CONSTRUCTION - SWITZERLAND AUTHORS

China Irwin
Model for dealing with geotechnical uncertainty:
FIDIC Emerald Book for underground works
29 July 2019 | Contributed by LALIVE SA

Introduction
Key provisions Sam Moss
Tendering for Emerald Book projects
Comment

Introduction

As in many other civil law jurisdictions, the allocation of risk for unforeseen ground conditions is not
specifically addressed under Swiss law. As a result, parties negotiating Swiss contracts for projects
involving significant geotechnical uncertainty, such as tunnelling and other underground works,
should carefully address the allocation of risk for ground conditions.

The International Federation of Consulting Engineers (FIDIC) 2019 Conditions of Contract for
Underground Works (Emerald Book) is a new standard form specifically for underground works that
is the result of a lengthy collaboration between FIDIC and the International Tunnelling and
Underground Space Association (ITA). The Emerald Book contains several features aimed at
addressing geotechnical uncertainty, including geotechnical baseline reports (GBRs) and
mechanisms to adjust the time for completion and contract price.

The Emerald Book is not the first standard form contract geared towards tunnelling projects. For
example, the Swiss Society of Engineers and Architects Norm 118/198 (General Conditions for
Underground Construction) is often used for tunnelling projects in Switzerland. However, there was
no version of the widely used FIDIC Conditions of Contract suitable for tunnelling projects before the
Emerald Book. Instead, parties often used other FIDIC or New Engineering Contract standard forms,
modified with reference to the recommendations, guidelines and checklists published by the ITA.

Key provisions

The Emerald Book is essentially a modified version of the 2017 Conditions of Contract for Plant and
Design Build (the Yellow Book), with special provisions to address the allocation of risk for
subsurface physical conditions. Its most notable features are the introduction of GBRs and
mechanisms to adjust the time for completion and contract price (in which the information
contained in GBRs plays a role).

GBR
A GBR is a document that must be included in tender documents and a final contract. It describes the
subsurface physical conditions and corresponding ground reactions. However, it is meant to include
more than simply geotechnical data (which should be set out in a separate document (ie, a
geotechnical data report)). A GBR is meant to be a careful and thorough analysis of the known and
potential ground conditions and possible ground behaviour in light of the intended construction
method. A contractor is deemed to have based its tender proposals on the information contained in
a GBR, even if such information is contradicted by other data made available thereto.

A GBR also sets out the allocation of risk between parties for subsurface physical conditions, as
employers will be responsible for any time or cost-related effects of the subsurface physical
conditions differing from those described in the GBR. Subsurface conditions outside the scope of
those defined in a GBR are deemed 'unforeseeable' for the purpose of Sub-clause 4.12 of the Emerald
Book; employers are responsible for any time or cost-related effects of unforeseeable conditions.

Adjustable time for completion and contract price


The other notable feature of the Emerald Book is that it includes a mechanism for adjusting the time
for completion and contract price based on the actual ground conditions encountered during an
excavation, even though the conditions remain within the scope of those defined in the GBR.
However, the mechanism applies only to the extent that the actual ground conditions affect the
quantities of the excavation and lining works set out in the schedule of baselines.

The schedule of baselines is another new feature of the Emerald Book, which sets out the quantities
for excavations and lining works items, as well as contractors' production rates for these items,
including for each excavation zone.

According to Sub-clause 13.8 of the Emerald Book, excavation and lining works are subject to
measurement, contrary to all other underground works which are deemed to be covered by the
accepted contract amount. The measurement of the excavation and lining works, which must be
performed by the contractor and agreed or determined by the engineer, then serves as the basis for
adjustments to the time for completion or contract price.

Engineers must reassess the time allowed in a completion schedule or programme by applying the
contractor's production rates set out in the schedule of baselines to the measured quantity of each
completed excavation and lining works item. Based on this reassessment, the engineer must then
determine whether the time for completion will be affected, based on the logic links identified in the
completion schedule or the programme, and adjust the time for completion accordingly. Adjusting
the time for completion goes both ways: while the time for completion may be extended in case of
ground conditions less favourable than those anticipated in the GBR, it could also be reduced if
conditions prove to be more favourable.

Engineers must also adjust the contract price by applying the appropriate rate from the bill of
quantities to the as-built quantities of the different excavation and lining works items.

Claims and dispute resolution


Like the contracts included in the 2017 FIDIC suite of contracts, the Emerald Book includes detailed
provisions concerning claim submissions and dispute resolution. Both employer and contractor
claims must be submitted to the engineer within specified time periods. Disputed claims are subject
to a multi-step resolution process, beginning with a standing dispute adjudication board (DAB),
appointed at the outset of the project, and continuing to International Chamber of Commerce
arbitration if the DAB's decision is not accepted.

Tendering for Emerald Book projects

Given the amount of information to be compiled and agreed in a GBR and schedule of baselines as
part of a tender process – and the potential consequences for the final time for completion and
contract price – tenders for a project subject to the Emerald Book may require more care than those
under other standard form contracts.

FIDIC and the ITA have recognised this by including in the Emerald Book roughly 20 pages of
guidance on preparing tender documents and annexes.

Using the Emerald Book and GBRs will significantly increase an employer's costs and the time
required to prepare the tender. Not only will they have to carry out extensive site investigations,
they must also analyse the results of the investigation and determine the range of possible ground
behaviour and potential impact on the project. When assessing a tender under the Emerald Book, an
employer should also look beyond the overall tender price and carefully consider the contractor's
proposed production rates, as they could have a significant impact on the time for completion.

On the contractor's side, they will have to carry out extensive preparatory work (eg, determining
production rates for each excavation zone) before knowing whether their tender proposal will be
accepted. For this reason, FIDIC advises employers to consider remunerating tenderers for the
preparation of tender proposals. Yet, depending on the size of the project and the employer's
resources, this may be unfeasible.

Comment

While the tunnelling industry has eagerly anticipated the release of the new Emerald Book, it remains
to be seen how quickly it will be put to use and for which types of project. Parties to contracts for
tunnelling and underground works have long adapted standard forms to address the specificities of
work that involves significant geotechnical uncertainty and may be reluctant to move away from the
bespoke contracts that they have developed over time. Their reluctance may be increased by the
considerable changes in the 2017 FIDIC suite of contracts, on which the Emerald Book is based and
with which the industry may take time to become comfortable. However, FIDIC's close collaboration
with the ITA in developing the Emerald Book, its reflection of best practice in the industry and the
extensive guidance provided for its implementation all suggest that it will be well received among
industry players that regularly work on projects with complex geotechnical aspects.
For further information on this topic please contact China Irwin or Samuel Moss at LALIVE by
telephone (+41 58 105 2000) or email ([email protected] or [email protected]). The LALIVE
website can be accessed at www.lalive.ch.