Compendium of Instructions For Station Development Projects 24 December 2022
Compendium of Instructions For Station Development Projects 24 December 2022
for
Station Development
Projects
Dec, 2022
INTRODUCTION
Provisions of estimates 94
2022/SD- Major Upgradation of stations
14 04.10.2022 for major upgradation
II/22/1/55 under Umbrella work
works
Comprehensive instructions for 95 – 96
umbrella work of Major up Preferable width of roof
2021/Stn.Dev.
15 gradation of Railway Stations on 03.10.2022 plaza 72 m, One station
-I/08/18
Indian Railways one product
Approval of plans, 97 – 99
DRM weekly meeting,
power and traffic
2021/Stn.Dev. Execution of station development blocks, shifting of
16 03.10.2022
-I/08/18 works. utilities, CE/SD nodal
officer, consultancy,
construction
organization
100 – 101
Provision of ballastless track at BLT, major/important
2021/CE-
major/important stations and station, major
17 II/TSC/10thEx 29.09.2022
stations identified under Major upgradation/redevelop
traordinary
Upgradation/Redevelopment ment
102 – 104
Material modification,
2022/CE- Indian Railway Code for
Para 1110,1111 and
18 I/CT/5/Engg.C Engineering Department- 26.09.2022
1112, ACS 59 to
odeRevision Advance Correction Slip No. 59.
Engineering Code
No. 2022/G S/Stn. Dev.-I /08/70 New Delhi, dated: 23.12. 2022
2 . Modali ty of scheme :
various
The Amrit Bharat Station scheme shall general ly be executed through
-53) sanction ed from time to time.
umbrella works for Custom er Amenities Plan Head(PH
to achieve the objectiv es of the scheme .
Existing Umbrella works of PH-53 can also be used
at differen t times as per needs of the station
DRMs can phase the hiring of suitable experts
be planned in
and engaging all experts in one go is not mandat ory. Works may also
differen t stages under differen t umbrella s as per the needs of the Master Plan.
Page 1 of 260
4. Scope of Work:
To meet the above objectives, following broad scope of work is envisaged for
stations selected under the Amrit Bharat Station scheme in order to achieve the instructions
issued vide letter no. 2021/Stn. Dev.- I/08/18 dated 04.05.2022 and 03.10.2022:
4.1 All improvement plans shall be made with help of architects/traffic planners
and/or user experience consultants as decided by DRMs. The Master Plans should
have elementary details of the most appropriate location of Roof Plaza to be
created in future.
4.2 The scheme envisages cost efficient improvement to facades, provision of wide,
well lit aesthetically pleasing entrance porches.
4.3 Existing building usage shall be reviewed and space should be released in favour
of passengers near the station entrances and the Railway offices should be
suitably relocated.
4.4 The scheme aims to" relocate redundant/old buildings in a cost efficient manner so
that space is released for higher priority passenger related activities and future
development may be carried out smoothly. Creation of new buildings should
generally be avoided other than those required for relocation of old structures or
relocation of structures to improve circulation or provision of structures to
improve the size of waiting halls. Decision in this regard shall be taken by DRM
considering all relevant factors.
4.5 Attempts shall be made to club different grades/types of waiting halls and provide
good cafeteria/retail facilities as far as possible. Suitable low level partitions may
be done in waiting halls if required.
4.6 Provision for minimum two stalls for One Station One Product shall be made.
4.7 Space shall also be created for Executive Lounges and places for small business
meetings.
4.8 At least one aesthetically designed hoarding(signage) on each side of the
circulating area at a prominent location shall be erected for display of important
information etc. The size of such hoarding shall not be less than 10mx20m.
4.9 Station approaches should be improved to ensure smooth access by widening of
roads, removal of unwanted structures, properly designed signages, dedicated
pedestrian pathways, well planned parking areas, improved lighting etc.
Necessary liaison should be established with local authorities for necessary
improvements to be carried out by local authorities in their areas.
4.10 Elements of landscaping, green patches and local art and culture should be used
to create a pleasant experience for the station users. This should be done with the
help of,suitable professionals.
4.11 Second Entry Station Building and circulating area shall be improved as per the
needs of the station. Wherever second entry building is n9t being provided
presently, space for circulating area will be well planned and a liaison shall be
established with the local bodies so that approach roads for second entry are kept
in the city's Master Plan and development around the station is suitably controlled.
4.12 High level platforms(760-840 mm) shall be provided at all categories of stations.
Length of the platforms shall generally be 600m.
4.13 Length, location and phasing of Platform shelters shall be decided by DRM based
on usage of the station. Generally,16m long bays at not more than 100 m centre
to centre distance may be taken as a reference.
4.14 Ballastless tracks(BLT) should be provided on platform lines and lines with train
maintenance facilities. Proposals and execution of works should be planned in
Page 2 of 260
suitable phases. Due care should be taken that provision of BLT on platform lines
which are also mainlines should not lead to reduction of speed potential or cause
imposition of any speed restriction in future.
4.15 Drainage of platform areas is of utmost importance. Special emphasis shall be
given to achieve self cleansing of drains as far as possible. Suitable cross drains,
sump and pump arrangement may be provided where natural slopes are not
adequate. Drains may be covered with aesthetically designed theft resistant
covers.
4.16 Cables should be laid in aesthetically designed duct or cable trays and should have
provision for future cables as well.
4.17 The Master Plan shall mark the space for Parcel handling spurs, storage and
handling facilities etc. Works should also be proposed and executed in suitable
phases.
4.18 Provisions may be made such that the station provides free WiFi access to its
users following all guidelines issued by DoT. The Master Plan should have suitable
spaces earmarked for SG tower/pole mounts.
4.19 Material finishes of elements, such as flooring, walls, structures, furniture,
sanitary fittings, etc. within the public areas of the station where surfaces either
come in direct physical contact of passengers or are visible to them should be
highly durable (preferably washable), generally dustproof and need low
maintenance.
4.20 The furniture available on Waiting halls, Platforms, Retiring Rooms, Offices shall
be reviewed and intervention planned for more comfortable and durable furniture
suitable to the Railway Stations of that area. In a phased manner, it shall be
planned to eliminate multi-design furniture. Released furniture etc. may be
suitably utilized on other stations/locations if deemed fit.
4.21 All signages/display boards including train indication boards and coach guidance
systems/boards should be positioned for intuitive way finding, should have good
visibility and be aesthetically pleasing. Public announcement system should be
designed with the help of suitable professionals to ensure quality.
4.22 Escalators may be provided at NSG/1-4 and SG/1-2 category stations irrespective
of footfall. Mode of procurement(works/stores) may be decided by DRMs. Planning
for approval of GADs should be done well in advance to speed up the work of
installation of escalator/lift and optimize the overall time schedule of
commissioning.
4.23 Amenities for Divyangjan at stations shall be as per guidelines issued by Railway
Board from time to time.
4.24 Ceremonial flags may be provided at appropriate space in the station.
4.25 At least two station name boards should be LED based with good visibility for the
passengers of trains passing through the station.
4.26 Circulating area boundary wall normally should not block the view of the station
from outside. Access may be controlled by iron/steel grill fencing.
4.27 Sufficient number of toilets shall be provided at all categories of stations with
separate provisions for women and Divyangjan. Location of toilets should be
appropriate to station usage, easily visible and accessible.
4.28 Gradual shift to sustainable and environmental friendly solutions as per availability
of funds and condition of existing assets.
4.29 Illumination levels specified vide Railway Board's letter no. 2008/Elect(G)/172/1
dated 08.03.2019 for the then Al and A category stations shall be applicable for
Amrit Bharat Stations(Annexure-1). To further improve the overall look of a
station through fa~ade lighting, the Railways can decide on their own type of
fa~ade lighting based upon the layout of a particular station.
Page 3 of 260
4.30 CCTV surveillance system along with panic button at various location in the
stations to be provided in consultation with security branch.
4.31 Any other item as considered necessary by DRM/GM.
7. This issues with approval of Board( M/Infra, M/O&BD, M/F, CRB & CEO).
~'\,,,~·,..'\,
(Rakesh Choudhary)
(Executive Director(SD & Trans.)
Railway Board
~~
for Member Finance, Railway Board
Copy to:-
1. PCEs, CCMs, CEEs & CSTEs, all zonal railways.
2. EDPM, EDF(X)-II, EDF(B), ED/Tele, ED/Signal, ED/EEM, DF(X), DTC(G), DDF(B),
DDF(X)-II, F(X)-II, TG-IV, Tele, Signal, Electrical(G) and Budget Branches Railway
Board.
*****
Page 4 of 260
Annexure-1
Lux levels for Stations selected under Amrit Bharat Stations Scheme
Page 5 of 260
Annexure - II
Master Plan should include the following minimum details in 4 nos. of A-3 sheets
4. Details of works as required for various items in tabulated manner along with approx. cost.
Page 6 of 260
Page 7 of 260
Page 8 of 260
Page 9 of 260
Page 10 of 260
Page 11 of 260
Page 12 of 260
Page 13 of 260
Page 14 of 260
Page 15 of 260
Page 16 of 260
Page 17 of 260
Page 18 of 260
Page 19 of 260
Page 20 of 260
Page 21 of 260
Page 22 of 260
Page 23 of 260
Page 24 of 260
Page 25 of 260
Page 26 of 260
Page 27 of 260
Page 28 of 260
Page 29 of 260
Page 30 of 260
Page 31 of 260
Page 32 of 260
Page 33 of 260
Page 34 of 260
Page 35 of 260
Page 36 of 260
Page 37 of 260
Page 38 of 260
Page 39 of 260
Page 40 of 260
Page 41 of 260
Page 42 of 260
Page 43 of 260
Page 44 of 260
Page 45 of 260
Page 46 of 260
Page 47 of 260
Page 48 of 260
Page 49 of 260
Page 50 of 260
Page 51 of 260
Page 52 of 260
Page 53 of 260
Page 54 of 260
127/128
2022/SD-II/22/01/4pt.1
1299285/2022/O/o ED/SD&T
Sub: Project Management Services tenders for station development works- ensuring
availability of key personnel reg.
Zonal Railways and Rail Land Development Authority (RLDA) have invited a number of
tenders for selection of Authority Engineer for providing Project Management Services (PMS)
for station development projects during last four months. It has come to notice that in some
cases the bidders have offered the same team for different station PMS tenders. Having same
full time key personnel for different projects constitutes conflict with requirement of
availability of the key personnel as per the model document for PMS services issued vide ref. 1
above. It is essential that availability of key personnel is examined in more details during
evaluation of tenders.
2.0 For stations where PMS tenders have not been awarded so far, each responsive and
eligible bidder may be asked to certify that no such PMS tender for Indian Railway projects has
been awarded to him which could cause a conflict regarding availability of key personnels for
the tender under consideration. It should be further certified by him that if any such conflict
comes to the notice of the bidder it shall immediately be brought to the notice of the tender
inviting authority. The tender inviting authority should take suitable action in terms of tender
conditions for such conflict coming to its notice. Any incorrect/false declarations should be
dealt as per terms of the tender documents.
Page 55 of 260
128/128
2022/SD-II/22/01/4pt.1
1299285/2022/O/o ED/SD&T
3.0 The contract handling authorities should be cautious of availability of personnel and in
case of non-availability of the same, swift action in terms of contract conditions for contractor's
default should be taken.
