59 - August Minutes - Final

Download as pdf or txt
Download as pdf or txt
You are on page 1of 73

Page 1 of 73

Ministry of Environment & Forests

(IA Division)

******

SUMMARY RECORD OF THE 30TH MEETING OF EXPERT APPRAISAL COMMITTEE FOR


ENVIRONMENTAL APPRAISAL OF MINING PROJECTS CONSTITUTED UNDER EIA
NOTIFICATION, 2006.

The 30th meeting of the Expert Appraisal Committee for Environmental Appraisal of
Mining Projects of the Ministry of Environment and Forests was held during August 29 th -
31st, 2012. The list of participants is annexed.

The Committee took note of the change of guard and welcomed the new Member
Secretary Dr. Saroj, Director, MoEF on the superannuation of Dr. S.K. Aggarwal. The
Committee felt that EAC (Mining) will amply benefit from her long and rich experience in EC
matters in other industrial sectors. After welcoming the Committee Members, discussion on
each of the agenda items was taken up ad-seriatim. With the approval from the Competent
Authority, two additional agenda items at 2.44 and 2.45 have been considered.

Item No. 1:

1.1 Confirmation of the minutes of the 29th Meeting.

The minutes of the 29th meeting were confirmed as circulated.

2.1 Bauxite Mining Project of M/s Prachi mines located at village Adi and Dharivali,
taluka Mahasala & Srivardhan, District Raigad, Maharashtra (Consultant: J.M.
EnviroNet Pvt. Ltd.)

The proposal was considered by the Committee and the proponent made a
presentation on the same. Prachi Mines proposes to carry out bauxite mining at Villages ADI
M Khadi, Karivane and Dhariwali, Taluka Shrivardhan and Mhasala, District Raigad
(Maharashtra). TORs for this project were prescribed vide MoEF F. No. J-11015/72/2007-
IA. II (M) dated 13th June 2007 and an amendment to the same has been issued on 23rd July,
2009 changing the names of villages. For the purpose of reckoning the validity period of
TOR of 4 years, the Committee felt the date on which the amendment was issued should be
considered. The total mine lease area is 73.2176 ha and the proposed production capacity of
the mine is 0.20MTPA. Maharashtra State Government has issued Letter of Intent (LOI) for
an area of 73.2176 hectares, vide their letter no.MMN-1004/C.R.70/Ind-9. Mining Plan has
been approved by Indian Bureau of Mines vide letter no. RGH/BX/MPLN-1031/NGP dated
24.04.2009.

Demarcation of HTL in the Cadastral level CZM map for the proposed mine in
Maharashtra State was taken up by “Institute of Remote Sensing, Anna University, Chennai.”
Longitudinal section & Cross section levels were measured along Savitri River using Auto
Page 2 of 73

Level at every 200 m as well as wherever abrupt changes were noticed in the coastal line.
Proposed bauxite mining lease area does not fall in CRZ area.
Method of Mining is Mechanized Opencast Mining and the life of mine is 20 years.
Elevation range of lease area is 176mRL - 179m RL. The Ultimate Working Depth is 4m from
surface level. The Ultimate Pit Slope angle is 45o. The total waste generation till the end of
life of mine is 5,80,628 m3.

Based on the presentation made and discussions held, the Committee sought
information on the following:-

1. Coverage of each of the item in TORs in the final EIA report shall be tabulated in the
report.
2. Disaster Management plan shall be provided.
3. Pollution control, material transportation and logistics on Rajpura Jetty road, shall
be detailed out.
4. Mangroves protection plan shall be prepared and submitted.
5. Plans to protect neighboring agricultural fields shall be spelt out.
6. Protection measures for river Savitri shall be indicated.
7. The details about R&R plan of private land shall be prepared and submitted.
8. Cumulative impact of all the Mines operating within the study area shall be brought
out.

It was decided that the proposal may be brought back before the Committee for its
further consideration after the requisite information as mentioned above has been
submitted.

2.2 Renewal of mine lease and expansion of Iron Ore Beneficiation Plant of M/s Tata
Steel Ltd. Located at P.O. Noamundi, District West Singhbhum, Jharkhand (EC-
Reconsideration) (Consultant: Ecomen Laboratories Pvt. Limited )

Terms of Reference (ToRs) were issued for the expansion project on 29th July 2011.
Public Hearing for the project was conducted on 12th March, 2012 and the proposal was
earlier considered by the Expert Appraisal Committee during its meeting held on 21st June,
2012 wherein the Committee had sought additional information/clarifications on various
related issues. Based on the additional information/clarifications, viz: detailed note on the
court order, selection of study area as specified in the TOR, biological study based on
primary survey, assessment of impact of the project on the biological component, adequacy
of the tailing pond for the life of the plan and reconciliation of water balance submitted by
the proponent, the proposal was considered further.

The 1,230.42 ha project area of Noamundi Iron Mine includes 762.43 ha forest land.
Out of this total forest land, 370.9 ha have already been utilized for mining activities and
there shall be requirement of 383.39 ha of more forest land till end of mine life. To restore
forest cover, about 163 ha of mined out and vacant land have already been afforestated. At
the end of mine life, a total of 1047 ha of area will be covered with plantation through
implementation of progressive and final Mine Closure Plan. Moreover, 70 ha will be left as
water bodies.

The mine fell due for lease renewal on 1st Jan, 2012. The earlier approved forest
clearance (370.92 ha) being co-terminus with the expiry of mine lease, the Company had
Page 3 of 73

applied for Temporary Working Permission (TWP) on 12th July, 2011 to work on already
broken-up forest area of 370.92 ha. Though the Forest Advisory Committee (FAC) had
recommended grant of TWP in favor of the Company, the TWP was not yet granted by the
MoEF within the lease period i.e., before 31.12.2011. On 30th Dec, 2011, DFO, Chaibasa
issued two letters to the Company directing closure of mining operation in forest areas of
346.490 ha and 24.43 ha (Total 370.92 ha) with effect from 01.01.2012. On the same date,
Assistant Mining Officer, Chaibasa, also served a letter directing discontinuation of mining
operation in absence of Environmental Clearance or Consent to Operate. Hon’ble Supreme
Court granted stay for operation of all above three letters on 6th Jan 2012, for a period of
one month. After further hearing on 30th Jan, 2012, the stay was extended for another 2
months. On 5th April, 2012, Hon’ble High Court, Jharkhand, granted interim stay on the
letters issued by the District Forest Officer, Chaibasa, Assistant Mining Officer, Chaibasa and
the Member Secretary, JSPCB. Because of stay order from Hon’ble High Court and grant of
TWP by the MoEF, the Company withdrew the case from the Hon’ble Supreme court.
Further on 18th April 2012, Hon’ble High Court, Ranchi, continued the stay order till next
date of hearing. The next hearing was held on 30th July, 2012 and the Hon’ble High Court
extended the stay.

Based on the presentation made and discussions held, the Committee recommended
the project for Environmental Clearance.

2.3 Proposed Vikram Cement Limestone Mine of M/s Ultra Tech Cement Ltd., Village
Nayagaon, Kesharpura, Damodarpura, Khor & Kanka, Tehsil Jawad, District
Neemuch, M.P. (564.106 ha) (EC-Reconsideration) (Consultant: J.M. EnviroNet
Pvt. Ltd. )

The proposal is for opening of a new mine for production of 2 MTPA of Limestone
for the captive use in their Cement plant. Mine lease area is 564.106 ha. No forestland is
involved. No National Park / Sanctuary / Wildlife Corridors are reported within 10 km of
the mine lease. TORs for this project were prescribed on 24.03.2010. Public hearing has
been held on 1.3.2012. Mine working will be opencast mechanised. Life of the mine is 29
years. Water requirement is estimated as 143 kld, which will be obtained from existing
mine sump water (Mine-I) and proposed mine sump after five years. Drinking water will be
sourced from bore wells. Ground water table is at 458 mRL to 455 mRL in post monsoon
and 433m RL to 423m RL during pre-monsoon season. Ultimate working depth will be
421m RL (52m bgl). Mine will intersect ground water table after 10 years of working. Total
OB waste generation at the conceptual stage will be 9.19 Million tonnes. OB dump area is
6.00 ha and backfilling is proposed after 7th year. Area under greenbelt/plantation will be
107.96 ha which will include 33.82 ha un-worked area.

The proposal was earlier considered by the Expert Appraisal Committee during its
meeting held on 25th July, 2012 wherein the Committee had sought additional
information/clarifications on various related issues. Based on the additional
information/clarifications submitted by the proponent, the proposal was considered
further.

Based on the presentation made and discussion held, the Committee recommended
the project for environmental clearance with the specific condition that the availability of
water after the first five years must be ascertained and ensured.
Page 4 of 73

2.4 Tiroda Iron Ore Mine (ML area- 34.4212 ha and production capacity of 0.40
MTPA) of M/s Gogte Minerals at Village Tiroda, Vengurla Taluk, Sindhudurg
District, Maharashtra - MA No. 1 OF 2011 IN Appeal No. 3 of 2011 Sarpanch
Gram Panchayat, Tiroda & Ors V/s Ministry of Environment and Forests & Ors
before Hon’ble National Green Tribunal (NGT for short).

It was noted that all the points raised by the Committee in the meeting dated May
23-25, 2012 have been responded adequately by the PP. The NGT had dealt with the subject
of applicability of the moratorium and the requirement of the CRZ map and concluded that
there is no necessity of going into any details thereof. The only relevant point was the
topographic map plotting all the iron ore mines therein. The Committee noted during the
presentation that such a map was submitted by the PP and in their presentation; they gave
details of the cumulative impact of all the Mines in the study area. The Committee noted that
various environmental parameters were within the prescribed limits.

The Committee, as directed by the Hon’ble NGT, has reexamined all the relevant and
additional information sought from the PP and found that the revised EIA/EMP and other
requirements of granting EC have been duly complied with. The Committee therefore
considers it appropriate to recommend revival/grant of EC to the Proposal.

2.5 Proposed Bauxite Mine of M/s Nilesh Mines Corp., Village Karivane, Taluka
Shrivardhan, District Raigad, Maharashtra (70.07 ha)-EC Reconsideration
(Consultant: J.M. EnviroNet Pvt. Ltd.)

