SIPAT PG TEST - Rev3
SIPAT PG TEST - Rev3
Customer:
Title:
INDEX
. PART-1
PART-2
This Performance Guarantee Test Procedure is applicable for the Distributed Digital
Control, Monitoring & Information System as configured, customized and supplied under
this contract and in line with the specification requirement.
2.0 Outline
The Performance Guarantee Test shall be carried out at the site upon
confirmation of the following.
Completion of commissioning of the system and full load operation of the
unit.
All erection, pre-commissioning checks have been completed.
Trial operation tests are successfully completed.
All control loops shall be in Auto mode and Loops pre-tuned before start of
test.
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 4
During the load variation/run back tests, if stability of furnace is endangered due
to the reduction of unit capability, then oil supportproper action will be taken by
customer manually/automatically.
Objective
Procedure
Necessary fine tuning of the control system shall be completed and all the loops
shall be running in automatic operation.
Steady load operation definition is missing. (contract?). (the steady load means Comment [JW1]: I did not find it .,
that the load setpoint does not change within the last one hour ) Formatted: Right
(a) Drop 50% of maximum load capability from approximately full load at a rate of Formatted: Font: Italic
10% per minute.
(b) Drop load from full ratedBCR output to the lowest runback limit, at a rate
corresponding to the fastest run back rate.
(c) Pick up 50% of the maximum load capability (MCR) from approximately 50%
load at a rate of 10% per minute.
(d) Following runback conditions shall be proved without any oil support. Comment [JW2]: We
FD/ID/PA Trip
BFP/CEP trip (CEP Trip Not Applicable as as per page documents 9518-
108-11-KO-PVI-G-089 & 9518-108-28-RU-PVI-G-089 )
Mill, feeder trip
Turbine trip/Turbine load rejection.
min
- C*: The test is only possible with mills trip while the runback happened and never with
100 %/BCR min. That is clear if is runback. That is made switching to Turbine Follow 2.
That Boiler reduces the load with demanded rate and turbine follows the boiler. Comment [JW3]:
Primary control – unit’s frequency influence MW load change value would be defined Comment [JW4]: What is a Droop and
scenario. That was not clear the last time
as no more than 3 % and if it happens that the load changed between the values 2% to we did.
3% it can be repeated only once per 30 minutes.
Note:
1) Sufficient time shall be allowed between the tests as settling period between
conducting the tests. The test is to be made once per 30 minutes. 15 minutes
for test and 15 minutes stabilizing the technology.
1)2) The Online trend facility shall be used to record the deviation in the
process parameter from the set point.
2)3) Plant operating conditions will allow and performing not limiting the all test.
All those , i.e. main equipment status, availability of auxiliaries, operational &
equipment constraints, which can influence the tests, shall also be recorded.
3)4) Control system shall be running in the CMC mode i.e. Boiler master, fuel flow,
air flow, feed water & turbine control shall be in automatic mode. Load set
point, maximum & minimum load set point, rate of raise/lower of load shall be
set through the Operator Work Stations, Large Video Screen.
Acceptance criteria
The control system limited does not cause the transient disturbances and
controls them within the acceptable limits as per the table and returned the
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 7
controlled variables to the set points within the shortest possible time, subject to
no constraints being imposed by process/equipment.
4.0 ParametricDCS parameters monitored during the Tests Comment [JW5]: My intention is that
they are not special test it is a part of the
parameters monitored during the tests.
4.1 Definition of worst case loading
The parametric tests shall be conducted during worst case loading of the system.
The worst case loading conditions for control system shall include the
following tasks.
The worst case loading conditions for MMIPIS shall include the following
tasks. Comment [JW8]: That text is
duplicated? why
o LVS – 3, 6 - Plant mimic display with one hundred and twenty (120)
numbers of dynamic data items.
o OWS (DROP211) - Overview display with max. no. of dynamic data
items.
o OWS – (DROP212) - Group display (twenty points, current data).
o OWS – (DROP213) - Alarm display of twenty (20) points.
o OWS –(DROP21 4) - 4 Nos. Windows each running current trend.
All PC Stations- X-T plots are displayed & updated on Station LAN and
unit LAN.
Data collection for all logs/reports in progress.
All printers connected to MMIPIS are in operation at rated speed.
MMIPIS processors and all peripherals health being monitored.
Data collection for trend function and historical data storage in progress.
Four alarm acknowledgements within a base period of one minute from
each OWS & LVS.
Calculations for long term storage of data being performed.
SOE Printing in Progress.
Data transfer with other DDCMIS sub-systems, all PLCs and SG/TG C&I
Systems in Progress for Controls (commands) as well as for information.
