Power Flow Analysis Using ETAP Software
Power Flow Analysis Using ETAP Software
By:
Tareq Foqha
Supervisor:
Nablus, Palestine
2020
ABSTRACT
Load flow is an important tool used by power engineers for planning, to determine the best
operation for a power system and exchange of power between utility companies. In order to
suitable and efficient for the system’s load flow analysis. This research will introduce a load
flow study and analysis for 36-bus power system using ETAP software to improve the power
II
TABLE OF CONTENTS
Cover Page I
Abstract II
CHAPTER 1: INTRODUCTION…………………..….………………………..….……..... 1
1.1 Load Flow Studies …..….…….…………………..….……….……………..……..…..…..… 2
1.2 Newton-Raphson Power Flow Solution ………………..….……………..….……….… 4
1.3 Control of Power Flow …………………..…………………………………..…………....… 6
1.4 ETAP ………………………………………..……………..….…………………………....….… 7
CHAPTER 2: LOAD FLOW ANALYSIS .…..…..………..…..…..…..…...…...……... 8
2.1 Power System Description ……………….....….…………….……….…..……….….……. 9
2.2 Load Flow Analysis for the 36-Bus System (normal condition) …...…….……… 9
2.3 Load Flow Analysis for the 36-Bus System (Maximum Load Condition) ….… 11
2.3.1 The Maximum Load Improvement ….………….………….………….……………... 12
2.3.1.1 Improvement by increasing the swing bus voltage ….……………..……… 13
2.3.1.2 Improvement by Using Tap-Changing Transformers ….……………..…… 15
2.3.1.3 Improvement by Using Shunt Capacitor Banks ….……………..…………. 17
2.3.1.4 Comparison between the three cases ….……………..………….….……….. 21
2.4 Load Flow Analysis For the 36-Bus System (Minimum Load Condition) ….... 22
2.4.1 The Minimum Load Improvement ….………….………….………….………….….. 24
2.4.1.1 Improvement by increasing the swing bus voltage ….………….….……... 25
2.4.1.2 Improvement by Using Tap-Changing Transformers ….……….….……... 27
2.5 Load Flow Analysis For the 36-Bus System (Post Fault Condition) ..….……...…. 28
2.5.1 The Post Fault Condition Improvement ….……………..………...….……………..... 31
2.5.1.1 Improvement by Using Shunt Capacitor Banks ….……………..………... 31
CHAPTER 3: CONCLUSION …………..…..…..…..…..…..…..…..…..…...…..…..……... 34
3.1 Conclusion …………………..….…………….……………....….…..……………….....……… 35
BIBLIOGRAPHY ………..….……...…………………..…………....….…..……..………….....……. 36
APPENDICES …………..….……...………………………………....….…..……………….....……… 37
III
CHAPTER ONE
INTRODUCTION
1
CHAPTER ONE
INTRODUCTION
Power flow (or load flow) is the solution for the normal balanced three-phase steady-state
operating conditions of an electric power system. In general, power flow calculations are
performed for power system planning and operational planning, and in connection with system
operation and control.
The data obtained from power flow studies are used for the studies of normal operating mode,
contingency analysis, outage security assessment, and optimal dispatching and stability [1].
The main objective of the load flow analysis is to identify the potential problems, in terms of
unacceptable voltage conditions, overloading of facilities, decreasing reliability, or any failure
of the transmission system to meet performance criteria. After this analysis stage, the planner
develops alternative plans or scenarios that not only will prevent the foreseen problems but
also will best meet the long-term objectives of system reliability and economy.
2
Successful power system operation under normal balanced three-phase steady-state conditions
requires the following:
The power-flow computer program is the basic tool for investigating these requirements. This
program computes the voltage magnitude and angle at each bus in a power system under
balanced three-phase steady-state conditions. It also computes real and reactive power flows
for all equipment interconnecting the buses, as well as equipment losses.