M/s Nilesh Mines Corporation proposes Bauxite mining lease of 70.07 ha with
production capacity of 0.20 MTPA at Village: Karivane, Taluka: Shrivardhan, District: Raigad
(Maharashtra). Letter of Intent was issued vide order No. MMN - 1004/CR 703/Ind–9. The
Mining Plan was approved vide letter no RGH/BX/MPLN-1032/NGP dated 24-04-2009.
TORs for this project were prescribed in June 2007 and an amendment to the same has been
issued in July, 2009 changing the names of villages. For the purpose of reckoning the
validity period of TORs for 4 years, the Committee felt the date on which the amendment
was issued should be considered. Later on Modified Mining Plan was approved vide letter
dated January, 2010 and final EIA/EMP Report was submitted to MoEF on 16thMay, 2012.

Based on the presentation made and discussions held, the Committee sought
information on the following:-

1) Coverage of each of the item in TORs in the final EIA report shall be tabulated in
the report.
2) Disaster management plan shall be provided.
3) Pollution control, material transportation and logistics on Rajpura Jetty road,
shall be detailed out.
4) Mangroves protection plan shall be prepared and submitted.
5) Plans to protect neighboring agricultural fields shall be spelt out.
6) Protection measures for river Savitri shall be indicated.
7) The details about R&R plan of private land shall be prepared and submitted.
8) Cumulative impact of all the Mines operating within the study area shall be
brought out.
Page 5 of 73

It was decided that the proposal may be brought back before the Committee for its
further consideration after the requisite information as mentioned above has been
submitted.

2.6 Malanjkhand Copper Ore Project of M/s Hindustan Copper Ltd., village
Malanjkhand, District Balaghat, M.P. (EC-reconsideration) – (Consultant: SENES
Consultants India Pvt. Ltd. Noida)

The proposal was earlier considered by the Expert Appraisal Committee during its
meeting held on July 25-27, 2012 wherein the Committee had sought additional
information/clarifications on various related issues.

Based on the additional information/clarifications submitted by the proponent, the


proposal was considered further. The proposal is for renewal of mine lease which will fall
due in August, 2013 and enhancement of production of copper ore from 2.0 million TPA to
5.0 million TPA with increase in lease area from 479.9 ha to 728.4 ha along with change in
technology from opencast to underground mining and beneficiation plant with a total
capacity of 5.0 million TPA by adding another Unit. The total project area is 2016.77 ha. The
facility wise break-up of land is as - Mine I&II and existing beneficiation plant 479.9 ha;
Mine-III 248.5 ha; tailing disposal facility 230.0 ha; housing complex, market, auditorium &
club, oxidation ponds for sewage disposal and others-1057.6 ha. 728.8 ha of forest land is
involved. The Kanha National Park (core zone) is reported at a distance of 8.05 km from the
project area and the buffer zone of the Kanha National Park is at a distance of 4.24 km from
the project area. The total water requirement is 52,577 m3/day out of this 21,260 m3/day
will be recycled and net water requirement will be 31,317 m3/day which will be sourced
from Banjar river. Method of mining will be underground mechanized with mass blasting
and filling. Life of U/g mine will be 30 years. There are two mine leases, one mine lease
consisting of mine-I & II which were amalgamated in 1993 on first renewal and now falling
due for 2nd renewal in 2013. Second mine is Mine–III of ML area 248.5 ha, the lease for
which is yet to be executed. TOR for the project was prescribed on 29.3.2011. Public hearing
was held on 6.1.2012. Issues have been adequately addressed. The mine is in operation
since 1973 and obtained environmental clearance in 1992. Mining Plan for 479.9 ha was
approved vide letter No. 314(3)/ 2012-MCCM (CZ)/MP-04 dated 23.08.2012. Application as
regards Wild Life was made to the State Government of Madhya Pradesh on 13.08.2012 for
onward submission to National Wild Life Board.

Based on the presentation made and discussion held, the Committee recommended the
project for environmental clearance.

2.7 Karampada Iron Ore Mine of M/s Singhbhum Mineral Co., Chaibasa, Distt West
Sighbhum, Jharkhand (141.64 ha)- EC Reconsideration

The proposal was earlier considered by the Expert Appraisal Committee during its
meeting held on December 22-23, 2011 wherein the Committee had sought additional
information/clarifications on various related issues.

Based on the additional information/clarifications submitted by the proponent, the


proposal was considered further. The proponent made a presentation on the same. The
proposal is for enhancement of production of iron ore from 0.0163 million TPA to 0.4006
million TPA and renewal of mine lease which is due since 1996. TORs for this project were
Page 6 of 73

prescribed on 4.9.2008. Public hearing has been held on 9.8.2010.

There is no National Park / Sanctuary located within the 10 Km radius of the proposed
ML area. The ML area is situated within the core zone of Singhbhum Elephant Reserve. A
wildlife conservation plan has been prepared and submitted to PCCF, Ranchi for their
approval. Map showing the location of Sanctuary / National Park / Wildlife Corridors etc.,
w.r.t. the mine has been authenticated by the PCCF, Ranchi vide letter no. 186(WL)10-
11/12 on dated 06.01.11.

The ML area of 141.64 ha is a forest land, falls within the Karampada Reserve Forest of
Saranda Forest Division in Chaibasa District of Jharkhand State. An area of 18.975 ha was
broken prior to 1980. An application for forest clearance along with the Forest Diversion
Proposal for 38.537 ha including the broken up area was made on 14.08.08 to the PCCF,
Ranchi. The highest production achieved prior to 1994 was reported to be 16,300.5 TPA.
The mine was reported to have been worked up to 1993 and closed thereafter. Mine
working will be opencast mechanized involving drilling and blasting. Life of mine is 15
years for the existing broken up area and 140 years for the entire area. Water requirement
for the project is estimated as 70 kld, which will be obtained from Kande nallah. Fresh
baseline AAQ monitoring data has been generated from Mar-2012 to May-2012. The project
being located in identified severely polluted area, comments of SPCB were obtained. The
parameters were found to be within permissible limits.

Based on the presentation made and discussion held, the Committee recommended
the project for environmental clearance.

2.8 Sand/Boulder mining of M/s Rajesh Kumar Dubey, Village Billi markundi, Distt.
Sonbhadra, U.P. (ML area-3.00 Acres) - TORs- On the direction of the Hon’ble
Supreme Court.

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.9 Hulsam Stone Quarry of M/s Sri Om Prakash Jaiswal, Village Hulsam, Tehsil
Chatarpur, Distt. Palamu, Jharkhand (1.11 acres) -TORs - On the direction of the
Hon’ble Supreme Court.

The proposal was considered and examined by the Committee on the directions of
the Hon’ble Supreme Court on bringing all mines within the fold of prior EC, irrespective of
their M.L. size. Thus, the present proposal, though of less than 5 ha lease area (and hence
not covered under the Sept. 2006 Notification), was appraised with the objective of
recommending summary issuance or denial of EC by MoEF. For this purpose, the proponent
has submitted information in the prescribed format (Form-1) along with a brief Pre-
Feasibility Report.

The Committee noted that the size of the mine, production rate, the mineral mined
and the eco-sensitivity of the area are such that the operation of the mine will have
negligible impact on the surroundings and as such the project deserved to be granted the
blanket environment clearance subject to the mines less than 5 ha area being formally
brought under the EC regime on the directions of Hon’ble Supreme Court.
Page 7 of 73

For the same reasons of size of the leasehold and environmental impact being
negligible, there will not be any need for issue of TOR, nor any formal EIA / EMP being
prepared in the instant case, nor will it be necessary for the PP to go for a Public Hearing.
These prescribed exemptions are recommended by the Committee in the instant case,
which will make the Project Proponent (PP for short) eligible for getting the EC forthwith.

However, the Committee noted that the PP has not prepared any Mine Plan duly
approved or to be approved (as may have been so required) by the Competent Authority; in
the instant case, the State Director of Geology & Mining / State Government either singly or
in a cluster. The Committee feels that it is in the best interest of the PP as well as the
Regulatory Agencies, that the PP prepares a simple Mine Plan (with proposed mining
method and environment protection measures therein) and cumulative impact of similar
mines in the neighbourhood, if any and submits the same at their earliest to the Ministry.

2.10 Open cast mining Activity from Mauja Chaparwar of M/s Anand Kumar Singh,
Village Chaparwar, Tehsil Hariharganj,Distt. Palamau, Jharkhand (1.2707
ha)- TOR- On the direction of the Hon’ble Supreme Court.

The proposal was considered and examined by the Committee on the directions of
the Hon’ble Supreme Court on bringing all mines within the fold of prior EC, irrespective of
their M.L. size. Thus, the present proposal, though of less than 5 ha lease area (and hence
not covered under the Sept. 2006 Notification), was appraised with the objective of
recommending summary issuance or denial of EC by MoEF. For this purpose, the proponent
has submitted information in the prescribed format (Form-1) along with a brief Pre-
Feasibility Report.

The Committee noted that the size of the mine, production rate, the mineral mined
and the eco-sensitivity of the area are such that the operation of the mine will have
negligible impact impact on the surroundings and as such the project deserved to be
granted the blanket clearance subject to the mines less than 5 ha area brought under the EC
regime on the directions from Hon’ble Supreme Court.

For the same reasons of size of the leasehold and environmental impact being
negligible, there will not be any need for a formal EIA / EMP being prepared in the instant
case, nor will it be necessary for the PP to go for a public hearing. These prescribed
exemptions are recommended by the committee which will entail the proponent for getting
the EC forthwith.

However, the Committee noted that the PP has not prepared any Mine Plan duly
approved or to be approved (as may have been so required) by the Competent Authority; in
the instant case, the State Director of Geology & Mining / State Government either singly or
in a cluster. The Committee feels that it is in the best interest of the PP as well as the
Regulatory Agencies, that the PP prepares a simple Mine Plan (with proposed mining
method and environment protection measures therein) and cumulative impact of similar
mines in the neighbourhood, if any and submits the same at their earliest to the Ministry.

