Traffic Management Plan
Traffic Management Plan
Contents
2 INTRODUCTION 15
2.1 Background 15
2.2 Purpose 17
2.3 Objectives 17
2.4 Performance goals 17
2.5 Review of Traffic Management Plan 18
Appendix A Photographs 44
List of tables
Table 1.1 M2G EIS Commitments 6
Table 1.2 M2G DA Conditions of Approval (ACT) 11
Table 1.3 M2G DoP Conditions of Approval (NSW) 12
Table 2.1 Key features of the M2G pipeline project 15
Table 3.1 Key Legislation 19
Table 5.1 Existing traffic count data 24
Table 5.2 Area of Works 26
Table 5.3 Construction Traffic Assignment 29
Table 5.4 Construction Traffic 29
Table 6.1 Construction traffic – haulage requirements 38
Table 6.2 Construction traffic – heavy vehicle movements for main preferred project components
39
Table 6.3 Construction traffic – light vehicle movements 39
Table 6.4 On-Site Parking 40
Table 7.1 Communication Network 41
List of figures
Figure 2.1 General Location 16
Figure 4.1 Site Structure 21
Figure 5.1 Affected Local Road Network 28
Figure 6.1 Construction Signage Placement Plan – Murrumbidgee to Googong Water Transfer 36
Abbreviation
169 The local community would be advised in advance of traffic disruptions and 7.3
controls, noisy work activities eg. piling or rock breaking, construction of
temporary detours and work required outside the nominated working hours prior to
such works being undertaken.
254 Stabilised access point and site traffic – including establishing stabilised 6.1.1
access points, limiting the number of entry/exit points, keeping vehicles to
well defined haul roads and the use of grid or vehicle wash bays;
281 • Traffic management measures to account for the special needs of the equine 5.12 / 6 / 7.3
owners;
295 Approved traffic management plans will be developed in consultation with relevant 6.5
(Roads, Traffic government agencies, including Palerang Shire Council. These will form part of
& Transport) the CEMP and will be implemented throughout the construction period to regulate
traffic movements and speeds. All restrictions on traffic movements and traffic
speeds will only be in place for the duration of the construction period.
296 Road dilapidation surveys will be conducted on all public roads along the pipeline 5.3
alignment prior to and following the construction period. The development and
implementation of these surveys will be done in consultation with Palerang Shire
Council.
297 The construction of pump stations may require road closures of Angle Crossing 5.11
Road for short periods when, for example, large pieces of equipment such as the
pumps are being delivered and unloaded by crane. Such road closures will be a last
resort and will only be used when lane closures and traffic management will not be
adequate to ensure public safety. Traffic will be diverted via Tharwa Bridge.
When road closures are needed warning signs will be in place and the proponent
will provide adequate notice to the local community via advertising using a wide
range of media outlets in consultation with TAMS (Roads ACT).
298 As discussed in Section 6.11.10 it is proposed to open trench at the location the 5.10
pipeline crosses the Monaro Highway.
This will require part road closure during daytime construction hours. One lane
will remain open at all times and will be managed through appropriate traffic
control and warning. Both lanes of the Monaro Highway will be open in the
evening.
299 (Monaro HWY) - It is proposed that the crossing be undertaken using an open 5.10
trench method of construction. This will involve a part road closure
during construction hours (managed by appropriate traffic control). The trench will
be covered outside of construction hours, and both lanes of the Monaro Highway
re-opened to traffic.
300 Trenching and pipe laying work will occur along Williamsdale Road during the 6.4 / 6.5
construction period. To ensure the safety of all road users, traffic control
measures would be in place at all times.
301 Regular users of the affected areas of Wiliamsdale Road will be consulted on the 5.11 / 7
proposed dates for closure prior to formal application to Palerang Shire Council for
the closure. Should the closure of Williamsdale Road be required, the potential
associated impacts on the Monaro Highway will be discussed with TAMS (Roads
ACT) and the National Capital Authority.
Lane closure does not require the complete closure of Williamsdale Road and will
be managed with traffic control devices…
…Tight working conditions on Williamsdale Road may mean that to ensure public
safety, a short section of the road will need to be closed when trenching and
pipelaying is taking place within the road reservation.
302 Arrangements will be made with property owners to ensure access to their 7.3
properties is possible at all times.