Both existing power systems and proposed changes including new generation and
transmission to meet projected load growth are of interest. Conventional nodal or loop analysis
is not suitable for power-flow studies because the input data for loads are normally given in
terms of power, not impedance. Also, generators are considered as power sources, not voltage
or current sources. The power-flow problem is therefore formulated as a set of nonlinear
algebraic equations suitable for computer solution [3].
Every power system have a special operation of the system depend on knowing the effects of
this power system with other power systems and we will have new loads ,new generating
stations and new transmission lines before they are installed. The required condition according
to load studies for any network which consider the most difficult are:
1. Maximum load;
2. Minimum load;
3. Faults.
3
1.2 Newton-Raphson Power Flow Solution:
(1)
(2)
(3)
(4)
(5)
4
The above Equation (4) and (5) constitute a set of non-linear algebraic equations in terms of
|V| in per unit and δ in radians. Equation (4) and (5) are expanded in Taylor’s series about the
initial estimate and neglecting all higher order terms, the following set of linear equations are
obtained.
In the above equation, the element of the slack bus variable voltage magnitude and angle are
omitted because they are already known. The element of the Jacobian matrix are obtained after
partial derivatives of Equations (15) and (16) are expressed which gives linearized relationship
between small changes in voltage magnitude and voltage angle. The equation can be written in
matrix form as:
(6)
The difference between the schedule and calculated values known as power residuals for the
terms ∆Pi(k) and ∆Qi(k) is represented as:
(7)
5
(8)
(9)
(10)
The addition of a shunt capacitor bank to a load bus corresponds to the addition of a negative
reactive load, since a capacitor absorbs negative reactive power. The power-flow program
computes the increase in bus voltage magnitude along with the small change in δ. Similarly,
the addition of a shunt reactor corresponds to the addition of a positive reactive load, wherein
the power-flow program computes the decrease in voltage magnitude.
6
Tap-changing and voltage-magnitude-regulating transformers are used to control bus voltages
as well as reactive power flows on lines to which they are connected. Similarly, phase-angle
regulating transformers are used to control bus angles as well as real power flows on lines to
which they are connected. Both tap-changing and regulating transformers are modeled by a
transformer with an off-nominal turns ratio c. A change in tap setting or voltage regulation
corresponds to a change in c. The power-flow program computes the changes in Ybus, bus
voltage magnitudes and angles, and branch flows [3].
1.4 ETAP:
7
CHAPTER TWO
8
CHAPTER TWO
The one line diagram of a 36-bus system is shown in Figure 1. The System data needed for
power flow are shown in appendix A. In this system one generator placed at bus number 36. In
short, this network consists of 36 buses, 35 branches, and 35 loads as presented in table (1).
System Description
Swing 1
Buses Regulated 0
Load 35
Transmission Lines 18
Branches
Transformers 17
Generators 1
Loads 30
2.2 Load Flow Analysis For the 36-Bus System (normal condition):
For load flow analysis we used the Newton Raphson method with max number of iterations of
50 and precision of 0.0001. Figure 2 shows the normal load flow analysis, after we run the
program the results are obtained from ETAP are shown in tables 2 and 3. Other results are
shown in Appendix A.
