Fundamentals m1 en
Fundamentals m1 en
Fundamentals
Project Initiation
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland
What is a project?
Theory
A project is a set of complex activities, the goal of which is to satisfy the needs of the
project's sponsor.
1. It is unique.
2. It implies a certain degree of novelty.
3. There is a sponsor.
4. There is a project manager.
5. A goal has been set.
6. A schedule has been determined.
7. A budget has been prepared.
Related concepts:
Stakeholders
Sponsor
Literature:
You’ll find further information about this topic in the following books:
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 2 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
IPMA Competence Element 1.01 Project management success
Baseline v3.0: Element 1.02 Interested parties
Element 3.01 Project orientation
Element 3.05 Permanent Organisation
Element 3.06 Business
Element 3.07 Systems, products & technology
How to do
How can one know if a mission is really a project?
1. It definitely isn't a project if at least one of the following conditions applies:
a. It's a routine job.
b. No completion date has been given.
c. The expenses are very small.
2. It is a project, however, if all of the following conditions apply:
1. The job is unique.
2. The job includes a number of innovative aspects.
3. The job was ordered by a sponsor.
4. The job has (or will have) a clearly specified goal.
5. The job has (or will have) an established completion date.
6. The job has (or will have) a set budget.
Example
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 3 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
departmental printers.
Checkliste
You are faced with a project when the following characteristics are in place:
A degree of uniqueness
A certain level of novelty
A sponsor
A project manager
A well-defined goal
A well-defined schedule
A well-defined budget
Pitfalls
If there's no sponsor, beware!
Has the goal been stated precisely (see "the goals of the project")?
Beware: if you consider all assignments to be projects, you will overload your project
management system.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 4 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
How to start a project?
Theory
Literature:
You can find further information about this topic in the following books:
How to do
How to start a project:
You are the project manager. Your superior (the sponsor) has entrusted you with a project.
These are the first steps to be taken:
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 5 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
1. Make sure that you have completely understood the problem or the need that has
given rise to the project. Try to re-formulate it in your own words and then present
that version to your sponsor.
2. Make sure that you have fully understood the goals of the project and the results
that need to be produced.
3. Define the main phases of the project in co-operation with the sponsor. These are
likely to depend on the size of the project: will there be a pre-project phase? Is it
necessary to present a proper project application? Should a plan for the project be
drawn up?
4. Define the main deliverables of the project.
5. Right from the start, you should determine the milestones where it will be necessary
to gain approval from the sponsor. These milestones could include the following:
a. An agreement concerning the goals of the project
b. The acceptance of the need for a pre-project phase
c. The choice of technical options
d. The acceptance of the project application
e. The acceptance of the project plan
f. The milestones for each deliverable.
g. General acceptance (acceptance of the project)
Example
The Web page
You work in the marketing department of your company and you have
some experience in the designing of web pages. You already have quite a
few successful Internet developments behind you.
Two days ago, your boss came into your office and said the following:
”Hello, how are things going? The other day I had a look at our
company's Internet site and I had the impression that it looked a bit
outdated. After all, one and a half years have passed since we last
updated it. Could you take a look at what might be done? There are so
many options as to what can be done on the Internet. I think we ought to
spend roughly 3 or 4 months developing it into an acceptable site”.
After this discussion, you still do not know what your boss has in mind.
However, you do know that he does not have a very profound
understanding of the Internet. You decide to adopt the following
'pedagogic' approach:
1. You will spend one working week looking into possible directions
the project could take, and into potential goals. For example:
Listing job opportunities at the company on the Web page.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 6 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
2. After this process, you will present these potential goals to your
boss, showing him examples of other companies' sites where
similar things have already been created.
3. Predictably, your boss is enthusiastic about all of the options, and
he would like you to set up all of the possibilities he was presented
with.
4. You explain that this would incur considerable expenses. He asks
you to determine the cost of these plans.
5. You spend another working week calculating the costs (with a
margin of error of +/- 30%) of all the possible directions the
project could take and determining the changes these would bring
in the organization of the company.
6. A further discussion with your boss serves to clarify the situation:
based on your rough predictions, he selects the direction in which
he would like to proceed: creating the possibility for clients to
order spare parts online is obviously the approach which offers the
most advantages to the company in relation to the costs
concerned.
Checkliste
Is the sponsor well defined?
Has the client been successfully identified?
Is the need/problem clearly understood?
Has the goal of the project been properly formulated?
Have the deliverables been properly identified?
Pitfalls
Everyone working at the company agrees that the project is necessary - but no
sponsor has yet been found for the project.
The various project stakeholders evidently have different goals in mind for the
project.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 7 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Identifying problems
Theory
In either case, it is essential to analyze the problem or need very carefully at the outset
of the project: “What is it exactly that the users or clients want?”
