder:
21
Minimum 7 years experience out of which 03 years in
Middle East. UAE experience preferred.
Leadership & Management abilities
Excellent oral and written English
In depth understanding of local government rules and
requirement.
Familiar with computers
A postgraduate qualification would be an advantage.
Head of MEP ’s review
Employee’s Review
22
5.04.04 - MEP Inspectors
MEP Inspectors
Job title:
Job holder:
Job description: This is key position for ensuring Implementation design with
quality. Follow quality program. Highest adherence of all
local regulation.
Responsibility: SEE IN STAFF RESPONCIBILTIES
Authority: Can recommend approval/suspension /rejection of inspection
notifying sr. engineer/engineer.
Recommend product changes.
Training of MEP staff under guidance of MEP Head.
23
Communication
external Regulatory authorities &Professional bodies notifying MEP
head in the project.
24
5.05 Department’s responsibilities and functions
5.5.01 MEP department will work with civil engineering in a close coordination.
5.5.02 it is the main responsibility of the department to approve all drawings/material
related to HVAC, Plumbing and electrical.
5.5.03 the department will carryout all schedule inspections requested by MEP
contractor.
5.5.4 It is the obligation of the department to verify and approve the sub contractor
For MEP work at site.
5.5.5 All services coordination under ground and other floors above ground is to be
checked and approved by department.
5.5.6 MEP department (Electrical) will assist sub contractor in solving DEWA
bottle necks.
5.5.7 MEP department (Mechanical) will assist sub contractor in solving the DM
problems related to water and drainage.
5.5.8 MEP department will also support civil and main contractor to solve civil defense
and fire fighting problems.
5.5.9 MEP department will scrutinize all the CVs of sub contractor and approve them
as per listed specification.
5.5.10 MEP department will participate in all weekly progress meetings.
5.5.11 MEP department will also participate in all other meetings called by client and or
his representative.
5.5.12 MEP department will coordinate with other infrastructure contractor working with
the specified area.
5.5.12 MEP department will submit periodic reports to MEP head at head office.
5.5.13 MEP department will keep all the records of inspection, material submittal
and drawing submittals.
5.5.14 Any other obligations not listed here but falls under the jurisdiction of the MEP
Department.
25
STAFF RESPONSIBILITIES
26
Index Page no.
27
6.1- Head of Department (H.O.D)-MEP
28
6.2- Assistant Resident Engineers (ARE) – MEP
6.2.1 To provide leadership and technical guidance to site MEP department at site.
To handle all incoming and out going correspondence related to MEP.
6.2.2 To review the Design of all MEP services and bring any concern to the
attention of H.O.D.
6.2.3 To ensure that DIAR Consult concept / procedures are strictly followed by all
the MEP staff.
6.2.4 Electro Mechanical (MEP) project management at site as per Dubai
Govt. /International norms
6.2.5 To review and approve the material submittals reviewed & recommended by
Sr. engineer / Engineer.
6.2.6 To review and approve the Drawing submittals reviewed & recommended by
Sr.engineer / Engineer.
6.2.7 Participating in weekly project review meetings for tracking site progress
& de-bottlenecking & implementation of procedures as per norms and
standards.
6.2.8 To ensure that the contractors / subcontractors are registered and obtained
license from local authorities before commencement of the work at site.
6.2.9 To obtain approval of H.O.D on all material submittal. (if they are not
specified)
6.2.10 To coordinate the MEP services with Civil / Architectural works.
6.2.11 To review the program of work submitted by the contractor and approve
comments
6.2.12 To ensure that all testing and commissioning procedure are strictly followed
by concerned all MEP staff.
6.2.13 To review, write and forward the performance appraisals to head of the
department for all the staff working under him.
6.2.13 To prepare periodic reports for the Head of the department related to site
progress and execution.
29
6.3- Senior Engineers (Electrical/Mechanical) (SEE/SEM)
Responsibilities
6.3.1 To check and review all the related material submittals documents and verify
their conformity with the specification and Contract documents and forward to
the MEP head.
6.3.2 To ensure that all the material submittals must be submitted as per standards
listed in specification book. Such as:
a.Submittal to have Main index list
b.Submittal to have Specified material list
c.Submittal to have Specification copy.
d.Submittal to have Catalogue copy
e.Submittal to have Data sheet i.e. to describe about the proposed
Technical characteristics of the material and also to show the catalogue
number of the proposed material.
f. Submittal to have Compliance statement showing the exact comparison
between specified and proposed material submittal and to be properly
stamped and signed by the main Contractor and Supplier.
g.Manufacturer/supplier address to be clearly shown on submittal form.
6.3.3 To advise sample approval of all related material before any installation in
the site for MEP Head.
6.3.4 To check and review all the related shop drawing as per the contract, tender
drawing and all addenda. To ensure that shop drawings are accurate and
detailed and are fully coordinated with all other services.
6.3.5 To note and review all the changes or variations coming in drawings or
BOQ (i.e. Quantity) during execution of the project.
6.3.6 To approve request for inspection for any Electrical/mechanical activity
done at site.
6.3.7 To check the quality of work at site and insure that site execution is as per
project specification and authorities regulations.
6.3.8 To check as per actual installation and forward the “As Built Drawings”
received from contractor to head MEP. To attend weekly site coordination
meetings.
30
6.3.9 To guide and liaise with contractor/sub contractor for obtaining all
approvals related to MEP from authorities.
6.3.10 To make correspondence with the Client, Main Contractor Sub-Contractor
under guidance of head MEP/ project RE.
6.3.11 To provide guidance and supervision to related inspectors for site inspection
work.
6.3.12 To counter sign on all the inspection reports performed at site by inspectors.
6.3.13 To report to immediate superiors all matters of non conformity and
irregularities of executed works and to record such matters consistently and
systematically in proper filing system.
6.3.14 To accept full responsibilities of site supervision of electrical / mechanical
works on project as assigned by management in a professional and
competent manner.
6.3.15 To work in full coordination with all members of staff at site / head office
and subscribe to the over all procedures.
31
6.4- Inspectors (Electrical/ Mechanical) (EI / MI)
Responsibilities
32
INSPECTION METHODOLOGY
(ELECTRICAL)
33
INSPECTION METHODOLOGY-(ELECTRICAL)
34
7.1- (L.V). Main Distribution Boards MDB
M.D.B should be checked & inspected as per approved material submittal and
Listed specification. The below mentioned checks should be done by
electrical inspector and verified by sr. engineer/engineer electrical.
7.1.1 MDB Should be from approved vendor as per approved material submittals IP
grade , color and “form” of the panel to be confirmed as per approval.
7.1.2 Check and verify “Factory Test Certificate” from panel manufacturer.
7.1.3 MDB should be as per approved component and drawings.
7.1.4 Make and rating of the Circuit Breakers, meters (A&V), ELCBs etc. should be as
per approved submittal.
7.1.5 Rating & Quantity of future space / spare feeders should be as per approvals.
7.1.6 Fault rating of the bus bar & circuit breaker should be as per approved drawings
7.1.7 Circuit Breaker settings verified / adjusted should be as per approved drawings
7.1.8 Bus Bar compartment should be fully shrouded and proper warning labels to be
provided
7.1.9 MDB door gaskets, protective covers / shrouds should be fitted
7.1.10 MDB installation should be done properly & sufficient supports provided
7.1.11 Cable glanding, termination, cables supports & tagging should be proper and
satisfactory.
