bd16080 FIELDTEST
bd16080 FIELDTEST
bd16080 FIELDTEST
SECTION 16080
FIELD TESTING AND DEMONSTRATION OF ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY
A. General: Provide Field Testing and Demonstration of Electrical Systems in
accordance with requirements of the Contract Documents.
1.2 SYSTEM DESCRIPTION
A. General:
1. Provide materials, equipment and labor required, and make such tests as
specified in the various Electrical Power and Lighting Systems and as deemed
necessary to show proper execution of the work in the presence of the
Consultant.
2. Any defects or deficiencies discovered as a result of such tests shall be
corrected without additional cost to the Employer.
3. After the installation is complete and properly adjusted, and at such time as the
Consultant may direct, the Contractor shall conduct operating tests. The
various equipment and systems shall be demonstrated to operate in accordance
with the requirements of the Contract Documents. Tests, including thermal
scanning of the entire electrical power distribution system, shall be performed
in the presence of the Consultant. Provide electric power, instruments and
personnel necessary for performing the various tests.
4. Engage the services of a recognized independent testing laboratory to perform
tests herein specified. Testing laboratory shall provide all material, equipment,
labor and technical supervision to perform such tests.
5. It is the intent of these tests to assure that all electrical equipment is operational
within industry and manufacturer’s tolerances.
6. Upon completion of the tests noted in these specifications, a label shall be
attached to all serviced devices. These labels shall indicate date serviced and
the service company responsible and the name of the Contractor.
7. Tests shall determine suitability for continued reliable operation.
8. Instructions for testing are compatible with and in most cases identical to those
recommended by the National Electrical Testing Association (NETA), from
whose copyrighted recommendations these instructions have been prepared.
Testing shall also comply with applicable IEE Wiring Regulations.
B. Division of Responsibility:
1. Contractor shall perform routine insulation resistance, continuity and rotation
tests for all distribution and utilization equipment prior and in addition to tests
performed by the testing laboratory.
2. Contractor shall supply suitable and stable source of test power to test
laboratory at each test site. Testing laboratory shall specify requirements.
3. Contractor shall notify testing laboratory when equipment becomes available
for acceptance tests. Work shall be coordinated to expedite project scheduling.
4. Contractor shall supply complete set of electrical plans, specifications and any
pertinent change orders to the testing laboratory prior to commencement of
testing.
5. Testing laboratory shall notify the Consultant prior to commencement of any
testing.
6. Testing laboratory shall be responsible for implementing all final settings and
adjustments on protective devices and tap changes in accordance with
specified values.
7. Any system material or workmanship which is found defective on the basis of
acceptance tests shall be reported directly to the Consultant.
8. Testing laboratory shall maintain written record of all tests and upon
completion of project, assemble and certify final test report.
1.3 SUBMITTALS
A. Certifications: Submit for Consultant’s information. Furnish certified test reports
for the equipment ratings of available fault current.
B. Quality Control Testing and Inspection Reports: Submit for Consultant’s
information. Furnish reports of the specified Quality Control inspections and tests.
C. Record Documents: Submit for Employer’s documentation. Furnish record
drawings annotated with the changes made during installation of the Work so as to
be a complete set of “as installed” plans and wiring diagrams.
1.4 QUALITY ASSURANCE
A. Contractor’s Quality Control Responsibilities: Contractor is solely responsible for
quality control of the Work.
B. Qualifications of Testing Agency:
1. Testing laboratory shall meet Safety and Health at Work Act criteria for
accreditation of testing laboratories.
2. Testing laboratory shall submit proof of the above qualifications.
3. All instruments used to evaluate electrical performance shall meet NETA’S
Specifications for Test Instruments.
4. Terms used such as Test Agency, Test Contractor, Contractor Test Company
mean testing laboratory.
C. Regulatory Requirements: Comply with applicable requirements of the laws,
codes, ordinances and regulations of the authorities having jurisdiction. Obtain
necessary approvals from all such authorities.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verification of Conditions: Examine the areas to receive the Work and the
conditions under which the Work would be performed. Identify conditions
detrimental to the proper and timely completion of the Work. Do not proceed until
unsatisfactory conditions have been corrected.