There are several methods and numerous tools at your disposal to perform this analysis:
The "five why's" approach
Simulations
Interviews
Benchmarking
However, one of the most important factors for success is very simple: if you really want
to understand the need or problem, you have to spend time with the end-users.
Literature:
You’ll find further information about this topic in the following books:
How to do
How is the need or problem analyzed?
1. Make a list of the persons concerned.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 8 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
2. Hold interviews with these persons, asking them open questions (for example:
“What are the things you don't like about the dashboard of this car?”).
3. Draw up a list of the problems or needs.
4. Try to determine whether these problems or needs are caused by another
problem.
Example
Your superior has charged you with locating new premises, because the employees in
the purchasing department have been complaining for months about the lack of space.
Before launching the project, you decide to investigate the situation yourself, so you ask
the employees in the department:
The answer is given straight away: there's not enough space; there are three of us in
every office.
You ask another question:
"How is it that there are three of you in every office?"
Answer: because we have to store the computers that still need checking here before we
send them to other departments. The whole floor is covered with computer boxes.
You continue your investigation:
"Why do you have to check these computers right here on the spot?"
Answer: Previously, the supplier performed the quality checks himself, but now we're
the ones who have to do them.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 9 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
You go on:
"But why doesn't the supplier do the quality checks himself any longer?"
Answer: Go and ask the purchasing manager. So, you ask him the same question, and
he answers that the supplier has increased the fee for these quality checks by 70%.
You give the supplier a call in order to get their point of view:
"But why did you increase the fee for these quality checks?"
The supplier answers: Because the quality manager at your company has completely
unrealistic expectations. The checks he has in mind would have cost us four hours of
work per computer.
After "five why's," you have finally discovered the real problem: the unrealistic demands
made by your quality department. You therefore requested a modification in these
demands and the supplier started doing the quality checks himself again. Since then, the
purchasing department has had enough space.
The "five why's" method often allows you to understand the real problem that is
concealed behind the false problem (in this case, not enough space in the offices). If you
had rented new premises, you would have solved the false problem.
Peter has just taken over the management of the BiMetax Company. This company
hasn't been flourishing; its products are outdated and turnover has been steadily
decreasing for the past two years.
After one month as the head of the company, Peter takes a six-week trip to visit no
fewer than 28 clients around the world. He doesn't just hold meetings with the
managers of the companies he visits, but always asks to be shown around the
workshops in order to find out exactly how certain categories of parts are machined.
On the basis of this long trip, he establishes, in cooperation with his team, a list of
the most urgent needs of the clients, determines specifications for a range of three
new machines, and launches the development project for these machines.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 10 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
These three machines immediately enjoy considerable commercial success.
Checklist
Did I talk with all of the different categories of users or people connected with the
project?
Did I write down all of the elements, problems, or needs?
Did I set the priority of the needs or problems?
Did I clearly identify each problem (i.e., did I put a name on it)?
Pitfalls
Only seeing the problem as it is presented by the users. Often, the real problem is
concealed.
Only talking with certain people, thus failing to include all of the stakeholders in the
project.
Spending too little time with the users.
Talking only with superiors, ignoring the actual users. Superiors often don't well
understand the real problems of the users.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 11 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Selecting the project manager
Théorie
Literature:
You’ll find further information about this topic in the following books:
How to do
How to select a project manager:
Try to find someone who has already conducted a similar project.
If such a person is not available, find someone who has already participated in a similar
project as a member of the project team.
The selected person should have the following qualities:
Good communication skills.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 12 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Ability to negotiate and solve conflicts.
Solid general knowledge in the area concerned.
Experience with project management.
Example
The Formalux company was founded 30 years ago by Mr. Carson. Right from the
beginning, they specialized in the production of injection molding tools and quickly acquired
an excellent reputation in this area. The particularly complex Formalux tools with multiple
slide valves became famous in the world of machining.
Some years ago, Mr. Carson, who is a highly inventive man, developed an ingenious
flanging system. This modular system, whose components are fabricated with a very high
degree of precision, allows for a kind of "palletization" of parts. This system is successfully
used in wire-cut EDM, milling and grinding. Known as Bridoflex, it enjoyed a dazzling boom,
and Mr. Carson had to quickly set up a production line for the Bridoflex components. He also
had to establish a Marketing department, at the head of which he placed a young and very
dynamic executive who soon disrupted some of the pre-conceived ideas inside the company.
The high growth rate in the Bridoflex department has created numerous problems at the
company, mainly because the Formalux corporate culture was based on the production of
unique parts, while Bridoflex components are mass-produced. This radical change has
proved hard to swallow, particularly for the production management. Mr. Meyer, who had
always managed tool machining so well in the past, has a very hard time understanding
why the Product Manager of Bridoflex, Mr. Sheen, imposes such tight schedules and makes
such frequent changes in the monthly planning.