7.1.12 MDB power cables, Cable glands and all components should be easily accessible
7.1.13 Cable tray and trunking in side the panel should be in installed properly with cove
on. Earthing to the panel to be provided.
7.1.14 Earthing and equiv. potential bonding of MDB is done properly & size of earth
cable should be as per drawing
7.1.15 MDB internal & external surfaces should be clean & all unused holes plugged
7.1.16 Insulation (Megering) resistance for MDB should be carried out at site and to be
recorded
7.1.17 Insulation resistance for main & all feeder cables should be carried out and to be
recorded
7.1.18 ATS operation (auto / manual) functional check should be carried out (if
applicable)
7.1.19 Earth Leakage / fault teat should be carried out & should be satisfactory where
ever applicable.
35
7.1.20 KWh installation, type, C.T ratio and locations should be as per local govt.
authority’s approval.
7.1.21 MDB main label with feeder description & Component identification labels should
be provided
7.1.22 Laminated approved load schedules should be provided inside the MDB.
7.1.23 As-Built drawing from panel builder should be provided in drawing pocket in
MDB.
7.2.1 SMDB Supplied From approved vendor should be as per approved material
submittal.
7.2.2 Factory test certificate from panel builder should be verified and values to
be accepted.
7.2.3 SMDB should be as per approved drawings, single line diagram and to be
requirements.
7.2.4 Rating & Quantity of the Circuit Breakers, meter etc. should be as per
approved drawing.
7.2.5 Rating & Quantity of future space / spare feeders should be as per approvals
7.2.6 Fault rating of the bus bar & circuit breaker should be as per approved
drawings.
7.2.7 Circuit Breaker settings verified / adjusted should be as per approved
drawings.
7.2.8 Bus Bar Compartment should be fully shrouded and to be proper warning
label provided.
7.2.9 SMAB door gaskets, protective covers / shrouds should be fitted
7.2.10 SMAD installation to be done properly & sufficient supports should be
provided.
36
7.2.11 Cable glanding, termination, cables supports & tagging should be
satisfactory.
7.2.12 SMDB power cables, Cable glands and all components should be easily
accessible.
7.2.13 Cable tray and trunking should be installed properly, covers and earthing
are to be provided.
7.2.14 Earth bonding of SMDB to be done properly & size of earth cable should
be as per drawing.
7.2.15 SMDB internal & external surfaces should be clean & all unused holes to
be plugged.
7.2.16 Installation resistance for SMDB should be carried out at site and to be
recorded.
7.2.17 Installation resistance for main & all feeder cables should be carried out and
to be recorded.
7.2.18 Functional Test for SMDB should be carried out and to be found
satisfactory.
7.2.19 Earth Leakage / fault teat should be carried out &to be found satisfactory (if
applicable).
7.2.2O Main Label, feeder description & Component identification labels should
be provided.
7.2.21 Laminated approved load schedules should be provided inside the SMDB
7.2.22 As-Built drawing from panel builder should be provided in drawing pocket
in SMDB.
7.2.23 As-Built drawing from panel builder should be provided in drawing pocket
in SMDB.
37
7.3- Final Distribution Board (DB)
D.B should be checked & inspected as per approved material submittal and
listed specification. The below mentioned checks should be done by
electrical inspector and verified by sr. engineer/engineer electrical.
7.3.1 DB Should be from approved vendor as per approved material submittals IP
grade, color and “form” of the panel to be confirmed as per approval.
7.3.2 Check and verify “Factory Test Certificate” from panel manufacturer.
7.3.3 DB should be as per approved component and drawings.
7.3.4 Make and rating of the Circuit Breakers, meters (A&V), ELCBs etc. should be as
per approved submittal.
7.3.5 Rating & Quantity of future space / spare feeders should be as per approvals.
7.3.6 Fault rating of the bus bar & circuit breaker should be as per approved drawings
7.3.7 Circuit Breaker settings verified / adjusted should be as per approved drawings
7.3.8 Bus Bar compartment should be fully shrouded and proper warning labels to be
provided
7.3.9 DB door gaskets, protective covers / shrouds should be fitted
7.3.10 DB installation should be done properly & sufficient supports provided
7.3.11 Cable glanding, termination, cables supports & tagging should be proper and
satisfactory.
7.3.12 DB power cables, Cable glands and all components should be easily accessible
7.3.13 Cable tray and trunking in side the panel should be in installed properly with cove
on. Earthing to the panel to be provided.
7.3.14 Earthing and equiv. potential bonding of DB is done properly & size of earth
cable should be as per drawing.
7.3.15 DB internal & external surfaces should be clean & all unused holes plugged.
7.3.16 Insulation (Megering) resistance for DB should be carried out at site and to be
recorded
7.3.17 Insulation resistance for main & all feeder cables should be carried out and to be
recorded
7.3.18 ATS operation (auto / manual) functional check should be carried out (if
applicable)
7.3.19 Earth Leakage / fault teat should be carried out & should be satisfactory where
ever applicable
7.3.20 DB main label with feeder description & Component identification labels should
be provided
7.3.21 Laminated approved load schedules should be provided inside the DB.
7.3.22 As-Built drawing from panel builder should be provided in drawing pocket in
MDB.
38
7.4- Capacitor Bank
Should be checked & inspected as per specification & material submittal approval by
the inspector & is to be cross checked by Engineer stated as follow.
7.4.1 Panel supplied from approved vendor should be as per approved material
submittal.
7.4.2 Factory Test Certificate from panel builder should be verified and values to
be accepted.
7.4.3 Panel should be as per approved drawings, load schedules and requirement.
7.4.4 Rating of circuit breakers, fuses, capacitor should be as per approved
drawing.
7.4.5 Switching step of capacitor banks should be as per approved drawing.
7.4.6 Fault rating of the bus bar & circuit breaker should be as per approved
drawing.
39
7.4.19 Functional test for the capacitor panel carried out & should be found
satisfactory
7.4.2O Panel main tag and components identification should be by
permanent labels
7.4.21 As-built drawing from panel builder should be provided in a drawing
pocket in panel.
7.5.1 Panel supplied should be from approved vendor and as per approved
material submittal.
7.5.2 Factory test certificate should be from panel builder to be verified and
result to be accepted
7.5.3 Control panel dimensions & arrangements should be as per the approved
drawings
7.5.4 Ratings and quantity of MCB / MCCB / ELCB should be as per approved
drawings.
7.5.5 Panel power and control wiring should be as per standard drawings and
requirements.
7.5.6 Rating of contactors / over load relays should be as per approved
drawings.
7.5.7 Permanent identification of all components inside the control panel should
be marked.
7.5.8 Wire sizes, color coding, terminations should be properly executed inside
the panel.
7.5.9 Panel gaskets, bus bar shrouding, protective cover & warning label should
be provided.
7.5.1O Installation of the panel should be done properly.