303 Vehicular access to properties will be maintained, either by keeping one lane 5.12
open or through the use of diversions and/or by use of steel plates over
sections of the pipe trench.
304 Arrangements will be made with property owners to ensure access to their 7.3/5.12
properties is possible at all times…
… Disruption to private property access will be minimised for the duration of the
construction works and access will be restored and maintained at each property as
soon as practicable as work moves along the pipeline corridor;
305 It is intended that Williamsdale Road will be open to traffic outside of construction 5.11
working hours.
306 The community will be notified prior to any scheduled closure of Williamsdale 5.11 / 7.3
Road and appropriate signage will inform the community of construction times and
alternate routes during those times.
307 The implementation and maintenance of these traffic control measures in 6.4 / 6.5
accordance with approved Traffic Management Plans will mitigate the impact of
the pipeline construction on traffic.
308 Williamsdale Road/Burra Road. The steep approach to the Burra Road intersection 5.6.2 / 6.5
restricts sight distance at the intersection and the additional traffic during the
construction phase will add to the risk of collisions. For safety reasons, it is
recommended that minimal stopping times be introduced for vehicles transporting
horses along Williamsdale and Burra Roads. In addition, a stop sign is
recommended to address the risk of Williamsdale Road traffic turning onto Burra
Road.
309 Outlet structure access road/Burra Road The proposed access road is located about 5.6.2 / 6.5
20 m south of the bridge over Burra Creek. At this location the embankment to the
south and the bridge rail to the north may limit sight distance for traffic entering
Burra Road. This should be addressed in the CEMP Traffic Management Sub-
Plan.
310 Mitigation measures will be in place to minimise the impact of construction works 5.3 / 5.8
on road surfaces and regular discussions will be held between the proponent,
Roads ACT and Palerang Shire Council regarding maintenance work.
311 Particular attention needs to be given to management of traffic during peak traffic 5.10 / 5.6
periods on Monaro Highway such as the ski season when traffic volumes increase
significantly.
312 The proponent will remedy this situation by widening the pavement to allow a 5.8
dedicated right turn lane from the Monaro Highway into Angle Crossing Road.
313 Appropriate traffic control devices will be installed during the construction period 6.5
in accordance with approved CEMP Traffic Management Plan.
314 Consultation with local riding groups will aim to minimise any impact on 4.2.6 / 7.3
equestrian activities and ensure the safety of horses and riders. It is recommended
that road signage warning of horse riders in the area be regularly maintained and/or
replaced as necessary.
315 During the construction period roads along the pipeline route will remain open to 6.9
emergency vehicles or other vehicles responding to emergency situations.
Procedures to improve the speed and efficiency with which safe passage can be
provided, such as early notice by emergency vehicles of the need for access, will
be included in the Emergency Response Plan prepared in consultation with
emergency services.
316 The pipeline will cross a number of property accesses. Detours will be set up at 5.12
these locations to ensure that access is maintained.
317 There will be temporary impacts on the Goulburn to Cooma Railway (Michelago 5.9
Tourist Railway), which is currently not in use due to structural deficiencies with
timber culverts. The railway line will be removed for construction of the pipeline
and then reinstated. Consultation with ARTC and the Australian Railway
Historical Society (ACT) will be undertaken to ensure that appropriate procedures
are in place to minimise impacts on the line.
318 In addition, the location of the proposed access road for the outlet structure may 5.6.2
not provide sufficient sight distance for traffic entering Burra Road.
Further assessment of the intersection will be undertaken as part of the traffic
management sub-plan and the appropriate mitigation measures will be put in
place to manage potential construction risks and impacts
319 • A traffic management sub-plan will be prepared as part of the CEMP, with 6.4 / 6.5
detailed measures in accordance with Australian Standard AS 1742.3:2002
Manual of uniform traffic control devices – Traffic control devices for works
on roads, including:
– Signage on Monaro Highway and Burra Road warning of trucks entering Angle
Crossing Road and Williamsdale Road;
– Management of construction traffic where traffic flow is affected by the
construction pipeline and in particular at locations where the pipeline crosses
the road or is located along and within the road reserve;
– Advance warning signs redirecting traffic to Tharwa Bridge for any
closure of the Angle Crossing Road causeway;
– Reduced speed limits on Burra Road on the approaches to Williamsdale Road
intersection to moderate the risk of collisions;
– Strategies to address the limited sight distance at proposed access road to the
outlet structure on Burra Road;
– Detours to be set up where the pipeline crosses property accesses. Where
possible, all property access crossings will be completed in one day, with any open
trenches covered overnight; and
– Early warnings about road or lane closures will be undertaken . Should the
closure of Williamsdale be required the impact there-off on the Monaro Highway
will be discussed with TAMS (Roads ACT) and the National Capital Authority.