Mr. Carson wonders which of his employees he should select as the manager for this
project. The range of possibilities isn't very broad in such a small company, and it
doesn't take Mr. Carson very long to draw up a list of the people who could be
considered for the job:
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 13 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Mr. Jenkins, 24 years old, ETS engineer, network manager.
Mr. Fraser, 45 years old, responsible for tools.
Think it over for a while before reading on, and make your choice. Have you made your
choice? If you have, read on.
It didn't take Mr. Carson that much time to reach the following conclusions. Mr. Kahn and
Mr. Jenkins are "technical specialists", which means that they aren't knowledgeable enough
about production. Mr. Fraser and Mr. Lawson don't have a general overview of the problem,
because of their highly specialized activity. Mr. Sheen is already too deeply involved with
the Bridoflex side of the problem, meaning that the whole production department would be
against him. Mr. Peters is a good builder but a poor manager. This leaves Mr. Meyer, who is
responsible for planning production. Yet, Mr. Meyer has difficulties with new concepts, such
as "Right on time". Won't he slow the project down?
Mr. Carson considers hiring an outsider to be the project manager. However, if he did that,
he would hurt Mr. Meyer's feelings – who, it seems, would like to be the manager of this
project. In the end, Mr. Carson chooses Mr. Meyer as the project manager but hires an
external "coach" to help him take the necessary steps towards understanding new
technologies.
Checklist
Is the project manager knowledgeable enough in this area?
Does the project manager have leadership skills?
Does the project manager know how to negotiate and deal with conflict?
Does the project manager have sufficient experience in this area?
Does the project manager have good communication skills?
In case he/she doesn't have all of these qualities, as is often the case, which are the
essential skills for this particular project?
Pitfalls
Selecting a project manager solely on the basis of his or her technical expertise.
Indeed, a project manager needs to know how to direct his or her team; in this
regard, technical expertise isn't much help.
Selecting a project manager who hardly knows the specific area at all and is really
only a manager. Such a project manager will be unable to perform the necessary
arbitration, and it will be difficult for him to gain respect.
If the project manager doesn't speak the language of the client, it can cause a lot of
problems.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 14 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Project organization
Theory
Literature:
You’ll find further information about this topic in the following books:
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 15 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
IPMA Competence Element 1.06 Project organisation
Baseline v3.0: Element 1.09 Project structures
Element 3.05 Permanent organisation
Element 3.06 Business
How to do
How is a project to be organized?
a) Projectized organization
b) Matrix organization
Within departments, work is often done in a matrix organization: projects are generally
smaller and shorter in duration, with the matrix organization ensuring optimal flexibility. If
you have to work in a matrix organization, proceed as follows:
1. Don't have ten people spending 10% of their time on the project, nor five people
spending 20%; try to get two people to work half-time. This way of proceeding is
much more efficient and also greatly reduces the administrative workload of the
project manager.
2. Try to establish a written contract with the superior of the employees joining your
team. This contract should stipulate that employees X and Y will be working for you
at Z % for a given period. Such a contract doesn't completely prevent unfortunate
surprises, but it does give you more weight should a resource-related conflict arise.
3. Try to choose the members of the team yourself as much as possible. It's much
more motivating for employees to be chosen by the project manager directly rather
than just being appointed by the head of department.
In a matrix organization, try, as much as possible, to gather the team members together in
the same office for the time they spend on the project. An employee spending 20% of his or
her time on the project should spend one day a week in the project office. That way, you
can be sure that he or she is really working on your project!
c) Functional organization
This is the weakest type of organizations. It is for example used in the preparation of complex
proposals that requires a strong coordination between Sales, Support, R&D and
Production.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 16 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Because, as project manager, you do not have any authority, it is crucial to treat the
relationship with the the lines manager and convince them of project’s benefits.
Try to obtain from the sponsor a written agreement which states, in coordination with the
lines, the allocation of human resources in the project (deliverables, work load, etc.)
Example
Example 1
At the insurance company where you work, you were
put in charge of the project "HotLine 7/7". This project
aims to establish a hotline service available 24 hours
per day, seven days a week. The preliminary study
carried out by your predecessor had shown that the
following people were needed for this project:
Example 2
As the assistant to the production manager, you've been put in charge of the project,
"Purchase of four machining centers". You're planning the following activities:
For this project, you only need a small project team. A few co-ordination meetings will be
sufficient. The type of organization you'll choose in this case will thus be the so-called "Staff
Organization".