7.5.11 Cable size type, glanding, terminations, support & tagging should be
satisfactory.
7.5.12 Panel cables, glands and all components should be accessible easily.
7.5.13 Control wiring type & size, dressing, terminations and marking should be
done properly.
7.5.14 Panel internal & external surfaces should be clean & all unused holes
should be plugged.
40
7.5.15 Earthing of the equipment and panel should be done satisfactorily.
7.5.16 Insulation resistance for power and control cables should be carried out
and to be recorded.
7.5.17 Test / commissioning of system in coordination with supplier should be
done & to be certified.
7.5.18 All functional checks and testing for circuits should be carried out & to be
found satisfactory.
7.5.19 Panel builder “As-built drawing” should provided inside the panel in
drawing pocket
7.6- Isolators
Equipment control panel should be checked & inspected as per approved material
Submittal and listed specification. The below mentioned checks should be done by
electrical inspector and verified by sr. engineer /engineer electrical.
41
7.7- Electrical Manholes (EMH)
Should be checked by inspector as per shop drawing. Location, specification & size are
to be checked. A co-ordination between electrical and civil is to be done as per following
steps.
7.7.1 Manhole construction should be as per specification.
7.7.2 Manhole size and location should be as per approved drawing and
requirement
7.7.3 Manhole inner finish should be smooth and coated with water proofing
material
7.7.4 Ducts should be as per approved vendor and material submittal
7.7.5 Duct location, arrangement should be in the manholes are to be satisfactory.
7.7.6 Duct size should be such that it remains with 60% empty space after
installing the cable/wire in it.
7.7.7 Spare ducts with pull wires should be installed for future use.
7.7.8 Duct ends should not be damaged and to be provided with end bell.
7.7.9 Ducts should be utilized evenly and spare space should be available in each
ducts.
7.7.1O Cable installations and neatness inside the manholes should be satisfactory.
7.7.11 Sufficient cable loops should be provided in side the Manhole (where
applicable).
7.7.12 All cable should be in the Manholes are to be identified by aluminum /
stainless steel tags.
7.7.13 All ducts ends should be sealed with gasoline resistance compound.
7.7.14 Cover size should be same as manhole size & is water tight.
7.7.15 Cover should be oil-gasoline resistance gasket, greased, painted and to be
tagged.
7.7.16 Cover should fit to the frame properly and no rattle cover after installation.
7.7.17 Manhole to have Arabic and English tagging, clarifying the manhole is for
Electrical.
42
7.8.4 Ducts should be as per approved material submittal.
7.8.11 Signal / Data cables inside Manhole should be installed in flexible conduits.
7.8.12 Sufficient cable loops should be provided in side the Manhole (where
applicable).
7.8.13 All cable in the Manholes should be identified by aluminum / stainless steel
tags.
7.8.14 All ducts ends should be sealed with gasoline resistance compound.
7.8.15 Cover size should be same as manhole size & is water tight.
7.8.16 Cover should be oil-gasoline resistance gasket, greased, painted and to be
tagged.
7.8.17 Cover fit to the frame should be properly and should not rattle cover after
installation.0.
7.9- Light Fittings (indoor fitting, Wall light & Emergency Lights)
Installation is to be checked & inspected as per specification, approved drawings &
Approved submittal by the inspector. Engineer has to ensured that the following
procedure is strictly followed.
43
7.9.7 Fitting and Ceiling rose / light point should be easily accessible and to be
replaceable.
7.9.8 Control Transformer (if any) should be install properly and to be easily
accessible.
7.9.9 wiring should be as per drawing (Plug in Ceiling rose, heat resistance cable,
etc).
7.9.1O Earth connection to the fittings should be done properly.
7.9.11 Conduit sizes are adequate & should be as per the specification.
7.9.12 Conduit installation to the ceiling roses / light points should be satisfactory.
7.9.13 Conduits above false ceiling should be clamped adequately (others
concealed).
7.9.14 Switch / Automatic controls, circuit wiring and wire sizes should be as per
the drawing.
7.9.15 Light fitting surface, trims and diffusers should be clean. They are to be
free from dust and stains.
7.9.16 Light fitting should be complete in all respects (annular glass/
emergency kit etc.).
7.9.17 Light fitting and circuit wiring should be tested for functionality.
7.9.18 Emergency light / kit should be tested for functionality.
44
7.10- Light Switches & Power Switches
7.10.1 Switches should be as per specification and approved make and should be
strictly as per approved material submittal.
7.10.2 Switch rating, type, poles rocker design and gang should be as per the
drawing & approved specification.
7.10.3 Location & mounting height of switch should be as per local authority rules
and regulation as well as per approved drawings and IP rating should be as
applicable.
7.10.4 Wiring and wire type, size, color coding etc. should be as per drawing
and specification.
7.10.5 Installation and finishing around the switch should be aesthetically
satisfactory
7.10.6 Phase barrier and warning labels should be provided (If applicable).
7.10.7 Power switches should be with light indicator.
7.10.8 Brushed / stainless steel front plate accessory should be provided (where
specified).
7.10.9 Power switches should be with approved flex outlet / connection unit to be
as per drawing.
7.10.1O Location, Installation & finishing around flex outlet / connect unit should
be satisfactory.
7.10.11 Functional test should be carried out and should be satisfactory.
45
7.11- Switched Sockets
46
7.12- Generator (As stand by power source)
Installation is to be checked & inspected as per IEE rules, approved drawings &
Engineer has to ensure that the following procedure is strictly followed.
7.12.1 Generator supplied should be from approved vendor /make and capacity is
as per approved material submittal.
7.12.2 Factory test certificate from manufacturer should be verified and values to
be accepted
7.12.3 Generator set should be as per approved, specification and capacity.
7.12.6 Linear vibration isolator & anti vibration pad should be provided and
leveling of the machine should be checked by calibrated level indicator and
expert engineer only.
7.12.7 Silencer and muffler should be provided.
7.12.8 Flame/ spark arrestor and rain cap at end of exhaust pipe should be
provided.
7.12.9 Type, rating of batteries and battery charger & controls should be
verified. 7.12.1O Fuel level gauge, Fuel low level alarm and shut down should be
verified.
7.12.11 Double earthing of Engine-generator frame and single earthing for fuel tank
should be done satisfactorily. Earthing should be with flat copper plate
/copper wire and should be as per IEE rules.
7.12.12 Generator neutral earthing should be done and tested. Earthing (Resistance)
value to be recorded periodically and during commissioning. The earthing
value should be less then 01 OHM when measure between two earthing
points separated six meters from each other.
Body earthing point and neutral earthing should not be mixed together.
7.12.13 Generator panel metering, control & alarms should be as per the
specification and to be verified. A mechanical and electrical isolation
should be provided as safety between DEWA power and generator.
7.12.14 Power cable glanding, termination, cable support & tagging should be
provided.
7.12.15 Cable tray & trunking should be installed properly; covers and earthing
should be provided.
47
7.12.16 Installation resistance for alternator (with - outgoing cable disconnected),
and out going cables (in open end status) should be carried out and to be
recorded.
7.12.17 Startup and commissioning should be carried out by authorized person from
dealer/supplier and all parameters are to be recorded such as frequency,
voltage, RPM, engine oil pressure and fuel governor function.