4.0 For stations where bidding has not started yet, the tender documents may be suitably
modified to take care of such issues.
Copy to:
The Vice Chairman, Rail Land Development Authority (RLDA), New Delhi for information
and necessary action please.
Page 56 of 260
Page 57 of 260
Page 58 of 260
Page 59 of 260
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
(RATLWAY BOARD)
Vide ref above, "Technical eligibility criteria and special conditions of contract for
design and construction of ballastless track on viaduct/ tunnels on Indian Railways" were
circulated. Zonal Railways were also requested to give any suggestions for further
improvement in the criteria.
It is understood that procurement process has been taken up by few Zonal Railways,
or being processed. Tonal Railways are requested to give their feedback/ remarks/
suggestions on the subject, based on difficulties faced before/ during/after tender award.
All zonal railways, especially where tenders have been processed/ awarded/ planned
must respond within one week's time, i.e., by 2no November 2O22.The response may please
be sent on email: Email lD-dcebsrb@gmail .com or [email protected] in addition to usual
mode of communication.
EDl B&S
Railway Board
Copy tol-
CMDI IRCON, RVNI. KRCL for providing feedback for similar procurement done by them on
lR network, if any within next one week's time.
PEDICEIP for information please.
PED/lnfra-1, ll/RDSO for information please.
Page 60 of 260
(
ctlYga:{ffiaNT Of lNntA
MTNTSTRY OF RAILWAYS
{n,*ILWAY *t}A*tr}
t{o' l0l6fJ9/CH-tIl/BRIBLT {r*cw t}*lhi I}t: t}6-$1.lSl8
Page 61 of 260
:Hgtists*t**Fft€t-Bfl={t{._ sBtrHHrA _A$a_*SFEgrAL _QQ$qr!"orlF tr
qo|srRecT. rgs p€$rsF{ ffifl$.sr oF._ sALLn$rL4$$
:fiASSSN VISSUSTT{$f isFl_F s-ffi f,ryp{*!'r F&t!SAy$
A" GANSREL
1.0 Ballasiless track is requirred to be provided at a number of locations e.g" tunnel,
visduds as &e interrnediate rnaintena*ce rnay not be economically feasibie.
?.0 Indian Raihvay is in effort to develop the design and construct h,allastle$$ trast{
ior lndian railways,which are proven a*d being used in wortdwide raih*ays
successfully- The proven design may require sorne nrodifications to suit to
lndian Raihrays ccnditicns. Ttris presant tender is invited foradoption of proven
teshnology of ballast less kack wcrldwide t*m the bidders wfiich can b*
suita$le to lndian Raiherays csndttion$.
4.1 The bidder csn be a firm ar a Joint Venture uV) nnn or a collaboration CIf
firms, frcm lndien/abroad, having a qritten 'Agreement' to tha effect that the
finns sfigff be joinily and severely resp*nsble for their portion of the wcrlt and
- shall'be assqciated till comptetion of tlre contract. The bidder nray consist of
maxirnum three members as under:
{s} Prinie Contracior- who has exp+rience of consttuction of ballastlees track
systern.
{b} Designer firm is e Srn wnich has experience of design of bel|astls$$ traek
that has been Euccessfully in opemtlon and wfrs can modfy the proven
system to suit the "lndian Railway requirements as per technical
requirements for ballastless track.
wE&IryW
\c.
Sr^11r.I
d'ga".r*ggrsc" ?€' j'lg
s4re{}{.#.
&Jr*'n
'Ir Et'rt
'
e>i*rit+
n
Page 62 of 260
(c] Systenn Provider- is a firm, which has provided the proveil batlastless fernfi
$y$t€rn or supplied proven tastening $y$te{fi.
ii) The Prime contractor shbuld have executed et least one single work of
hallastlees track far a minirnum 3$Yo of leng$! of advertiEsd value ot &e
work within qualifying period i.e. last 5 frnarucial year$ & cunant financi*l
year. For farcign frms, the tender value in lndian curency wilt be
c$fivsrted to equirmlefit foreign curency bassd en the exch*nge rate
prevailing on the date of publishtng cf fte tender"
5.0 Bidder will subrnit foltowtng documents along wtth tender to eetahlish technicel
'eligibili&rs rnentione{ in Para 4.2 aboVe.
{i} Proof sf use of proven ballasfiese track sy$tem sr pr*vsn fastening systenr
a$ offerpd in the iender- Offiurnent shsuld aontsin details s.$ mentioiled in
Fara 7.4{a}. h ees docuraent ds not cofit€ifl reguiled details, bidder shell
give seff certifrcation to this affeet and Raihffiy will like to confirm the
vatldity of pr*rreness wfrlch witl be ana*ged by bidder et his own ccst
befcre award of tender.
iii) Te*t report of thfi fascning systern ss meflficiled in Para 7'2.
(iii) Details sf railway e&ninistration and drawings rnentioned in Para 7.4{bi.
{iv}Ccrtifrcstts af exmdion sf work as nent}sned in Para 4.?(ii}.
{v} Experierne of &signerfirm as rner*isrted in Para 4-2{tii}.
5.1 At the tiine of submissbn af the qffer, fiTe biddsr shculd subm* preliminery /
coneeptual design and drawings of ba$ast tre$s tracK {main lins and /sr loop
llne" as applicable) inctuding fustening syste$}, pr€veflfion df dersilment
arrang€ments if required. srrangsment with provision of ducts for *ignal
/telecor"nmunicetion, electric&l etc. in lcngitudinal fansver$e directi*n,
l"' t
W@ iil'.*.*-.-"*--"Page 63 of 260
4S;.-o
d*.,"t. ?,-D'l'fi
transiiion $y$tern, drainage sy*ter* with cCIn$truction procedure, &
merntenaf rce/repair procedure, QAP eiic.
5.2 The bidder snsuH submit an undertaking to fie effect that if the bidder
ber,omes the successful bidder and tfle system of ffack andlor fastenirrg
systern sffered by the bnderer is e patranted one then the bidder shall before
the award of contract shalt fumish copy ol agreement entered into between
&e bidder and tfie palent holder permitting the tenderer tc use the pat€nted
Iterns fsr tender work.
ri2 The detail design induding fastening systern, wttich will be submitted on
award of contrmt should not deviate from the prelirninary lccnceptual design
or ib generic version on the basis atwhich ths propoaal is qccepted"
5"4 Railvay w{ll get the prooJ check the design subrnitted by contractor by en
indepensent deeign agency uftose credential$ shall nst be less than
rne*tioned in claus* 4.2 iiiii.
6.SThe frndJV shalf indemnify Ministry of Railways against any c{aims from any
other party in connectian with the intetlectual prcpe*y rights af the drawings and
designl fastening oyeiem/ bal|astless track system or any other docur*ents
submitted by the firmJJV sr any ather Ftent rights.
B. TESHtrICAL REQIIIRE$IIE.NTS
tn d*signing ballast less fack far siraight & curved tmek on lndian Reilway*,
t*e foflowing pararnetsrs may be considered fsr guidance.
.a
ii Sallasfiess Track shall be designed for the foltctwing:-
a. Main line fsr ZSt axle toed & speed 10$krnpfi {pr*posed for good*
traffic) &?ZTaxte load & spead l6$lqmpn{fsr Bas.rtrlg*rtratrG)
b. Loop line for 25 t axle load & speed S0krnpn.
w &'*,**
1-''
i?ruP .
Aa '] ';&
nv
L-zrt N[\ F
Page
+ - 64
. c of 260
l'\'&
ivl Upward reaction/ pre$$ure liom support base should be ciearly
nlentioned in design.
v) Design shetl be a$ per relevant codes of practice such as BiS, EN, !R$,
IRC and UtC with latest, rsvisiorl edition). lf for any itemA*rork, above
rnentioned codes are not relevant" best available f,rgineering practice /
fnternati*rna! codes shall be rnentioned.
vi) Design & detail of suitabte Transition System fcr smaoth transition fior':
beilagbd track to ballasftess track en boih ends shall be pari of ihe
design of ballastless tnacL
viii) Technical paremeters required far foundatiorr of Ballast lese track *haitr
be suitabty considcrcd far Indian csnditions and shall b* mentioned in
th* d*sign along wtth their test code & procedure" A design monograptr
cf varying sub-gftIde 6fr*racteristic$, if applicable, to he provicied by the
f,rm /designers.
ix) Design servic* life of bellaet s$s track shsuid b* a rninimum +f 60 years.
Concrete f*r RCC strustures shsuld corilply relevant para cf lndian
$tandard t$:4S - 2Sg0 & retsvant para af |R$-Concrete tsridge Sode
taking care of relevant durcbility dause for expmted life of RCC a*
minimurn S0 years.
W4t \-"-F*--
Page 65 of 260
(
xtiii The design shauk! be coet effeotive serving all functional requir*rnents
expected af ballaatless track.
Ch*nges in the above per:arneters {ii} and iiii} mey be aoneidered, in case ihe
biddar is able to support n with the relevant documents and cades as per
practice in other Railw*ys.
t,S Traek &tailE: $aflas{ess track for indian raihreys shall be designed far
falfowing track details:-
i) Raif sectian: Rail prsfile strall co*foN'rn ts UIC S0 {gS UTS} and Rail
material shetl confCIm to IRS-T-12-2OS* clas#A, including
manufacfuring and t+stirg in eccorda*ee with lR$*T-12-?*09 with latest
*tnendments.
ii) $cfi*dule *f Dirnensisns {SOn} and Maxirnum Moving Dimslr*isfl {ilfM*}
st Indlan Railways f*r BG ehalt be fellowed.
iii) Ruling gradient 1 in 8G srflatter {tG bs nctified by tenderer}
iv) Reil cent at Rail seat (inward): 1 in 20
v) Maxir*um degree of curvature: upto STar bslla*t less track"
vil Maximurn pemrisaible cant 165mm.
vii] Speed pste*t*al: Fuil.speed prwailing sn main line{16$krnph}& lqop
line{S$kmph} to be decided hy Reilwaye-
viii) Traffic: Mixed -pase€nger& treiqht
ix) Oufig seivice i'f some paranreter goes out in case sf any unfcreseen
r circumstances, tfie leeway / margin availabie to conect the parerneter,
Verlical: + J0 mrn l - 3mrn, Horiaontal * 3 m$.
Xl) fiesign terRperature r?nge: 7O degree Celsius variaticrr otrailternperatxre
ss per zone & chart af Indian Fathn*y L!1& nnanual and 4S Fegree
veriation of ambient ternpenature"
ilt6s-l tr'
rr-i
f ' d*'*
Page 66 of 260
A^ -,-
'J-i,t""' \.
' i*;*q** '- J' '-c*t*
;Gauge {with referencs t0 1673 mrn, +1mm +3mm
lmeasured betow 14 mm rail top) far
straight track and fcr curve upto the
mdius af 350 m"
I
i
+1nm itSmm
:.2 i
t --" t.,>4--!!.-r.
i3 tgmm It6rnrn
ii
t20 m chord with half ovedappingi I
A
j-.. ye*ical_*lisllryglt* t +'l mrn
f 9.6 m ehgr.{_ Il"j :-' t*
't _- ''.-
e min
Lateral alignrnent sv*r a 7.2 m chord l3 r rtlm j*3mm
on siraight tr€* t
1
I
,. .----
'
Twi$t on 3.6 m base i *.t mm i*5nnrn
I
! i
.i
The absve installation parameters are not sacrosanct and firms/JV *an also
advise their own limits for the ebcve pararneters atong with hasis for
suggesting the changes. V*riaticn in horizontaf alignment, vertical alignment,
versine, twist and gerye silall nat sxhibit cyclic pafi*m.