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 17 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Example 3
For the realization phase of the motorway tunnel under the Ben Nevis, your job is to create
and take charge of the project team. This team will comprise, among others, the following
people (who will be employed on the project full-time for a period of at least three years):
For a project with such a long duration, you have decided to choose the "Projectized
Organization" type. The members of the project team will be your direct subordinates for
the entire duration of the project.
Checklist
For a matrix organization
Make sure that the members of your team are actually available.
Prepare a shared workplace (a project office).
Establish an excellent working relationship with the superiors in the organizational
hierarchy of the members of your project team.
Consider, well in advance, the reintegration problems the members of your team will
face when they return to their relevant departments, especially if they will spend
more than 50% of their time on your project.
Often a project is organized in an ad hoc manner: the team of employees under the
direct supervision of the project manager often has to be complemented by one or
more people from other departments. NB: in this case you are faced with a matrix
organization superimposed onto a "Projectized Organization". Make sure that
everything runs smoothly despite this!
Pitfalls
Caution: in a matrix organization, you are responsible for the project, but you don't
have any direct control over the employees. You are dependent on the goodwill of
the line managers, a situation that often leads to conflicts over the allocation of
resources.
In a matrix organization, there is a major risk that the employees will be completely
wrapped up in their daily work, which is always urgent, therefore neglecting their
work on your project. Make them change offices on the days they are working on
your project!
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 18 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
In projectized organization, the employees risk finding themselves out of work by the
end of the project. You should therefore plan their reinsertion at the end of the
project rather early.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 19 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Pre-project Phase
Theory
Literature:
You’ll find further information about this topic in the following books:
How to do
How to carry out the pre-project phase:
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 20 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
- The pre-project phase is a miniature project in itself, with no concrete results: it
consists mainly of analyses, reports, and studies.
- A pre-project phase requires resources. As a result, initiating a pre-project phase needs
the approval of a sponsor (an executive or member of management) who has the
necessary authority to allocate the financial resources required for the pre-project
phase.
- Many companies have a standard form for pre-project applications. This form usually
includes the following aspects:
Present situation, need, and problem to be solved
The aim of the pre-project phase
The importance of the pre-project phase
The milestones
The planned resources
The cost of the pre-project phase
Example
With respect to the implementation of a new software system for
the management of employee-related data (the company employs
1,680 people spread over two separate sites), Mrs. Jackson of the
personnel department has applied for the following funds to allow
her to launch her pre-project:
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 21 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
e) a study of the degree of compatibility of these software packages with our
accounting software.
Goals of the pre-project: the pre-project phase is intended to provide all of the
information necessary to specify the requirements for a new personnel management
software package, to inform the choice between available software packages, and to allow
an estimation of the costs and benefits expected from the introduction of such a software
package, taking into account a margin of error of +/- 20%.
Aim of the project: the aim of the present project is to replace the three existing
employee data management systems with a single system that is compatible with our
accounting software, meets the requirements of data protection legislation, and also allows
the firm to control access to the data in a much more transparent manner than at present.
Milestones:
April 30th: Report on the current situation, the degree of confidentiality of the data, the
legal requirements relating to data protection, and the data needs of line managers.
May 20th: Evaluation of the range of software packages available, and analysis of their
compatibility with accounting software in the IT department. The pre-project phase ends.
Resources:
Personnel department: Mrs. Jackson: 30% of her working time to be spent on the project
from March 15th to April 30th, rising to 60% of her working time from May 20th to 31st.
Information Technology department: One person spending 10% of their working time
between March 15th and April 30th, increasing to 25% in May. Total requirement: 64 hours.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 22 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.
Cost of the pre-project phase:
160 hours in all, which is equivalent to 20 days work at €1000 per day, or €20,000 in total.
Checklist
Have I clearly separated in conceptual terms the aspects of the pre-project phase
from those of the project?
Have the resources needed for the pre-project phase been set aside?
Has the budget for the pre-project phase been fixed?
Has the budget for the pre-project phase been approved?
Will the project manager have sufficient time to complete the pre-project in the
allocated time?
Pitfalls
Important: don't confuse the goal of the pre-project phase with the aim of the
project itself when writing the pre-project application!
Often, pre-projects will be accorded a lower priority than actual projects. For this
reason, it is very important to make sure that the necessary resources for the pre-
project will actually be made available.
Some project managers like to play down the risks that may be involved in a project
in order to increase the chances of gaining approval for their project. This is a very
dangerous approach to adopt. In a pre-project, transparency is essential at all times.
Copyright © 1996-2014 STS Sauter Training & Simulation SA, Lausanne, Switzerland. Page 23 of 23
PMP, CAPM, PgMP, PMI-RMP, PMI-SP, PMI-ACP, PMBOK, REP logo are registered marks of the Project Management Institute, Inc.