7.13.7 Transformer & RMU body earthing should be satisfactory and as per
authority / IEE regulation.
7.13.8 Transformer neutral earthing should be satisfactory and as per authority
regulation. Neutral and body earthing should not be mixed. The earthing
resistance value when measured should be less 01 OHM.
48
7.14- Equipment Earth pits / Neutral Earth pits (EP)
7.15.1 Fire Alarm system supplied should be as per approved make and as per material
submittal.
7.15.2 Factory QC test certificate from supplier should be verified.
7.15.3 Fire Alarm panel zone, alarm and indications should be as drawing /
specification.
49
7.15.4 Mounting arrangements and installation of fire alarm panel should be
satisfactory.
7.15.5 Cable glanding, terminations, & tagging in the fire alarm panel should be
satisfactory.
7.15.6 Fire alarm panel internal and external surface should be clean.
7.15.7 Cable for out door (XLPE armored) / in door (FP200) and correct size should be
used.
7.15.8 Fire sensor terminal box / Cover (From approved manufacture) should be in
white color.
7.15.9 Junction box location and ducts location should be as per drawing.
7.15.1O Cable glanding, terminations & tagging inside junction box should be
satisfactory.
7.15.11 Fire alarm detectors, Break glass, and bell their numbers and location should be
as per approved drawing / specifications.
7.15.12 Location of fire alarm devices should be as per drawing and requirement.
7.15.13 Bell and Break glass installed out door should be W/P type (where
applicable).
7.15.14 Installation and wiring of fire alarm devices should be as per drawing /
satisfactory.
7.15.15 Wires for devices installed should be in conduit and concealed (except above
false ceiling).
7.15.16 Installation resistance for cables should be carried out and to be recorded.
7.15.17 Test / Commissioning of system in co-ordination with supplier should be done
& to be certified. The system should be connected through telephone line to
local fire station where necessary and mandatory as per local rules.
7.15.18 Functional test should be carried out, should be recorded and to be found
satisfactory
7.15.19 Engraved zone chart should be provided adjacent to fire alarm panel.
Emergency telephone numbers of fire station should be written with bold letters
on or near to fire alarm system/panel.
50
7.16- Voice Data / Structured Cabling System
The responsible Engineer must ensure that the following procedure is strictly
followed and checked
51
7.17- Intruder Alarm System
The responsible Engineer must ensure that the following procedure is strictly
followed and checked
7.17.1 System should be supplied from approved vender and should be as per
approved material submittal.
7.17.2 Panel, keypad, sensor, LIM & motion detector location should be as per
drawings.
7.17.3 Panel and LIM above false ceiling should be easily accessible / replaceable.
7.17.4 Ceiling mounted glass break sensors should cover the entire glass area.
7.17.5 Cabling, terminations & tagging of intruder elements should be satisfactory.
7.17.6 Cable installed should be in conduits and concealed (except above false
ceiling).
7.17.7 Intruder alarm buzzer location should be as per drawing & outdoor use (If
applicable).
7.17.8 Intruder alarm programmed should be as per user requirement.
7.17.9 Test / Commissioning of system in co-ordination with supplier should be
done & to be certified and recorded.
7.17.10 Functional test should be carried out and recorded and to be found
mandatory satisfactory.
7.17.1 Engraved zone chart for intruder system should provide adjacent to key
pad.
7.18.1 System should be supplied from approved vendor & should be as per
approved material submittal
7.18.2 Cameras, monitors, switching & recording, modem locations should be as
per drawings.
7.18.3 Poles specification & installation should be as per approved drawings / user
requirement.
7.18.4 Cameras should be PTZ type and monitor is 17” size minimum (color
monitor).
7.18.5 Camera installation should be per approved drawing and to be easily
accessible.
52
7.18.6 Ceiling mounted and pole mounted cameras should installed properly.
7.18.7 System cable installation, termination & tagging should be satisfactory.
7.18.8 Power cable installation, termination and tagging for cameras should be
satisfactory.
7.19.01 All wiring and tubing should be properly supported and run in a neat
and workmanship manner.
7.19.02 All wiring and tubing exposed and in equipment rooms should run parallel to or
at right angles to the building structure.
7.19.03 All piping and wiring with in enclosures should be neatly bundled and to be
enclosed to prevent obstruction to devices and terminals.
7.19.03 Soft copy of Master computer programs and data files is to be preserved.
(Including all control programs, initial approved parameters, settings, English
descriptors, and color graphics complete with dynamic dispersed data)
7.19.04 Diskette should be copied and preserved and to be used/reloaded in cash of
system crash and memory failure.
7.19.05 Should be completely checked for calibration test of all connected hardware
and software to be insure that the system performs in accordance with the
approved specification and sequences of operation submitted.
53
7.19.06 All instruments, switches, sensors, transmitters etc. should be suitably wired
and mounted. They are to be protect them from vibration, moisture, mechanical
damages and temperature variations.
7.19.07 All equipment and panels should be identified, with permanently mounted tags.
7.19.08 Auxiliary pilot duty relays on all starters is require for control function.
7.19.09 All wiring should be as recommended by system supplier and manufacturer.
All communication cables/wire should be of low impedance type and should be
screened type.
7.20.10 All blower motors for AHUs connected to BMS system should be speed
controlled with frequency control device.
7.21.11 if system is monitored and controlled type then it should be connected to PC as
specified and directed by user.
7.19.12 Functional test should be carried out and to be found satisfactory.
7.20.1 System supplied should be from approved vendor and make and as per
approved material submittal.
7.20.2 Speakers for public address and music system location should be as per
approved drawing.
7.20.3 Public address system cabinet and control installation should be as per
approved drawing / requirement.
7.20.4 Radio Channel, VCD Channel, Tape channel, provided should be as per
approved drawing / requirement.
7.20.5 Zoning of each area to be required by the detail design as indicated in the
single line diagram.
7.20.6 PA system interlinked with the fire alarm system and provision for automatic
broad cost of emergency evacuation message should be satisfactory and
requirement.
54
7.20.7 Sound pressure level (SPL) and distribution for the various area should be
satisfactory.
7.20.8 Paging microphone mounted on a table desk with illuminated push buttons
for selective paging of different zone should be satisfactory.
7.20.9 Test / Commissioning of system in co-ordination with supplier should be
done and to be certified
7.20.1O Functional test to be carried out, should be recorded and to be
found satisfactory.
55
7.21.8 Splitters and tap-off boxes used with in system for distributing the signal to
the outlet sockets have a minimum frequency range of 0.15 MHZ up to
2050 MHZ should be as per requirement and to be satisfactory.
7.21.9 Test / Commissioning of system in co-ordination with supplier should be
done satisfactorily and to be certified.
