Bachelor of Information Technology (Hons)
Assignment Cover Sheet
Course Code: - EC3306 Course Title: - Software Project Management
Test Title:- Assignment-2 Report Due Date: - 9-10-2023
Date Submitted:- 9-10-2023 Lecturer Name: - Mr. Nirdosh Bista
To be completed if this is an individual assignment.
| declare that this assignment is my work. | have not worked collaboratively, copied from any other
student's work or any other source except where due acknowledgment is made explicitly in the
text, nor has any part been written for me by another person.
Student Name: - Niranjan Sharma Student ID:- 00019449
Signature: Lecturer's Signature:
To be completed if this is a group assignment.
We declare that this is a group assignment and that no part of this submission has been copied
from any other student's work or source except where due acknowledgment is made explicitly in
the text, nor has any part been written for us by another person.
Student ID Student Name Signature
Lecturer's comments:
Total Marks:
Lecturer's Signature:
Feedback for the student:
Vie acknowledged receiving feedback from the lecturer on this assignment.
Student's Signature:
Extension certification:
This assignment has been given an extension and is now due on
Lecturer’s Signature:Table of Contents
Introduction
Gantt Chart ..
Network Analysis
Network Diagram...
Data flow Diagram
Function Point Analysis.
COCOMO basic model ..
COCOMO intermediate mode ..
Effort Cost.
Distribution by effort
Distribution by Calendar.
Hardware/Software/Other Cost
Total Cost
Justification/Rationale ..
Conclusion
Acknowledgement.
References ..Introduction:
This is the second assignment in software project management. This assignment focuses on software cost
and timeline estimations. Estimating software costs and timelines is a critical component of project
management. Itentails estimating the resources, time, and expenses needed to complete a software project
within the set timetable and spending
The cost assessment models are available for the COCOMO
model, Checkpoint, ESTIMACS, SLIM, and Knowledge Plan. The COCOMO model, on which | will work for
this project, is one of the most accessible and well-documented cost estimation models available. The
project manager, architecture, development, and test teams executing the task should establish and
support a robust software cost estimate. In this assessment report, | will present a thorough work plan for
predicting software costs and schedules. I'l go through numerous cost estimation models and
methodologies and advise on how to produce reliable estimates. | will also go through recommended
practices for project estimation and planning for change requests. Let us begin our task with page number
four. (Eby, no date)
The Examination Seat Plan Management Web Application Project is a large-scale software
development project that aims to simplify the process of planning and maintaining examination
seating arrangements. This project includes several tasks critical to its success, including project
planning, requirements gathering, system design, development, testing, documentation, training,
deployment, post-deployment evaluation, and project closure.
This report will look at the project's projected length, critical path, cost estimation, function point
analysis, and hardware/software needs. We will defend our choices and assumptions, provide a
justification for our calculations, and conclude with a thorough grasp of project planning and
execution.Gantt Chart: -
fj itn
feauemen gates
[ten desig
fctamene
fami
[reg
a
fst deoyentevew
frsieccosze
1 2075
D6, 2017
uta 3
De 707
eta 203
bee, 207
oss 20
eric
ama
ae
ae
or 205
9
fo, 2023
Dect, 207|
[1,205
[Dec 207|
fo. 203|
[Deco 207
fox, 203
bee, 207|
fo 2225
loa
[oss
na
nav 25
[SETNetwork Analysis:
Description
The followingactivities are included in the Examination Seat Plan Management Web Application
Project, which consists of 10 activities:
Activities Preceding Optimistic Most Likely Pessimistic
Activity Duration Duration Duration
1) ) 1)
Project Initiation - 4 5 12
Requirements - 1 15 5
Gathering
System Design A 2 3 4
Development A 3 4 "
Testing A 2 3 4
Documenting c 15 2 25
Training D 15 3 45
Deployment BE 25 35 75
Post-Deployment H 15 2 25
Review
Project Closure FGI 1 2 3The provided project's network is depicted below.
Network Diagram:
Fig. 1.0- Network Diagram
From the above Network diagram, we can see that | have calculated the Expected duration,
whose formula is
ie. T= T+ 41+ T,
Also, From the above Network diagram, we can see that | have also calculated the Forward Pass
Method and the backward pass method.Let us see a tabular representation of the expected duration, which is as follows:
Activities
Time Estimate (Weeks)
Preceding | Optimistic | Most Likely | Pessimistic | Expected
Activity Duration | Duration | Duration | Duration
(Tr) (T,) 1)
Project Initiation - 4 5 12 6
Requirements - 1 15 5 2
Gathering
System Design A 2 3 4 3
Development A 3 4 " 5
Testing A 2 3 4 3
Documenting c 15 2 25 2
Training D 15 3 45 3
Deployment BE 25 35 75 4
Post- H 15 2 25 2
Deployment
Review
Project Closure FG, 1 2 3 2Also, let us see a tabular representation of the Forward Pass Method and the backward pass
method
Time [Earliest and Latest] are calculated, which are as follows:
Forward Pass Method
Backward Pass Method
E=0
E=E+t,=0+6=6
E=E+t.=6+3=9
E =B+t.=6+5=11
E =E4+t.-944=13
E =max(E+tyE+tsE+td
max [9+2; 11+3; 13+2] = 15
E =E+t.