The worst case loading condition shall mean continuous data transfer
between the distributed modules (Control System/MMIPIS), at their
individual worst case loading conditions defined above.
Outline
The Controller CPU load is verified to determine the spare duty cycle. Spare duty
cycle is defined as the accumulated spare time available over a period of one
minute after the execution of all control and monitoring algorithms. CPU load
shall be verified under worst case loading condition.
Objective
To confirm 20% spare duty cycle when measured over any one minute period.
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 9
Procedure
Under worst case loading conditions, the controller CPU load is monitored on the
engineering station.
Acceptance criteria
The CPU load is within 80% when measured over 1 minute period.
Outline
Objective
To confirm that controller cycle time for each task area is properly defined as per
NTPC logic requirements.
Procedure
CLCS
1. Simulate a trip signal through a Digital input and observe the digital input
and digital output (stop command) with two channels of oscilloscope.
2. Observe the time interval between the changes in input to output change
3. Keep start permissive avialble and give start command from DI & observe
DO issued. Indicate loop reaction tim expected for Electrical and other
OLCS logics, which will be demonstrated.
4. Verify following
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 10
Acceptance criteria
The task area cycle time settings are as per the various logic requirements
implemented in that particular task.
Outline
Objective
Procedure
Each controller has a capacity for 999 sheets. The utilized no of sheets is noted
for each controller and spare available is calculated.
Acceptance criteria
The function block memory usage is not more than 80% of the control capacity.
Outline
The MMIPIS controller CPU load is verified to determine the spare duty cycle.
Spare duty cycle is defined as the accumulated spare time available over a
period defined below, after the execution of all control and monitoring functions of
MMIPIS. CPU load shall be verified under worst case loading condition.
Objective
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 11
To confirm
(i) 40% free time when measured over any two second period
(ii) 50% free time when measured over any one minute period.
Procedure
The CPU usage on the controllers shall be monitored through the Performance
monitoring tool of windows.
Acceptance criteria
The MMIPIS controller CPU load is within 60% when measured over 2 seconds
and 50% when measured over one-minute period
Standard windows utilities of PCs will be used to check spare capacity of the
following.
The system network load is checked to determine the spare duty cycle. Spare
duty cycle is defined as the accumulated spare time available over 2 seconds
period, after the transmission of control and monitoring information over the
network. System bus load shall be verified under worst case loading condition.
Objective
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 12
To confirm 50% free time when measured over any 2 seconds interval.
Procedure
Acceptance Criteria
The Network load is within 50% when measured over any 2 seconds interval.
Various displays of the operator station should appear without considerable delay
after the display command is issued. To check this selected display screen shall
be called and the time taken for the screen to appear may be noted. The display
response time is defined as the time interval between the pressing of the last key
by the operator for demanding a display and completion of requested display on
CRT with full foreground and background information. The display response time
shall be checked under the worst case loading conditions.
Objective
To confirm operator station display response time as per the table below.
Procedure
Selected operator displays of above types are called by pressing the navigation
button or a key on the key board and the time taken for the selected display or
faceplate to appear fully, after the command shall be measured using a stop
watch.
Acceptance criteria
Operator station display response checked and confirmed as per the table.
The overall system accuracy from the signal input terminals to output
presentation on display and printers for the least accurate input range and
maximum scan rate shall not be worse than +0.1% of full scale of the engineering
process / measurement range of the channel/module. The accuracy is measured
as the error in %.
Since the accuracy tests are conducted for all the channels during hardware
testing as part of Factory tests, channels will be selected at random for each type
of module and accuracy reconfirmed as part of PG tests.
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 14
The display of the parameter under testing shall have a display resolution of 2
decimal places.
Procedure
The selected channels shall be simulated using analog simulators (mA, mV). The
display on CRT shall be noted in a table. The simulation shall be done at 0%,
25%, 50%, 75% and 100% of the range configured. For each type of input (mA,
thermocouple, RTD), one channel per card in ten different cards will be checked
for different engineered measurement ranges.Format for accuracy test is
attached shall be similar to ATST format (Annexure 1).
Acceptance criteria
The overall channel accuracy (expressed as error) of the selected channels shall
be within +/-0.1% of the engineering process range of the channel/module.
SOE inputs :
Acceptance criteria
The report shall contain the simulated SOE points in same chronological order
(of their occurrence) with 1 ms time difference.
DDCMIS PG Test Procedure Revision: 03
Doc No: SI1-0-TG-G-71-OOO-0003/9518-108-21-RU-PVM-W-011 Issue Date 23-Apr-15
Project: 3X660 MW Sipat STPP NTPC Page No. 15
Annexure-1