Small Earth Dam Type Drawing I X

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

STANDARD CROSS SECTIONS

2.00
0.50

2.50
1.00
1.50
D= depth of overflow

0.50
0.50

2.00
0.50

2.50

1.00
1.50
1.00
1.50
SCALE 1 : 100 plus safety
0 0 b (m) 0 (m) 0 (m)
1.40 HEIGHT OF WINGWALL b3 b
1.00
H 1.40 1.00 1.00
1.40 1.40
2.00
2.00 2.00
H3 H1
3.00
3.00 3.00
H2
4.00
4.00 4.00
b 5.00 b b H2 (m)
5.00 b b
Upstream Downstream H (m)
0.65 H1 (m)
Upstream Downstream
DESIGN PROCEDURE

1. Storage requirements - H1
0.20 A 2. Q50 and length of overflow section - Depth of overflow d
FINAL ELEVATION 0.20
3. Depth of overflow plus safety
3. STAGE
D = 1.5d + 0.10m
4. Height of wing wall
2. STAGE H = H1 + D
B B 5. H2 = H - 1.40m
B 0.20
B
1. STAGE (1.40m fixed by stability calculations
(INITIAL ELEVATION) 6. H = 1.40m - D
SECTION A-A 0.50 7. Base width from graphs

A H = 3.80m no overflow NOTE: max. D = 1.40m


INCLINED LUMBER SHUTTERING
NUMBER AND ELEVATIONS OF REQUIRED H = 3.20m D = 0.30m. overflow
CONSTRUCTION STAGES HAVE TO BE VERTICAL LUMBER SHUTTERING
ESTIMATED ACCORDING TO SEDIMENT 0.50

0.80
OVERFLOW D=0.30m
TRANSPORT OF RESPECTIVE RIVER

1.40
SECTION 0.85
D=0.80m

3.80
DETAIL OF FOUNDATION

0.60
H2 = 2.40m
0.20
SCALE 1 : 50 H1=2.90m H=3.20m

650
R 400 0.40 CONCRETE 1:3:6
100.00 0.50
CONCRETE 1:3:6 b1=1.90m 0.65 with plums
with plums 0.65 b2=1.40m
800 @ 200mm SPACING b1=1.50m T=0.30 b2=1.0m
b2=0.90m
Client: Location:

FIRM ROCK Surveyed By: Scale:


File Name:
T SECTIONS WITH OVERFLOW ONLY AS SHOWN
300 Drawn By:
Project:

H (m) 1 2 3 4 5 CREST DETAIL Designed By:


T (cm) 20 25 30 35 40 Drawing Title:
STANDARD CROSS SECTIONS CONCRETE SAND
SCALE 1 : 50 Checked By:
STORAGE DAMS
THE DEPTH OF THE TRENCH MIGHT BE ALTERED Approved By:
Drawing No: Rev: Sheet:

ACCORDING TO THE ROCK ENCOUNTERED TYPE DRAWING IX 13/17

You might also like