5+2=17
min (9 133 25)=6
L=bL-tu=134=9
L=L-t.=15-2=13
L=L-t.=15-3=12
L=L-t,=15-2=13
L=B-t.= 172515
L
7
Finally, as we can see, there are two critical paths along which E - Values & L- Values are the same
But the longest network of the critical network is known as the critical path
Hence, the Critical Path is 1-2-3-6-7-8 and the expected length or Duration of the critical path is
6+3+4+2+2 = 17 Weeks.
Duratio
Critical Path = AE-H4-J
7 weeks:Data Flow Diagram (DFD):
ay ees
< Si) 5
a
‘ie | aa
RO Sy
No) =
an sean no
/
Se Schedule Updated Schedule no
lanage Exam >/
(ng Schedule
\
Sey i‘ cost 7)
Fig. 1.1 - Data Flow DiagramFunction Point Analysis:
Functional | Weighting Factor Weighting Factor Weighting Factor
Unit (Low) (Average) (High)
El 3 4 6
EO 4 5 7
EQ 3 4 6
ILE 7 10 15
EIF 5 7 10
From Data Flow Diagram (DFD)
External Input (El) =4
External Output (EO)
External Enquiry (EQ) =1
Internal Logic File (ILF) =3
External Interface File (EIF) =0
After recognizing the function point analysis from the DED, we can now represent it in tabular
form, We also select a weighting factor from the table above.
Function Unit Count Weighting Factor | Count * Weighting
(Average) Factor
El 4 4 16
EO 1 5 5
EQ 1 4 4
IF 3 10 30
EF 0 7 0
Unadjusted Function Points (UFP) 55
10We can utilize the data from the above table to calculate the Complexity Adjustment Factor (CAF)
and Function Points (FP) for the specified Unadjusted Function Points (UFP) using an Average
Weighting Factor.
We know that,
Xfi = (4 x Count of External Inputs) + (5 x Count of External Outputs) + (4 x Count of Internal
Logical Files) + (10 x Count of External Interface Files) + (7 x Count of External Inquiries)
Now, Xfi = (4x 4) + (5x 1) + (4x3) + (10x 0) + (7x1)
Therefore, XFI= 40
Again, Calculating complexity adjustment factor (CAF)
We know that,
CAF = 0.65 + (0.01 x Xfi)
We get,
CAF = 0.65 + (0.01 x 40)
Therefore, CAF = 1.05
Finally, Calculating function point (FP)
We know that,
FP =UPF x CAF
We get,
FP =55x 1.05
Therefore, the answer is 57.75 FP
uCOCOMO Basic Model
LOC/KDSI/Selected Mode/Rationale/effort/calendar/staffing
This technique is the simplest and offers basic estimations based on the number of lines of code
(LOC) in the software project.
Software al a2 bI b2
Projects
Organic 24 1.05 25 0.38
Semi-detached [3 12 25 0.35
Embedded 36 12 25 0:32
Since 1FP = 60LOC
We've already identified our function point, therefore
57.75FP = 57.75 x 60
= 3465LOC
Since, 1KLOC is 1000LOC
Therefore, 3465 / 1000 = 3.465KLOC
The software project is organic because the size ofthe code falls between 2-50KLOC
Now finding Effort(€)
We know that,
1. Effort(E) = a1 x (KLOC)a2
24x 3.465% 1.05
Therefore, Effort (E) =8.849
12Rationale: For effort estimate, | utilized the COCOMO formula using the constants "al" and "a2."
These variables’ values are crucial since they define the form of the effort curve. My selection of "a1"
(2.4) and "a2" (1.05) indicates an Organic development mode, which depicts an initially
complicated project with a somewhat steady growth environment.
2. Development Time (Toe) = b1 x (Effort)Ab2
= 2.2x8,84900.38
Therefore, Development Time = 5.037 Months
Rationale: | calculated the development time using the COCOMO formula, which takes into
account effort and the constants "b1" and "b2." My selection of "b1" (2.2) and "b2" (0.38)
corresponds to the development mode of choice (Organic) and shows the ratio between effort and
development time.
3, Staffing = E / Toev
= 8.849 / 5.037
Therefore, Staffing = 1.756
Rationale: Effort (E) divided by Development Time (TDev) equals staffing. This computation
determines the number of team members needed to execute the project within the time range
selected. In my situation, the predicted team size is roughly 1.756 team members, implying that a
small team is required to execute the project within the specified period.