2.11 Open cast mining Activity from Mauja Chaparwar of M/s Anand Kumar Singh,
Village Chaparwar, Tehsil Hariharganj, Distt. Palamau, Jharkhand (2.238
ha) -TOR- On the direction of the Hon’ble Supreme Court.
Page 8 of 73

The proposal was considered and examined by the Committee on the directions of
the Hon’ble Supreme Court on bringing all mines within the fold of prior EC, irrespective of
their M.L. size. Thus, the present proposal, though of less than 5 ha lease area (and hence
not covered under the Sept. 2006 Notification), was appraised with the objective of
recommending summary issuance or denial of EC by MoEF. For this purpose, the proponent
has submitted information in the prescribed format (Form-1) along with a brief Pre-
Feasibility Report.

The Committee examined and noted that the size of the mine, production rate, the
mineral mined and the eco-sensitivity of the area are such that the operation of the mine
will have negligible impact on the surroundings and as such the project deserved to be
granted the blanket clearance subject to the mines less than 5 ha area brought under the EC
regime on the directions from Hon’ble Supreme Court.

For the same reasons of size of the leasehold and environmental impact being
negligible, there will not be any need for a formal EIA / EMP being prepared in the instant
case, nor will it be necessary for the PP to go for a public hearing. These prescribed
exemptions are recommended by the committee which will entail the proponent for getting
the EC forthwith.

However, the Committee noted that the PP has not prepared any Mine Plan duly approved
or to be approved (as may have been so required) by the Competent Authority; in the
instant case, the State Director of Geology & Mining / State Government either singly or in a
cluster. The Committee feels that it is in the best interest of the PP as well as the Regulatory
Agencies, that the PP prepares a simple Mine Plan (with proposed mining method and
environment protection measures therein) and cumulative impact of similar mines in the
neighbourhood, if any and submits the same at their earliest to the Ministry.

2.12 Proposal for collection of Sand, Stone and Bajri of M/s AARESS Grits, Village
Kuthar Beet, Tehsil Haroli, Distt. Una, H.P. (4.556 ha)-TOR- On the direction of
the Hon’ble Supreme Court.

The proposal was considered and examined by the Committee on the directions of
the Hon’ble Supreme Court on bringing all mines within the fold of prior EC, irrespective of
their M.L. size. Thus, the present proposal, though of less than 5 ha lease area (and hence
not covered under the Sept. 2006 Notification), was appraised with the objective of
recommending summary issuance or denial of EC by MoEF. For this purpose, the proponent
has submitted information in the prescribed format (Form-1) along with a brief Pre-
Feasibility Report.

The Committee examined and noted that the size of the mine, production rate, the
mineral mined and the eco-sensitivity of the area are such that the operation of the mine
will have negligible impact on the surroundings and as such the project deserved to be
granted the blanket clearance subject to the mines less than 5 ha area brought under the EC
regime on the directions from Hon’ble Supreme Court.

For the same reasons of size of the leasehold and environmental impact being
negligible, there will not be any need for a formal EIA / EMP being prepared in the instant
case, nor will it be necessary for the PP to go for a public hearing. These prescribed
exemptions are recommended by the committee which will entail the proponent for getting
Page 9 of 73

the EC forthwith.

However, the Committee noted that the PP has not prepared any Mine Plan duly
approved or to be approved (as may have been so required) by the Competent Authority; in
the instant case, the State Director of Geology & Mining / State Government either singly or
in a cluster. The Committee feels that it is in the best interest of the PP as well as the
Regulatory Agencies, that the PP prepares a simple Mine Plan (with proposed mining
method and environment protection measures therein) and cumulative impact of similar
mines in the neighbourhood, if any and submits the same at their earliest to the Ministry.

2.13 Proposed Niwada Sand Mining of M/s Sri Shripal, Village Niwada, Tehsil
Baghpat, Distt. Baghpat, U.P. (1.9550 ha)- TOR- On the direction of the Hon’ble
Supreme Court.

The proposal was considered and examined by the Committee on the directions of
the Hon’ble Supreme Court on bringing all mines within the fold of prior EC, irrespective of
their M.L. size. Thus, the present proposal, though of less than 5 ha lease area (and hence
not covered under the Sept. 2006 Notification), was appraised with the objective of
recommending summary issuance or denial of EC by MoEF. For this purpose, the proponent
has submitted information in the prescribed format (Form-1) along with a brief Pre-
Feasibility Report.

The Committee examined and noted that the size of the mine, production rate, the
mineral mined and the eco-sensitivity of the area are such that the operation of the mine
will have negligible impact on the surroundings and as such the project deserved to be
granted the blanket clearance subject to the mines less than 5 ha area brought under the EC
regime on the directions from Hon’ble Supreme Court.

For the same reasons of size of the leasehold and environmental impact being
negligible, there will not be any need for a formal EIA / EMP being prepared in the instant
case, nor will it be necessary for the PP to go for a public hearing. These prescribed
exemptions are recommended by the committee which will entail the proponent for getting
the EC forthwith.

However, the committee feels that it is in the best interest of the PP as well as the
regulatory agencies; the PP prepares a simple mine plan and submits the same at their
earliest to the Ministry.

The committee noted that the PP has not prepared any mine plan duly approved or
to be approved by the Competent Authority, in the instant case the State Director of Geology
& Mining / State Government either singly or in a cluster.

2.14 Mining of Sand stone and Bajri of M/s Ranjit Rana, Village & PO Spail, Tehsil
Jawali, Distt. Kangra, H.P. (14.0036 ha) -TORs.

This item, already dealt with, has got repeated inadvertently; hence passed over.

2.15 Devpura-I Soapstone Mine of M/s Associated Soapstone Distributing Co. Pvt.
Ltd., Village Devpura, Tehsil Sarada, Distt. Udaipur, Rajasthan (70.40 ha)-TORs
(Consultant : ENKAY ENVIRO SERVICES)
Page 10 of 73

The proposal was considered by the Committee to determine the Terms of


Reference (TORs) for undertaking detailed EIA study for obtaining Environmental
Clearance (EC for short) in accordance with the provisions of the EIA Notification, 2006. For
this purpose, the proponent has submitted information in the prescribed format (Form-1)
along with a Pre-Feasibility Report.

The proposal is of Soapstone Mine of 0.075 MTPA capacity of M/s Associated


Soapstone Distributing Co. Pvt. Ltd., Village Devpura, Tehsil Sarada, Distt. Udaipur,
Rajasthan. The Project Cost is 7.75 Crores. The mining operations are continuing since
1953. The lease is effective from 24.01.1993 and upto 23.01.2013 for 20 years, as granted
vide Government order no. P 5 (86) Khan/ Group-2/ 92 dated 05.08.2000 over an area of
70.214 ha. Jaisamand Game Sanctuary exists at a distance of 6.0 km towards East from mine
site. Proposal for NOC has already been initiated for approval by the Chief Wildlife Warden/
State Wildlife Department.

Vide letter no. J-11015/161/2003-IA.II (M) dated 16th February 2005, EC was
granted from MoEF, New Delhi. Compliance report of the Conditions stipulated by MoEF has
been certified by Regional Office, Lucknow vide letter no. IV/ENV/R/MINE-
211/320/2005/357 dated 17.08.2012. Current Scheme of Mining and Progressive Mine
Closure Plan was approved by IBM vide letter no. SME/ UD-Cir/Mining Plan/ Scheme/
UDR/ F01/09/879-885 dated 03.06.2009, which is valid from 2009-10 to 2013-14. The
mining operation is being carried out by mechanized open cast method of mining.

The water demand is being met from dug well situated outside the lease area. The
daily water demand is 33.0 KLD. The ground water table is at 305 MSL. The ultimate
working depth in Block – A is 325 MSL and in Block – B it will be 410 MSL. Hence, water
table will not be encountered during the life of mine. Overburden/ waste generated during
the first year of scheme period is 12,90,892 tons and at the end will be 79,35,156 tons. The
generated waste will be initially dumped on non-mineralized zone in the form of terraces of
10 m height. The lease area is in forest land and consist of two blocks (30.83 ha in Block A –
Mahadev and 39.384 ha. in Block – B Ganesh) in addition to this 0.186 ha. area is for road,
which is outside to lease area. Thus, the total retained area is 30.83 ha + 39.57 ha = 70.40
ha. As the area, falls in Forest and the clearance for the same has been obtained from MoEF,
New Delhi, vide letter no. 8-67/ 97 – FC dated 29.10.1999 in favour of M/s. Associated
Soapstone Distributing Co. Pvt. Ltd.

Based on the information furnished and presentation made, the Committee


prescribed the following TORs for undertaking detailed EIA study:-

1) Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t. the highest production
achieved prior to 1994.
2) A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
Page 11 of 73

the name of the lessee.


4) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5) Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
6) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions? Details of this system may be given.
8) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
10) Land use of the study area delineating forest area, agricultural land, grazing
land, wildlife sanctuary and national park, migratory routes of fauna, water
bodies, human settlements and other ecological features should be indicated.
11) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above, should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
of funds for implementing the same should be made as part of the project cost.
14) Impact, if any, of change of land use should be given.
15) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly,
integrating the sectoral programme of line departments of the State
Government.
16) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location
Page 12 of 73

of the monitoring stations should be such as to represent whole of the study


area and justified keeping in view the pre-dominant downwind direction and
location of sensitive receptors. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The
mineralogical composition of PM10, particularly for free silica, should be given.
17) Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account the impact
of movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
18) The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
19) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
20) Details of water conservation measures proposed to be adopted in the project
should be given.
21) Impact of the project on the water quality, both surface and groundwater,
should be assessed and necessary safeguard measures, if any required, should
be provided.
22) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
23) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24) Details of rainwater harvesting proposed, if any, in the project should be
provided.
25) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
26) Quantity of solid waste generation to be estimated and details for its disposal
and management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dumps (number of dumps, their height,
terraces etc. to be brought out).
27) The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
28) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
Page 13 of 73

network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
29) Details of the infrastructure facilities to be provided for the mine workers
should be included in the EIA report.
30) Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
31) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33) Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed
remedial measures should be detailed along with budgetary allocation.
34) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
35) Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the projects.
36) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
37) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
38) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous page
numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
Page 14 of 73

instructions for the consultants issued by MoEF vide O.M. No. J-


11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.