3.2 GENERAL REQUIREMENTS
A. General: The Contractor shall procure sufficient number of instruments in order to
meet the Construction / Testing and Commissioning Schedule.
B. Test Instrument Traceability:
1. Testing laboratory shall have calibration program which maintains all
applicable test instrumentation within rated accuracy.
2. Instruments shall be calibrated in accordance with following frequency
schedule.
a. Field Instruments: 6 months maximum.
b. Laboratory Instruments: 12 months.
c. Leased Speciality Equipment: 12 months. (Where accuracy is
guaranteed by lessor)
3. Dated calibration labels shall be visible on all test equipment.
4. Records must be kept up-to-date which show date and results of all instruments
calibrated or tested.
5. An up-to-date instrument calibration instruction and procedure shall be
maintained for each test instrument.
C. Test Report: Test report shall include the following. Furnish copies of the
completed report to the Consultant no later than thirty (30) days after completion of
project unless directed otherwise.
1. Summary of project.
2. Description of equipment tested.
3. Description of test.
4. Test results.
2. Electrical Tests:
a. Perform insulation resistance test on each phase to earth and from
each phase to each other phase.
b. Perform A.C. or D.C over-potential test on each pole to earth and pole to
pole.
c. Perform contact resistance test across each switch blade.
3. Test Values:
a. Over-potential test voltages shall be applied in accordance
with Table 8.
TABLE 8
A.C. / D.C. Overpotential Test Voltages
A.C. Test D.C. Test
Rated kV Voltage kV Voltage kV
5 14.3 20.2
15 27.0 37.5
b. Contact resistance shall be determined in micro-ohms. Any value
exceeding 50 micro-ohms or any value which deviate from adjacent
poles or similar switches by more than fifty percent (50%) should be
investigated.
F. Circuit Breakers - Medium Voltage (Vacuum):
1. Visual and Mechanical Inspection:
a. Inspect for physical damage and compare nameplate data with plans and
specifications.
b. Inspect anchorage, alignment and earthing.
c. Perform all mechanical operator and contact alignment tests on both the
breaker and its operating mechanism in accordance with manufacturer’s
instruction.
d. Check tightness of bolted bus joints by calibrated torque wrench method.
Refer to manufacturer’s instruction for proper foot pound levels. A mark
shall be placed on each tightened bolt to insure completeness.
e. Cell fit and element alignment shall be checked.
2. Electrical Tests:
a. Measure contact resistance.
b. Perform minimum pickup voltage tests on trip and close coils.
c. Circuit breaker shall be tripped by operation of each protective device.
d. Perform an insulation resistance test pole to earth, pole to pole and
across open pole.
e. Perform insulation resistance test at 1000 volts D.C. on all control
wiring. (Do not perform this test on wiring connected to solid state
relays.)
f. Perform overpotential tests, or power factor test with breaker in the open
and closed position.
3. Test Values:
a. Circuit breaker shall be checked for proper mounting, conductor size and
feeder designation.
b. Operate circuit breaker to insure smooth operation.
c. Inspect case for cracks or other defects.
d. Check tightness of connection with torque wrench in accordance with
manufacturer’s recommendations.
2. Electrical Tests:
a. Contact resistance shall be measured.
b. Time-current characteristic tests shall be performed by passing three
hundred percent (300%) rated current through each pole separately. Trip
time shall be determined.
c. Instantaneous pickup current shall be determined by run-up or pulse
method. Clearing times should be within four (4) cycles or less.
d. Insulation resistance shall be determined pole to pole, across pole and
pole to earth. Test voltage shall be 1000 volts D.C.
3. Test Values:
a. Contact resistance shall be compared to adjacent poles and similar
breaker. Deviations of more than fifty percent (50%) shall be
investigated.
b. Insulation resistance shall not be less than fifty (50) megohms.
c. All trip times shall fall within Table 9. Circuit breakers exceeding
maximum three hundred percent (300%) time (column 5) shall be
replaced.
d. Instantaneous pickup current levels should be within twenty percent
(20%) of manufacturer’s published values.