4, Productivity = KLOC / Effort
3.465 / 8.849
13Therefore, Productivity = 0.391KLOC/PM [KLOC per staff months]
Rationale: Productivity is expressed in KLOC per person-month (KLOC/PM) by dividing the project
size (KLOC) by the effort (E). In this case, the computed productivity is roughly 0.391 KLOC/PM,
reflecting the development process's efficiency in terms of code generated per unit of labor.
5. Calendar (Duration) = Toev-+ Overheads
Overheads involve time spent on non-development activities like as planning, testing, and
documentation.
Let us assume that the overhead time is one month for this calculation:
Calendar (Duration) = 5.037 months + 1 month = 6.037 months
Therefore, the approximate calendar or project time for this software development project is
6.037 months.
Rationale: To account for non-development tasks, | used a normal overhead time of one month.
This extra time contributes to a more realistic project timetable by ensuring that the project's
duration covers planning, testing, and other critical duties.
Development Mode: Based on the constants and values given, I've picked the Organic
development mode, which corresponds to the project's moderate complexity and reasonably
steady environment.
14COCOMO Intermediate Model:
The COCOMO (Constructive Cost Model) Intermediate mode is a software cost estimation model
that aids in determining the effort, time, and staffing required for a software development project.
It is more accurate and comprehensive than the Basic COCOMO model and takes a larger range of
factors into account that may have an impact on project outcomes. Let us see by doing
mathematical solution.
Software al a2 bt b2
Projects
Organic 32 1.05 25 0.38
Semi-detached [3 12 25 0.35
Embedded 28 12 25 0.32
Let us choose and calculate the Effort adjustment factor based on the following data.
Cost Driver Priority Values
Required Reliability High 115
Main storage constraints Extra High 1.56
Product Complexity Normal 1.00
Database Size Low 0.94
Now to find effort adjustment factor (EAF) we know that,
EAF = Required Reliability x Main storage constraints x Product complexity x Database size
Therefore, EAF => 1.68636
15Now, its time to calculate Effort, Development time and Staffing.
For,
Effort (E) =a x KLOC * a2 X EAF
= 3.2 x 3.465 4 1.05 x 1.686
Therefore, Effort (E) => 19.892 PM
Again for,
1 x effort *b2
Development Time (Toes
=2.5x 19.892 4 0.38
Therefore, Development Time (Tbe.) => 7.78 Months
Finally for,
Staffing= Effort / Development Time
= 19.892 /7.78
Therefore, Staffing => 2.55 (Rounded up to 3 Persons)
Rationale:
About 19.892person-months of effort are required, according to the projection. An estimated 7.78
months will pass throughout the development phase. It is recommended to staff the project with
roughly 2.55 individuals (rounded up to 3 people) in order to finish it within this time limit.
16Effort Cost:
The word "effort cost" in the context of software development or project management refers to the.
monetary cost associated with the employees required to complete a project. It lists the labor costs,
which cover salaries, wages, benefits, and any other expenses related to the project's employees.
To calculate effort cost we have,
Effort cost= Toa* (cost of the company)
Here. From the earlier mentioned COCOMO intermediate model, we learned that it is necessary of
3 Employees who will work there for 7.78 months from now. The following is an assumption of the
staff members necessary salaries.