The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the Public Hearing conducted and take further necessary action for obtaining
Environmental Clearance (EC for short) in accordance with the procedure prescribed under
the EIA Notification, 2006.

2.16 Iron Ore Beneficiation & Pelletization Plant of M/s Archana Hi Tech
Automation System Pvt. ltd., Hargarh, Tehsil Sihora, Distt. Jabalpur, M.P. (0.72
Million Ton/year and 0.64 Million Ton)-EC (Consultant: Enviro Techno
Consult)

The proposal is for setting up of a iron ore Beneficiation Plant with a capacity of 0.72
million TPA along with Pelletization Plant with a capacity of 0.64 million TPA. The land
requirement for the project is estimated as 1.096 ha, which will be located in Hargarh,
notified industrial area in Silhora Tehsil, District Jabalpur, Madhya Pradesh. The fresh water
requirement for the project is estimated as 910 kld, which will be obtained from Hiren river.
It was stated that the low grade iron ore will be beneficiated and the fines will be used in
the Pellet Plant.
The proponent made a request for exemption from Public Hearing for this project
on the ground that the said project will be located in the notified industrial area and
submitted letters no. 2096/3093/2011/B-11 dated 18.10.2011, no. F-11-61/2005/B-11
dated 13.3.2007 from the Commerce, Industry and Employment Department, Govt. of
Madhya Pradesh, as also a Notification of the Govt. of Madhya Pradesh dated 23.5.2008 in
support of their claim. A perusal of the documents showed that the State Govt. of Madhya
Pradesh have notified this land for industrial purpose. As such, it only confirms the land use
of the area. Further, since industrial estates / parks/ complexes/areas/EPZ/SEZ have found
a specific entry in the EIA Notification, 2006, the Notification of these areas would require
Environmental Clearance under the provisions thereof as per the prescribed procedure.
Only thereafter, the individual projects / activities to be located in such areas would be
exempted from separate public hearing. In the instant case, no such EC document was made
available for the Hargarh Industrial area. In the absence of the requisite supporting
documents, the Committee did not agree with the request of the Proponent for exemption
from Public Hearing. Bohra Reserved forest is at 2.0 Km and Dhanwahd RF is at 6.5 km. The
Page 15 of 73

proposed Plant [located in Notified Industrial Area at Hargarh (Sihora), Dist. Jabalpur,
Madhya Pradesh] is at Latitude: 23° 29’ 09’’ North and Longitude: 80° 06’54’’ East. The
Project area is 23,488 sqm and Lora Hill Forest is located 2.0 km to the North. The Hiren
River at 1500m to south and is a source of water for MPAKVN. 2 villages namely Hargarh &
Daraula, exist within 2 km radius.
Availability of the raw material is within 10 km, and existing roads shall be used for
transportation of ore in dumpers duly covered. About 85% water will be recovered through
water reclamation system and recycled. Water used for beneficiation will be in closed
circuit and will not be allowed to go out of the system. Raw ore, concentrates and waste
stocks will be protected by coir mats followed by RCC bedded trenches leading to tailing
pond.

The solid waste will be allowed to settle in the settling ponds and will be scraped
out of the ponds and dumped at designated place, the seepage water coming out from the
scraped solids will go to tailing pond again through the surrounding RCC bedded trench.

Based on the presentation made and discussion held, the Committee desired the PP
to get the Public Hearing conducted by the concerned SPCB, following the due process and
submit the Report along with the Video Recording thereof, time bound Action Plan on the
issues raised and agreed upon in the PH and final EIA/EMP to MoEF for further
consideration of the EC proposal by the EAC (Mining). The Committee also desired
submission of AAQ data of December /Winter Season as discussed.

2.17 Limestone Production of 2.0 MTPA of M/s Adhunik Cement ltd., Village
Thangskai, Jaintia Hills Distt., Meghalaya (128.52 ha and 19.33 ha outside
dump)-EC (Consultant: B .S. Envi – Tech Pvt. Ltd, Hyderabad)

The proposal is for opening of a new mine for production of 2.0 million TPA of
limestone for the captive use in their cement plant adjacent to the mine lease. The mine
lease area is 128.52 ha and approved by IBM. It was reported that Environmental Clearance
for the cement plant has already been obtained. The PP has obtained Stage – I FC clearance
for 147.85 ha (128.52 ha and 19.33 ha outside dump), the same also includes the safety
zone of 9.736 ha (out of which ML area safety zone is 7.55 ha and dump area is 2.18ha). The
mine working will be opencast mechanized mining involving drilling and blasting. Life of
mine is 31 years. Ultimate working depth will be 30 m bgl. Water requirement is 30 kld.
River Lubha is at 8.5 km and River Umluner is at 6.3 km. Blasting of the mineral at the
mining lease will be done using slurry explosive. Cumulative impact of cement plant, power
plant and Captive limestone mine was estimated. Total waste generation will be 24.0 MT
(rocky overburden – red sandstone) and will be dumped outside the lease in an area of
19.33 ha up to a height of 25 m.

On being informed by the PP about Change of Land Category, the Ministry had
issued additional TORs, to be addressed appropriately in the Draft EIA report already
prepared. Comparison of changes made in the Draft EIA Report (submitted for public
hearing) and Final EIA Report was submitted as part of final EIA document.

Government of Meghalaya, Office of Chief Conservator of Forests, Wild Life circle of


Meghalaya, Shillong, vide letter dated FWC/G/117 dated 16th November, 2010 has
confirmed that there are no threatened species except one species of Schedule–I i.e.,
Page 16 of 73

Bambusicola Fitchi Hapkinsoni (common name: Assam Bamboo Patridge) belonging to Avi
Fauna observed in study area of 10 km radius. The issues raised during Public Hearing were
also considered and discussed during the meeting. It was reported that there is no court
case pending against the project. Areas of afforestation will cover 7.5 m wide statutory
barrier zone (7.55 ha) and Dump area (19.33 Ha) – outside lease. Apart from the above, an
area of about 26.55 ha will be developed on the bench slopes.

Based on the presentation made and discussion held, the Committee recommended
the project for Environmental Clearance subject to an apprppriate Conservation Plan for the
sited Schedule–I species, i.e., Bambusicola Fitchi Hapkinsoni (common name: Assam Bamboo
Patridge), duly approved by the concerned Chief Conservator of Wild Life.

2.18 Proposed Manganese ore mining of M/s Aditya Minerals Pvt. Ltd., Village Guda,
Distt. Adilabad, A.P. (89.03 ha)-EC

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.19 Chawandiya & Madpura Limestone Mine of M/s MW Mines Pvt. Ltd., Village
Chawandiya - Madpura, Testily Khminsar, Distt. Nagpur, Rajasthan (335.37
ha)-EC

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.20 Fatepur Stone Mine of M/s Hindustan Construction Co. Ltd., Village Fatepur,
Distt. Pakur, Jharkhand (5.61 ha)-TOR-(Consultant: MANTEC CONSULTANTS
PVT. LTD., NEW DELHI)

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining Environmental Clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
proponent has submitted information in the prescribed format (Form-1) along with a Pre-
Feasibility Report.

The project is located at Village: Fatehpur, Taluk: Patharia, Block: Hiranpur, District:
Pakur, State: Jharkhand at latitude/longitude of 24044’59.17”N / 87047’16.41” E. The land is
a Government waste land. The life of mine is 2 years. Opencast Mechanized method will be
used. No blasting shall be used. Water demand is 11 KLD and the source of water is
borewell. The lease deed has been executed in favour of M/s Hindustan Construction
Company Ltd., vide letter no. nil dated 08/07/2010 for a period of 10 years, w. e. f. 08-07-
2010 to 07-07-2020. The mine lease area is within 3.0 kms from interstate boundary
between Jharkhand and West Bengal States. River Kanlai, is about 5 km from the mine and
Ganga Feeder Canal is within 10 km of mine. One primary school is located within 200
meters from the Lease boundary.

Based on the information furnished and presentation made, the Committee


prescribed the following TORs for undertaking detailed EIA study:-
1) A copy of the document in support of the fact that the proponent is the rightful
Page 17 of 73

lessee of the mine should be given.


2) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in the
name of the lessee.
3) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
4) Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
5) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
6) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC conditions.
Details of this system may be given.
7) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
8) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should be
for the life of the mine / lease period.
9) Land use of the study area delineating forest area, agricultural land, grazing land,
wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features should be indicated.
10) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
11) A confirmation may be adduced, duly authenticated by the competent authority in
the State Government to the effect whether the project falls in Aravalli and
whether it is covered by the order of the Hon’ble Supreme Court dated 8.4.2005 in
the contempt petition (c) 412/2004 in writ petition 202 of 1995 in the matter of
Godavarman vs Union of India.
12) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of the
mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be furnished
based on primary field survey clearly indicating the Schedule of the fauna present.
In case of any scheduled-I fauna found in the study area, the necessary plan for
their conservation should be prepared in consultation with State Forest and
Wildlife Department and details furnished. Necessary allocation of funds for
implementing the same should be made as part of the project cost.
14) Impact, if any, of change of land use should be given.
15) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Page 18 of 73

Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
assess their requirement and action programmes prepared accordingly integrating
the sectoral programme of line departments of the State Government.
16) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be collected
and the AAQ data so collected presented date-wise in the EIA and EMP report.
Site-specific meteorological data should also be collected. The location of the
monitoring stations should be such as to represent whole of the study area and
justified keeping in view the pre-dominant downwind direction and location of
sensitive receptors. There should be at least one monitoring station within 500 m
of the mine lease in the pre-dominant downwind direction. The mineralogical
composition of PM10 particularly for free silica should be given.
17) Air quality modelling should be carried out for prediction of impact of the project
on the air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model used
and input parameters used for modelling should be provided. The air quality
contours may be shown on a location map clearly indicating the location of the site,
location of sensitive receptors, if any and the habitation. The wind roses showing
pre-dominant wind direction may also be indicated on the map.
18) The water requirement for the project, its availability and source to be furnished.
A detailed water balance should also be provided. Fresh water requirement for
the project should be indicated.
19) Necessary clearance from the Competent Authority for drawl of requisite quantity
of water for the project should be provided.
20) Details of water conservation measures proposed to be adopted in the project
should be given.
21) Impact of the project on the water quality both surface and groundwater should be
assessed and necessary safeguard measures, if any required should be provided.
22) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground water
and for pumping of ground water should also be obtained and copy furnished.
23) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24) Details of rainwater harvesting proposed, if any, in the project should be provided.
25) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for the
same.
26) Quantity of solid waste generation to be estimated and details for its disposal and
management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should be
indicated. Details of backfilling proposed, if any, should also be given. It may be
clearly indicated that out of the total waste generated during the mine life, how
much quantity would be backfilled and how much quantity would be disposed off
in the form of external dump (number of dumps, their height, terraces etc. to be
brought out).
Page 19 of 73