320 Grading of Angle Crossing Road and unsealed sections of Williamsdale Road will 5.12
be undertaken where the construction works have disturbed the road pavement.;
321 Any damage to road surfaces that result from the preferred project will be repaired 5.3
at the expense of the proponent;
322 As an example of public benefits resulting from the upstream outlet cost savings, 5.8.2
ACTEW is working closely with Palerang Shire Council to fund the upgrading and
sealing a section of Williamsdale Road at Gibraltar Hill.
Survey and design work have been completed, and road widening land acquisition
negotiations are underway by the Council. The land proposed to be acquired will
be sufficient to include a bridle path or “greenway” along this section of road. This
work will significantly improve road safety at this location. Any extension of
ACTEW’s current funding commitments to cover the road construction will be
conditional on planning agency approval of the water transfer project.
Any restrictions on planting and structures within permanent pipeline easement are
subject to payment of a once off compensation payment to the affected party.
Except in emergency situations, it is ACTEW’s general policy to consult with
landholders prior to accessing easements through private property.
337 The CEMP will include the following (traffic) sub plans: 5.5 / 6.5
• Traffic Management Sub-Plan – The plan will include truck movements to and
from the construction sites, interactions with general public and property access,
parking and access requirements for construction personnel and safety signage
and training of personnel in traffic management. It will include the measures
listed in Chapter 25 (of the EIS).
338 Traffic Management Sub-Plan – The plan will include parking and access 6.1
requirements, safety signage and training of personnel in traffic management. It
will include the measures listed in Chapter 25 (of the EIS).
C59 Traffic management measures to account for the special needs of the equine 5.12 / 7.3
(social & owners and local business within the area.
economic)
C63 Monaro Highway/ Angle Crossing Road intersection will be improved by 5.8
(traffic & widening the road pavement to provide a right turn land from the Monaro
transport) Highway and improved geometry for the left turn from Angle Crossing Road.
C64 Grading of Angle Crossing Road and unsealed sections of Williamsdale Road will 5.12
(traffic & be undertaken in the vicinity of the pipeline construction be undertaken.
transport)
C65 Disruption to private property access will be minimised for the duration of the 7.3
(traffic & construction works and access will be restored and maintained at each property as
transport) soon as practicable as work moves along the pipeline corridor.
C66 Any damage to road surfaces that result from the project will be repaired at the 5.3
(traffic & expense of the proponent.
transport)
C67 Consultation with the lessee of the rail crossing - the Australian Railway Historical 5.9
( traffic & Society will be undertaken to ensure that timing of the works minimises impacts on
transport) any use of the Goulburn to Cooma Railway (Michelago Tourist Railway).
C68 A traffic management sub-plan will be prepared as part of the CEMP, with 5 and 6
(traffic & detailed measures to manage impacts from traffic as a result of construction of the
transport) project.
B14 Prior to works commencing on site a Temporary Signage Plan that details 6.4
signage in public places, and within the recreational areas noted as sensitive
receivers in the EIS must be submitted to ACTPLC for Approval. The plan must
include information on blasting, construction and traffic movements within the
area and any potential disturbance / annoyance that this might have on recreational
activities.
(b) A dilapidation survey and associated report for all public roads to be used for
construction traffic;
5.3
(c) A detailed Construction (Temporary) Parking Plan for the building phase.
This place must take into account all construction. demolition vehicles and
equipment, and construction workers vehicles, and how and where they will
6.1
be accommodated within the site.
B18 Prior to commencement of works on site., the following requirements must be This Plan
submitted to and approved by the Manager, Traffic Management and Safety,
Roads ACT, TAMS:
(b) a Temporary Traffic Management sub-plan that includes truck movements to 6.5
and from the construction sites, interaction with general public and property
access, parking and access requirements for construction personnel and safety
signage and training of personnel in traffic management.