Nominal Voltage
Bus Number Bus Type PF
% Angle
1 Load Bus 89.078 -5.6 69.9
2 Load Bus 86.527 -5.2 69.9
3 Load Bus 86.193 -5.1 70.4
4 Load Bus 86.193 -5.1 75.5
5 Load Bus 86.132 -5.1 64.6
6 Load Bus 86.098 -5.1 73.9
9
7 Load Bus 86.106 -5.1 66.9
8 Load Bus 86.202 -5.1 74.4
9 Load Bus 86.321 -5.1 60.8
10 Load Bus 86.170 -5.1 68.7
11 Load Bus 86.393 -5.1 71.4
12 Load Bus 85.526 -5.0 67.5
13 Load Bus 86.495 -5.1 68.6
14 Load Bus 85.558 -4.9 68.0
15 Load Bus 86.007 -5.0 67.5
16 Load Bus 85.129 -4.8 68.0
17 Load Bus 85.116 -4.8 66.6
18 Load Bus 85.110 -4.9 70.9
19 Load Bus 85.416 -4.9 61.5
20 Load Bus 76.747 -9.3 67.4
21 Load Bus 81.932 -6.7 70.7
22 Load Bus 82.863 -5.7 75.5
23 Load Bus 80.874 -7.2 65.6
24 Load Bus 79.266 -9.1 78.4
25 Load Bus 77.474 -9.5 70.7
26 Load Bus 79.511 -8.8 72.9
27 Load Bus 80.147 -7.5 64.0
28 Load Bus 79.804 -8.4 70.7
29 Load Bus 78.101 -10.2 74.6
30 Load Bus 78.909 -8.7 70.7
31 Load Bus 78.488 -9.5 70.7
32 Load Bus 78.444 -8.9 71.5
33 Load Bus 76.979 -9.5 72.0
34 Load Bus 76.674 -9.5 70.7
35 Load Bus 77.168 -9.8 74.9
36 Slack Bus 100.00 0.0 62.3
Table (2)
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 143.465 180.335 230.440 62.26 lagging
Total Demand 143.465 180.335 230.440 62.26 lagging
Total Losses 8.407 48.888
Table (3)
We conclude that all voltages are less than the nominal voltage. And there is a high voltage
10
Figure (1): 36-bus power system.
2.3 Load Flow Analysis For the 36-Bus System (Maximum Load
Condition):
In this section maximum load state will be studied and we will see the optimization problems
and will search solution for this optimization problem; and obtain results and make
recommendations.
11
Figure (2): Load Flow Analysis in normal condition.
When the original condition analyzed we noticed that there is a drop voltage in most of the
buses. The calculated voltages shown in the table are not acceptable because of the extra drop
voltage in the networks; and the voltages should be adjusted to Vmax = (105% - 110%)
Vnominal. This is required in max load for better performance of the network, because of the
drop in voltage; we have three methods to increase the voltage on the buses:
12
1. Increasing the swing bus voltage;
For this network we assume that we can increase the voltage on the swing bus up to 5% from
the nominal voltage (220 kV), the new value of the swing bus voltage will be (231 kV), After
running the ETAP the load flow results obtained are shown in the tables 4 and 5, other results
are shown in the appendix B, Figure 3 shows the load flow analysis after increasing the swing
Nominal Voltage
Bus Number Bus Type PF
% Angle
1 Load Bus 94.680 -5.6 70.1
2 Load Bus 92.246 -4.7 70.2
3 Load Bus 91.926 -4.7 70.4
4 Load Bus 91.926 -4.7 75.5
5 Load Bus 91.868 -4.6 64.7
6 Load Bus 91.838 -4.7 74.4
7 Load Bus 91.845 -4.6 67.4
8 Load Bus 91.935 -4.7 74.7
9 Load Bus 92.049 -4.7 61.1
10 Load Bus 91.905 -4.6 68.9
11 Load Bus 92.117 -4.7 71.7
12 Load Bus 91.292 -4.5 67.9
13 Load Bus 92.214 -4.6 68.9
14 Load Bus 91.322 -4.5 68.4
15 Load Bus 91.763 -4.6 68.0
16 Load Bus 90.928 -4.4 68.4
17 Load Bus 90.917 -4.4 67.1
18 Load Bus 90.911 -4.4 71.4
19 Load Bus 91.203 -4.4 62.2
20 Load Bus 83.043 -8.3 67.4
21 Load Bus 87.870 -6.1 70.7
22 Load Bus 88.750 -5.2 75.5
23 Load Bus 86.873 -6.5 65.6
24 Load Bus 85.379 -8.2 78.4
13
25 Load Bus 83.709 -8.5 70.7
26 Load Bus 85.603 -7.9 72.9
27 Load Bus 86.192 -6.8 64.0
28 Load Bus 85.875 -7.6 70.7
29 Load Bus 84.303 -9.2 74.6
30 Load Bus 85.036 -7.8 70.7
31 Load Bus 84.656 -8.6 70.7
32 Load Bus 84.606 -8.1 71.5
33 Load Bus 83.260 -8.6 72.0
34 Load Bus 82.977 -8.6 70.7
35 Load Bus 83.440 -8.9 74.9
36 Slack Bus 105.000 0.0 63.2
Table (4)
Figure (3): Load flow analysis after increasing the swing bus voltage by 5%.