?.1 Genedel
il The fastening system shall te designed ta hold the iwo rails of the tack
strongly to the supporting structure in upright pcsitien by resisting t}te vedical,
lateral and longitudinai forms {iraluding tfiermal forces) and vihrations.
ii) The fastening shall provide insulatisil to take cere of retum curent of traction
sy$t€m.
iit) Fastening should satidfy the required performance fisrrns as siated below:
7.2 Test report of the reputed independent institute / teh*ratory will have to he
submitted. The test report should be accompnicd wifi the drawing of tlt*
fastening syatem including ib componsrd$ which have been iested and
reparted ripon is exactly $erne as the fastening system includi*g its
components that have been proposed by the bidder in $:e tender. The testing
is to be done for Cat-'E'as specified in EN-1348{-Fartl 2912 & EN-134S1-5
.2A12 with ruif section to be used in propcsed eysiem. Elidder should submit a
statement showing compliance or otherwlse, in jrxtapositiorl tg each clause
and sub dausa'of the es specified in EN-13481-PertJ 2812 A fN-13481-
5:2Q12"
(bi The biddar shatl whmit detaits co*ialning but not lirnited tcnrno*aof line in whicfi
the system is in uee far minimum 5 yearc, details of ilwr raifi*ray adrninistraticn such
as name of the r:ailway administrdion and its contraci person, address, telephone
number. en*il lD 6tc. The bidder shall also $rbmit details of drawing of Ballastless
tra*k system or fastening system along with its components th€t hss been prcposed
by the bidder in the tender.
/.
ULrq*^-- *f,+rr'':'
**o.*b ,%":.lg
3a 'qt'l&
Page 69 of 260
*F
7'5 ltidian Raihrays shall get tlre random te*ting of the fastening system afrer it
has
heen supplied frorn a reputed test lab and system shosld be able ts
meet the
requirernents af rner*ioned in thi$ dccu.n€nt- Cost sf th*
same shall be borne by the
contractof"
t\
CSN$TRIJCTIOH FROCESS
FinnslJV are advised t$ vlsit tocsl sits locations a$ specified in tender
to g*t
femiliar with typical local envlrcnment. kocedure of construstion prccess
*f
ballastle$s track should he mentioned in details suitable to local
site
eanditiofls,construc{icn prcae,ss & systern sffered should be sasy
ir}
construction suitsble ta conditions preveiling en specified siation in tender,
cleerly der*cnstr*ting how it can be canstndcted & instafled within
a
reasonable tirne frame
iviAny visible crack of widtfr more thanss stipulated in lR$ Concrete Bridge
code- para 10.2.'l) in concrete I Rcc portion of slab which impairs the
functicnality cf baltasflese feck.
, -"L** -- t?F.*r* $-
''
1; ' o*'' "
Wrr^-JI4 erls- '1't?
Page 70 of 260
-F
"*
v) Any special observaiion"
The decision of zonal raihrvay about performance cf the Sallastless track after
rnonitoring period shall be finat-
q. i'Y\ a "
c,i*"'*
,t \ je.r*r.r,!,
''-i"4+--'-^*
kfrar-/1a *l=n e':*'''"-
' -'?- Ftola*r.s-a l&:rs* B*'t'1#
gal6-Y'rr*W
r'r;;\*a$r*
Page 71 of 260
Page 72 of 260
Page 73 of 260
Page 74 of 260
Page 75 of 260
Page 76 of 260
"+iHd~HcfSI~ GOVERNMENT OF INDIA 7~
7~~ ~d+ht1aq MINISTRY OF RAILWAYS Azadi Ka
Amnt Mahotsav
AzadiK•
Amnt Mahotsav
~aaifl aRAI LWA Y BOARD)
New Delhi, dated: 19.10.2022
No. 2021/Stn.Dev.-1/08/18
ering,
Model documents for execution of Station Development Projects on Engine
above. The EPC
Procurement and Construction (EPC) mode has been issued vide ref (1)
'Contractor' and
document referred above, defines 'Authority', 'Authority Engineer' and
the same meaning shall be used in the following paras.
s (PMS) agency as
2. The Authority Engineer (AE) may be a Project Management Service
E-I/CT/3/PMS
per model document issued by Railway board vide its letter No. 2022/C
dated 05.05.2022 or it may be a Railway engineer nominated a_ s per clause No. 16.1.1 of
to the Contractor is
the EPC agreement. Copy of every communication made by the AE
g the EPC/PMS
also to be given to Authority. The JAG/SG officials of the Authority handlin
contractor and AE
contracts should keep a watch on the correspondences made by EPC
contracts.
and take necessary actions to ensure compliance of the provisions of the
of designs by the
3. The EPC document envisages preparation and proof checking
the authority for
Contractor and review by the Authority Engineer (AE). For all works,
ctor shall lie with
review/approval of the document/drawing/design submitted by the contra
as laid down by the
the Authority Engineer to the extent permitted by the EPC contract or
checker regard ing
instructions given by the Authority. In order to guide the designer/ proof
Page 77 of 260
Authority's requirements and terms of contract, Design Basis Report or Preliminary
Design Report, as defined in the contract clarifying the codes/standards and design
criteria to be adopted, should invariably be prepared and approved by Authority to ensure
good progress of works and avoid later date conflicts.
4. The EPC agreement also envisages the Authority Engineer to advise to the contractor
regarding certain works requiring prior sanction of Commissioner of Railway Safety
(CRS). In view of Railway Board's letter No. 2022/Trans cell/Civil/CRS dated 21.06.2022
and 2022/CE-I/ACS-11/IRWM dated 30.09.2022, the works of subways, FOBs including
roof plaza, ROBs etc shall require sanction of Principal Chief Engineer (PCE).
Accordingly, the approval of relevant authorities shall be obtained as per the laid down
process. For all such works, the relevant design criteria shall also be got approved from
the design office of PCE at an appropriate stage and the General Arrangement Drawings
shall be approved by the SAG officer handling the contract.
5. Other than items requiring specific approval of Authority as per the EPC/PMS contracts,
approval of drawings/designs/documents or test checks of bills is not envisaged by the
Authority in cases where a PMS agency is nominated as Authority Engineer. Wherever a
Railway engineer is nominated as the Authority Engineer, the existing instructions for
drawing/design approval and test checks shall be applicable.
6. Whether the nominated AE is a PMS agency or a railway engineer, the JAG/SG officer
handling the EPC/PMS contracts shall carryout regular inspections of sites and contract
related drawings/designs/documents and submit monthly reports to CE/CPM handling the
contract. Such reports should be comprehensive and inter alia detail the inspections
carried out by them, quality of works at the site, progress of the works against contractual
milestones, compliance of contractual obligations by the EPC/PMS contractors, any other
important item coming to their notice etc. The CE/CPM handling the contracts shall also
carryout his own inspections and submit similar report every two months to his controlling
officer. Zonal Railways may modify the instructions in this para with approval of
PCE/CAO(C).
7. The Zonal Railways are also required to evolve quarterly audit system (departmental
and/or third party) for engineering, procurement and construction related items apart from
compliances ensured above. The audits/inspections shall be within the Authority's right to
inspect/audit the site/works/documents/progress as per the EPC/PMS contracts and
should be so implemented that the execution of EPC/PMS contracts is not adversely
Page 78 of 260
affected. The audit team should also refer a few randomly selected designs for check by
design office of PCE/CAO(C}/third party.
8. It should be ensured that the communications to the EPC/PMS contractors by Zonal
Railways are routed through the concerned JAG/SG officer or above handling the
contract except cases involving emergencies like safety of trains/passengers etc.
9. This is issued with approval of Board(MI}.
Copy to:
1. Advisor to MR, EDPG to MR, OSD to MR, EDPG to MOS(D), EDPG to MOS (J}
2. PSO/Sr PPS CRB & CEO, Member (Finance}, Member (Infra), Member (TRS),
Member (O&BD), Secy, DG(RHS), DG(RPF)
3. PCEs, CCMs, CEEs, CAO/Cs , CSTEs and DRMs, all zonal railways.
4. Vice Chairman, Rail Land Development Authority, DMRC Building, Ajmeri Gate, New
Delhi for adopting suitable system for the projects being handled by RLDA.
Page 79 of 260
'ifmr e {cfil <(GOVERNMENT OF INDIA)
~ '1'11~'-4 (MINISTRY OF RAILWAYS)
~il)t (RAILWAVBOARD)
Vice Chairman,
Rail Land Development Authority
The documents for Request for Proposal (RFP) and Standard Engineering, Procurement and
Construction (EPC) Agreement for Development/Redevelopment of Railway Stations, as approved by
Board (M/lnfi-a, M/Fin. & CRB&CEO) are attached herewith. The same will be uploaded on JR
website on Station Development page also. Zonal Railways may take further necessary action
accordingly.
£)~1.•ll,Y\
(Rakesh Choudhary)
Executive Director/SD&T
Railway Board
I. The Deputy Comptroller & Auditor General of India (Railways), Room No. 224, Rail
Bhawan, New Delhi.
Page 80 of 260
1:-ffH:f ~ -~·'$T~ Government of lodia
ii-!' lJ'.?l'Ti-!''lJ Ministi'}' of Railway-s 7~~- :,,,;
A za·d 'Ka
(i~cf ilfi Railway lioard)
Amrit M~hotsav
2. This ·doc;ument is applicable for sµperyi~!(m of _ any EPC c'O.ntt~cts. Th¢ .PMS. s,hall
be. considered at par wlth servfo.es other- than cqn.sultancy. Tenders shall be· callecf with
approval ofSAG -offi-cer. Level of tend~r :COf'T!m:lttee shal_l ~e SAG with acceptance by
.PHOD irrespective .of value .of tender. Project spb;iffc clauses an~ appendice-s wH.h
square parenthesis shall be inser~e~ by th'e tenc;!eri11g au(~Qtlt_y with releviuit information.
Por cha.nges in other clauses approv~I of PHOD ~lth conct1rrence· of -associate fin~ce
wlll be required.
. _·~ -----
. -, 'jLl-r-)1
¾r110 , _·~-. ~· S'·l--1,,
r~~~
cf, 1£fQlclcti R~-~1q;Atfc@ ~ ;(uft)~ ~
[Phone: 030.-44803: R.ly: 0 I 1-23383'379:MTNL]
e-mai'I address : [email protected]
Page 81 of 260
ln'ta .tf{cfil< Govenm•t of la"'8
� '1 ,11 el.q . Mhdltry of Railwayl
( � � Railway Board)
Su:- Gaette Notifleatloa for IDIDpelGa ia 'lie blJwy Act 1119'· DllpeuldM of
CRS Suctioa la cer1ala Item
Ref: (i) Gazette Notification No. S.0.2368(E) elated 24.05.2022
(iJ.) Railway Board's letter No. 20161CBDO/ORVO/O I dated 17 .09.20 I 9
(iii) Railway Boud's letter No. 2017/lnm/6133 dated 02.08.2018
I. Please find encloaod herewith a copy of the OucUe Notification No. S.0.2368(E) dated
24.05.2022, regarding exemption in •:rru •Ut,.,y Ad 1'19' - Dilpe1111tioll fJI CRS
Salldloll la certaia IINl1 (a) to (&).
