TH 10 012
TH 10 012
TH 10 012
IGC 2022
15th – 17th December, 2022, Kochi
Kochi Chapter
1,2,3,4,5,6,7
KLS Gogte Institute of Technology, Belagavi
1 Introduction
TH-10-012 1
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
1.2 Need
This area receives abundant rainfall but does not have a structure in order to store this
water. A few years ago, the old earthen Dam was breached due to heavy rainfall and
improper methods of construction. Thus, construction of a composite earthen dam is
proposed across one of the streams running in this area to meet the water
requirements of the habitants of Gokuldham vedic village.
1.3 Objective
To prepare a detailed project report to submit to the village panchayat in order to get
approval and funds sanctioned for the construction of proposed composite earthen
dam at Gokuldham. The report consists of surveying, results of various tests
conducted on soil samples collected from the vicinity of the dam site and the material
estimation for the dam.
2 Preliminary Stage
In the preliminary stage of the project surveying of dam site, its catchment area and
reservoir was carried out. Soil from different sources in the area was also tested for
suitability as a construction material for the dam. Methodology of the work is shown
in Fig.1.
Based on the requirement of a dam site, a suitable location was chosen across the
natural stream flowing through the area to construct the dam. The important feature of
the site includes a strong substrata and natural elevated apartments on either sides of
TH-10-012 2
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
the reservoir with sufficient capacity and no danger to life and property on the
downstream side in case of breach. A contour map was developed after surveying the
site to establish different elevations to be used in the design and determine the
reservoir capacity. Google map of the catchment area was provided the run off
volume into the reservoir. Fig.2 shows the topographical map of the project site on
Google map. Fig.3 shows the project boundary on Google map. Dam site as shown in
Fig.4.
Location map
TH-10-012 3
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
Based on Indian Standard Soil classification system (ISSCS), Classified the soil
samples like silty gravel (GM) for Electrical pole, high compressibility clayey soil
(CH) for tree, high silty soil (MH) for pond, Intermediate silty soil (MI) for dam,
Intermediate clayey soil (CI) for new plot. Among these soil samples Near Electrical
pole (GM) soil is used for pervious casing and Near Tree (CH) soil is used for
Impervious core.
Where G showing specific gravity, LL represents liquid limit in %, PL represents
plastic limit in %, MDD represents maximum dry density in kN/m3 and OMC
represents optimum moisture content in %.
TH-10-012 4
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
Suitabil
ity
[IS:121
MD
LL PL OM 69-
Soil Particle Size D Classifi
G % % C% 1987(R
locati distribution % [2] kN/ cation
[1] [3] [3] [4] 2006)
on m3[4]
Appen
dix A]
[5]
G S M C
Suitabl
Near
e for
Electr
45 27 21 8 46 30 38 14.7 GM perviou
ical
2.65
s
Pole
casing
Fairly
suitable
Near for
4 16 32 48 58 20 28 14.5 CH
Tree impervi
ous
2.65
core
Poorly
suitable
for
Near
4 40 29 27 57 27 52 14.9 MH both
Pond
core
and
2.60
casing
Poorly
suitable
for
Near
1 9 53 37 40 20 35 16.7 MI both
Dam
core
2.70
and
casing
Fairly
suitable
Near
for
New 5 12 41 42 45 26 24 14.3 CI
impervi
Plot
2.66
ous
core
TH-10-012 5
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
1. Cut-off
2. Core
3. Casing
4. Internal drainage system
5. Slope protection
6. Surface drainage
TH-10-012 6
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
For surplus water, Design of weir is done and Table 2. shows the dimensions of the
weir.
Table 3. Dimensions of Weir
TH-10-012 7
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
Quantity Estimation
Quantities of Dam stripping, Excavation for key trench, Key trench filling, Hearting
Embankment for core, Casing Embankment, Upstream stone pitching and
downstream grass turfing have been calculated. Estimated quantities is shown in
Table 4.
Table 4. Quantity Estimation
The quantity of soil required to be excavated from the borrow pit is 810m3 , 1876.1m3
and 375.6m3 for core , casing and trench filling respectively.
Rate Analysis
The Rates adopted in the estimate are as per the SR Minor Irrigation Belagavi
Circle for the year of 2018-19. The estimate is framed by adopting economic way
of execution. Rate analysis has been done for the above quantities calculated.
The final estimated cost of Earthen Dam is Rs.14,00,000. Table 5 showing the
results of rate analysis.
TH-10-012 8
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
TH-10-012 9
Shanta Boli, Shripal C Shamarayanavar, Shriharsh Shintre ,Venkatesh P Channadasar,
Shashank Bangi , Vikhyat Katti and Vikas Gingine
4 Discussion
5 Conclusion
In this case it was possible to locate borrow pits for the soil required to construct the
earthen dam in the vicinity of the site. This makes the project environment-friendly as
the transportation effort to carry soil from borrow pits to the dam site is considerably
reduced. The cost of borrowing soil is also considerably reduced because of this. For
small dams (like the one in this project) simple guidelines given in codes of practice
may be used to proportion the geometry of the dam. These guidelines provide a
conservative geometry of the dam in simple steps.
6 References
TH-10-012 10