Production Planning
Production Planning
Production Planning
Production activity control is responsible for the execution of the master production schedule and the
material requirements plan. It also makes good use of labour and machines, minimize work – in- process
inventory and maintain customer service
The material requirement s plan authorizes PAC:
To release work orders to the shop for manufacturing
To take control of work orders and make sure they are complete on time
To be responsible for the immediate detailed planning of the flow of orders through
manufacturing, carrying out the plan, and controlling the work as it progresses to completion
Activities of PAC can be classified into Planning, Implementation, and control functions
Planning
Work flow through each work centre must be planned to meet delivery dates, which means production
activity control must achieve the following:
o Ensure that the required materials, tooling, personnel, and information are available to
manufacture the required components.
o Schedule start and completion dates for each shop order at each work centre so that the
completion date of the order can be met.
Implementation
Once the plans are made, production activity control must put them into action by advising the shop
floor what must be done. This is done by issuing a shop order.
Production activity control will:
Gather the information needed by the shop floor to make the product.
Release orders to the shop floor as authorized by the material requirements plan. This is called
dispatching
Control
Once plans are completed and shop orders released, the process is monitored to establish the progress
against the plans so that corrective action is carried if there is a deviation from the plans
Production activity control will:
Rank the shop orders in desired priority sequence by work centre and establish a dispatch list
based on this information.
Track the actual performance of the work orders and compare it to the planned schedules.
Where necessary, PAC initiates corrective action by replanning, rescheduling, or adjusting
capacity to meet final delivery requirements
Monitor and control work – in – process. Lead times, and work queues.
Report work centre efficiency, operation times, order quantities, and scrap.