2. In view of Dispensation of CRS Sanction provided in the above Gaeac Notification, the
allamite procedun: to be followed by l.onalRailways for ensuring safety is detailed below:
i. For items (11) Con.structlon, nlndlding. modl.fication and ltmlglhenlng ofjoot-oHT
brldgu and l"OtllHNl'-brldgu; (6) Condn,ctlon. rebuilding. nglrderlng and
brldgu. ot,,.,
strengtMning of minor brldgu; (c) /legirderlng and &tNngthening of all atrting
than >nlnor brldga; (d) Elimination of� lnel croutng; and
(e) Upgradatlon oflevtl cro.ulng, inchtdlng bwrlocklng Olll8lde station llml&r.-
. (A) The ■-:don to eueate ucl opea above mcndGoed works shall be accorded by
Genaal Manager of -Zonal Railway with· no further delepdon by �
Manager.
(B) For seeking sanction of GM. all neccsmy documents required shall be prepared
in the same formats as laid down in "The Railway Opc,nlng for Public Carriage
of Paaengen Rules, 2000".
(A) 2Skv ac charging of �on for Railway electrification work & Energisation of
any hip tansioo installation in this reprd lhall be done with the approval of
Elcctrical inlpector to Govt. of India (BIG) IS laid down In Indian Electricity Aa
2003.
(B) The sanction to open the section with electric tn1ction shall be accorded by
Ocncnl Manger of the Zonal Railway with no further delegation of power.
contd•• J-
Page 82 of 260
I -2-
(C) Joint impection report of the Elcc:lrified mion by Chief Eleclrical Diltn1'udon
. Engineer (CEDE), Chief Siau] P:riginer, (CSE), Chief Safety Officer (CSO) 111d
Territorial Head of the Dq,lrtmcnt {nlOD (F.ng.)} of 1.ooal Railway sblll be
made.
(D) For IOekina IIDCdon of OeoenJ Manaaer, all nee y documcntl requhed shall
be prepan,d in the 111110 formals a lai~ down in --Jbo Railway Opening for
Public Clrriaae of Passengers Rules, 2000•.
iii. For Worb relattld to Ded/cat,d FrwlghJ Corridor (IIMlt (g)J, Railway Board's letter
No. 201'711afn/W dated 02.08.2818 lhall be strictly followed. .
3. Zonal Railway aball tako .neceamy action for openina of item (a) to (I) above u per
ahemate procedure. Ocner11 M1111pr of Railway lball inspect the works before am and
sanction, u is beiq done by Commisliicner of Railway Safety (CRS}. Amcodmmt in Rule
and Manual will follow. .
Page 83 of 260
'-ITTa ffl'iJ'Tl Government of India
~ if 1(~11 Ministry of Railways 7~:
Azad
. .,;
(tint ~hf Railway Board) I Ka
Amrlt Mahotsav
Sub:- Gazette Notification for exemption in 'Tiu Rallway Act 1989'- Dispensation of
CRS Sanction in certain items
1.0 The alternate procedure to be followed to replace CRS sanction for the works mentioned in
the gazette notification at reference (i) above was issued by Railway Board vide letter Under
reference (iv) above.
2.0 References have been received from Zonal Railways to revise the alternate procedure. The
matter has been examined in detail in Board's office & in view of Dispensation of CRS
Sanction provided in the above Gazette Notification, Board (MTRS, MI, CEO & CRB) has
approved the revised alternative procedure to be followed by Zonal Railways for ensuring
safety is u detailed below:
2.1 For items (a) Construction, rebuilding, modification and strengthening offoot-over-
bridges and road-over-bridges; (b) Construction, rebuilding, regirdering and
strengthening of minor bridges; (c) Regirderlng and strengthening of all existing
bridges, other than minor bridges; (d) Elimination of manned level crossing; and (e)
Upgradation of non-lnterlocud level crossing & diversion of Roads at LCs. 'J:M_
competent authority to grant sanction to execute and open above mentioned works
shall be PCE of Zonal Railwqv, with no further delegation. For Upgradation of
interlocked Jevel crossing, including interlocking outside station limits, the competent
Page 84 of 260
I
I 2.2
authority to grant sanction to execute and open works shall be PCSTE of Zonal
Railway. with no further delegation.
2.3 For Worb related to Dedicated Freight Corridor {item (g)), Railway Board•• letter
No. 2017/lnfra/6/33 dated 02.08.2018 shall be strictly followed.
2.4 For seeking sanction, all necessary documents required shall be prepared in the same
fopnats as laid down in "The Railway Opening for Public Carriage of Passengers
Ruka,2000".
3.0 Zonal Railway may take necessary action for opening- of i~m (a) to (g) above as per above
alternate procedure. Amendments in Rule & Manuals will follow.
4.0 This supersedes Railway Board letter No. 2022/frans cell/Civil/CRS, dated 01.06.2022.
DA:asabove
~i
'}t1/1
"91t1I..
.)
)y.,J
'lr,,·)Y
(~JltR~
q;,if4,aq; Plast,ct>tftmffl~.~ il1t
[Phone: 030-44803: Rly: 011-23383379:MlNL]
e-mail address : [email protected]
The Chief Commissioner of Rahay Safety, Office Compound of DRM/NER, Ashok Marg,
Lucknow
Page 85 of 260
"'TT«f lllct;R Government of India
ttir lf?Tra'lf Ministry of Railways
,•~~.--
.71:'-
Azadr:'a
{ttiri lh{ Railway Board) Amrit Mahotsav
1. Ministry of Railways has decided to include definition of 'Foot Over Bridge' under
Para-417 and also decided to amend Item No. 'd' of Para-417 of Indian Railway
Works Manual, 2000 as Advance Correction Slip No. 11, shown as under:-
,
Foot Over Bridge (FOB) is an elevated structure ofany span and width over/across
the railway track/road, primarily used for pedestrian movement and is not directly
used by 'motor vehicles as defined in Motor Vehicle Act, 1988.
Item No. 'd' of Para-417:- The design for the foot-over-bridge should provide for
covering which should preferably be provided at the initial stage itself. The number
of floors envisaged and their usage should be clearly mentioned in the General
Arrangement Drawings of the FOB. The structural design should cater to the
intended usage ofthe FOB.
Page 86 of 260
I
1fmf ij <"'I< GOVERNMENT OF INDIA
~ +i~l\"14 MINISTRY OF RAILWAYS
(~ il1t RAILWAYBOARD)
No. 2021/St n. Dev.-1/0 8/18 New Delhi, dated: .03.10.20 22
The General Managers,
All Zonal Railways.
Vice Chairma n,
Rail Laod Develop ment Authorit y
2. Approval of .Plans:
2.2.1. Floor Plans shall be circulated among BOs by CPM/GS for taking inputs
from concerned Branch Officers in writing. If no inputs are received within
15 days or the Inputs received are agreeable to CPM/GS, the Floor Plans
shall be approved . by CPM/GS. In case there are differences of opinions,
the decision of DRM shall be final. BOs will be informed of the final
deci.sion taken. Floor Plans shall be approved by Division and HQ approval
will not be required.
2.3. After approval of Concept Plan/Master Plan at Division level, CE/Sp will
make a presentation to General Manager (GM) and Principal Head of
Departments (PHODs) and issue the minutes of presentation, with the
approval of GM, conveying such approval. Signatures of individual
PHODs/HODs wlll not be required.
~ t)~
Page 87 of 260
r
3 .1.
DRMs shall hold weekly meetings to review the progress of
station
develo pmen t works executed by any agency (Dlvlsion/Construc
tion/RLDA),
make all efforts to keep the progress of works as per sched
ule and shall
report the progress of stations in the MCDO submitted to Gener
al Manager.
3.2. For station development works executed by any unit (Divisi
on,
Construction or RLDA), DRMs may exercise the existing financ
ial delegation
for utility shifting or other enabling works llke providing right
of way by
constructing temporary accommodation or temporary
hiring of
accommodation for the staff to be relocated etc. The expenditure
for such
works may be charged to the sanctioned estimates of station
works. development
3.3. DRMs shall have full powers for granting traffic blocks for
station
development works executed by any agency (Division/Construction/RL
DA).
3.4. Traffic/power · blocks, signalling disconnections, caution order
required for station development works being executed by etc
CPM/GS,
Construction Organisation or RLDA shall be assisted by the concer
ned officers
and supeivisors of the Division.
3.5. During the construction phase, in cas.e there are disputes betwee
n the
parties regarding handing over and taking over of assets In conne
ction with
station development works, the matter should be referred to the
ORM. The
DRM, after considering the concerns of both sides, shall issues
written
instructions after which the responslblllty for further operat
ion and
maintenance shall Ile with the party so nominated by the ORM. Such
decision
should be communicated as expeditiously as possible but not later
than 10
days from the reference being made to the DRM.
4. Each Zonal Railway shall have a CE/SD who shall be the nodal
officer "for station
development and customer amenities works at the Zonal HQ. CE/SD
will report to
PCE or CPD/SD wherever CPD/SD Is posted. CE/SD shall be suppo
rted by one Dy
CE or XEN who l!l turn wlll be supported by office staff and/or SSEs.
The CE/SDs
and the supporting staff should normally not be shifted for three
years to ensure
sustained focus and desired outcomes.
Page 88 of 260
( 5
• New techno-economlc feaslblllty studies for station development works should, as
• far as possible, not be assigned to construction organization. Existing consultancy
tenders assigned to Construction Organisation should be finalised by Construction
Organisation and the consultancies may be novated to GS units of the Divisions
on case to case basis as decided by GM. Existing EPC contracts/tenders for
station development presently assigned to Construction Organisation shall
generally continue with Construction organisation.
6. Thl.s Issues with approval of Board(M/Infra, M/O&BD, M/F, CRB & CEO).
~:i,to• t..v
Rakesh ChOudhary
Executive Director( Station Dev & Transf.)
Railway Board
Mob.9717643650
Email: [email protected]
~~, ,
for Member Finance, Railway Board
Copy to:
1. Advisor to MR, EDPG to MR, OSD to MR, EDPG to MOS(D), EDPG to MOS
(J)
2. PSO/Sr PPS CRB & CEO, Member (Finance), Member (Ir:ifra), Member
(TRS), Member (O&BD), Secy, DG(RHS), DG(RPF)
3. PCEs, CCMs, CEEs, CAO/Cs , CSTEs and DRMs, all zonal railways.
Page 89 of 260
Page 90 of 260
\l'ml" ff(cfil( Government of India 7j:-s.
....
t~ Ministry of Railways Aza d I Ka
Amrit Mahotsav
(t~~ Ui Railway Board)
Sub: Adoption of CPWD Delhi Schedules of Rates- 2021 (DSR-Vol. I, DSR-Vol. II,
DSR-Horticulture & Landscaping), Analysis of Rates for DSR (AOR-Vol. I, AOR-
Vol. II) & CPWD Specification (Vol. I, Vol. II) and IRUSSOR-2021 on Indian
Railways.