7.21.1O Functional test should be carried out , to be recorded and should
found satisfactory
56
INSPECTION METHODOLOGY
(MECHANICAL)
57
8- INSPECTION METHODOLOGY-(MECHANICAL)
58
8.1- Piping Installation
8.1.1 Where possible, store pipe and tube inside and protected from weather
8.1.2 All piping under buildings and roads shall be encased in concrete with 150 mm
cover on all sides
8.1.3 Provide thrust blocks for buried water mains, at every change in direction of
the pipe
8.1.4 Provide expansion joints for all piping at building expansion joints
8.1.5 All horizontal drainage piping for sizes Ø100mm and above shall be installed
with 1 % minimum slope unless otherwise indicated and 2% for sizes less
than Ø100mm
8.1.6 All pipe work shall be tested hydraulically to a pressure equal to twice the
working pressure. If the working pressure is greater than 600 kPa the test
pressure may be one and a half times the working pressure
8.1.7 Install air vents at all high points where air may collect and not be carried by
The system
8.1.8 Arrange and install piping to obtain maximum head room, avoiding structural
interference
8.1.9 Install piping parallel to building walls
8.1.10 Pipes transporting hot fluids shall be installed at least 6" (150 mm) away from
pipes transporting cold fluids
8.1.11 Electrical conduits shall not touch or be supported on pipe
8.1.12 Protect the open ends by using temporary plugs or caps.
8.1.13 All reductions in pipe size shall be made by using reducing fittings
8.1.14 Provide flanged or union connections for ready disconnection of piping at
equipment
8.1.15 Provide drip pans below all water, or drain piping, if any, located in
electrical rooms and transformer rooms
8.1.16 All piping work in finished areas shall be concealed in ceiling spaces and
shafts or chased into walls.
8.1.17 Cover all temporary openings n ducts and pipes with polyethylene sheets or
caps until final connection is made.
59
8.2- Sleeves and Escutcheon
8.2.1 Escutcheons shall be provided at all penetrations of piping into finished areas.
8.2.2 Pipes, ducts and conduits shall have sleeves where they pass through walls,
floors, ceilings and partitions, with minimum 12 mm clearance
8.3.1 All parts of the installation requiring periodic maintenance shall be accessible
and provided with access panel
8.4- Protection
8.4.1 Fixtures and equipment shall be properly protected from damage during
the construction period
8.4.2 All equipment shall be thoroughly cleaned before start-up and again before
handover.
8.5- Identification
8.5.1 All piping and ductwork shall be marked in English to show the service and
direction of flow.
8.5.2 Marking shall be placed at 10 m intervals on all exposed piping and ductwork
and at each access panel or door.
8.5.3 All the equipments shall have a manufacturer’s name plate which shall show
full details as manufacturer's name, unit and unit motors serial numbers,
model numbers, date of manufacture and BS or other number.
8.5.4 All the equipments should be identified by name.
8.5.5 The schedules and schematic diagrams of all the systems shall be framed and
glazed and hung in the relevant plant rooms.
60
8.6- Vibration Control
8.7.1 All the insulations stored at site should be protected from dirt and moisture by
Adopting proper storing procedure.
8.7.2 Fungicidal protective coatings shall be applied over external surfaces of
chilled water pipes and interior and exterior surfaces of ductwork.
8.7.3 All the pipe and ductwork exposed externally to the building, installed on roof
is to be insulated and clad with aluminum.
8.7.4 Diesel engine exhaust pipe and muffler shall be insulated.
8.8- Valves
8.8.1 Provide valves at inlet and outlet of equipment to isolate from the system for
ease of maintenance.
8.8.2 Do not support weight of piping system on valve ends.
8.8.3 Install all valves with the stem in the upright position keeping aero marking
towards direction of liquid flow.
8.8.4 Prior to flushing of piping systems, place all valves in the full-open position.
8.8.5 Provide drain valves at low points of piping systems.
8.8.6 Install shut-off (NRV) valves at all equipment and at each branch take-off
from mains.
8.8.7 All equipment inlet piping should be connected through “V” mess filter
installation.
61
8.9- Drainage Specialties
8.9.1 All roof and floor drains shall be installed with water proof membrane
extended up to and within the drain and flashed to prevent any water
penetration through the drain.
8.9.2 Make sure that only approved drains as per material submittal is only used.
8.9.3 Co- ordinate with civil engineer for roof floor sloop. The sloop should lead to
drain point from all direction.
8.9.4 Floor drains should be located at the center of the floor tiles.
8.9.5 Position roof drains and floor drains for easy access and maintenance.
8.9.6 Co- ordinate with civil and make sure that sloop of the floor is such that it
gives easy flow of water to drain. Grates of drains are to flush with finish floor
level.
8.9.7 Clean outs shall be installed at change of direction of drainage pipes.
8.10- Fire Fighting System
8.10.1 Run all piping as straight as possible There should be minimum possible
bend to avoid dropping of water pressure/head.
8.10.2 Where piping is embedded in masonry or concrete, provide protective
sleeve Covering.
8.10.3 System drain point to be provided at the lowest level of piping.8.10.4 Ensure
that all the fire protection piping system shall be tested hydrostatically
8.10.5 Motorized /manual (as applicable) fire dampers should be installed in
all ductwork crossing fire walls.
8.10.6 Fire dampers will be included in return and extract ductwork at each fire
zone crossing.
8.10.7 While approving the sprinkler system shop drawings, ensure that it is
well Co-ordinate with reflected ceiling plan.
8.10.8 All fire hydrant piping should be painted with florescent red paint.
8.10.9 All fire hydrant piping should be aero marked for the flow of water.
8.10.10 No valves are allowed to be installed in the piping.
8.10.11 Insure for battery’s make capacity and battery recharger in the system.
8.10.12 Functional test of the jet and spray at the end of hose to be done and ensure no
leakage.
8.10.13 Hose real box is to be marked with “FIRE HOSE REAL”. The hose real box
should not be locked.
8.10.14 Water level indicator should be installed in fire tank.
8.10.15 System should be commissioned by authorized person from supplier before
presenting the system to civil defense and to be recorded.
62
8.11- Fire Pumps
8.11.2 Examine areas, equipment foundations, and conditions with installer present
for compliance with requirements for installation and other conditions
affecting pump performance
8.11.3 Check the alignment of pump and driver shafts after complete unit has been
leveled on foundation.
8.11.4 All systems shall be field tested and run on load, with all automatic controls in
operation and all circuits balanced to produce design conditions.
8.11.5 Contractor shall arrange the system manufacturer or factory trained
representative to conduct on-site training for Client’s personnel.
8.11.6 Maintenance manual and operational manual to submitted by supplier.
8.11.7 Check for battery make, capacity and in built charger in the control panel.
8.11.8 Testing and commission procedure to be recorded.
63
8.13- Chilled water pumps
8.13.1 While approving pumps, full hydraulic calculations and head of the pump to
be verified in accordance with approved shop drawings.
8.13.2 Examine areas, equipment foundations, and conditions with installer present
for compliance with requirements for installation and other conditions
affecting pump performance.
8.13.3 Check the alignment of pump and driver shafts after complete unit has
been leveled on foundation.
8.13.4 All systems shall be field tested and run on load, with all automatic controls in
8.14.1 Provide automatic air eliminators at all high points on piping mains for
chilled water system
8.14.2 Arrange all piping to prevent interference with other services and to achieve
a neat satisfactory workmanship installation.
8.14.3 Provide adequate allowance for expansion and contraction of piping
by providing expansion joints.