27) The reclamation plan, post mine land use and progressive greenbelt development
plan shall be prepared in tabular form (prescribed format) and submitted.
28) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
29) Details of the infrastructure facilities to be provided for the mine workers should
be included in the EIA report.
30) Conceptual post mining land use and Reclamation and Rehabilitation of mined out
area (with plans and with adequate number of sections) should be given in the EIA
report.
31) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33) Public health implication of the project and related activities for the population in
the impact zone should be systematically evaluated and the proposed remedial
measures should be detailed along with budgetary allocation.
34) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
35) Detailed environmental management plan to mitigate the environmental impacts
which, should inter-alia also include the impact due to change of land use, due to
loss of agricultural land and grazing land, if any, occupational health impacts
besides other impacts of the projects.
36) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
37) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
38) The cost of the project (capital cost and recurring cost) as well as the cost towards
implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous page
numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
Page 20 of 73

prescribed by the Ministry shall also be filled and submitted.


f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the
EIA Notification, 2006) covering the above mentioned issues, the proponent will get the
public hearing conducted and take further necessary action for obtaining environmental
clearance in accordance with the procedure prescribed under the EIA Notification, 2006.

2.21 Mining of stone, sand & Bajri of M/s Krishna Stone Crushing Co., Village & PO
Paragpur, Tehsil Dehra, Distt. Kangra, H.P. (18.6875 ha) –TOR

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.22 Mining of Sand stone and Bajri of M/s Sh. Sanjay Kumar, Village & PO Dabhiri,
Tehsil Barsar, Distt. Hamirpur, H.P. (19.4970 ha)-TOR

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.23 Januda Limestone Area of M/s GHCL, Village Januda, Taluka Maliya Hatina,
Distt. Junagadh, Gujarat (78.0426 ha)-TOR-(Consultant: UDAIPUR MIN–TECH.
PVT. LTD.)

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining Environmental Clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
proponent has submitted information in the prescribed format (Form-1) along with a Pre-
Feasibility Report.

The proposal is for opening of a new limestone mine of M/s GHCL Ltd to meet the
limestone requirement for its 2400 TPD Soda ash plant situated in Sutrapada village of
Junagarh distt. The chemical grade limestone is the basic raw material used in soda ash
Page 21 of 73

manufacturing process, therefore the company has applied for a new lease for mineral
limestone over an area of 94.4208 ha. Near village Januda, Taluka–Maliya Hatina, Dist.
Junagarh of Gujarat for a period of 30 years on 21.12.2006. The company was issued a LOI
for grant of mining lease vide letter no MCR-102010-ML-123-(105)- CHH-1 dated
21.01.2011 by Industries & Mines Department, Gujarat, over an area of 78.0426 ha. The
mine is located at a Longitude / Latitude of 21º 01΄ 44΄΄- 21º 02΄ 20΄΄ N / 70º 19΄ 03΄΄- 70º
20΄ 55΄΄ E. River Hiran is 6.0 Km South East, River Megal is 2.0 Km North West and Arabian
Sea is at 8.45 Km. South. The production target is 2,24,719 TPA (ROM) and the method of
mining will be open cast with drilling & blasting and maintaining the bench height of 3.0 m.
The slope of benches will be 700. The ultimate depth will be 25 – 27 mRL (3 - 7 m bgl) upto
mine life.
The water requirement is 23 KLD. Out of total area of 78.0426 ha, 12.3615 ha is
Private land and 65.6811 ha is Government Waste land. About 11.27 ha mined out benches
will be used for plantation and remaining 50.73 ha for rain water storage. Total 20 ha will
be covered by plantation out of which 11.27 ha will be over mined out benches & 8.73 ha for
green belt development along lease boundary.
Based on the information furnished and presentation made, the Committee
prescribed the following TORs for undertaking detailed EIA study:-

1) The PP may examine the use of Surface Miners and furnish the outcome thereof..
2) Combined impacts should be presented. The prediction of impacts should take
into consideration the soda ash plant as well as any other activity within the
study area.
3) A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
4) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
5) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
6) Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
7) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
8) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
9) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
10) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
11) Land use of the study area delineating forest area, agricultural land, grazing
land, wildlife sanctuary and national park, migratory routes of fauna, water
Page 22 of 73

bodies, human settlements and other ecological features should be indicated.


12) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
13) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
14) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
of funds for implementing the same should be made as part of the project cost.
15) Impact, if any, of change of land use should be given.
16) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State
Government.
17) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location
of the monitoring stations should be such as to represent whole of the study
area and justified keeping in view the pre-dominant downwind direction and
location of sensitive receptors. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The
mineralogical composition of PM10 particularly for free silica should be given.
18) Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account the impact
of movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
The combined impact should be worked out.
19) The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
20) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
21) Details of water conservation measures proposed to be adopted in the project
should be given.
Page 23 of 73

22) Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required should be
provided.
23) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may
be provided. In case the working will intersect groundwater table, a detailed
hydro geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
24) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
25) Details of rainwater harvesting proposed, if any, in the project should be
provided.
26) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
27) Quantity of solid waste generation to be estimated and details for its disposal
and management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
28) The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
29) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
30) Details of the infrastructure facilities to be provided for the mine workers
should be included in the EIA report.
31) Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
32) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted
33) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
34) Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed
remedial measures should be detailed along with budgetary allocation.
Page 24 of 73

35) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
36) Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the projects.
37) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
38) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
39) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous page
numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
Page 25 of 73

environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.24 Mining of Sand Stone and Bajri of M/s Kajla Stone Crusher, Village & PO Moch,
Tehsil Fatehpur, Distt. Kangra, H.P. (11.2279 ha) –TOR
The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.25 Proposed Ullikallu Dolomite Mine of M/s Ullikallu Dolomite Mine Pvt.ltd.,
Village Ullikallu, Singanamala Mandal, Distt. Ananthapur, A.P. (67.017 ha)-
TOR (Consultant: Pragati Labs and Consultants).

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining Environmental Clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
Project Proponent (PP) has submitted information in the prescribed format (Form-1) along
with a Pre-Feasibility Report.

The proposal of Ullikallu Dolomite Mine of M/s Ullikallu Dolomite Mine Pvt. ltd.,
Village Ullikallu, Singanamala Mandal, Distt. Ananthapur, A.P. to an extent of 67.017 ha is for
the production of Dolomite @ 1,00,550 tonnes per Annum (Max) and Life of Mine is 222
Years. No forest land is involved. The highest R.L. is 453.0 m (MSL) and Lowest R.L. is 350.5
m (MSL). The Latitude is 14° 52’ 30” N to 14° 53’ 13” N and Longitude is 77° 48’ 02” E to 77°
49’ 07” E. The mining method will be opencast and the water requirement will be 20
m3/day. The Mining Plan is approved by IBM vide Letter No. 5027/MP-TDP/2008 dated 20-
11-2008. The mining Lease is obtained from Industries and Commerce (M-III) department
vide Letter No. 1728/M-III (1) /2007 dated 04-07-2008. Total waste at the end of lease
period will be 89,500m3. Area occupied by waste dump will be 44,750m2 and Height of
waste dump will be 2 m.

Based on the information furnished and presentation made, the Committee prescribed
the following TORs for undertaking detailed EIA study:-

1) Year-wise production details since 1994 onwards should be given clearly


stating the highest production achieved in any one year prior to 1994. It may
also be categorically informed whether there had been any increase in
production after the EIA Notification, 1994 coming into force w.r.t. the highest
production achieved prior to 1994.
2) A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
4) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5) Does the company have a well laid down Environment Policy approved by its
Page 26 of 73

Board of Directors? If so, it may be detailed in the EIA report.


6) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
8) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc
should be for the life of the mine / lease period.
10) Land use of the study area delineating forest area, agricultural land, grazing
land, wildlife sanctuary and national park, migratory routes of fauna, water
bodies, human settlements and other ecological features should be indicated.
11) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas
as mentioned above should be obtained from the State Wildlife Department/
Chief Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy
furnished.
13) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary
allocation of funds for implementing the same should be made as part of the
project cost.
14) Impact, if any, of change of land use should be given.
15) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State
Government.
16) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location
of the monitoring stations should be such as to represent whole of the study
area and justified keeping in view the pre-dominant downwind direction and
Page 27 of 73

location of sensitive receptors. There should be at least one monitoring station


within 500 m of the mine lease in the pre-dominant downwind direction. The
mineralogical composition of PM10 particularly for free silica should be given.
17) Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account the impact
of movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
18) The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
19) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
20) Details of water conservation measures proposed to be adopted in the project
should be given.
21) Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required should be
provided.
22) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may
be provided. In case the working will intersect groundwater table, a detailed
hydro geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
23) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24) Details of rainwater harvesting proposed, if any, in the project should be
provided.
25) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
26) Quantity of solid waste generation to be estimated and details for its disposal
and management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
27) The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
28) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement
Page 28 of 73

for improving the infrastructure, if contemplated (including action to be taken


by other agencies such as State Government) should be covered.
29) Details of the infrastructure facilities to be provided for the mine workers
should be included in the EIA report.
30) Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
31) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33) Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed
remedial measures should be detailed along with budgetary allocation.
34) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
35) Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the projects.
36) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
37) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
38) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous page
numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
Page 29 of 73

website of this Ministry should also be followed.


h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.26 Proposed Mining of Sand/Morrum of M/s Mr. Virender Kumar Rai, Village
Devisinghpura, Luhargaon, Maukhas, Bhakoro, Sitora & Khishi Bujurg, Tehsil
Mauranipur, Distt. Jhansi, U.P. (54.61 ha) –TORs

Inadvertently repeated hence passed over.