Ref: Railway Board letter No. 2020/CE-I/USSOR/W&M/1 dated 05.07.2022
2. Board (MI and MF) have now decided to adopt CPWD Delhi Schedules of Rates
(DSR-2021) (DSR-Vol. I, DSR-Vol. II, DSR-Horticulture & Landscaping-2020),
Analysis of Rates for DSR (AOR-Vol. I, AOR-Vol. II)-2021 & CPWD Specification
(Vol. I, Vol. II) for execution of all civil engineering works related to Building work,
Road works and Horticulture works etc. (except Formation works, Bridge works and
P. Way works).
3. Board (MI and MF) have also decided to execute Bridges works, Formation works and
P.Way works with 'Indian Railways Unified Standard Schedule of Rates (IRUSSOR-
2021)'. Accordingly, Railway Board vide letter No. 2020/CE-I/USSOR/W&M/l,
dated 05.07.2022 has issued IRUSSOR-2021. Indian Railway Unified Standard
Specification-2021 (IRUSS-2021) has also been finalized and uploaded on
CE-Directorate web page.
4. CPWD DSR is published from CPWD Headquarters at New Delhi and applicable all over
India with suitable factor called 'Building Cost Index'. The 'Building Cost Index' is
worked out as per Annexure-IV of 'PLINTH AREA RATES-2021 based on concurrent
rates of the geographical area for various components. IREPS has the provision of
Five Numbers of 'BCI' for each zone.
5. As per prevalent system of CPWD, 'Building Cost Index' is derived by all Zonal heads
of CPWD (Chief Engineer or ADG) for different places under their jurisdiction.
6. The CPWD DSR- (Vol. I, Vol. II, Horticulture & Landscaping) has been uploaded on
Civil Engineering Directorate webpage of Ministry of Railways and link is also available
in IREPS system.
7. The head of Civil Engineering Department of the organization shall adopt the Building
Cost Index of respective zone of CPWD or work out the same duly updating the rates in
Page 91 of 260
, INTH AREA RATES-2021 '), with Y'?
IV of PL '
Building Cost Index (Annexure-
concurrence of Associate Finance.
. . . . D artment in !REPS has been '
The Department Admin of HQ of C1v1l Engmeermg e: h d of Civil Engineering
8. authorized to update 'Building Cost Index' as approved y ea
Department, on !REPS time to time.
. . re available on
The CPWD DSRs , AORs &. . Specifications a y change or new
9.
http://cpwd.gov.in/Documents/cpwd_pubhcat1on.aspx. However an . 0 10 d. 30
guideline related to CPWD DSRs, AORs & Specifications shall be effe_ctive ~ '.
. . f R . on Civil Engmeermg
1
Railways only when uploaded by Mm1stry o a1 ways
Directorate webpage of Ministry of Railways. . b
SORs, AORs & Specification has been uploaded on Railway Board's website. It may e
accessed through the following path:
www.indianrailways.gov. in/railwayboard> > "About Indian Railways">> "Railway
Board Directorates" >> "Civil Engineering" >> "4.Schedule of Rates, AOR and
Specifications">> Schedule of Rates, Analysis of Rates and Speci$cations-2021 >> JR
& CPWD- SOR, AOR & Specification
Railways are advised to finalize 'Building Cost Index' as per latest Board's instructions
10.
(at least once every 6 months) and adopt CPWD DSR 2021 & CPWD Specifications for
execution of all civil engineering works related to Building work, Road works and
Horticulture works etc. (except Formation works, Bridge works and P. Way works) and
follow 'Indian Railways Unified Standard Schedule of Rates (IRUSSOR-2021)' for
Bridges works, Formation works and P.Way works on Indian Railways.
Zonal Railways are required to adopt CPWD DSR-2021 & IRUSSOR-2021 not later than
11.
15.11.2022. Board has also decided to discontinue the use of directions of
IRUSSOR-2010, IRUSSOR-2019 or CPWD-2019 from 15.11.2022 onward. Board has
also decided that in future, any updation by CPWD in DSR, Analysis of Rates &
Specification, will be automatically adopted by IR through !REPS without any further
approval. While finalizing the tender and preparation of DPR, LARs of successfully
completed works may be considered. {}
~r171 '1',z
(~~l--11-{~3·
cf>l441ctcf> Pl~S<lcf>/~fqct ~.('5fi)ittm mt
[Phone: 030-44803: Rly: 011-23383379:MTNL]
e-mail address : [email protected]
No. 2022/CE-I/CT/8/CPWDDSR New Delhi, Dated 13.10.2022
Page 92 of 260
V )
'0,
LIST FOR DISTRIBUTION (Letter No. 2022/CE-I/CT/8/CPWDDSR, dated 13.10.2022)
I.
General Managers, All Indian Railways & Production Units
2. General Manager (Con), N.F. Railway, Guwahati
3. General Manager /CORE, Allahabad.
Chief Administrative Officers (Con), All Indian Railways (Except N.F. Railway)
4.
5. Principal Chief Engineers, All Indian Railways
(A)
I. CAO, COFMOW, Tilak Bridge, New Delhi
2. Principal CAO, Diesel Loco Modernization Works, Patiala (Punjab)
CAO (Workshop Projects), Chamber Bhawan, Judge's Court Road, Anta Ghat, Patna-800001, Bihar
3.
(8)
I. Director General, ROSO, Manak Nagar, Lucknow
2. Director General, NAIR, Vadodara
3. Director, IRICEN, Pune-411 001 (Maharashtra)
4.
Director, IRIEEN, PB No.-233, Nasik Road-422101 (Maharashtra)
Director, IRIS ET, Taa Naka Road, Lalla Guda, Secunderabad-500017
5.
6.
Director, IRIMEE, Jamalpur Distt-Jamalpur, PIN-8112 I4 (Bihar).
Director, IRITM, Sarswati Residential Estate, IRITM Campus, Manak Nagar, Lucknow
7.
(C) MD, CONCOR, Concor Bhawan, C-3, Mathura Road, Opp. Apollo Hospital, New Delhi- 110076.
I.
IRCON International Limited, C-4, District Centre, Saket, New Delhi- I 10017
2.
MD, RITES Ltd., RITES Bhawan, Plot No. I, Sector-29, Gurgaon.
3.
4. CMD, RVNL, August Kranti Bhawan,Plot No.25, Ist Floor, Bhikaji Cama Place, New Delhi.
5. MD, MRVC Ltd., Churchgate Station Bldg, Mumbai- 400020
6. CMD, KONKAN Railway Corporation Ltd, Rail Bhawan, New Delhi-I I 0001.
7. MD, DFCCIL, 5th Floor, Pragati Maidan Metro Station Building Complex, New Delhi-I 10001
8. MD, RLDA, Near Safdarjung Railway Station, Moti Bagh, Phase-I, New Delhi- 110021
9. MD, CRIS, Chanakyapur, New Delhi.
10. CMD, Rai!Tel Corporation of India Ltd. Plot No. I43, Institutional Area, Sector-44, Gurgaon - 122003.
11. CME, !ROAF, 12th Floor, Core-I, Scope Minar, Distt. Centre, Laxmi Nagar, Delhi-110092
12. Managing Director, IRFC Limited, UG Floor, EastTower, NBCC Place, Bhisham Pitamah Marg,
LodhiRoad, Pragati Vihar, New Delhi.
13. CMD, IRCTC Ltd., 8-148, I Ith Floor, Statesman House, Barakhamba Road, New Delhi I 10001
14. CMD, Braithwaite & Co. limited, 5 Hide Road Kolkata 700043.
Copy to:
w I. General Secretary, IRCA, ORM Office, New Delhi.
2. General Secretary, AIRF, Rail Bhawan, New Delhi
3. General Secretary, NFIR, Rail Bhawan, New Delhi
4. General Secretary, IRPOF, Rail Bhawan, New Delhi
5. General Secretary, FROA, Rail Bhawan, New Delhi
6. General Secretary, AIRPA, Rail Bhawan, New Delhi
7. General Secretary, AISC & STREA, Rail Bhawan, New Delhi
8. The Secretary, RBSS, Group (A) Offices Association, Rail Bhawan
9. The Secretary, RBSS, Group (B) Offices Association, Rail Bhawan
10. General Secretary, RBSSS Association, Rail Bhawan
11. The Secretary, RBMSA, Rail Bhawan
12. The Secretary, Railway, Group (D) Employees Association, Rail Bhawan
(B) Concerned PSO for kind information of Chairman cum CEO, M/Infra, MIT&RS M/O&BD M/Finance
I.
Railway Board ' '
2. Adv./MR, EDPG/MR, OSD/MR, OSR(Co-ord)/MR
3. Chief Vigilance Officers, All Indian Railways.
4. DG(RHS), DG(RPF), AM(CE), AM(Works), AM(B), AM(Elec.), AM(RS), AM(ME), AM/Tele,
AM/C&IS, AM/Sig., AM(Plg.), PED(B&S), PED(Vigilance), PEDCE(P), EDCE(G), EDTK(M&MC),
EDCE(B&S), EDF(X)-1, EDF(X)-11, ED(Works), EDW(Plg.), ED/Project(Mon.), ED(L&A), ED(PSU),
EDVE, ED(Safety), ED(Sig. Dev.), ED( Tele), EDRS(G), EDRE, EDEE(G), EDFE, EDE(N),
E~~Accounts), . ED/T&MPP,. EDME(Chg.), EDME(Frt.), ED/Pig., JS(conf), JS(P), JS(G), JS(D),
V1g1lance-III, V1g(Conf) of Railway Board.
Page 93 of 260
Page 94 of 260
Page 95 of 260
Page 96 of 260
irrnf ij <cfil < GOVERNMENT OF INDIA
~ '1-:ii1~<4 MINISTRY OF RAILWAYS
(m- ~ RAILWAY BOARD)
Vice Chairman,
Rail Land Development Authority
2. Approval of Plans:
2.2.1. Floor Plans shall be circulated among BOs by CPM/GS for taking inputs
from concerned Branch Officers in writing. If no inputs are received within
15 days or the inputs received are agreeable to CPM/GS, the Floor Plans
shall be approved by CPM/GS. In case there are differences of opinions,
the decision of DRM shall be final. BOs will be informed of the final
decision taken. Floor Plans shall be approved by Division and HQ approval
will not be required.
2.3. After approval of Concept Plan/Master Plan at Division level, CE/SD will
make a presentation to General Manager (GM) and Principal Head of
Departments (PHODs) and issue the minutes of presentation, with the
approval of GM, conveying such approval. Signatures of individual
PHODs/HODs will not be required.
Page 97 of 260
(R t>~
2.4. After app~oval of concept/master plan at Zonal HQ level, CE/SD shall
make presentation to SD Directorate of Railway Board for finalisation of draft
concept. plan/conceptua l architectural plans with 3-D views submitted under
Key Dehverable(KD )-3 stage and subsequently another presentation on final
m~ster plan submitted under KD-4 stage of the model document issued by
Railway Board for appointment of technical consultants.