14
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 145.585 178.444 230.440 63.22 lagging
Total Demand 145.585 178.444 230.440 63.22 lagging
Total Losses 7.598 44.148
Table (5)
The increasing of the swing bus voltage by 5% didn’t achieve the required, so we have to
In this network the max tap of the transformer T20 is +1 x 5% and the rest of the transformers
have max tap of +1 x 2%, so we put the settings of the transformers tap’s as shown in the
following table:
Table (6)
After running the ETAP the load flow results obtained are shown in the tables 7 and 8, other
results are shown in the appendix C, Figure 4 shows the load flow analysis after changing the
15
Figure (4): Load flow analysis after Changing the Tap of the transformers.
Nominal Voltage
Bus Number Bus Type PF
% Angle
1 Load Bus 99.474 -4.7 70.4
2 Load Bus 97.123 -4.4 70.4
3 Load Bus 96.813 -4.3 70.4
4 Load Bus 96.813 -4.4 75.5
5 Load Bus 96.757 -4.3 64.8
6 Load Bus 96.730 -4.3 74.8
7 Load Bus 96.736 -4.3 67.7
8 Load Bus 96.822 -4.3 74.9
9 Load Bus 96.933 -4.3 61.4
10 Load Bus 96.793 -4.3 69.1
11 Load Bus 96.998 -4.4 71.9
12 Load Bus 96.201 -4.2 68.2
13 Load Bus 97.092 -4.3 69.1
16
14 Load Bus 96.231 -4.2 68.7
15 Load Bus 96.663 -4.3 68.4
16 Load Bus 95.859 -4.1 68.8
17 Load Bus 95.848 -4.1 67.5
18 Load Bus 95.842 -4.2 71.8
19 Load Bus 96.124 -4.1 62.7
20 Load Bus 89.357 -7.6 67.4
21 Load Bus 93.912 -5.6 70.7
22 Load Bus 94.748 -4.8 75.5
23 Load Bus 92.965 -6.0 65.6
24 Load Bus 91.561 -7.5 78.4
25 Load Bus 89.990 -7.8 70.7
26 Load Bus 91.772 -7.3 72.9
27 Load Bus 92.323 -6.2 64.0
28 Load Bus 92.026 -6.9 70.7
29 Load Bus 90.564 -8.4 74.6
30 Load Bus 91.222 -7.2 70.7
31 Load Bus 90.891 -7.8 70.7
32 Load Bus 90.819 -7.4 71.5
33 Load Bus 89.556 -7.9 72.0
34 Load Bus 89.290 -7.8 70.7
35 Load Bus 89.728 -8.1 74.9
36 Slack Bus 105.00 0 63.9
Table (7)
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 147.947 177.921 231.396 63.94 lagging
Total Demand 147.947 177.921 231.396 63.94 lagging
Total Losses 7.045 40.817
Table (8)
The changing of the tap on the transformers still didn’t achieve the required, so we have to add
After running the ETAP the load flow results obtained are shown in the tables 9 and 10, other
results are shown in the appendix D, Figure 5 shows the network after adding the capacitor
bank and Figure 6 shows the load flow analysis after installing the capacitor banks.