B19 Traffic Control Device drawings for all new and amended works must be 6.5
submitted to the Senior Manager, AA, TAMS for approval prior to the
installation of such devices
C8 The following requirements must be initiated and maintained for the duration of
the works in accordance with the plans required under Conditions 815, 815 &
817, to the satisfaction of the Senior Manager, AA, TAMS:
(a) that any damage to road surfaces recognised as a result the Dilapidation
Survey must be reinstated to pre-construction condition to the satisfaction of 5.3
TAMS as required during construction and prior to the completion of work;
(b) that the site and surrounds must be managed in accordance with the Traffic
Management Plan; and 2.3 / 4.3
C9 Temporary Traffic Management must be initiated and maintained for the duration 2.3 / 6.4
of the works in accordance with the plans required under Conditions 818, to the
satisfaction of the Manager, Traffic Management and Safety, Roads ACT, TAMS.
2.21 Where the pipeline is located along and within a public road formation the 5.3
Proponent shall:
The Proponent shall restore the relevant roads to a state, described in the original
Road Dilapidation report. The cost of any restorative work described in the
subsequent Report or recommended by the relevant road authorities after review of
the subsequent Report, shall be funded by the Proponent. Such work shall be
undertaken at a time as agreed upon between the Proponent and the relevant road
authorities. In the event of a
dispute between the parties with respect to the extent of restorative work that may
be required under this condition, any party may refer the matter to the Director-
General for resolution. The Director-General’s determination of any such dispute
shall be final and binding on the parties.
2.22 The Proponent shall ensure that all pipeline crossings of roads are constructed 5.12
using construction methods and depth cover determined in consultation with the
relevant road authority.
2.23 The Proponent shall apply to the relevant authority for any proposed temporary 5.11
road closures at least one month prior to the proposed closure. Advertisement of
the closure shall be funded by the Proponent.
2.24 The Proponent shall obtain the relevant consent to utilise the nominated Council 5.4
storage areas within Williamsdale Road Reserve subject to Council requirements.
2.25 The Proponent shall consult with the Australian Railway Historical Society to 5.9
ensure the timing of any construction impacts on the use of the Goulburn to
Cooma Railway (Michelangelo Tourist Railway) are minimised.
2.34 The Proponent shall construct and operate the project in a manner that minimises 6.8.1
dust emissions from the site, including wind-blown and traffic- generated dust.
All activities on the site shall be undertaken with the objective of preventing
visible emissions of dust from the site. Should such visible dust emissions occur at
any time, the Proponent shall identify and implement all practicable dust
mitigation measures, including cessation of relevant works, as appropriate, such
that emissions of visible dust cease.
6.3 d. a Traffic Management Plan to manage traffic conflicts that may be generated This Plan
during construction of the project. The Plan shall address the requirements of the
relevant road authority and shall include, but not necessarily be limited to:
i) details of how construction of the project will be managed in
proximity to local and regional roads;
ii) details of traffic routes for heavy vehicles, including any necessary route
or timing restriction for oversized loads;
iii) demonstration that all statutory responsibilities with regard to road
traffic impacts have been complied with;
(iv) details of measures to minimise interactions between the project and
other users of the roads such as the use of fencing, lights, barriers, traffic
diversions etc;
(v) procedures for informing the public where any road access will be
Infrastructure Description
Intake/low lift pump station The intake/low lift pump station will comprise a concrete box structure built into the
riverbank. The low lift pump station will include a screen, grit collection and removal,
pumps and valves and filtration to prevent fish transfer.
High lift pump station The pump station will pump water to a high point at Gibraltar Range, from where it will
run under gravity to the discharge point. The high lift pump station will consist of a
building enclosing a pump hall and electrical services and an amenities area.
Pipeline The pipeline will transfer the water from the low lift pump station to the high lift pump
station, then onto the outlet structure. It will be constructed of 1016 mm diameter steel pipe.
The pipeline will be approximately 12 km long, with the pipe located approximately 1.8 m
to 4 m below ground level. Air valves and scour valves will be located at regular intervals
along the pipeline to provide pressure relief and to allow cleaning.