3. Role of Divisions:
3.1. DRMs shall hold weekly meetings to review the progress of station
development works executed by any agency (Division/Construction/RLDA),
make all efforts to keep the progress of works as per schedule and shall
report the progress of stations in the MCDO submitted to General Manager.
3.3. DRMs shall have full powers for granting traffic blocks for station
development works executed by any agency (Division/Construction/RLDA).
3.5. During the construction phase, in case there are disputes between the
parties regarding handing over and taking over of assets in connection with
station development works, the matter should be referred to the DRM. The
DRM, after considering the concerns of both sides, shall issues written
instructions after which the responsibility for further operation and
maintenance shall lie with the party so nominated by the DRM. Such decision
should be communicated as expeditiously as possible but not later than 10
days from the reference being made to the DRM.
3.6. Separate instructions shall be issued for the post commissioning stage
of the redeveloped station i.e. post completion operation and maintenance of
the station through facility management agencies. Till such instructions are
issued, existing practice of operation and maintenance by the Division shall
be followed.
4. Each Zonal Railway shall have a CE/SD who shall be the nodal officer_ for station
development and customer amenities works at the Zonal HQ. CE/SD will report to
PCE or CPD/SD wherever CPD/SD is posted. CE/SD shall be supported by one Dy
CE or XEN who in turn will be supported by office _staff and/or SSEs. The CE/SDs
and the supporting staff should normally not be shifted for three years to ensure
sustained focus and desired outcomes.
Page 98 of 260
I
5. New techno-economic feasibility studies for station development works should, as
far as possible, not be assigned to construction organization. Existing consultancy
tenders assigned to Construction Organisation should be finalised by Construction
Organisation and the consultancies may be novated to GS units of the Divisions
on case to case basis as decided by GM. Existing EPC contracts/tenders for
station development presently assigned to Construction Organisation shall
generally continue with Construction organisation.
6. This issues with approval of Board(M/lnfra, M/O&BD, M/F, CRB & CEO).
~1,to, t-v
Rakesh Choudhary
Executive Director( Station Dev & Transf.)
Railway Board
Mob. 9717643650
Email: [email protected]. in
~~v
for Member Finance, Railway Board
Copy to:
1. Advisor to MR, EDPG to MR, OSD to MR, EDPG to MOS(D), EDPG to MOS
(J)
2. PSO/Sr PPS CRB & CEO, Member (Finance), Member (Infra), Member
(TRS), Member (O&BD), Secy, DG(RHS), DG(RPF)
3. PCEs, CCMs, CEEs, CAO/Cs , CSTEs and DRMs, all zonal railways .
Page 99 of 260
Page 100 of 260
File No. No.2022/SD-II/22/08/06/Misc. (Computer No. 3404385)
1245326/2022/O/o SO2/SD-II
of Railways
Gov emment of India-Ministry
Rescarch Designs & Standards Organis5ation
cOMMITTEE'S RECOMMENDATIONS:
Committee recommended that for major and important stations where it is
not practicable to maintain the track to required standards, construction of
washable aprons with proper design may be taken up on case to case basis.
In view of above, all Zonal railways are requested to take necessary action as per
Railway Board's orders
DA: As above
(A.M. Rizvi)
Executive Director/Track-lll
5
Page 101 of 260
Generated from eOffice by RAJENDER SINGH, Insp/CE-II(RS), INSPECTOR/CE-II, Civil Engineering Dte on 29/09/2022 04:38 pm
TrsF
Gn-f,F{tqr
cIT{tT
ia
grirT{ Governmentof India
qeraq MinistrT of Railways TrwF
AZAd! 66
GrTdE6iffiq
_
(tad std Railway Board) Amrit Mahotsav
Sub:- Indian Railway Code for Engineering Department - Advance Correction Stip No.59.
Ministry of Railways has decided to amend Para 1109, Para 1110, Para llll &
Para I ll2
of Indian Railway Code for Engineering Department, Fourth Re-print 2012 as shown
in enclosed Advance Correction Slip No. 59.
This issues with concurrence of the Finance Directorate of the Ministry of Railways.
Encl: As above.
. r.>
h29' 4nic
)
V\ri
2c'1'vw Page 103 of 260
Advance Correction Stip (ACS) No. 59 to Indian Railway Code for Engineering
Department Revised Edition-1982 and Fourth Re-print 2012
Para No. 1109, Para No. 1110, Para No. 1111 & Para No. 1112 should be amended as under:
Material Modification in a work or a scheme as sanctioned are an exception which should not be
ordinarily resorted to. However, where it becomes necessary it should be permitted or
undertaken only with the prior approval of the authority as per prevailing delegation of powers.
PARA 1110:-
a. Modifications that arise due to issue of policy by Board for change in specification or
standards of
i. Construction
ii. Interlocking
iii. Electrification
iv. Traction
v. SOD requirement
b. Minor Modification during execution of the work required during sanctioned yard work for
completing the work.
c. Modifications resulting out of statutory/ regulatory requirements
d. Modifications to bring in economy in construction and timely delivery of project.
e. Any work essentially required for completing the project.
PARA 1111:-
Any work which is independent work per se, as a new service, but is essentially required to be
done with existing work will be treated as Material Modification to the existing work provided it
is in direct link with the existing work. The sanction of same will be as per delegation of powers
issued by Board from time to time.
Note: As a general rule any additional scope of work should be got sanctioned separately and
should not be taken up as Material Modification of an existing work.
PARA lll2z-
Any modification other than a Material Modification in the scheme or project sanctioned by
Zonal Railway/ Railway Board or a higher authority may be sanctioned by the competent
authority provided that the amount of additional expenditure if any necessitated by such
modification does not cause an excess beyond his powers of sanction.
**!F**
Vice Chairma n ,
Rail Land Developm ent Authority
Format for Detailed Project Reports (DPRs) for station developm ent/
redevelo pment/ major upgradat ion projects is attached herewith as
Annexur e-1. The annexed format is indicative. For identified stations, the
DPRs may be sent to Railway Board for sanction of works.
The above referred format is only for the submissi ons being made to
the Railway Board for sanction of itemized works under the umbrella
works. The DPR's being uploaded as part of tenders shall be customized as
per needs by the authority inviting the tenders.
~ .\ . Lll--
Rakesh Choudha ry
Executive Director(Station Dev & Transf.)
·Railway Board
Mob.971 7643650
Email: [email protected]
1. Executiv e Summary
a. Purpose and objective of the report
b. Structure of the report
c. Overview of the project
d. Heritage context, Status and any other importanc e of station/ structures
and surroundi ng areas
e. Architectu ral Theme: Brief on the evolution of the design inspiratio n and
connectio n with the local context, art and culture, etc.
2. Introduc tion and site context
a. Existing site features - existing structures , utilities, trees, religious
structures , and important structures .
b. Existing site photograp hs and photograp hs of site visits/ Consultat ions
held.
c. Surveys reports and Assessmen ts: Engineerin g surveys, Existing utility
mapping, building condition survey, Inventory of Structures of
Importanc e, Study of sensitive structures , Traffic Survey Report,
Passenger Survey Report, Geotechni cal Investigati on report, Land Due
Diligence Report, Infrastruc ture Developm ent Report, Railway Data and
Requirem ents report, Byelaws and Master Plan report, Site analysis map
and report, Passenger Forecast Report. (Executive Summary shall be
included in main report and actual reports may be kept in Annexure s on
need basis for tendering purpose).
3. Three-Di mensiona l Views of the station
a. 3-D Architectu ral View
b. Bird's Eye View (It is preferable to have the existing aerial view and
the new developme nt from same angle(s) to understan d the scope and
scale of new developme nts)
4. Traffic Survey Analysis
a. Review of Existing Traffic Plan: Summary of a traffic study conducted -
Data collection and analysis
b. Inferences from all Investigati on Reports regarding bottleneck s and
problem areas
c. Demand forecast - Future modal share and requireme nts as per PHT
Calculatio ns
d. Planning of movemen ts within the station - segregatio n of departing and
arriving passenger s.
e. Drop-off and Drop-pick -up Planning
f. Parking- demand and other related ~~cilities. .
g. Multi-mod al integratio n and walkabilit y strategies
17. Statu tory cleara nce / Licen ses etc/Ap prova ls/ NOC/ Stake holde r
Consu ltatio ns
a. Local author ities, other govt. depart ments , Traffic police, Railwa
ys,
Airpo rts author ities, Enviro nment , Heritage, etc.
b. List of stakeh older consu ltation and record s (Impo rtant letters , MOM
etc.)
3 No. of Platforms -
(High
Level/ Medium/ Rail
Level)
7 Annual Passengers-
Departure (Nos)
8 Annual Passengers-
Arrival (Nos)
9 Annual Unreserved
Passengers (Non-
suburban)-D eparture
(Nos)
10 Annual Unreserved
Passengers (Non-
suburban)-A rrival (Nos)
13 Annual Reserved AC
passengers- Departure
(Nos)
14 Annual Reserved AC
passengers-A rrival (Nos)
15 Annual Number of
Visitors to the Station
(Nos)
16 Peak Hour Traffic (PHT)
17 Type of Modes of
Transportat ion at
Station like Bus-Stop,
Metro-Statio n, Local
Taxi etc
18 No. of Lifts
19 Access Controls
20 No. of Escalators
21 No. of Travellators
CPM/CE
(Signature)
*****
Please refer to the Northern Railway's letter as mentioned in (ii) above thereby
forwarding a draft MOU to be signed among Northern Railway, National Highway Logistic
Management Limited (NHLML) and RLDA. The subject matter has been examined in
Railway Board and following has been decided by the competent authority: -
1. Kashi Railway Station, its circul ating area, road approaches and Rail cum Road
Bridge across river Ganga along with its connectivity with Railway Station may be
developed by Northern Railway at its own cost.
1
1. Commercial development may be explored by Northern Railway/ RLDA at a later
stage.
iii. Other Road network and Inter State Bus Terminus (ISBT) may be developed by
National Highway Logistic Management Limited (NHLML) and/or by State
Government separately at their own cost. Suitable proposal , if any , in this regard
may be submitted to Railway Board for approval.
In view of the above and Hon'ble pM,s vision of Gati Shakti for
creation of infraqtructure in the country, it has been decided to start
GSUs in all the remaining divisions of IR.- The organizational structure of
the GSUs will be as follows.
1.2 If divisions are having more than two ADRMs, the post of one
ADRM will be re-designated as CpM/Gati Shakti of that division.
1.3 In case there are two or less ADRMs in the division, CpM/GS
will be posted by making suitable adjustment in the cadre in
accordance with the post codes mentioned in Annexure .A, (at
present) .to. fast track the execution of infrastructure works.
However, in future, these post codes may be changed, if required
by the GM.
0/* Cd,,A
Page 122 of 260
_-...-.-
that of CPMi GS shall be charged to the projects.
1.6 GM's in consultation with PCOM may decide about the traffic
officer to be associated with CPM/GS. In case, a need is felt to
augment the traffic establishment of the division, separate
JA6/SG officers may be posted under the administrative control
of CPM/GS.
1 TSr.DFMoftheDivisionwillbetheassociatiFinancefortheGati
ShaktiUnitandestablishmentexpenditurewillcontinuetobe
charged to Revenue.
3.1 Gati Shakti Unit of division can use pSSA (project Supervisors
Services Agencies) and pMS as per the need of thl pro.leci.