17
This equation will be used to calculate the reactive power needed from the capacitors:
Qc= P(tan cos-1 (PFold) - tan cos-1(PFnew)) PFnew (desired) = 0.94 lag
Table (9) shows the voltage level before and after adding the capacitors:
18
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 149.626 71.177 165.699 90.3 lagging
Total Demand 149.626 71.177 165.699 90.3 lagging
Total Losses 3.595 20.772
Table (10)
19
Figure (6): Load flow analysis after installing the capacitor banks.
We conclude that all voltages are within the specifications required in the case of maximum
load.
20
2.3.1.4 Comparison between the three cases:
Table (11) shows the effect on the bus voltage after using each improvement method.
21
2.4 Load Flow Analysis For the 36-Bus System (Minimum Load
Condition):
In this case the network will be studied at its minimum load that the load will be decreased by
70% that we will multiply the real and reactive power by 0.3 at each load, the new data for the
22
22 Load Bus 0.230 0.200 0.069 0.06
23 Load Bus 1.390 1.600 0.417 0.48
24 Load Bus 2.400 1.900 0.720 0.570
25 Load Bus 5.600 5.600 1.68 1.68
26 Load Bus 2.980 2.800 0.984 0.934
27 Load Bus 1.000 1.200 0.3 0.36
28 Load Bus 2.700 2.700 0.810 0.810
29 Load Bus 8.350 7.450 2.505 2.235
30 Load Bus 6.130 6.130 1.839 1.839
31 Load Bus 7.350 7.350 2.205 2.205
32 Load Bus 6.670 6.530 2.001 1.959
33 Load Bus 7.600 7.330 2.280 2.199
34 Load Bus 7.600 7.600 2.280 2.280
35 Load Bus 8.000 7.070 2.400 2.121
36 Slack Bus 0.384 1.920 0.1152 0.576
Total Number of buses = 36 144.543 140.6 45.595 42.318
Table (12): New Load values for minimum load condition.
Figure 7 shows the load flow analysis for minimum load condition, after we run the program
the results are obtained from ETAP are shown in tables 13 and 14. Other results are shown in
Appendix E.
Nominal Voltage
Bus Number Bus Type PF
% Angle
1 Load Bus 97.186 -1.6 77.4
2 Load Bus 96.393 -1.6 77.3
3 Load Bus 96.300 -1.5 70.6
4 Load Bus 96.185 -1.6 95.7
5 Load Bus 96.283 -1.5 65.4
6 Load Bus 96.278 -1.6 77.4
7 Load Bus 96.278 -1.5 69.9
8 Load Bus 96.298 -1.6 74.7
9 Load Bus 96.337 -1.6 63.3
10 Load Bus 96.294 -1.5 70.2
11 Load Bus 96.450 -1.5 73.2
12 Load Bus 96.215 -1.5 70.0
23
13 Load Bus 96.478 -1.5 70.4
14 Load Bus 96.224 -1.5 70.6
15 Load Bus 96.363 -1.5 70.7
16 Load Bus 96.126 -1.5 71.1
17 Load Bus 96.123 -1.5 69.8
18 Load Bus 96.121 -1.5 74.0
19 Load Bus 96.205 -1.5 66.0
20 Load Bus 93.996 -2.5 67.4
21 Load Bus 95.150 -1.9 70.7
22 Load Bus 95.276 -1.7 75.5
23 Load Bus 94.880 -2.1 65.6
24 Load Bus 94.502 -2.5 78.4
25 Load Bus 94.065 -2.6 70.7
26 Load Bus 94.260 -2.5 70.7
27 Load Bus 94.698 -2.1 64.0
28 Load Bus 94.698 -2.3 70.7
29 Load Bus 94.622 -2.7 74.6
30 Load Bus 94.334 -2.4 70.7
31 Load Bus 94.414 -2.6 70.7
32 Load Bus 94.388 -2.4 71.5
33 Load Bus 94.055 -2.6 72.0
34 Load Bus 93.981 -2.6 70.7
35 Load Bus 94.109 -2.6 74.9
36 Slack Bus 100.00 0 71.2
Table (13)
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 45.4 45.228 64.084 70.84 lagging
Total Demand 45.4 45.228 64.084 70.84 lagging
Total Losses 0.642 3.688
Table (14)
We have to increase the buses voltage up to 100%, for this case firstly we will increase the
When the minimum load condition analyzed we noticed that there is a drop voltage in most of
the buses. The calculated voltages shown in the table are not acceptable because of the extra
drop voltage in the networks; and the voltages should be adjusted to Vmax = (100%) Vnominal.