2.27 Mining of Sand Stone and Bajri of M/s Sh Navneet Sharma, Village & PO Har,
Tehsil Jawali, Distt. Kangra, H.P. (11.7281 ha) –TOR.

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.28 Mining of Sand stone and Bajri of M/s Shiv Shakti Stone Crusher Co-Operative
Industrial Society, Village Anuhi, Jangal, Soldha, Tehsil Jawali, Distt. Kangra,
H.P. (16.9752 ha)-TOR

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.29 Lohagarh Saopstone Mine of M/s Associated Soapstone Distributing Co. Pvt.
Ltd., Village Lohargarh, Tehsil Dhariawad, Distt. Pratapgarh, Rajasthan
(85.314 ha)-EC

The proposal was considered by the Committee and the proponent made a
presentation on the same. The proposal is for renewal of mine lease, which fell due from
January, 2011 for production of 30,000 TPA of soapstone. TORs for this project were
prescribed on 28-04-2011. Public Hearing has been held on 16.4.2012.
Page 30 of 73

The mine lease area is 85.31 ha. The Latitude is 23057’ 47.5’’– 23058’ 39.5’’ North
and Longitude is 74015’ 59.47’’–74016’50.06’’ East. Lohagarh Soapstone mining lease was
granted in the year 1971 over an area of 85.314 hectares including: Govt. Wasteland 56.224
ha and Private agriculture land 29.090 ha. Mining Plan has been approved by IBM vide
letter no. SME / BHIL-CIR / Mining Scheme / ML1 / 90 /1342-1350 dated 08.11.2010 for
production capacity of 30,000 TPA. Central Ground Water Authority vide order no. 21-
4(147)/ WR/CGWA/07-88 dated 16.04.2010 granted permission for withdrawal of ground
water not exceeding 115 m3/day. Life of the mine at proposed production capacity is 23
years and total O.B. Generation would be 1,48,14,652 T.
No forestland is involved. Mine working will be opencast semi-mechanised
involving drilling and blasting. It is estimated that 61,67,084 m3 of waste will be generated
up to the end of the mine life. Backfilling is proposed. Life of mine is 23 years. Ultimate
Depth of mining will be 120 m bgl. Depth of ground water table during post monsoon period
in the lease hold area is 200 m AMSL. Hydro Geological Study has been conducted to assess
impact of mining on Ground Water. Groundwater table is reported to vary between 8 – 15 m
bgl. Mine working will intersect groundwater table. Water requirement will be around 22
KLD (from Ground Water: 0.885 KLD for drinking & from Mine Sump: 20.20 KLD for water
sprinkling, plantation). No Ecologically Sensitive areas exists within the study area (10km
radius from m.l. boundary like National Park, Wildlife Sanctuary, Biosphere Reserve and
Bird Sanctuary, Elephant Corridors, etc.

The issues raised during Public Hearing were also considered and discussed during
the meeting. It was reported that there is no court case pending against the project.
Based on the presentation made and discussion held, the Committee recommended
the project for environmental clearance.

2.30 Sand Stone and Khanda Mine of M/s Sh. Laxmi Chand Goyal, Village Chaikora
and Kharaga ka Nagala, Tehsil Rupbas, Distt. Bharatpur, Rajasthan (48.70 ha)-
EC (Consultant: ENKAY ENVIRO SERVICES)

The proposal was considered by the Committee and the proponent made a
presentation on the same. The proposal is for renewal of mine lease for production of
1,00,037 TPA of sand stone and khanda (minor mineral). TORs for this project were
prescribed on 20-05-2011. Public Hearing has been held on 20.3.2012. The mine lease area
is 48.70 ha. No forestland is involved. It has been considered as category ‘A’ project
because of inter-state boundary of U.P. and Rajasthan at a distance of 1 km. No National
Park / Sanctuary is reported within 10 km of the mine lease. The proposed method of the
mining will be by manual open cast. The height and width of bench will be maintained at
3.0m. The mining will be done from top to bottom by cutting 1.0m thick slices. The
exploitation of mineral will be done from 174m AMSL to 156m AMSL (conceptual phase).
Considering the stability of rocks, the ultimate pit slope proposed is 45° from vertical. Haul
road will be developed up to point of loading. Transportation of the mineral from pit –
mouth to destination will be by trucks. No drilling and blasting is involved for mineral
production.

Life of the mine is 41 years. Water requirement is 15 kld, which will be obtained
from nearby villages. The mine is reported to be closed for the last 7 years.

The lease was originally granted for an area of 153.6 ha. for a period of 30 years. The
Page 31 of 73

application for renewal of 48.70 ha was submitted on 11.06.1997 and remaining area was
surrendered. Renewal of revised lease area 48.70 ha is pending for want of Environmental
Clearance. The Eco-friendly mining plan has been approved by the Mining Engineer, DMG,
Bharatpur vide letter no. 2514 dated 24.02.2011. A confirmation duly authenticated by the
Mining Engineer, Bharatpur, Department of Mines and Geology stating that the project does
not falls in Aravalli has been obtained vide letter dated 14.06.2011. There is no National
Park, Wildlife Sanctuary, Wildlife Corridor, Tiger/ Elephant Reserve within 10Km radius
from the mine site. The same has been duly authenticated from the Office of Divisional
Forest Officer, Bharatpur vide letter dated 14.12.2011. An authenticated list of flora and
fauna has been obtained from the Office of Divisional Forest Officer, Bharatpur vide letter
dated 14.12.2011. No objection certificate has been obtained from the Office of Gram
Panchayat–Chaikora, Tehsil–Rupbas, District-Bharatpur (Rajasthan). There is no legal issue
against the project in the court of law.

Based on the presentation made and discussion held, the Committee recommended
the project for environmental clearance.

2.31 Mining Lease for Silicate Boulders of M/s Mohunta Mining & Mfg. Co. Pvt. Ltd.,
Village Mauza Bathri, Tehsil Haroli, Distt. Una, H.P. -TORs- Re-consideration
(Consultant: Eco Laboratories and Consultants, Mohali).

The proposal was considered by the Committee in its 16th meeting on 22.6.11 to
determine the Terms of Reference (TORs) for undertaking detailed EIA study for the
purpose of obtaining Environmental Clearance in accordance with the provisions of the EIA
Notification, 2006. During consideration of the proposal, it was observed that the mine lease
was only for silicate, though the Project Proponent proposes to collect other minerals also.
The Committee, therefore, desired that the proponent should first get the mine lease
modified by including all the associated minerals which are proposed to be excavated /
collected and thereafter come back and they have got approval from Department of
Industries, Government of H.P- Lease dated 01.04.2008 is valid for 20 years and inclusion of
associated minor minerals is taken on 4.1.2012.
Mining Lease is for Collection of Silica Boulder in an area of 8.98-35 ha at Khasra No.
303, 304 and 305 Mauza Bathri Part of Hum Khad, Sub Tehsil Haroli, District Una, H.P. Land
is on Lease from Private Individuals (Gair Mumkin Khad) as well as from Government (1-
54-85 ha) on bed of Hum Khad (a seasonal rivulet). There is no Forest Land involved.
Project land is at an aerial distance of 2 Km from the state boundary of neighboring State of
Punjab and hence is submitted to MoEF for Environmental Clearance. Maximum material
handling is 54,000 MT/annum.
Joint Inspection report from SDM, Forest Department, Pollution Control Board, PWD
and IPH Department and NOC from Village Panchayat is also obtained. Approval of Working
cum EMP from Govt. of H.P. dated 7-10-2008 (and amended for inclusion of associated
minerals on 27.2.2012) has been obtained.
Based on the information furnished and presentation made, the Committee prescribed
the following TORs for undertaking detailed EIA study:-

1) Year-wise production details since 2006 after the EIA Notification, 2006 coming
into force.
2) A copy of the document in support of the fact that the proponent is the rightful
Page 32 of 73

lessee of the mine should be given.


3) All documents including approved Working cum EMP plan, EIA report and public
hearing should be compatible with one another in terms of the mine lease area,
production levels, waste generation and its management and mining technology.
4) The terms and conditions imposed, if any, by the Competent Authority in the
State Government while granting mining lease / permit / contract should be built
into the Working cum EMP as well as the EIA report. It may inter-alia include;
area of working (length and breadth of the river stretch), mode of working,
working shift, transportation of mineral, restriction, if any imposed for working
etc.
5) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
6) Cumulative impact of all mines within the study area should be worked out and
presented in the EIA.
7) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
8) Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
9) Does the Environment Policy prescribe for standard operating
process/procedures to bring into focus any infringement / deviation / violation
of the environmental or forest norms / conditions? If so, it may be detailed in the
EIA.
10) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions? Details of this system may be given.
11) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
12) A study should also be carried out to decide on the quantum of mineral which can
be removed on sustainable basis taking into account the replenishment potential
of the area and details furnished.
13) Land use of the study area delineating forest area, agricultural land, grazing land,
wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features.
14) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases.
15) Impact of the project on the wildlife in the surrounding and any other protected
area and accordingly detailed mitigation measures required should be worked
out with cost implications.
16) The vegetation in the RF / PF in the study area, if any, should be indicated.
17) A study shall be got done to ascertain the impact of the mining project on wildlife
of the area including aquatic life.
18) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed) within 10 km of the mine
lease should be clearly indicated supported by a location map duly authenticated
by Chief Wildlife Warden. Necessary clearance from the Chief Wildlife Warden
for operating the mine within 10 km of the National Park/Sanctuary, if any,
should also be obtained and furnished.
Page 33 of 73

19) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] including the aquatic fauna in the
riverine system shall be carried out. Details of flora and fauna, duly
authenticated, separately for core and buffer zone should be furnished based on
primary field survey clearly indicating the Schedule of the fauna present. In case
of any scheduled-I fauna found in the study area, the necessary plan for their
conservation should be prepared in consultation with State Forest and Wildlife
Department and details furnished. Necessary allocation of funds for
implementing the same should be made as part of the project cost.
20) Impact of the project on land use including change of river course, if any should
be given.
21) Impact on topography, drainage, agricultural fields, cattle fields, wildlife, water
logging leading to water borne diseases, if any. It may also be shown whether it
will lead to change of watercourse of the river. Modelling exercise should also be
carried out through an expert agency to show the change in river flow dynamics,
if any.
22) Collection of one season (non-monsoon) primary baseline data on ambient air
quality (PM10, SO2 and NOx), water quality, noise level, soil and flora and fauna,
site-specific meteorological data should also be collected. The location of the
monitoring stations should be such as to represent whole of the study area and
justified keeping in view the pre-dominant downwind direction and location of
sensitive receptors. Date wise collected baseline AAQ data should form part of
EIA and EMP report. The mineralogical composition of PM10 particularly for free
silica should be given. There should be at least one AAQ monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction.
23) Air quality modelling should be carried out for prediction of impact of the project
on the air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
The impact of other mines in the impact zone as also the stone crusher and other
industries, if any, nearby should also be taken into account.
24) The water requirement for the project, its availability and source to be furnished.
A detailed water balance should also be provided. Fresh water requirement for
the project should be indicated.
25) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
26) Impact of the project on the water quality should be assessed and necessary
safeguard measures, if any required should be provided.
27) Information on site elevation, working depth, groundwater table should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
28) Quantity of solid waste generation, if any, should be estimated and details for its
disposal and management should be provided.
29) Impact on local transport infrastructure due to the project should be evaluated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) and whether it is capable of
handling the increased load should be estimated. Arrangement for improving the
Page 34 of 73

infrastructure, if contemplated including action to be taken by other agencies


such as State Government, if any, should be covered.
30) Details of the infrastructure facilities to be provided for the mine workers should
be furnished.
31) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation clearly indicating the area to be covered under plantation and the
species to be planted should be provided.
32) Occupational health impacts of the project activity should be anticipated and
reported and proposed preventive measures indicated. These along with details
of pre-placement medical examination and periodical medical examination
schedules and medical facilities proposed to be provided should be incorporated
in the EMP.
33) Measures of socio economic influence to the local community, proposed to be
provided by project proponent should be spelt out. As far as possible,
quantitative dimensions should be given.
34) Detailed environmental management plan to mitigate the environmental impacts.
Specific safeguard measures to control PM10 as well as pollution due to
transportation should be given. It should also address the impact due to stone
crusher nearby.
35) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
36) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
37) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points will also to be followed:-

a) A note confirming compliance of the TOR, with cross referencing of the


relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index, page numbers and
continuous page numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
Page 35 of 73

modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.

The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.32 Banrobar Bauxite Mine of M/s Leela Devi, Village Bandobar, Distt. Lohardaga,
Jharkhand (TOR- Re-consideration) (Consultant: Grass Roots Research and
Creation India (P) Ltd., Noida)

The proposal was considered by the Committee in its 20th Meeting during October
20th–22nd 2011to determine the Terms of Reference (TORs) for undertaking detailed EIA
study for obtaining Environmental Clearance in accordance with the provisions of the EIA
Notification, 2006. During consideration of the proposal, it was observed that the proposal
is for renewal of mine lease, which fell due in 2010 for production of 1,99,092 TPA of
bauxite. It was stated during the presentation that Smt. Deepali Pandey and Smt. Punita
Pandey are the present owners of the mine in their capacity as legal heirs of Late Smt. Leela
Devi. However, in the absence of documents in support of their legal succession, the
Committee had deferred consideration of the project.
The total mine lease area is 25.9 ha. The working will be opencast by mechanized
method. The IBM had approved Mining Plan on 16-10-1990. This is a violation case. Water
requirement is 8 KLD. Chupat river is at 4km NW. No National park/Wildlife
sanctuary/Biosphere reserve/Tiger reserve/Elephant reserve etc. are reported to be
located in the core and buffer zone of the mine.
Based on the information furnished and presentation made, the Committee
prescribed the following TORs for undertaking detailed EIA study:-
1) Status of compliance of the earlier EC conditions along with supporting
documents and photographs should be submitted.
2) Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t. the highest production
achieved prior to 1994.
3) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
4) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5) Does the company have a well laid down Environment Policy approved by its
Page 36 of 73

Board of Directors? If so, it may be detailed in the EIA report.


6) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
8) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
10) Land use of the study area delineating forest area, agricultural land, grazing
land, wildlife sanctuary and national park, migratory routes of fauna, water
bodies, human settlements and other ecological features should be indicated.
11) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12) Details of the land for OB dump outside the mine lease such as extent of land
area, distance from mine lease, its land use, R&R issues, if any should be given.
13) High Resolution Satellite Imagery of the proposed area clearly showing the land
use and other ecological features of the study area (core and buffer zone) should
be furnished.
14) A Certificate from the Competent Authority in the State Forest Department
should be provided, confirming the involvement of forest land, if any in the
project area, or otherwise, based on land use classification (revenue record) as
also in terms of the definition of forest as pronounced in the judgment of the
Hon’ble Supreme Court of India in the matter of T.N. Godavarman Vs. Union of
India. In the event of any claim by the project proponent regarding the status of
forests, the site may be inspected by the State Forest Department along with the
Regional Office of the Ministry to ascertain the status of forests, based on which
the Certificate in this regard as mentioned above be issued. In all such cases, it
would be desirable for representative of the State Forest Department to assist
the Expert Appraisal Committees.
15) Status of forestry clearance for the broken up area and virgin forestland
involved in the project including deposition of net present value (NPV) and
compensatory afforestation (CA) should be indicated. A copy of the forestry
clearance should also be furnished.
16) Implementation status of recognition of forest rights under the Scheduled Tribes
and other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006
should be indicated.
17) Impact of the project on the wildlife in the surrounding and any other protected
area and accordingly detailed mitigative measures required should be worked
out with cost implications and submitted.
18) The vegetation in the RF / PF area with necessary details should be given.
19) A study shall be got done to ascertain the impact of the mining project on
wildlife of the area including on the elephant population and details furnished.
20) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
Page 37 of 73

the mine lease should be clearly indicated, supported by a location map, duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
21) A detailed biological study of the core zone and buffer zone (10 km radius of the
periphery of the mine lease) shall be carried out. Details of flora and fauna, duly
authenticated, separately for core and buffer zone should be furnished based on
primary field survey, clearly indicating the Schedule of the fauna present. In case
of any scheduled-I fauna found in the study area, the necessary plan for their
conservation should be prepared in consultation with State Forest and Wildlife
Department and details furnished. Necessary allocation of funds for
implementing the same should be made as part of the project cost.
22) Impact, if any, of change of land use should be given.
23) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State
Government.
24) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location of
the monitoring stations should be such as to represent whole of the study area
and justified keeping in view the pre-dominant downwind direction and location
of sensitive receptors. There should be at least one monitoring station within
500 m of the mine lease in the pre-dominant downwind direction. The
mineralogical composition of PM10 particularly for free silica should be given.
25) Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account the impact
of movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
26) The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
27) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
28) Details of water conservation measures proposed to be adopted in the project
should be given.
29) Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required, should be
provided.
30) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may
be provided. In case the working will intersect groundwater table, a detailed
Page 38 of 73

hydro geological study should be undertaken and report furnished. Necessary


permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
31) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
32) Details of rainwater harvesting proposed, if any, in the project should be
provided.
33) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
34) Quantity of solid waste generation to be estimated and details for its disposal
and management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
35) The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
36) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
37) Details of the infrastructure facilities to be provided for the mine workers
should be included in the EIA report.
38) Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
39) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted, clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
40) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
41) Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed
remedial measures should be detailed along with budgetary allocation.
42) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
43) Detailed environmental management plan to mitigate the environmental
Page 39 of 73

impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the projects.
44) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
45) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
46) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous page
numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.33 Mining Lease for Silicate Boulders of M/s Mohunta Mining & Mfg. Co. Pvt. Ltd.,
Village Mauza Bathri, Tehsil Haroli, Distt. Una, H.P. -TORs- Re-consideration.
Page 40 of 73

Same as Item No. 2.31 inadvertently repeated; hence passed over.

2.34 Banesti Mine for Minerals China Clay, Silica and Red Ochre of M/s Mohd. Sher
Khan, Village Banesti, Tehsil and Distt. Chittorgarh, Rajasthan – Change in
TORs (Consultant: Udaipur Min-Tech Pvt. Ltd.).

Banesti mine (ML no. 5/97) was granted for mineral China Clay & Red Ochre near
village Banesti over an area of 48.56 ha, in favour of Sh. Mohd. Sher Khan, resident of village
and P.O. Sawa Dist. - Chittorgarh. Mineral silica sand was included in the mining lease on
15.07.2002. Another mining lease (ML No. 10/2000) for mineral China Clay and Red Ochre
near village Banesti, over an area of 64.75 ha, in favour of Sh. Mohd. Sher Khan was renewed
for the first time and both of these mining leases were amalgamated vide State Government
order No. DMG/Chittor/ CC-3/Ren./P- 1(1)5/97/2073 dated 27.08.2003. Thus total lease
area became 113.31 hectares for minerals Red Ochre, China Clay & Silica Sand effective up
to 24.06.2018.

Environment Clearance was granted by MoEF, New Delhi for production of China
clay 1,20,000 TPA, Silica sand 3,00,000 TPA and Red Ochre 50,000 TPA vide letter no. J-
11015/191/2006-IA.II (M) dated 24/01/2007. The lessee applied for TORs under
expansion category for production of China Clay from 1,20,000 to 4,00,000 TPA, Silica Sand
from 3,00,000 to 10,00,000 TPA and Red Ochre from 50,000 TPA to 4,00,000 TPA. After
presentation before EAC, TORs were issued for expansion vide MoEF letter no. J-
11015/140/2011/IA.II (M) dated 21/09/11.

