Lecture 5A - Mine Scheduling
Lecture 5A - Mine Scheduling
By
Dr. B. Besa
The University of Zambia
School of Mines
CONTENTS
4
MINE SCHEDULING
Important because a $ received today is
more valuable than a $ that we might
receive in a year’s time;
Labour and equipment requirements are
estimated, performance rates and standard
costs are applied and then the mine’s
progress and viability can be planned and
monitored;
Usually an iterative process;
'a list of tasks to be performed, especially
within a set period'; or as a 'plan of
procedure for a project’ 5
TYPES OF MINING SCHEDULE
Production schedules
1. Long Term or Life of Mine (10+ years)
2. Medium Term (5 years approx.)
3. Short Term (3 months – 2 years)
4. Extremely Short Term (down to a shift, or for specific jobs)
Exploration drilling schedules
Development schedules
Production drilling schedules
Equipment schedules
Labour schedules
Filling schedules
Consumable schedules
6
Special project schedules
Operational
Strategic Mine Tactical Mine Mine Planning
Planning Planning
3-Month Plan
Strategic Life-of-Mine Budget/ 1-Month Plan
Review Plan Re-Forecast 1-Week Plan
1-Day Plan
12
EXPLORATION DRILLING SCHEDULE
Fairly simple schedules indicating when
drilling needs to be done to satisfy the key
dates indicated on the long term and medium
term production schedules.
Shows when drilling sites are required and
hence the development needed to access the
sites
Shows various types of exploration drill rigs
required, the labour needed to operate these
rigs and the drilling rates per shift for each of
these rigs.
13
DEVELOPMENT SCHEDULE
14
PRODUCTION DRILLING SCHEDULE
Shorter term schedules
Give number and type of production drill rigs,
their location, layout required and drilling rates
are shown;
Its aim is to complete as much of the production
drilling as possible within each stope prior to
that stope commencing production;
Stope drilling costs can be added at a standard
rate and the cost per stope calculated;
Aim is to have stopes ready for production when
scheduled and to have the production drilling 15
crews continuously occupied.
EQUIPMENT SCHEDULE
Prepared mainly from production,
development and drilling schedules;
Some equipments can be shared between
activities;
Estimates to be made for general
servicing equipment;
Provide vital information for estimating
requirements for maintenance.
16
LABOUR SCHEDULE
19
CONSUMABLES SCHEDULE
20
SPECIAL PROJECT SCHEDULES
Used for preparation, development, installation
and commissioning of major infrastructure
components at mines
Critical path for the complete project is
determined and resources required for each
time segment calculated
Updated regularly and used as one of the
project management tools to control the project
to meet its targets in terms of time and cost
21
OPEN PIT SCHEDULING
22
OBJECTIVES
The following are the objectives of open pit
scheduling;
1. Providing a steady and balanced ore feed to
the mill;
2. Maximising the NPV of the project;
25
AIMS
The objective of this schedule aim to:
1. Providing a steady and balanced ore feed to the mill
or a steady blended product for direct shipping
2. Maximising the NPV of the project by accessing
higher grades early and always filling the mill with
the best available feed
3. Providing a steady, balanced workload for the
development and production equipment
4. Deferring development as long as possible
consistent with access for exploration, infill drilling
and stope development
5. Setting development rates which are unit multiples
of the capacity of a standard development crew or
fleet
6. Minimising the number of active working areas to
reduce the cost of supervision and services; 26
SCHEDULING
Minimising the time development has to be kept open
in recognition that there is a maintenance cost for
development;
Maximising the size of stopes or stoping blocks while
keeping a minimum number of active stopes to protect
against stope outages (failure);
Providing time in the development and stoping cycle for
surveying, infill drilling, planning, ground support, and
production drilling;
Sequencing the stopes from bottom up or from top down
according to the mining method and filling
requirements;
Minimising the requirement for crown and bridge
pillars;
Minimising broken stocks which tie up working capital
and ore at risk of re-cementing insitu. 27
SEQUENCING
Importance of sequencing;
1. control mining-induced stresses
according to geotechnical
requirements;
2. Maintaining ventilation and services
as required;
3. Provide a steady usage of backfill and
maximise the utilisation of backfill
material;
4. Minimise the need to remove
development waste from the mine. 28
SEQUENCE OF ACTIVITIES
Calculate diluted tonnes and grade for each
stope;
Select mining sequence, defining primary and
secondary stopes and permanent pillars;
Re-define stopes if necessary to suit the
schedule;
Estimate production profile for each stope;
Decline development
40m/wk average, 70m/wk best
Level development
75m/wk per jumbo (3 faces available)
Shaft sinking
35-40m/wk (strip and line); 15-20m/wk
(blind)
Raiseboring
2m/day (200MPa rock)
Trucking
2500 tonne.km/day (40 tonne truck)
31
SCHEDULING PROCEDURE (AFTER GEMELL 1998)
Activities:
1. Have start and end time = Duration
2. Correspond to physical work ( or
Process)
3. Activities can be represented by a
“Gantt Chart” (or Activity bars)
4. Activities may be divided into sub-
activities
35
3,000t @ 3t/m
1,000m @
200m/d
Slot &
rings
Drill
3,000t @
300t/d
Blast
Survey
Bog/Muck
B Fill
cure
Fill
Road
Stope X (TMP & OMP Yr 1-2): 300t/d, 19d pre- and post-bog/muck delays
EXAMPLE OF GANTT CHART
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12
Task or Activity
Review geology
Plan drilling programme
Diamond drilling
Core logging
Lab testwork
Data analysis
Failure mechanisms
Stability analysis
Slope design
Draft report
Report review
Final report
37
Scheduled physicals
physical report items, by option
visualisation, including plans
non-physical report items
Critical path
Resource requirements
Approvals
Sustainability issues 38
END
39