24
This is required in minimum load for better performance of the network, because of the drop
in voltage; we have three methods to increase the voltage on the buses:
For this network we assume that we can increase the voltage on the swing bus up to 5% from
the nominal voltage (220 kV), the new value of the swing bus voltage will be (231 kV), After
25
running the ETAP the load flow results obtained are shown in the tables 15 and 16, other
results are shown in the appendix F, Figure 8 shows the load flow analysis after increasing the
swing bus voltage by 5%.
Nominal Voltage
Bus Number Bus Type PF
% Angle
1 Load Bus 102.281 -1.5 77.4
2 Load Bus 101.512 -1.4 77.3
3 Load Bus 101.422 -1.4 70.6
4 Load Bus 101.311 -1.5 95.7
5 Load Bus 101.406 -1.5 77.5
6 Load Bus 101.401 -1.4 77.5
7 Load Bus 101.401 -1.4 69.9
8 Load Bus 101.420 -1.4 74.8
9 Load Bus 101.458 -1.4 -63.3
10 Load Bus 101.417 -1.4 70.3
11 Load Bus 101.568 -1.4 73.3
12 Load Bus 101.340 -1.4 70
13 Load Bus 101.595 -1.4 70.4
14 Load Bus 101.349 -1.4 70.8
15 Load Bus 101.484 -1.4 70.8
16 Load Bus 101.254 -1.4 71.1
17 Load Bus 101.251 -1.4 69.9
18 Load Bus 101.250 -1.4 74.1
19 Load Bus 101.331 -1.4 66.1
20 Load Bus 99.196 -2.3 67.4
21 Load Bus 100.310 -1.8 70.7
22 Load Bus 100.431 -1.6 75.5
23 Load Bus 100.048 -1.9 65.6
24 Load Bus 99.684 -2.3 78.4
25 Load Bus 99.262 -2.4 70.7
26 Load Bus 99.450 -2.3 70.7
27 Load Bus 99.873 -2.0 64.0
28 Load Bus 99.800 -2.1 70.7
29 Load Bus 99.522 -2.5 74.6
30 Load Bus 99.678 -2.2 70.7
31 Load Bus 99.599 -2.4 70.7
32 Load Bus 99.573 -2.2 71.5
33 Load Bus 99.253 -2.4 72.0
34 Load Bus 99.182 -2.4 70.7
35 Load Bus 99.305 -2.4 74.9
36 Slack Bus 105.00 0 74.4
(Table 15)
26
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 46.279 45.849 65.145 71.04 lagging
Total Demand 46.279 45.849 65.145 71.04 lagging
Total Losses 0.601 3.455
Table (16)
The increasing of the swing bus voltage by 5% didn’t achieve the required, so we have to
the settings of the transformers tap’s are set as shown in the following table:
After running the ETAP the load flow results obtained are shown in tables 18 and 19, other
results are shown in the appendix G. If we change the tap of the transformer T20 the buses
voltage will be out of the range
Nominal Voltage
Bus Number Bus Type PF
% Angle
1 Load Bus 102.275 -1.5 77.4
2 Load Bus 101.505 -1.4 77.3
3 Load Bus 101.415 -1.4 70.6
4 Load Bus 101.304 -1.5 95.7
5 Load Bus 101.399 -1.5 77.5
6 Load Bus 101.393 -1.4 77.5
7 Load Bus 101.394 -1.4 69.9
8 Load Bus 101.414 -1.4 74.8
9 Load Bus 101.451 -1.4 -63.3
10 Load Bus 101.410 -1.4 70.3
11 Load Bus 101.561 -1.4 73.3
12 Load Bus 101.332 -1.4 70
13 Load Bus 101.588 -1.4 70.4
27
14 Load Bus 101.341 -1.4 70.8
15 Load Bus 101.476 -1.4 70.8
16 Load Bus 101.246 -1.4 71.1
17 Load Bus 101.243 -1.4 69.9
18 Load Bus 101.241 -1.4 74.1
19 Load Bus 101.323 -1.4 66.1
20 Load Bus 100.225 -2.3 67.4
21 Load Bus 101.334 -1.8 70.7
22 Load Bus 101.453 -1.6 75.5