TABLE 9
Values for Overcurrent Trip Test
(at 300 percent of Rated Continuous Current of Breaker)
Tripping Time (Seconds)
Voltage Range of Rated Minimum Maximum Maximum
(volts) Continuous Thermal Magnetic (For Cable
Current Breakers Breakers Protection*)
(Amperes)
(1) (2) (3) (4) (5) (6)
240 15- 45 3 - 50 100
240 50 - 100 5 - 70 200
600 15 - 45 5 5 80 100
600 50 - 100 5 5 150 200
2. Electrical Tests: Perform earth continuity test between main earth system and
equipment frame, system neutral and/or desired neutral point. This test shall be
made by passing a minimum of ten (10) amperes D.C. current between earth
reference system and the earth point to be tested. Voltage drop shall be
measured and resistance calculated by voltage drop method.
3. Test Values: The main earth electrode system resistance to earth shall be no
greater than one (1) ohm or less.
N. Motor Control Centers and Motor Starters:
1. Visual and Mechanical Inspection:
a. Inspect for physical damage, proper anchorage and earthing.
b. Compare equipment nameplate data with design plans or starter
schedule.
c. Compare overload heaters with motor full load current for proper size.
d. Check tightness of bolted connections.
2. Electrical Tests:
a. Insulation Tests:
1) Measure insulation resistance of each bus section phase to phase
and phase to earth for one (1) minute. Test voltage and minimum
acceptable values in accordance with requirements hereinafter
specified.
2) Measure insulation resistance of each starter section phase to phase
and phase to earth with the starter contacts closed and the
protective device open. Test voltage and minimum acceptable
values in accordance with requirements hereinafter specified.
3) Measure insulation resistance of each control circuit with respect
to earth.
b. Motor overload units shall be tested by injecting primary current thru
overload unit and monitoring trip time.
c. Perform operational tests by initiating control devices to affect proper
operation.
3. Test Values:
a. Bolt torque levels shall be in accordance with Table 1 unless otherwise
specified by manufacturer.
b. Insulation resistance test to be performed in accordance with Table 2.
c. Control wiring insulation test voltage shall be 500V D.C. Manufacturer
shall be consulted for test voltage where solid state control devices are
utilized.
d. Overload tests shall be made at three hundred percent (300%) of motor
full load current. Trip times shall be in accordance with manufacturer’s
c. Power factor tests should show similar dielectric loss between similar
arresters.
d. Earth grid connections should not exceed 0.5 ohms maximum.
S. Engine Generator:
1. Visual and Mechanical Inspection:
a. Inspect for physical damage.
b. Compare nameplate rating and connection with specifications and single
line diagram.
c. Inspect for proper anchorage and earthing. Engine cooling and fuel
system integrity shall be verified.
2. Electrical Tests:
a. A dielectric absorption test shall be made on generator winding with
respect to earth. A polarization index shall be determined.
b. Phase rotation test shall be made to determine compatibility with load
requirements.
c. Protective relay devices shall be tested in accordance with applicable
sections of these specifications.
d. Engine shutdown features shall be function tested:
Low oil pressure
Over-temperature
Over-speed
Other features as applicable.
e. Perform vibration base line test. Amplitude vs. frequency to be plotted
for each main bearing cap.
f. Perform resistive load bank test at 100% nameplate rating. Loading shall
be as follows.
25% rated for 30 minutes
50% rated for 30 minutes
75% rated for 30 minutes
100% rated for 3 hours
Record voltage, frequency, load current, oil pressure and coolant
temperature during test. Voltage regulation, frequency stability and
maximum temperature rise shall be calculated.
g. Perform overpotential test between winding to earth.
3. Test Values:
a. Dielectric absorption test shall be made at test voltages hereinbefore
listed in Table 2. Polarization index shall be made for ten (10) minute
durations. Readings less than three (3) shall be investigated.
END OF SECTION