8.14.4 Install drain valves at lowest points for draining the system . The drainage
8.14.5 point to be located at easy to operate location.
8.14.5 Arrange piping to permit ease of equipment removal.
8.14.6 Install all valves in equipment rooms in accessible locations from the floor.
8.14.7 All valves should be of raised flange end type. Use Teflon gasket only for
flange joints.
8.14.8 Valve should be checked for its proper installation as per aero pointing
towards flow.
8.14.9 Mostly ball valve with working parts made of SS or Butter fly valve is to
used in the chilled water piping system.
64
8.14.10 All valves are to be insulated as per specification.
8.14.11 All chilled water pipes should be of ASTM grade seam less class “C”.
8.14.12 Where required used long bend only. Avoid installing half bend.
8.14.13 All welding are to be done after making “V” at the pipe end.
8.14.14 After installation do the pressure testing of the piping before insulation.
Pressure should be double then working pressure for 10-15 holding at
pressure gauge.
8.14.15 Apply zinc oxide paint followed by insulation as per specification and
thickness. Make sure that there are no air pockets in the insulation.
8.14.16 Apply aluminum cladding after insulation. Mark aero at intermediate places
for flow of the liquid in side the pipes.
8.14.17 Before commissioning the system clean the piping with cleaning procedure.
8.15- Chillers
8.15.1 Connect inlet and outlet water piping to the chillers with flange joints.
8.15.2 Provide gate valves in piping upstream and downstream of the evaporator
water boxes for isolating shells for maintenance.
8.15.3 Provide globe valve/balancing valve in out let line for pressure balancing
and trim system.
8.15.4 Provide vapour proof flow switches in the chilled water piping properly
interlocked to ensure that units can operate only when the flow is
established.
8.15.5 Provide wells and taps for thermometers sensors and pressure gauges in
chilled piping adjacent to inlet and outlet connections of evaporators.
8.15.6 Provide drain valves to each water box. Provide vent cocks to each water
box.
8.15.7 Provide valves, pressure gauges, temperature gauges and all accessories as
shown in the details on the drawings.
8.15.8 Provide certified wiring schematics to the electrical division for chillers,
associated equipment and controls.
8.15.9 Provide necessary wiring for control items, such as flow switches,
temperature sensors etc., as recommended by the manufacturer.
65
8.15.10 Provide necessary power wiring from starter to chillers control panel,
control power transformer as required, purge motor, oil pump motor, oil
heater, motor protection system, etc. as recommended by the chillers
supplier
8.15.11 The manufacturer shall furnish a factory trained service engineer to
supervise installation, field testing, and initial start-up of each chillers.
8.15.12 The manufacturer shall also allow for a one-week training program of
client’s personnel to provide thorough understanding of supplied equipment,
and full awareness of the daily checks and preventive maintenance
procedures.
8.15.13 Submit maintenance and operational manual.
8.16.1 Check material as per approved material submittal and install as shown on
the drawings and according to AHU manufacturer's installation instructions.
8.16.2 Install units at appropriately made foundation above floor to insure proper
condensate trap depth and condensate drainage piping.
8.16.3 Check for proper installation of filters and their specification. Check for filter
integrity by using proper testing method.
8.16.4 Install air handling unit to provide for adequate service access. Co-ordinate
location to ensure air handling unit does not infringe upon access or service
clearances of other equipment.
8.16.5 Lubricate fan bearings. Verify fan isolators have proper deflection. Check
the cleanliness of equipment. Check for blower leveling. Check for belt
tension. There should be 5% slip in the belt.
8.16.6 Upon completion of installation of air handling units, start-up and operate
equipment to demonstrate capability and compliance with requirements.
Field correct malfunctioning components then re-test to demonstrate
compliance.
8.16.7 Furnish one spare set of fan drive belts per fan for each AHU.
66
8.17- Fan Coil Units
8.17.1 Install and level the fan coil properly. Location of the fan coil should be as
per approved drawing.
8.17.2 At the time of “testing and commissioning” all the “throw away” filters shall
be replaced by permanent washable filters for each fan coil unit.
8.17.3 Ensure that units are installed in such a way that all condensate from the
drain pan flows freely
8.17.4 The actual location of thermostats should be decided at site coordinating
with Arch. finishing details however the general location of the thermostat
should be close to return duct in cash of ductable unit or it should be on the
farthest corner in cash of unit installed in the room.
8.17.5 All FCU with duct should be installed with flex joints to avoid vibration
isolation.
8.17. 6 Check for proper electrical wiring and speed controls wirings.
8.18.7 While commissioning check for current drawn and CFM of the machine.
8.18- Ductwork
8.18.1 Insure ducts are manufactured with proper material and thickness as per
approved material submittal.
8.18.2 Insure ducts are manufactured and installed as per approved drawings. The
routing of duct is proper and as per approved drawings.
8.18.3 Insure all elbow has inside radius equal to the depth of the main duct.
8.18.4 Provide access ports at convenient locations in all main ducts and main branch
Takeoffs with airtight covers and extension sleeves through insulation to allow
Air meter readings
8.18.5 Paint visible internal surface behind each grille or register flat black.
8.18.6 Provide temporary capping of ductwork to prevent entry of foreign
material during construction.
8.17.6 Clean duct systems with high power vacuum machines.
8.17.7 Carry out light test of each branch of the duct to insure no leakage in the
system. All joints should be leak proof.
8.17.8 Any leak detected to be blinded with silicon pest.
67
8.19- Air Outlets
8.20.1 Access doors shall be provided for maintenance and renewal of filter
elements and related items.
8.20.2 Where air handling equipment is to be used for temporary heating or
ventilation of a facility, do not operate the equipment until specified filter
media has been installed
8.20.3 Where air handling apparatus is used during the construction period, install
new filter media prior to start of air balancing.
8.20.4 All filters to be checked for integrity and proper fitting.
8.20.5 A proper cleaning procedure is to be place for cleaning of all washable
filters.
8.20.6 Air pressure or water pressure is only to be applied /used during the filter
cleaning from the opposite side of the flow of air in the installation.
68
8.21- Coordination / Roof Works
8.21.1 Ensure that Contractor has obtained approval for roof coordination drawing
for MEP services, prior to the commencement of work.
8.21.2 While approving the AC units and other equipments in the roof area, its
height should be checked against the parapet height and ensure that none
of the units and equipments are visible from outside.
8.21.3 While approving the shop drawings for roof mechanical services like
chilled water piping, AC and Ventilation ducting, water tanks, water
supply piping, LPG tank and its piping, etc., ensure that none of the
services are visible from outside.
8.21.4 While approving the roof MEP services coordination layout the
following details should be checked.
Drawing scale should be bigger enough to review all the details
All the details shown in the drawing should be of the same scale.
Ensure that all the details shown in the approved individual services
shop drawings are included in the coordination layout.
Mechanical equipments, chilled water piping, AC and ventilation
ducting, water supply piping, etc installation location and routing
should be well studied and ensure that it occupies minimum possible
roof area and are not making hindrance to the roof access.
Wherever the services are crossing one over another, it’s cross sectional
details should be studied Number of directional changes of chilled water
piping and ducting to be kept as minimum as possible.
