Boq For Gikomba Godown

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

BOQ FOR GIKOMBA GODOWN

N0 DESCRIPTION UNIT QT RATE AMOUNT


Y

01 Allow for plan preparation, approvals by ITEM 380,000


Nema, NCA
02 Excavate, fill, concrete column bases CM 20 15,000 300,000

03 Reinforcement to column bars KG 60 200 120,000


0

04 Supply & fix hold down bolts NO. 40 680 272,000


0

05 Supply and fix M.s plate N0. 4 32,000 128,000

06 Supply and fix cement mortar screed to floor SM 47 450 211,500


0

07 Supply and fix H-BEAM NO. 45 12,000 540,000

08 Supply and fix 4x2x3mm sq. Tubes NO. 80 6.500 520,000

12 Supply and fix 1.5x1X1.5mm NO. 30 1220 36,600

13 Supply and fix 16 gauge black sheet NO. 33 4700 1,551,000


0

14 Supply and fix gauge 16 chequered plate NO. 6 6900 41,400

15 Supply and fix gauge 30 box profile iron sheets NO 70 1870 130,900

16 Supply and fix 2x40mm Round pipes NO. 25 3850 96,250

17 Supply and fix gauge 16{1x2.5mm} round pipe NO. 70 2250 157,500

18 Supply and fix gauge 16{1x2.5mm} round pipe NO. 8 2950 23,600

19 Supply and fix Roller shutter doors SM 15 7400 1,110,000


0

20 Allow for block work walling SM 46 1500 697,500


5

Allow for plaster & painting SM 93 450 48,000


0

21 Allow for plumbing works ITEM 120,000

22 Allow for electrical works ITEM 350,000

23 Allow for labour & transport ITEM 650,000

TOTAL 7,464,350