Staff Salary (Per month in RS)
Designer 50000
Project Manager 65000
Software Developer 68000
Project Analyst 44000
The mean salary for the staff => 50000 + 65000 + 68000 + 44000
Therefore, total amount is RS. 1'94'000
Now for the Effort Cost
We know that,
Effort Cost = The” £ (cost of the company)
=7.78x 194000
Therefore, Effort cost => 1509320
7Distribution by effort
Factors Concept | Inception | Elaboration | Construction] Release | Presentation
Effort 20% 17% 13% 20% 25% 5%
Schedule 15%. 25% 30% 10% 15% 5%
Schedule | 15%*7.78 | 25%*7.78 | 30%*7.78 | 10%*7.78 |15%*7.78 | 5%*7.78
[Months] 1.167 1.945 2.334 0.778 1.167 0.389
Months Months Months Months Months Months
18Distribution by calendar:
Activities Calendar Month Time Period Performed by
Project Initiation 1Oct- 20" Oct 1 week Project Manager
Requirements 1Oct- 14" Oct 2weeks Project Analyst
Gathering
System Design 14" Oct 5!" Nov 3weeks Designer
Development SNov-18"Nov 2Weeks Software engineer
Testing 18" Nov - 24"Nov 1 week Software Developer
Documenting 24% Nov-1*Dec 1 week Stake Holders
Training 1 Dec-7"Dec 1 week Project Team
Deployment 7 Dec- 14" Dec 1 week Software Deployer
Post-Deployment 14 Dec - 20"Dec 1 week Software Deployer
Review
Project Closure 20" Dec- 26"Dec 1 week Project Manager
19Hardware/Software Cost/Other Cost:
Server (Cloud Hosting - AWS)
Type RAM Storage Data Transfer Price
3. medium 4GB min 100GB min 1TB per month 2'40'000
User
Tools Minimum Recommended Price
Requirements Requirements
Operating System Windows 7 Windows 10/11 20000
MacOS Mojave MacOS Big Sur or
above
Libraries / APIs Authentication Data Visualization | 5000
Memory, 4GB 8GB or above 8000
Hard Drive 128GB 256GB or above 14000
Browser Chromium based Chromium based Open source
Processor Intel i3 10" Gen or Intel iS 11" Gen or 16000
Michip above & M1 chip or
above
Total 63'000
Total cost for a single client is RS. 63000
Now,
Total cost [for 3 clients/developers per 8 workstations] = 15'12'000
We also have total cost for server = 2'40'000
Therefore, Hardware/software/other cost = RS [15'12'000 + 2'40'000] = RS. 17’52'000
20Total Cost:
the sum of the project's costs, taking into account the price of the required hardware, software,
and other items as well as labor, effort, and administrative and software operating costs.
Particulars Costs
Software/Hardware/Other costs 1752000
Effort Cost 1509320
Administrative and other operational cost.__| 230000
(Assumption)
Gross cost 3491320
Profit Margin (15% of gross cost) 523698
Total Cost 75,06,338
The total cost for the project is 75,06,338. [Seventy-five lakh six thousand three hundred and
thirty-eight]
21Justification/Rational
Finally, this study examined the Examination Seat Plan Management Web Application Project in
full. By analyzing the expected time, essential route, function points, effort, manpower, and
associated expenditures, Ideveloped a framework for successful project planning and
management. The critical path analysis aids in identifying the most time-sensitive activities for the
project and ensuring that they are managed properly in order to meet the project's deadline, The
function point analysis provides insight into the program's functional complexity, which assists in
resource allocation and project scheduling.
Estimating effort, manpower, and costs enables project managers to appropriately allocate
resources and prepare budgets. Using a rational and data-driven approach, this report provides a
solid foundation for the project's effective implementation.
Overall, this thorough assessment and planning will serve as a guide for the project team, ensuring
that the Examination Seat Plan Management Web Application Project is finished effectively,
efficiently, and on time.
22Conclusion:
Finally, this paper presents a comprehensive overview of the Exam Seat Plan Management Web
Application Project. By doing exhaustive estimations of projected time, critical path analysis,
function points, effort, staffing, and related expenditures, | have built a solid foundation for
complete project planning and management.Furthermore, | used industry-standard diagramming
tools, such as Microsoft Visio or Lucid chart, to develop the Data Flow Diagram (DFD), which helped
my project planning,
In the future, my evaluation will pave the way for additional work, such as improving the user
experience, creating a mobile application, investigating integration possibilities with other
educational systems, strengthening security measures, incorporating machine learning for
optimization, and considering scalability for the needs of larger educational institutions.
Ultimately, this comprehensive assessment and planning report will serve as a guiding beacon for
the project team, ensuring that the Examination Seat Plan Management Web Application Project
is completed efficiently, on budget, and on time, while leaving room for exciting future
enhancements and advancements.
23Acknowledgment:
The success and outcome of this assignment were likely due to my work in this course. | am
incredibly privileged to have gotten this along with my assignment report. | appreciate and thank
Mr. Nirdosh Bista for granting me the opportunity to do the assignment report activity and
providing me with all the support | needed to finish the assignment correctly. | am really thankful
to him for providing excellent support and guidance despite his busy schedule.
References:
Fingent Technology. (2020). Function Point Analysis - Introduction and Fundamentals. [online]
Available at: https://www-fingent.com/blog/function-point-analysis-introduction-and-
fundamentals/.
EDUCBA. (2020). COCOMO Model | Types of COCOMO Model | Pros and Cons [online] Available
at: https://www.educba.com/cocomo-model/.
Educative: Interactive Courses for Software Developers. (n.d.). What is the COCOMO
model?{online] Available at: https://www.educative.io/answers/what-is-the-cocomo-model.
Lucidchart (2017). What is a Data Flow Diagram | Lucidchart [online] Lucidchart.com. Available at:
https://www lucidchart.com/pages/data-flow-diagram.
Teamgantt (2019). What is a Gantt Chart? Gantt Definitions & Uses | TeamGantt [online]
Teamgantt.com. Available at: https://www.teamgantt.com/whatis-a-gantt-chart.
24