23 Load Bus 101.074 -1.9 65.6
24 Load Bus 100.712 -2.3 78.4
25 Load Bus 100.292 -2.3 70.7
26 Load Bus 100.480 -2.3 70.7
27 Load Bus 100.900 -1.9 64.0
28 Load Bus 100.827 -2.1 70.7
29 Load Bus 100.554 -2.5 74.6
30 Load Bus 100.704 -2.2 70.7
31 Load Bus 100.631 -2.3 70.7
32 Load Bus 100.601 -2.2 71.5
33 Load Bus 100.280 -2.3 72.0
34 Load Bus 100.209 -2.3 70.7
35 Load Bus 100.331 -2.4 74.9
36 Slack Bus 105.00 0 71.4
Table (18)
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 46.374 45.941 65.279 71.04 lagging
Total Demand 46.374 45.941 65.279 71.04 lagging
Total Losses 0.602 3.456
Table (19)
2.5 Load Flow Analysis For the 36-Bus System (Post Fault
Condition):
In this section we will assume that the network is affected by a fault condition in some
locations of the transmission lines of the network, after the fault occurs we will try to optimize
the problem. Line (1-15) one of the most important lines in the network, which is carries max
power as shown in figure (8). It will be assumed that a fault happened at one line of the double
28
line, because of that the resistance and inductance will be multiplied by 2 and we will divide
the admittance by 2.
Figure (8): Load flow analysis for post fault condition (determine the critical transmission
line in the network).
After we change the line 1-15 parameters as follows and run ETAP the load flow results
obtained are shown in tables 20 and 21, other results are shown in the appendix H, Figure 9
shows the load flow analysis for this case.
29
Figure (9): Load flow analysis for post fault condition
Nominal Voltage
Bus Number Bus Type
%
1 Load Bus 105.470
2 Load Bus 103.774
3 Load Bus 103.553
4 Load Bus 103.540
5 Load Bus 103.504
6 Load Bus 103.466
7 Load Bus 103.493
8 Load Bus 103.566
9 Load Bus 103.649
10 Load Bus 103.533
11 Load Bus 103.609
12 Load Bus 103.028
13 Load Bus 103.733
14 Load Bus 103.100
15 Load Bus 101.281
30
16 Load Bus 100.675
17 Load Bus 100.675
18 Load Bus 100.643
19 Load Bus 100.895
20 Load Bus 99.0160
21 Load Bus 102.807
22 Load Bus 102.672
23 Load Bus 102.835
24 Load Bus 101.308
25 Load Bus 101.453
26 Load Bus 102.076
27 Load Bus 102.771
28 Load Bus 102.322
29 Load Bus 101.589
30 Load Bus 101.828
31 Load Bus 102.087
32 Load Bus 101.669
33 Load Bus 98.6070
34 Load Bus 98.6070
35 Load Bus 98.4010
36 Slack Bus 105.000
Table (20)
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 150.055 72.944 166.839 89.94 lagging
Total Demand 150.055 72.944 166.839 89.94 lagging
Total Losses 4.477 21.595
Table (21)
We conclude that after the fault the voltage of some buses reduced, for this case we will add
capacitor bank at bus 19 with 12 Mvar rating,
After adding a capacitor bank at bus 19 with 12 Mvar rating then running the ETAP the load
flow results obtained are shown in the tables 22 and 23, other results are shown in the
appendix J, Figure 10 shows the load flow analysis after installing the capacitor banks.