Outlet structure The outlet structure will take the form of a weir box arrangement located on the bank of
Burra Creek. It will comprise a rectangular concrete box approximately 12 m along the
creek bank with a 250 mm grated opening along the west bank of Burra Creek. Water will
flow into the weir box from the pipeline and will discharge over the weir and run down the
creek bank to the creek, which flows to Googong Reservoir. This method of discharge is
designed to minimise scouring of the creek bed near the outlet.
Electric power supply The electrical infrastructure will comprise a 132 kV/11 kV substation in Williamsdale
and a single 11 kV cable to the high lift pump station.
Mini-hydro power Electricity provided by the grid will be supplemented by electricity generated by a mini-
generator hydro electric power facility which will be constructed as part of the project.
This document identifies project access points and the local road network. The plan also addresses all vehicle
movement issues raised in the conditions of approval set down by NSW Department of Planning and ACT Planning and
Land Authority.
2.3 Objectives
The objectives of the TMP are:
• To document existing local traffic conditions, measure impact of additional construction traffic and
implementation of appropriate mitigation measures;
• Control of vehicles movements within the Murrumbidgee to Googong Water Transfer project works boundary of
affected areas in accordance with the specifications and requirements of this management plan;
• To go beyond a culture of business as usual (compliance) by demonstrating excellence in traffic control
management;
• To comply with EIS / DA (ACT), EA (NSW) and PER (Commonwealth) commitments and conditions of
approval;
• To minimise complaints from individual landowners / leaseholders and the community relating to traffic control
management;
• Outline strategies to safely implement public management during construction relating to vehicular and
pedestrian movements;
• To prevent the spread of noxious weeds and the dispersal of alien plant and animal species with appropriate
traffic control management;
• To reinstate local road networks to their original condition, if required;
• To ensure erosion control measures are installed in erosion prone areas;
• To consult with individual landowners and relevant stakeholders to incorporate their feedback during
development and implementation of the TMP; and,
• Ensure that landowners, community members, and other stakeholders are kept informed of any traffic changed traffic
conditions and notified if of any impacts to access particularly to properties and premises near the construction
corridor.
The review letter and signature page can be found in Appendix E of this report.
AS 1742.3:1996 Manual of Uniform Traffic Devices - Part 3: Traffic control devices for works on
roads
SAA HB 81.1-1996 Field Guide for Traffic Control at Works on Roads – Short term urban works,
daytime only
NSW RTA Traffic Control Manual at Worksites TAMS
Road Signage Guidelines
Permanent Structures
Low Lift Pump Station (Area 1) ACT
Area 1A: 750 m2 3530 m2
Area 1B: 40 m2 160 m2
Area 1C: 250 m 2
450 m2
Pipework Easements
Chainage 0-94 ACT Easement 40m width
Temporary Areas
Pipe Laydown Area 2 (Angle ACT Temp Only 2300 m2
Crossing)
Road Location Light Vehicle trips Heavy Vehicle trips Total Traffic
per day per day
Monaro Highway
The additional construction traffic on Monaro Highway represents an increase in the daily traffic of between 5% and
8%. This relatively small increase in traffic can be easily accommodated at the existing Level of Service C. LOS C is
described as “stable flow but most drivers are restricted to some extent in their freedom to select their desired
speed”. (RTA Guide to Traffic Generating Developments, Vers 2.2, 2002).
Williamsdale Road
Williamsdale Road carries more traffic than Angle Crossing Road but is also considered to be lightly trafficked. The
increased traffic volume due to construction is below 1100 VPD and therefore the road would continue to operate LOS
A or B described by Austroads as very good.
Williamsdale Road will be realigned between CH 8800 and CH 9160 to remove several tight horizontal curves. The
pipeline will run parallel to and south of the realigned road.
Williamsdale Road crosses Burra Creek near its intersection with Burra Road. This is a single-lane low-level crossing
and subject to flooding. The vertical alignment of Williamsdale Road across the creek and approaching Burra Road is
constructed to a minimal standard (refer Photos 13 and 14 in Appendix A) with very limited sight distances at the
intersection. This section of Williamsdale Road and its intersection with Burra Road will need to be carefully
controlled to safely accommodate the additional traffic during construction. The introduction of a temporary stop sign
for vehicles exiting Williamsdale Road will be proposed in the Traffic Control Plan for the area.