3.2 Gati Shakti unit of Division can hire retired railway supervisors
below the age of 65 years with the approval of DRMs *ithin th.
4.0 Gati Shakti Unit will monitor approvals of all Plans, L-Sections,
ESPs, SIPs, LOPs, GADs, Yard plans, Blocks and PNIs/NIs of all the
works executed by the GSU.
6.0 Vehicles for field officers and supervisors shall be provided within the
overall provisions in the estimate, to facilitate faster execution and
supervision of works.
g.o GMs will nominate one sAG/ HAG Officer as zonal co-coordinator for
the divisional Gati Shakti Units in respective zones'
g.0 The works to be executed by Gati Shakti units of Divisions are given
in Annexure tB'.
10.0 This issues with the approval of Board (M/lnfra, M/TRS, M/O&BD'
MF and CRB&CEO).
L
,.t--
(Mohit
Director/Gati Shakti (Civil) UI
RailwaY Board
l. Advisorto MR, EDPG to MR, OSD to MR, EDPG to MOS(D), EDPG to MOS(J)
2. PSO/ Sr PPS CRB, Member (Finance), Member (lnfra), Member (TRS), Member
(O&BD). Secy, DG (RHS). DG (RPF)
3. Alt AMs, Principal Executive Director & Executive Directors of Railway Board
L
1:1
(Mohit Kumarf'i.t.D-
Director/Gati Shakti (Civilf UI
Railway Board
R"ihr ry Post Codc Post COdC CE Dt-Ilt & Post Cod€ Post Code Remarks regarding Electrical I X\t
SO/ Fin
l)ivision cPM/CS SG/JAG (eich) Sigrrlling Electricrl
SC/JAG SG/ JAG
I CR BSL 03C R,lP0 l.l 03cR5P034 I l0cR5P006 04cR5P006 2180
2 CR CS'IM 03RC4P002 03cR5P035 I l0cR.5P0l6 04cR5P004 2016
3 CR NCP 03cR4P0 t6 03cR5 Pol6 t0cR5P0 t7 04cR5P027 22t7
4 CR PUNE t 0cR4P006 0l Rc5 P03 7 I t0('R5 P0 | 5 04CR5P02 r Sr. DF.E/lRI) rvill ltxrk afbr t052
thc rvork ol'(ialiShrkti
5 CR SUR 05MC4P006 0icR5P038 I l0cR5P0 t9 04cR5P034 t608
6 ER ASN 048R4P002 03ER5P049 I l0ER5P0 t I 04ER5P0 t 7 2123
7 ER HWH 03ER4P0 t0 038R5 P050 I l0uR5P008 04ER5P004 2223
8 I'R MI,DT IOER.IPO()8 03ER5P05l I t 0ER5 P0 l4 048R5 P0 | 9 1207
9 ER SDAH 03ER4P006 0l ER5 P052 I roER5P0ll 04F]R5P027 1775
t0 ECR DDU 03EC4P020 03EC5P060 I t 0EC5P00 t 04EC5P0 t2 138 r
22 NR I]MB 04RC4P002 03NR5 P084 I l0NR5P027 04NR5P005 Sr. DEE/TRD will look after 22t6
the work ofGatishakti
23 NCR AGC Available l l0NC5P0l7 04RE5P005 1418
NCR J TIS t0NC4P005 03NC5P039 I loNC5P0l3 04RE5P0l0 24t',1
25 NCR PRYJ 04RE4P003 03NC5P040 I l0NC5P0t0 04RE5 P002 2606
26 NER I]SB 04c04P006 03NE5P034 I t 0NE5P006 04Ntr5P007 1638
2'1 NER IZN - 03NE4P008 03N85P035 I l0NE5ml I 0,lN E5P006 l0t8
28 NER I,JN 04NW4P007 03NE5P036 I i0NIt5P003 04N85P008 1393
29 NFR APDJ t 0NIt4P003 03NF5P06E t0c N5P006 0,1NF5P001 Sr. DEE/TRD will look after the It44
Page 127 of 260
hzL-
Poit Codc CI DFll & Post Code Posl Code Remarks regarding Electrical r Klt
SN R{il*rl Post Code SO/ Fin
Division SG/JAG (erch) Sign.lling lllectricd
cPM/CS SG/ JAG
SG/JAG
work ofGati Shakti
03sc5P049 I I 0sc5 P0l3 04sc5P026 Sr. DEEffRD will look after the 7'73
45 SCR GNT IOSC4POO5
work ofcali Shaldi
03sc4P0 03sc5P050 l0sc5P0l5 04sc5P023 Sr. DEE/TRD will look after the 2233
46 SCR GTL t5 I
work of Gati Shakti
"179
4'7 SCR HYB 04wc4P007 03sc5P047 I tosc5P008 04sc5P00 |
03sc4P020 03sc5P052 I l0sc5P002 04sc6P007 Sr. DEE/TRD will look after the 1068
18 SCR NED
work ofGati Shakti
03sc5P05l losc5P0l7 04sc5P003 2406
49 SCR SC 03 sc4 P005 I
03sE4P0l5 03sE5P033 t0sE5P003 04sE5P02l Sr. D[]E/IRD will look after thc 1464
50 SER ADRA I
work ofGati Shakti
03sE5P034 r0sE5P008 04sE5P003 2227
5l SER CKP 03sE4P0l2 1
(y
03sE5P035 I t0sE5P0l2 04s85 P0 l2 2224
52 SER KGP 04sE4P00l
Page 128 of 260
DFM & Post Code Remarks regarding Electrical
'rK\r
SN R,ilsr! Post Code Post Code CE
SO/ l'in
Post Code
Division SG/JAG (esch) Signrtling 0lectrical
CPM/GS
SG/JAG SG/ JAG
SER RNC l0sE4P006 03sE5P036 I l0sE5P0l4 04sE5P022 Sr. DEE/TRD will look afte. the 164
53
work ofGati Shakti
BSP Available I t0RC5P0l3 04RC5P008 2t'13
54 SECR
l0RC4P004 03RC5P029 10RC5 P0l6 04RC5P015 1850
55 SECR NGP I
64 WR RJT 03wR4P0l3 03wR5P049 I t0wR5P020 JAOTCOREOO6 Sr. DEE/TRD will look after the 6'10
work ofGati Shakti
65 WR R'IM 04wR4P003 03wR5P050 I l0wR5P0l7 04wR5P020 t59t
BPL 03wc4P007 03wc5P025 l0wc5P008 04wc5P0l0 2051
66 WCR I
Note:
post codes, within the Zonal
l. Zonal Railway with the personal approval of GM may decide to replace/post officers of different disciplines with different
Railways.
2. One ofthe Traffic Oflicer of Division may be designated to look after duties ofGSU in addition to their own work.
lt!.--
t_/"-- 2*r_
v---
Note: GM may however decide the executing agency of the works based
on urgency, need and peculiarity of the individual project for faster
.".crtio., and delivery of the project without affecting the targets fixed for
the current year.
ft1,*- Mns
In terms of Board's letter of even number dated 22.1 1.2021, the documents for
Request for Proposal (RFP) and Standard Engineering, Procurement and Construction (EPC)
Agreement for Development/Redevelopment of Railway Stations were issued.
2. One of the Zonal Railways has asked for a clarification in reference to Clause No.
2.2.2.1,Subclause 2) of Standard RFP for Development/Redevelopment of Railway
Stations on EPC mode (Vol.-1 - Instruction to Bidders) whether the "Eligible
Projects" should satisfy any one or both of the sub criteria viz. (i) Passenger
terminals; (ii) Social and Commercial infrastructure.
It is apparent from the above document and clarified here also that any project meeting
the requirement of Passenger terminals or Social and Commercial infrastructure as per
the above referred RFP Document issued by Railway Board on 22.11.2021 will be
considered as "Eligible Project" subject to other provisions of the RFP document.
3. This disposes of the ECoR's letter No. CE/C/II/BBS Stn.Dev/41 dated 17.06.2022.
Or,.,.~1\--
(Rakesh Choudhary)
Executive Director/SD&T
, Railway Board
Copy to:-
The Vice Chairman, Rail Land Development Authority, New Delhi
and
Sub: Authorization for Minor modifications in Request for Proposal (RFP)
for
Standard Engineering, Procurement and Construction (EPC) Agreement
Development/Redevelopment of Railway Stations -reg.
In terms of Board's letter of even number dated 22.11.2021, the documents for Request
for Proposal (RFP) and Standard Engineering, Procurement and Construction (EPC) Agreement
for Development/Redevelopment of Railway Stations were issued with the approval of Board
(MI. MF and CRB&CEO).
Board (MI, MF and CRB& CEO) has now decided to authorise zonal railways to make
minor modifications in the documents of RFP and EPC Agreement for
development/redevelopment of railway stations including modifications in financial and
technical eligibility criteria, with concurrence of associate finance and approval of General
Manager.
3. This disposes of the NWR's letter No. NWR/HQ/S&C444283903 dated 23.05.2022.
4. This issues with the concurrence of Finance Directorate of the Ministry of Railways.
(Ohm Meher)
Director/Station Development
Railway Board
2022/Stn.Dev.-I/08/24/EPC New Delhi, dated: -06-2022
Copy to:1. PFAs, all zonal railways.
2. The Principal Director of Audit, all zonal railways.
3. Dy.Comptroller and Auditor General of India (Railways), Room No.224, Rail Bhavan.
New Delhi.
03-8-2022
for Member Finance, Railway Board
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
(RAILWAY BOARD)
5. The powers already delegated to other officers under CAO/C will remain
unchanged.
2
5 (B)(i) Consutancy CAO/C Authority:
1. Item No.30(a) of GM's delegation. Bd's
Full powers
(i)Consultancy works for other than property Letter No. F(X)II- 2016/PW/ 3 dt.14.09.2016
development schemes from outside bodies 2. Railway Board Letter no F(X)-
including PPP projects II/2015/PW/7 dated 12.06.2017
3. 2017/Trans/01/Policy dtd 18.10.2017
1
Kindly read this annexure alongwith letter no. 2022/FX()/PW1 dated: 10/05/2022 Page 167 of 260
473/476
2018/CE-I/CT/17
1155471/2022/F(X)II
P
474/476
2018/CE-I/CT/17
1155471/2022/F(X)II
43 (ii)
To sanction expenditureon testing CAO/C Authority
charges of steel,
concrete cubes, ballast, Full power 1.From reputed institutes Like IIT/NIT/
4
Kindly read this annexure alongwith letter no.
2022/FX()/PW1 dated: 10/05/2022 Page 170 of 260
476/476
2018/CE-I/CT/17
1155471/2022/F(X)II
soil, drinking water etc.from Govt. Shriram Institute for Industrial Research/
Institutions/ Govt. approved laboratories MSME etc
2. Rates, Finance concurrence required For
cases in excess of RS
25000/
Note:
1. Testing of the materials shall be caried out from Engineering insttute like IIT's, NITS, National Test House, or any other NABL (National Accreditation
Board for Testing and Calibration Laboratories) accredited Laboratories.
2. In case of institutions of National repute like IT, NIT, NTH etc. - Advance payment can be made if demanded.
o 111
EDFN
To
As per list attached
Railway Board vide letter of even number dated 08.02.2021 had fixed the rate of interest
as l0o/o on 'Advances to Contractors' in terms of Para 1264 of Indian Railways Code for
Engineering Department for tenders to be opened in the Financial Year 2021-22.