31
Nominal Voltage
Bus Number Bus Type
%
1 Load Bus 106.343
2 Load Bus 104.664
3 Load Bus 104.445
4 Load Bus 104.432
5 Load Bus 104.397
6 Load Bus 104.359
7 Load Bus 104.386
8 Load Bus 104.458
9 Load Bus 104.540
10 Load Bus 104.425
11 Load Bus 104.499
12 Load Bus 103.924
13 Load Bus 104.623
14 Load Bus 103.997
15 Load Bus 102.804
16 Load Bus 102.208
17 Load Bus 102.208
18 Load Bus 102.175
19 Load Bus 102.733
20 Load Bus 101.055
21 Load Bus 103.745
22 Load Bus 103.597
23 Load Bus 103.787
24 Load Bus 102.268
25 Load Bus 102.437
26 Load Bus 103.039
27 Load Bus 103.732
28 Load Bus 103.283
29 Load Bus 102.565
30 Load Bus 102.796
31 Load Bus 103.063
32 Load Bus 102.642
33 Load Bus 100.293
34 Load Bus 100.300
35 Load Bus 100.080
36 Slack Bus 105.000
Table (21)
Summary of total generation, loading and demand are shown in the following table:
MW Mvar MVA PF
Source (Swing Bus) 150.445 57.651 161.111 93.38 lagging
Total Demand 150.445 57.651 161.111 93.38 lagging
Total Losses 4.19 20.371
Table (22)
32
Figure (10): Load flow analysis for post fault condition after adding capacitor bank.
33
CHAPTER THREE
CONCLUSION
34
CHAPTER THREE
CONCLUSION
3.1 Conclusion:
Power flow analysis is an essential step for operational purposes to evaluate various operating
states of an existing system. Also it is necessary for enhancement and development projects. In
this research Load flow study using ETAP software is carried out to analyze the system under
various conditions. By using ETAP load flow program, it is found that the 36-bus network
experiences many technical problems including: poor power factor, low voltage levels and
power losses. And the aim of this load flow studies is to determining the system voltage under
various conditions, and to use proper methods that used to maintain the problem of under
voltage. And they are useful to determine if system voltages remain within specific limits
under various conditions, and whether equipment such as transformers and transmission lines
are overloaded. It is used to identify the need for additional generation, placement of shunt
capacitors or reactors to maintain the system voltages within the limits.
35
BIBLIOGRAPHY
36
Appendices
37
Branch Connections:
38
2-Winding Transformer Input Data:
39
40
A.3 Branch Losses
41
Appendix (B): Maximum Load Condition (Swing Bus)
42
43
B.2 Branch Losses (Swing Bus)
44
Appendix (C): Maximum Load Condition (Tap Changing Transformer)
45
46
C.2 Branch Losses (Tap Changing Transformer)
47
Appendix (D): Maximum Load Condition (Capacitor Bank)
48
49
D.2 Branch Losses (Capacitor Bank)
50
Appendix (E): Minimum Load Condition
51
52
E.2 Branch Losses
53
Appendix (F): Minimum Load Condition (Swing Bus)
54
55
F.2 Branch Losses (Swing Bus)
56
Appendix (G): Minimum Load Condition (Tap changing Transformer)
57
58
G.2 Branch Losses (Tap changing Transformer)
59
Appendix (H): Post Fault Condition
60
61
H.2 Branch Losses
62
Appendix (J): Post Fault Condition (Capacitor Bank)
63
64
J.2 Branch Losses (Capacitor Bank)
65