The load rating of the bridge structure is will be determined. Construction loads will be restricted to ensure that this
is not exceeded.
ARTC have informed the Alliance that the railway line is no longer in use and the construction of the pipeline will not
affect any ARTC assets.
The methodology for the works within the Rail Corridor (BWA-M2G-CO-RPT-005) was submitted to ARTC, and
with some modifications to be implemented. The methodology was approved in principal on 11 August 2010. The
plan and associated drawings are required to be updated and issued to ARTC for final approval.
5.12 General
The Alliance will, as a minimum, ensure:
Vehicular access to properties will be maintained at all times; the method of achieving this will be agreed
with each property owner. Possible solutions include keeping one lane open, and the use of steel road plates
to span over the pipeline trench.
That the pipeline will be fenced to prevent livestock from straying close to operating plant
All traffic changes must consider the impact to equine tracks and local equine groups, emergency vehicles,
pedestrians and the general public.
Where the pipeline crosses a road, the pipeline will be installed with suitable construction techniques to ensure
the current traffic conditions can be maintained.
The road where the pipeline crosses must be restored to original (or better) condition.
Delivery drivers and plant operators engaged on the project will be educated on the importance of not
unnecessarily frightening livestock that may wander close to the pipe line corridor and of being vigilant of
possible stock on the local roads
Vehicles movements within the Pipeline Construction Right of Way (RoW) will be managed with signage, barricades,
and in some instances, local traffic controllers. As these vehicles enter onto public road, traffic control plans will be in
place.
The other major contributor to construction traffic will be the haul vehicles transporting excavated rock to the Material
Stockpile Sites.
All Temporary Traffic Management will be setup and maintained for the duration of the works in the area.
1
Area 7
Caltex 1
Services
Station 3
Monaro
Highway
Intersection
1
2 1
Area 5
1 2 1 3
Area 4 Area 6
Area
2
Area
Area
1 Area 8 Area 9
2 3
1
1 Sign 1: Size A1
Area Duration
Monaro Highway Intersection Traffic Control Plan in place for duration of Intersection Works
Works
Monaro Highway Pipeline Traffic Control Plan in place for duration of Pipeline crossing and for access into the
Crossing Railway Easement.
Low Lift Pump Station (at Angles Traffic Control Plan in place for the duration of the works in this area
Crossing) – Area 1 and 2
High Lift Pump Station – Area 3 Traffic Control Plan in place for the duration of the works in this area
High Lift Pump Station Roadways Traffic Control Plan in place for the duration of the works in this area
(Angles Crossing Road)
Pipe Laydown Area 4 (Angle Traffic Control Plan in place for the duration of the works in this area
Crossing Cattle Grid)
Incl PS site office
Main Site Office (Area 5) Traffic Control Plan in place for the duration of the project
Incl Storage Facility and Pipe storage
area
Pipe Laydown Area 6 (DP 754889 Traffic Control Plan in place for the duration of the works in this area
Property)
Pipe Laydown Area 7 (Borrow Pit) Traffic Control Plan in place for the duration of the works in this area
Mini hydro (Area 8) and Traffic Control Plan in place for the duration of the works in this area
Discharge Structure ( Area 9)
Pipeline Construction Zone Traffic Control Plans will be developed and Implemented for entrances, remain in
entrances (Monaro Highway and place for duration of works in these areas
Burra Road)
Minor Road Crossings Traffic Control Plans will be developed for all road crossings.
Pipeline in Road Corridor Traffic Control Plans will be developed, implemented and managed by the
Subcontractor
BWA staff will ensure controls are implemented and maintained.
37
M2G TRAFFIC MANAGEMENT PLAN
BWA-M2G-CO-PLN-002
Formwork
Sand and Gravel
The delivery of materials has the potential to interrupt traffic flow if the delivery driver(s) do not know where on the
Project they are required to deliver their materials to; therefore, a Project Deliveries Instruction Sheet will be developed
to ensure that all construction deliveries are aware of Project Rules and know where their materials are to be delivered.
The Project Deliveries Instruction Sheet and Site Map are to be issued to suppliers upon placement of an order for
materials or equipment.