2. Board (MI & MF) have decided that the rate of interest shall be RBI Bank Rate + 57o
(five percent) simple interest for the tenders to be opened in the Financial Year 2022-23
onwards.
\ \3 21-
(q6q
t,rffift?qrtlfrftniiffffitrffi)
ls++S
[Phone : Rly: 030-45536, MTNL:Oll-478455361
{e-mail address: pankaj.tyagi@ gov.in}
w
(ii) Dy. Comptroller and Auditor General of India (Railways), Room No.224, Rail Bhawan,
New Delhi.
forMember F'inance
LIST FORDISTRIBUTION
(A)
l. CAO, COFMOW, Tilak Bridge, New Delhi.
2. Principal CAO, Diesel Loco ModernizationWorks, Patiala (Punjab).
3. CAO (Workshop Projects), Chamber Bhawan, Judge's Court Road, Anta Ghat, Ftana-800001, Bihar,
(B)
(c)
l. MD, CONCO& Concor Bhawan, C-3, Mathura Road, Opp. Apollo Hospital, New Delhi- 10076.
2. IRCON International Limited, c-4, District cente, Saket, New Delhi- 110017
3. MD, RITES Ltd., RITES Bhawan, Plot No.1, Sector-29, Gurgaon.
4. Cl6, RVNL, August Kranti Bhawan,Plot No.25, l" Floor, Bhikaji Cama Place, New Delhi.
5. MD, IVIRVC Ltd., Churchgate Station Bldg, Mumbai- 400020
6. CMD, KONKAN Railway Corporation Ltd, Rail Bhawan, New Delhi-I10001'
7. MD, DFCCIL, 5h Floor, Pragati Maidan Metro Station Building Complex, New Delhi-l10001.
8. MD, RLDA, Near Safdarjung Railway Station, Moti Bagh, Phase-I, New Delhi- I10021
9. MD, CRIS, ChanakyaPur, New Delhi.
10. CUb, Raitfel Corporation of India Ltd. Plot No. 143, Institutional Area, Sector-44, Gwgaon-22003
I t. Managing Director, IRFC Limited, UG Floor, East Tower, NBCC Place, Bhism Pitamah Marg, Lodhi
Road. Pragati Vihar, New Delhi.
12. cME, IROAF, l2th Floor, core-I, Scope Minar, Distt. centre, Laxmi Nagar, Delhi- l]909?.
13. CMD, IRCTC Ltd., B-148, 116 Floor, Staesman House, Barakhamba Road, New Delhi-l10001'
14. CMD, Braithwaite & Co. limited, 5 Hide RoadKolkata-700043.
CopY to:
(A)
(B)
Concerned PSO for kind information of Chairman cum CEO, M/Infra, lvI/Tr.&RS,
MlFinance,
l.
N4/O&BD, RailwaY Board.
2. Chief Vigilance Offtcers, All Indian Railways.
DG(RHS-), DG(RPF), AM(CE), AM(Wo;ks), AM(B), AM(Elec.), AM(RS), AM(ME),
Alvl/Tele,
3. EDCE(G), EDCE(P)'
eulcgts, arvilsig..AM(bE:), AIWL&A, PED(B&S), PED(Vigilance),
EDTK(M&MC;, EOCp6iZS),. pOrG)-I, EDFCX)-II, ED(Works), EDW(PLg.), ED/Projec(Mon.)
ED(L&A), ED[TSU), sbvp,.po(Safety), ED(Stn.Dev.), ED(Tele.) EDRS(G),_EDRE, EDEE(G)'
EDiE, EDE(N)', eOngfrpp, EDME(Cirg.), EDME(FrI.), ED/Plg., JS(Conf.), JS(P), JS(G), JS(D),
Vigilance-Ill, Vigilance(Conf.) of Railway Board.
To,
As per list attached
2. Ministry of Finance (MOF) vide OM under ref-(ii), has now extended the validity of
its earlier OM No. F.91412020-PPD dated 12.1 1.2020 til|31.03.2023.
3. Accordingly, the instruction issued vide ref (i) above, stands extended up- to
3r.03.2023. I
4. This issues with the concurence of the Finance Directorate of the Ministry of
Railways.
(B)
3 ffi Nl:*frx#,H$###:m,:,r*f ir#,,o,'oo,u,paha.,oooo,
, Bihar
I.
Naear' Lucknow
2.
3.
ffi SJH|; X?,s*o'n'ranak
rrrrector, IRICEN, pune _ 4l
I 0OI (MahamshEa)
4. Dtreclor. IRIE_EN, pB No.-233,
Nasik Road<ZZiot
5. 1v"h"r^t t ut
6. :i:*.
urrecror, rRrMEE,
raa Naka Road, hla crar,
lllfEl, Jamatpur s*r,;i"-;;"d--#;6r z,
Disn-Jamalp_, pilr_i iilinis"lh.l:,
7. urrector, IRITM, Sarswati Residentiat
(c) Eitars ,'iiiil ail.r::-ri_a.k Nasar, Lucknow
l.
2.
3.
4.
5.
6.
7.
8.
9.
10.
I l.
ffffiffiffiffii$$*Hffi-
3il3:,ttl;lc;,f.,Tliu3lt":,l lll.o. r43, rnsritutionar Arca. secror-,r4, cursao n- t2zoo3.
12.
,qff i,"ff.il1fl;11il"?ffi lf f ,J:;.;,i?ll{ffi#;.;;;,_"",
13.
ru*;l,,,lf fif i$:ifl
14. 3il3: fl?il# T.i,1?iffiililH?,:#".ba Road, New Derhi I r000r
Copy to: ""#li,ll
G)
l. ceneral Secrctary, IRCA, DRM OfEce, New Delhi.
z. uenerat secretary, AIRF, Rail Bhawan, New Delhi
r. uenerat secnetary, NFIR, Rail Bhawan, New Delhi
:. :eneral *crerary, IRpOF, Rait Bhawan, New Dethi
j. :"n"q Secretary, FROA, Rail Bhawan, New Delhi
o. uenerat SecretaD/, AlRpA,
,. uenerat s€crcta4/, AISC & Rail Bhawan, New Delhi
STREA, Rsil Bhawan, New D€lhi
8. The Secrerary, RBSS, croup (A) Om.o e*ro"int.or, i."ilti"*".
ie $iltrtfl ,#llssri:i*tf__r.,ri:t*
;;.1i il;#
I l. The Secretary, RBMSA, Rail Bhawan
12. The Secrelary, Railway, Group (D) Employees
Association, Rail Bhawaa
(B)
' *'lff"]f"n for kind information of chairman cum cEo, Mflnfi4 M/T&RS M/o&BD, M/Finance,
9*I.Yiqltyg" officerc, A[ rndian Rairways.
?. DG(RHS),
3' DqRPF), AM(CE). AM(Work.), eM(s), aV(pr"".),
AM/sis., AM(prs.), pED(B&s)..pED(vreii*""i, AM(RS), AM(ME), A M/Tete. Ar\4/C&rS,
ie ii6bti;i''li]i.rol
EDF(x)-r, EDF(X)-rr. ED(Works), 'eo-wtprg.1. 'e-5rp-.1;"i*ria?.1 EDrK(M&Mc), eoce(sast.
ED(safety), ED(sig. Dev.). qgl.nl, doji{ci ED(L&A), ED(.SU), ED'E.
ib,i''e,"iili[tcr, uooe. EDE(N), ED(Accounts).
EDME(Frt')' io'pie-'isi"",o.jsi.ffiro, iS(D), Vieirance-rr,
vig(confl
"tP#f#i?"1?yt(chs')'
daled 12.11.2020 (copy enclosed) regarding the subject cited above and to say that
it has been decided to extend the validity of the said OM dat€d 12.11.2020 regarding
Encl. : As above. 1-
go.
rn
Kanwa preet
Director (Procurement Policy)
Tel.: 23093811
Email: [email protected]
To
OFFICE IIEIIORAilDUM
3.
- ln view of all above, il b decided to reduce performrnce Securlty tom
exlsung 5-10% b 3% of the narue of tfie conkrct fur alr existing coirtracu.
Horewr, the benefit d the rcducd performance S€curfty will not be liven in G
Gonhagtc under dbpub whercin arbihation/ couil proceedings have U&n afreaay
started or are contemplabd.
4. Further, alr tender6/ contacts issued/ concluded till 31.,12.2021 should also
have lhe provision of reducod performanoe Security.
7. These inshuctions will be applicable for all kinds of procurements viz. Goods,
consultancy, work6, nonronsulting services etc and ar6 issued under Rub 6(1) of the
GFRS 2017.
d&_.-
(KoUurif Narayana f,eddY)
DePutY secretary
" "" 9.I;$',10#
Email: [email protected]
To,
Vision:
To be carbon neutral, the renewable energy produced over time will offset not just
the total operational energy but all the other emissions as well. These include the
embodied energy of the building as well as all other ongoing uses of energy like fuel,
gas, coal, etc.
Performance Specifications:
The following performance specifications are required to be met for all the new
buildings being proposed.
1
Net Zero Energy Buildings (NZEB )
NZEBs are buildings that, through renewable means, produce as much energy as they consume, when
accounted for annually. They embody the highest level of energy efficiency and climate responsive design
by first reducing energy demand, then meeting the residual demand through renewable means. The
architectural design of such buildings follows the logical sequence of achieving NZEB status - focusing on
building form and orientation for load reduction, resource efficiency, energy efficiency, and low-energy
comfort systems before strategizing to meet the residual load through renewable means.
Page 1
Page 258 of 260
existing buildings (EB) to be achieved and maintained for the tenure of
the contract.
2. Net-Zero Energy:
a. Renewable energy2 produced onsite should be at least equal to the
total energy used by the building annually. The buildings will be grid-
connected; consuming grid power when required, and feeding excess
power to the grid when the renewable energy system is producing
extra.
b. The renewable energy systems can be installed anywhere on site,
including building rooftops, ground mounted, and other locations
within the project boundary.
c. In cases where on-site renewable energy is not sufficient or feasible,
off-site 3renewable energy should be installed so as to achieve NZEB
for the building.
3. Net-Zero Run-off
a. Demonstrate rainwater storage and harvesting as per local ground
water authority recommendations, so as to ensure 100% rainwater
management for the project boundary considering typical rainfall.
4. Net-Zero Waste
a. Provide facilities and infrastructure for waste management as given
below
i. No waste sent to landfill
ii. All organic waste processed on site
iii. Toxic and Hazardous waste to be sent for safe disposal
iv. Electronic waste to be sent to e-waste recyclers
v. All others (plastic, paper, metals etc.) sent for recycling offsite
vi. All sewage treated onsite and treated water to be reused
b. During construction ensure 100% of the waste is reused or recycled
and is not sent to landfills
c. Maintain Net-Zero waste status as proposed during the contract
period
2
Renewable Energy systems can in include Solar PV, Solar Thermal, Biogas, Geothermal, Micro
wind, etc. as per MNRE definition
3
Off-site systems may or may not be connected directly to the proposed building
Page 2
Page 259 of 260
Page 260 of 260