Title: Material lifting operations
Document No.-
Annex D: Lifting Plan (Refer Section 4.53.)
1.General
Project
Location of lifting operation
Contractor carrying out lifting Date/Time of lifting
operation operation
Validity period of lifting
operation
2.Details of the Load/S
Description of load/s
Overall dimensions
Weight of load Kg/Ton
▫ Known weight ▫ Estimated
weight
Centre of gravity
▫ Obvious ▫ Estimated ▫ Determined by
drawing
3.Details of the lifting Equipment/Lift Gears
Types of lifting equipment Sling/webbing/chains/shackles/spreader/beam/receptacle
Maximum SWL as certified on the LM Date of last
Cert certification
Max boom/Jib Length Fly jib/offset
Intended load radius Distance between SWL at the radius
the
load and the crane
Type of lifting gears
Combined weight of lifting gears
SWL at Lifting Gear
Can the operator see the loading and unloading point for the load from his position?
▫Yes ▫No
What are the means of communication between the lifting crew?
▫ Standard hand signals ▫ Others
Position Name Qualification/Experience
Site Supervisor
Lifting Supervisor
Crane Operator/Lifting Equipment Operator
Rigger
Signalman
Others(Please state)
6.Physical and Environmental Consideration(please include any details in the space provided)
Is the ground made safe/levelled firm
(e.g. Placing steel plate)?
▫
Yes
1
Title: Material lifting operations Issue Date:
Document No.-
Ground conditions
▫No
Are the outriggers evenly extended ?
▫Yes
▫No
Position of Outrigger/Signalman Is diagram/sketch of lifting operation
enclosed?
▫Yes
▫No
Are there any overhead obstacles
such as power lines ?
▫Yes
Obstacles ▫No
Are there nearby buildings or
structure, equipment or stacked
▫Yes
materials that may obstruct lifting ▫No
operation from being carried out
safely ?
Lighting Is the lighting condition adequate ?
▫Yes
▫No
Demarcation Has the zone of operation been
barricaded (with warning signs and
▫Yes
barriers)to prevent unauthorized ▫No
access?
Do not proceed with the lifting
operation under the following
circumstances:
Environment
▫ Thunderstorm and lightning strikes
in the area, The ground condition
must be checked after a thunderstorm
▫ Strong winds that may sway the
suspended load
▫ Other circumstances (please
specify)
7.Special Precautions
8.Sketch of the zone of operation (It is recommended that you include the initial location of
the load, the final location and path of the load. It is also
important to indicate any obstructions or equipment that
may obstructed the lifting operation).
Appointed person Lifting supervisor Competent Person
2
Title: Material lifting operations Issue Date:
Document No.-
Annex F: Crane Inspection checklist (Refer section 4.5.18)
General Appearance Yes/No Comments
Is the crane visually in good condition and clean
Are the accessories properly stored
Are the storage containers clean and well
organized
Mechanical
Check fluid levels:
Engine oil
Hydraulic oil
Battery fluid
Radiator coolant
Fuel
Are pressure gauges operational?
Is the windscreens clean with good visibility ?
Are all steps and handles free of grease ?
Is the crane deck tidy and clean from oil spills?
Have all operational functions of crane been
checked ?
Are crane and winch controls well positioned and
laid out ?
Hydraulics
Are hoses in good condition ?
Are there any leaks in hoses or valves ?
Electrical
Is wiring in good condition ?
Are lights operational?
Safety system
Is level gauge installed?
Is main horn operational ?
Is safe working load displayed ?
Is height-limiting device fitted on all lines with
automatic shutdown ?
Are load/radius charts displayed ?
Are over boom/under boom stops available
functioning correctly ?
Are load limiting devises operational?
Is the boom angle indicator available that can be
seen by the operator ?
Lifting gear
Has winch been certified in last 12 months?
(including load test)
Are brakes adequately rated for SWL?
Do brakes auto apply on loss of power?
Is a waring displayed to check failsafe brake
application being used ?
Have brakes been serviced in last 3 months ?
3
Title: Material lifting operations Issue Date:
Document No.-
Is cable of correct type and size for winch ?
Is cable properly terminated ?
Is the hook rating adequate for SWL ?
Is the hook in good condition (inclu. swivel safety
latch)
Do operating levers return to neutral position
when released?
Are operating levers clearly labeled?
Are slings/chain tagged certified as per OFS QHSE
standard 013 ?
Are slings/chains in good conditions?
Are sheaves in good conditions ?
Check for missing or damaged hardware like bolts
,cotter pins snap rings ?
Are all safety guards installed?
Certification of crane
Has crane been load tested in last 12 months ?
Is valid certificate available ?
Training
Is crane operator qualified ?
Sitting of crane
Is ground condition checked through civil SH and
if required necessary arrangement of compaction
of soli or proper timber is being used.