8.21.4 The drawing should be finally checked and signed by Project Manager/
Architect with ‘No Objection’ status from Civil/Architectural works for
the approved details in the drawing While approving AC and Ventilation
roof shop drawings, Air discharge from the exhaust fans and AC
equipments should be checked and ensure that:
Hot air discharge from the equipments is not making any closed loop
circuit with air suction of other nearby equipments Air discharge is not
directed towards the parapet wall or minimum required distance is
maintained between the parapet wall and air stream. Mechanical services
shaft (OTS) size to be checked against the number of services entry like
AC &Ventilation ducting, chilled water piping, drainage and storm water
piping, water supply piping, etc. Ensure that all the referred services can
be accommodated with required clearances.
Ensure that AC drain from the roof equipments are terminated to the
nearest Ground floor gully traps via separate piping. Do not discharging to
the roof rainwater outlet with free discharge in ground
floor. If the AC ducting and chilled water piping insulation and cladding
are completed during the execution of project, ensure that all of them are
well protected against any damages from the civil work or other
mechanical damages.
69
8.21.5 Vent pipes, exhaust hoods or other mechanical equipment mounted on
roof, or housing for such equipment, shall not be closer to the edge of
roof than a distance equal to the height of the pipe, hood or equipment
8.21.6 Ensure that all the equipments can be installed in the available space of
roof or equipments room and that there is adequate access to all
equipments for easy maintenance.
8.21.7 The coordination drawings must be comprehensive showing all details,
dimensions, equipment, supports for all services and sections through
critical areas.
8.21.8 The contractor shall employ an approved Acoustic Consultant to ensure
and implement appropriate noise and vibration control systems and
elements (If Applicable).
70
8.23 - Testing & Commissioning
TESTING
8.23.2 The Contractor shall include for the cost of all tests, necessary
instruments, plant, supervision and labour both at works and on site. The
accuracy of the test instruments shall be demonstrated where so directed
by the engineer.
8.23.3 The site test shall be of at least six hours duration. On large installation
the site test may last several days and shall be long enough to allow the
taking of all the measurements required in subsequent clauses of this
section and to demonstrate the performance of the installation. Any
defects in workmanship, materials and performance, maladjustments or
other irregularities which become apparent during the tests shall be
rectified by the contractor at his expense and the tests shall be repeated at
the contractor's expense to the satisfaction of the engineer.
8.23.4 The Contractor's representative present at the site tests shall be fully
conversant with the operation of the thermostatic controls, the control
panel and the refrigeration system. In addition representatives of the
manufacturer/supplier of the equipment shall be present.
8.23.5 Test pressure for water systems shall be 1 1/2 times working pressure.
repair any leaks or defects and repeat the tests to the satisfaction of the
engineer .
8.23.6 Test for leakage in all ductwork between air handling units and outlets.
Seal ducts at all equipment connections and pressurize with a small
blower. Leakage shall not exceed 5% of total designed air volume of the
system at the maximum design working pressure. In addition seal any
leaks causing noise. Test system as a whole or in parts provided all
ductwork is accessible for inspection at the time of test. Provide blower,
and all test equipment for inspection to the engineer.
71
Commissioning
72
recorded by the Contractor (or his Specialist) on the Commissioning
Certificate forming part of the contract documents and shall be endorsed
by the engineer. The items on the Certificate shall be read in conjunction
with the appropriate clauses of the contract and any supplementary
specification and the design requirements of the drawings and the certified
results and statement pertaining to the commissioning procedure shall be
interpreted accordingly. The Commissioning Specialist is required to
insert the certificate of temperatures and other data indicating the thermal
performance of central and sub-plants. The information shall be recorded
at the time of commissioning.
73
8.23.14 Training for “End User (Client) Personnel”
Contractor’s specialist engineers shall train the Client’s maintenance
personnel to adjust, operate and maintain different mechanical equipment
and systems as follows:
a) Train the Client’s maintenance personnel on procedures and
schedules for starting up and shutting down the system. Minor
trouble shooting, routine servicing and maintaining different
mechanical equipment.
b) Review data in maintenance manuals.
c) Schedule training with the advance notice.
74
STANDARD OF SUBMITTALS
75
9- STANDARD OF SUBMITTALS
76
9.1- Shop Drawing Submittals
9.1.1 Shop Drawing Should be prepared on A3 Size with proper scale & Proper No &
Revision (If any).
9.1.2 Shop drawing Should have proper logo showing detail description for client,
consultant, main contractor, sub-Contractor.
9.1.3 Shop drawing Should be fully coordinated with all services before submitting
drawing for approval.
9.1.4 Shop drawing shall be signed & stamped by the contractor to indicate that has
properly checked the drawings for conformance with all requirements of the
drawing and specification.
9.1.5 Shop drawing should indicate clearly all services and materials / requirements
actually being supplied & installed at site.
9.1.6 Shop drawings should indicate details of construction & installation, accurate
dimensions, capacity for all materials / requirements.
9.1.7 Shop drawing should indicate sufficient sectional details required for the approval
by the consultant
9.1.8 Shop drawing should have complete details of locations, sleeves, Opening for all
passage through structure (trenches & ducts), & other such builder's work for all
services
9.1.9 With in one month from the date of awarding of the contract the contractor should
submit to the Engineer for his approval, the detailed schedule of proposed shop
drawing in a format acceptable to him.
9.1.10 The drawing will be reviewed by the concerned Engineer, forwarded to MEP Head
for rechecking.
77
9.2- Materials Submittals
9.2.1 With in one month from the date of awarding of the contract, the contractor should
submit to the Engineer for his approval a detailed schedule of proposed material
in a format acceptable to him.
9.2.2 Material submittal should have main index / list of items showing all the contents
Inside the file.
9.2.3 Material submittal should have a complete project specification, properly
highlighted for the proposed items.
9.2.4 The contractor should submit 4sets of material submitted for the consultant
approval
9.2.5 Material submittal should have our specified / approved manufacture list and to be
highlighted for the proposed item.
9.2.6 Material submittal should have original catalogue & properly highlighted for the
proposed item.
9.2.7 Material submittal should have data sheet, showing the catalogue reference, model
number, quantity of the proposed item.
9.2.8 Material submittal should have supplier a contact number & contact person mobile
number.
9.2.9 The approved submittal form given by Engineer, should be properly filled by the
contractor.
9.2.10 The material submittal will be reviewed by he concerned Engineer and forwarded
to MEP Head for rechecking.
78
9.3- Samples Submittals
9.3.1 The contractor has to submit samples of all items proposed for use in the project
Other then the major equipment or as directed by the engineer.
9.3.2. The sample will be checked & Confirmed by the relevant Engineer and forwarded to
MEP Head for rechecking and final approval
9.3.3 The contractor shell obtain manufacturer's installation directions and should submit
two set of copies of such directions to the consultant prior to installation
9.4.1 The contractor should submit work procedure according to the type of installation.
9.4.2 The work procedure should indicate the scope , risk involved, safety precaution to
be observed, tools to be used and indicate clearly the laying of execution
responsibility
The work procedure should also indicate the name and designation of the persons
“prepared by”, “checked by” and “approved by”. Finally it should be submitted to
engineer for his authorization to be used this work procedure at site.