There will be several crews working simultaneously along the pipeline alignment at any given time. As a result, heavy
vehicle movements will occur on a regular basis during normal construction hours (7 am to 6 pm Mondays to Fridays
and 8 am and 1 pm on Saturdays). Generally, no work is proposed on Sundays or public holidays. There may be
infrequent times when work will need to happen outside of these hours. For example, some after hours delivery of
oversized equipment may be required. Wherever practicable the community will be notified prior to any out of hours
heavy vehicle movements.
As many of the construction activities will occur at different times, an estimate of the peak heavy vehicle traffic
movements was made as shown in Table 5.2 below. It is assumed that deliveries of concrete and reinforcement
deliveries will not be concurrent with structural and mechanical equipment deliveries.
Site compound 12
Pipeline 104
In addition, there will be some truck movements associated with the construction of ancillary infrastructure works.
Table 5.3 summarises the light vehicle construction traffic for the main construction components, generated on local
roads during the construction phase of the preferred project. There will also be minor light vehicle movements
associated with construction workers for the ancillary infrastructure.
Site compound - - 12 2 24
Pipeline 13 2 1 2 28
6.8 Environmental
6.8.1 Dust Management
• The management of dust on the project is a significant issue. Refer to the Murrumbidgee to Googong Water
Transfer - Air Quality Management Plan BWA-M2G-EN-ECP-006-C.
39
M2G TRAFFIC MANAGEMENT PLAN
BWA-M2G-CO-PLN-002
If an emergency requires the need for immediate temporary traffic management then the standard RTA TCP846 (see
Appendix B) will be adopted. This TCP has been selected as it will apply to the 2 way undivided carriageway roads in
and around the Project. The signage required to set-up this TCP will be readily available for use in emergency
situations.
In the case of traffic accidents involving the travelling public (vehicular or pedestrian) either witnessed or reported,
from which legal proceedings might arise, the following actions will be completed:
Gather work records, diary entries, traffic control check sheets and audits;
Record the actual type, size and location of signs and devices in use at the time of the accident. Details of
the pavement width, its condition and weather conditions should also be recorded;
Notify Council as soon as possible; and
Take photographs of the sign arrangement for subsequent reporting.
A record shall be kept of any traffic accident including any relevant information on traffic arrangements used and
completed using form NSW-2F-117A – Traffic Accident Record.
If incidents are required to be reported to WorkCover, Section 6.2 of the RTA Traffic Control at Work Sites Manual
will apply. All personnel will adhere to BWA’s incident reporting process (flowchart in BWA Emergency Management
Plan – BWA-PRW-PD-PLN-004).
BWA to inform the CESM team of the incident so that they can appropriately direct any call that may be received
from the public on the Project Number 1800 221 242.
Area 3 - High Lift Pump Station Parking for High Lift Pump Station and Low Lift Pump Station Construction
Area 4 - Zone 1: Pipe Storage Parking for personnel working in the Zone 1 corridor; from here personnel will be
Area moved to the current workface.
Area 5 - Main Site Office Parking to service the main site office, and overflow for wages from other site
areas.
Area 6 – Zone 2: Pipe Storage Parking for personnel working in the Zone 2 corridor; from here personnel will be
moved to the current workface.
Area 7 – Zone 3: Pipe Storage Parking for personnel working in the Zone 3 corridor; from here personnel will be
moved to the current workface.
Area 8 and 9 – Discharge and Parking for the construction of the mini hydro and discharge structures.
Mini Hydro Structures
Communication
Communication
41
M2G TRAFFIC MANAGEMENT PLAN
BWA-M2G-CO-PLN-002
• A protocol for registering and responding to complaints will be
established as detailed in the Complaints Management Procedure and
CESM Management Plan.
43
M2G TRAFFIC MANAGEMENT PLAN
BWA-M2G-CO-PLN-002
Appendix A Photographs
TCP 846
September 2003
Issue 1
Appendix C Monaro Highway Crossing
I have reviewed the documents provided for Murrumbidgee to Googong traffic management
plan and these documents are in accordance with the RTA requirements. These documents
are also acceptable in the A.C.T.
We (Clearwater) use our own risk assessments & checklists as Roads A.C.T do not provide these
documents. If needed I can forward these to you
Regards Mark
Hogg
Supervisor-Traffic Control Clearwater
Asset Services 0408889875
[email protected]
BULK WATER ALLIANCE
56 SEPTEMBER 2010