.
9.4.3 The work procedure should have a fixed sequence of operations required to
complete any system installation.
9.4.4 The contractor should have the responsibility to schedule his all type of installation
at work so that all types of work will be installed at proper time and without
delaying the completion of the entire project.
9.4.5 The contractor should be responsible for coordination with any other trades or his
subcontractor so that there is no conflict during the proper execution of project.
79
Technical Administration/Procedure
80
10- PROCEDURES & FORMS FOR MEP WORKS.
81
10.1- Shop Drawing Submittal for Approval (SD).
82
10.3.7 Sub-Contractor Submittal for approval should have the valid copy of trade
licenses.
10.3.8 Sub-Contractor Submittal for approval should include a list of similar projects
(i.e., same as awarded) executed in the UAE.
10.3.9 Sub-Contractor Submittal for approval should include company profile and
prequalification documents.
83
10.5- Request for Information (RFI)
84
10.9- Operation & Maintenance Manuals (OM)
85
ANNEXSURES
(Templates)
86
Index Page Nos.
87
SITE INSTRUCTION
Project :
Consultant :
Contractor :
Subject :
88
PROJECT :
CLIENT :
CONSULTANT:
CONTRACTOR :
Architect/Engineer:
Non-Conformance Details
89
Signature of the Contractor
Date agreed for Completion
90
REQUEST FOR CHANGE No. :
Contractor:
RFC Dated :
PROPOSED
ORIGINATOR ORIGINATOR'S REFERENCE
CHANGE
91
CLIENT'S COMMENTS / AUTHORISATION
92
PROJECT BUDGET AMENDMENT REQUEST No. : PBAR / ??
PBAR Dated :
93
(Company & Name)
94
DOCUMENT ISSUE
To : Job. No : STATUS
CODES
Ref. No. :
Information 1
Attn : Date : Comments 2
Approval 3
C.C. : Coordination 4
From : Preliminary P
Tender T
Project : Construction C
As Built
Z
Dear Sirs,
Yours faithfully,
For Contractor
.…………………………………………………………..
95
MATERIAL SUBMITTAL FOR APPROVAL
PROJECT Ref.
CONSULTANT Date
.
CLIENT Job No.
CONTRACTOR
Description
Location/Use
B.O.Q. Ref.
Spec. Ref. Drawing Ref.
Manufacturer/ Origin
Supplier
FOR ENGINEER
Date of receipt by Engineer
Submittal is :-
APPROVED
NOT APPROVED
APPROVED WITH COMMENTS
RETURNED FOR RESUBMISSION
ENGINEERS COMMENTS
For
Contractor :
Date of
96
REQUEST FOR INFORMATION (RFI)
Project :
Subject :
Request No.
for
for Consultant.
97
SUBMITTAL FOR APPROVAL OF SUB-CONTRACTOR/ SPECIALISTS
PROJECT/ Activity
Discipline . Ref.
Proposed Name
CONSULTANT Date
.
FOR ENGINEER
Ownership of Company & Supporting Documents Job No.
CLIENT
Origin
Date of receipt by Engineer
CONTRACTOR
Submittal is :-
List of attachments to this form :
APPROVED
Statement of relevant experience
NOT APPROVED
Statement of ownership / origin
Resources Statement
APPROVED (labour, machinery & equipment)
WITH COMMENTS
Management
RETURNED FORStructure.
RESUBMISSION
Affiliation
ENGINEERS with International Firms.
COMMENTS
Others / Photographs of relevant project
Engineer
Stamp
Signature
Date :
98
TEMPPLATE FOR METHOD STATEMENT
Objective:
Scope:
Responsibility:
99
Title: Method statement for-------------------------(mention the name of method statement
Code No. As per department write code no. Page No: current page no./ total page no.
Abbreviation:
Standard Component:
10
Title: Method statement for-------------------------(mention the name of method statement
Code No. As per department write code no. Page No: current page no./ total page no.
Description of Hazard:
10
Title: Method statement for-------------------------(mention the name of method statement
Code No. As per department write code no. Page No: current page no./ total page no.
1.
2.
3.
4.
5.
6.
7.
n.
The end of the document
10
JOB DESCRIPTION (Template)
Job title:
Job code:
Job holder:
Reports to:
First reports: .....
.....
Job description:
Responsibility: .....
.....
.....
Authority: .....
.....
.....
10
10
.....
.....
internal .....
Communication
.....
.....
external ....
Requirements: ......
.....
.....
......
Department manager review
Employee Review
Human resource review
10
ABBERIVATIONS
10
>MEP : Mechanical Electrical and Plumbing
>MEP : Mechanical Electrical and Plumbing
>MDB : Main Distribution Board
>SMDB : Sub Main Distribution Board
>DB : Distribution Board
>ISO : International Standard Orders
>BS : British Standards
>ASTM : American society for temperature and material
>ASHRE: American society for heating and Refrigeration Engineers.
>IEE : International Electrical Establishment
>IP : (I) Environmental Protection.
>DEWA : Dubai Electrical and Water Authority
>BOQ : Bill of Quantity
>FIDIC : Federation of Construction Engineer-France
>RE : Resident Engineer
>ARE : Assit. Resident Engineer
>MD : Managing Director
>UAE : United Arab Emirates
>HVAC : Heating Ventilation and Air Conditioning
>HOD : Head of Department
>IR : Inspection Request
>RFI : Request for information
>NCR : Non Compliance Report
>MS : Method statement
>TC : Testing & Commissioning
>OM : Operation Manual
>MCB : Molded Circuit Breaker
>ELCB : Earth Leakage Current Breaker
>A&V : Ammeter & Voltmeter
>EP : Earth Pit
>QC : Quality Control
>XLPE : Cross Link Polyethylene
>WP : Weather Proof
>DP : Double Pole
>JB : Junction Box
>CCTV : Close Circuit Tele Vision
>BMS : Building management System
>VCD : Video Compact Disc
>PA : Public Address
>LNB : Local Net work Band
>FM/AM : Frequency Modulation /Amplification modulation
>NRV : Non Return Valve
>AC : Air Condition
>A/C : Alternating Current
>LPG : Liquid Petroleum Gas
>CFM : Cubic feet p
10
About the author
Since then he has handled various projects comprising industrial and domestics.
Industrial projects include: airport runway extension, chemical, textile, industrial
plastics, bulk drug, pharmaceutical and disposable surgical items including plastic
syringes.
Domestic projects include skyscraper towers for hotel and residential purposes.
Row town houses and villas in victory height project at Dubai international sports
city- Dubai.
Dr. Sharma is renowned and seasoned electro mechanical project engineer in India
and in Middle East. He had been on various senior executive positions at corporate
sector both in India and in Dubai. Presently he is engaged with DIAR consult –
Dubai as A. Resident engineer (MEP) for “Dubai International sports city” at
Dubai.
Contact:
Dubai +971-50-6848309
India +91 731 2402503
Email:drsanwaria10@gmail.com
drsanwaria10@yahoo.ca
10