It was observed that the compliance to the earlier EC conditions needs to be further
improved and presented with supporting data and photographs at the time of consideration
of proposal for environmental clearance. The method of mining is open cast using excavator
cum loader for extracting mineral as it is soft and bedded deposit, hence can be mined by
machinery without drilling and blasting. The ultimate depth will be 35.00 tm (370.0 mRL)
for China Clay and 50.00 mt (360.0 mRL) for Silica sand. There is no perennial source of
water except seasonal river like Berach river (7.00 km towards West), Gambhir Nadi (8.50
km towards north east) & Satkhanda Nadi (7.50 km towards east) flowing within the study
area of 10 km of buffer zone. Total water demand will be 100.00 KLD i.e., 48.00 KLD for dust
suppression, 2.00 KLD for drinking & 50.00 KLD for plantation.
Based on the information furnished and presentation made, the Committee
revalidated the TORs for undertaking the detailed EIA study.

2.35 Sanindpur Iron & Bauxite mine of M/s Rungta Sons (P) Ltd., Village Sanindpur
& Oraghat, Distt. Sundergarh, Orissa (147.10 ha)-TOR (Consultant: Ecomen
Laboratories Pvt. Ltd.).

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA Notification, 2006.
For this purpose, the proponent had submitted information in the prescribed format (Form-
1) along with Pre-Feasibility Report.

The proposal is for enhancement in Iron Ore Production Capacity of the mine from 1.65
MTPA to 2.85 MTPA (ROM) ; dry processing of 1.65 MTPA of low grade iron ore &
Page 41 of 73

installation of wet beneficiation plant of capacity 1.44MTPA at Villages – Sanindpur &


Oraghat, Tehsil-Bonai, Dist.- Sundergarh, Odisha. Mine Lease Area is 147.10 ha and mine in
operation since 1985. At present lease is under deemed renewal as per clause 24(A) of M.C.
Rules, 1960 for 20 years w.e.f., 06/092005 to 05./09/2025 The lessee had applied for 1st
renewal over 147.10 ha on 04/02/2004 vide RML application no. 141 which was further
revised on 16/05/2006 over a reduced area of 88.737 ha for 20 years. The mine is located
at Latitude: 21055’ 18.11” to 21055’54.91” and Longitude: 85017’19.49” to 85018’29.96”. The
Total lease area of the mine is 147.10 ha. The lessee had applied for renewal of mining lease
for the entire area. The lessee had reapplied for renewal for reduced area only of 88.737 ha.
relinquishing forest area of over 58.189 ha. & non forest land of over 0.174 ha. The reduced
RML applied area comprises of 68.135 ha. forest land and 20.602 ha non-forest land.
STAGE-II CLEARANCE was granted by MoEF, Govt. of India vide letter no. 8 - 135/2003,
dated 1 9.06.2006 for an area of 52.742 ha. STAGE-I CLEARANCE is further obtained by the
lessee from MoEF, Govt. of India vide no.8 -135/2003 (Vol) dated 21/12/2010 for balance
15.393 ha forest land in addition to already diverted 52.742 ha of forest land. The Scheme of
Mining for the period 2010-11 to 2014-15 for the required production capacity has been
approved by IBM Nagpur vide letter no. 314(3)/2010 MCCM(CZ) MS-04 dated 28/05/2010.
Life of Mine is 11.52 years.
Based on the information furnished and presentation made, the Committee
prescribed the following TORs for undertaking detailed EIA study:-
1) Status of compliance of the earlier EC conditions along with supporting
documents and photographs should be submitted.
2) Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t. the highest production
achieved prior to 1994.
3) A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
4) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
5) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
6) Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
7) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
8) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions? Details of this system may be given.
9) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
10) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
Page 42 of 73

be for the life of the mine / lease period.


11) Land use of the study area delineating forest area, agricultural land, grazing
land, wildlife sanctuary and national park, migratory routes of fauna, water
bodies, human settlements and other ecological features should be indicated.
12) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
13) Details of the land for OB dump outside the mine lease such as extent of land
area, distance from mine lease, its land use, R&R issues, if any should be given.
14) High Resolution Satellite Imagery of the proposed area clearly showing the land
use and other ecological features of the study area (core and buffer zone) should
be furnished.
15) A Certificate from the Competent Authority in the State Forest Department
should be provided, confirming the involvement of forest land, if any in the
project area, or otherwise, based on land use classification (revenue record) as
also in terms of the definition of forest as pronounced in the judgment of the
Hon’ble Supreme Court of India in the matter of T.N. Godavarman Vs. Union of
India. In the event of any claim by the project proponent regarding the status of
forests, the site may be inspected by the State Forest Department along with the
Regional Office of the Ministry to ascertain the status of forests, based on which
the Certificate in this regard as mentioned above be issued. In all such cases, it
would be desirable for representative of the State Forest Department to assist
the Expert Appraisal Committees.
16) Status of forestry clearance for the broken up area and virgin forestland
involved in the project including deposition of net present value (NPV) and
compensatory afforestation (CA) should be indicated. A copy of the forestry
clearance should also be furnished.
17) Implementation status of recognition of forest rights under the Scheduled Tribes
and other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006
should be indicated.
18) Impact of the project on the wildlife in the surrounding and any other protected
area and accordingly detailed mitigative measures required should be worked
out with cost implications and submitted.
19) The vegetation in the RF / PF area with necessary details should be given.
20) A study shall be got done to ascertain the impact of the mining project on
wildlife of the area including on the elephant population and details furnished.
21) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated, supported by a location map, duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
22) A detailed biological study of the core zone and buffer zone (10 km radius of the
periphery of the mine lease) shall be carried out. Details of flora and fauna, duly
authenticated, separately for core and buffer zone should be furnished based on
primary field survey, clearly indicating the Schedule of the fauna present. In case
of any scheduled-I fauna found in the study area, the necessary plan for their
conservation should be prepared in consultation with State Forest and Wildlife
Department and details furnished. Necessary allocation of funds for
implementing the same should be made as part of the project cost.
Page 43 of 73

23) Impact, if any, of change of land use should be given.


24) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State
Government.
25) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location of
the monitoring stations should be such as to represent whole of the study area
and justified keeping in view the pre-dominant downwind direction and location
of sensitive receptors. There should be at least one monitoring station within
500 m of the mine lease in the pre-dominant downwind direction. The
mineralogical composition of PM10 particularly for free silica should be given.
26) Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account the impact
of movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
27) The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
28) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
29) Details of water conservation measures proposed to be adopted in the project
should be given.
30) Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required, should be
provided.
31) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may
be provided. In case the working will intersect groundwater table, a detailed
hydro geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
32) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
33) Details of rainwater harvesting proposed, if any, in the project should be
provided.
34) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
35) Quantity of solid waste generation to be estimated and details for its disposal
Page 44 of 73

and management should be provided. The quantity, volumes and methodology


planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
36) The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
37) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
38) Details of the infrastructure facilities to be provided for the mine workers
should be included in the EIA report.
39) Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
40) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted, clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
41) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
42) Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed
remedial measures should be detailed along with budgetary allocation.
43) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
44) Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the projects.
45) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
46) Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
47) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
Page 45 of 73

a) A note confirming compliance of the TOR, with cross referencing of the


relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous
page numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on
the website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought
to the attention of MoEF with reasons for such changes and permission
should be sought, as the TOR may also have to be altered. Post Public
Hearing changes in structure and content of the draft EIA/EMP (other
than modifications arising out of the P.H. process) will entail conducting
the PH again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.36 Mining Project of white clay mine of M/s Harish Clays, Village Chandi, Tehsil
Kolayat, Bikaner, Rajasthan (75.13 ha)(M.L.No. 8/92)-TOR (Consultant: Apex
Mintech Consultants)

The proposal was considered by the Committee to determine the Terms of Reference
(TOR) for undertaking detailed EIA study for obtaining Environmental Clearance in
accordance with the provisions of the EIA Notification, 2006. For this purpose, the
Proponent has submitted information in the prescribed format (Form-1) along with Pre-
Feasibility Report.

The proposal is for white clay mine [M.L. No.24/2012 (Old M.L. No. 08/1992), Area
75.13 ha] Near village Chandi, Tehsil Kolayat District Bikaner (Rajasthan). Earlier
Environment clearance was granted by MoEF, New Delhi for enhancement of production of
1,50,000 M.T. per year for mineral White Clay vide letter No. J-11015/13/2005-IA. II (M) dt.
Page 46 of 73

14th June, 2005. The Latitude is 27°53’9.59” N to 27°53’48.64” N and Longitude is


72°59’56.67” E to 73°00’39.38” E. Life of mine is 14 years.

Based on the information furnished and presentation made, the Committee prescribed
the following TORs for undertaking detailed EIA study:-

1) Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t., the highest production
achieved prior to 1994.
2) A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
4) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5) Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
6) Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7) What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
8) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
10) Land use of the study area delineating forest area, agricultural land, grazing
land, wildlife sanctuary and national park, migratory routes of fauna, water
bodies, human settlements and other ecological features should be indicated.
11) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
Page 47 of 73

fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
of funds for implementing the same should be made as part of the project cost.
14) Impact, if any, of change of land use should be given.
15) R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State
Government.
16) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location
of the monitoring stations should be such as to represent whole of the study
area and justified keeping in view the pre-dominant downwind direction and
location of sensitive receptors. There should be at least one monitoring station
within 500 m of the mine lease in the pre-dominant downwind direction. The
mineralogical composition of PM10 particularly for free silica should be given.
17) Air quality modelling should be carried out for prediction of impact of the
project on the air quality of the area. It should also take into account the impact
of movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modelling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
18) The water requirement for the project, its availability and source to be
furnished. A detailed water balance should also be provided. Fresh water
requirement for the project should be indicated.
19) Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
20) Details of water conservation measures proposed to be adopted in the project
should be given.
21) Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required should be
provided.
22) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may
be provided. In case the working will intersect groundwater table, a detailed
hydro geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
23) Details of treatment and disposal / management of effluents generated from the
washing plant should be given.
24) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
Page 48 of 73

25) Details of rainwater harvesting proposed, if any, in the project should be


provided.
26) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
27) Quantity of solid waste generation to be estimated and details for its disposal
and management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
28) The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
29) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
30) Details of the infrastructure facilities to be provided for the mine workers
should be included in the EIA report.
31) Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
32) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
33) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
34) Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed
remedial measures should be detailed along with budgetary allocation.
35) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
36) Detailed environmental management plan to mitigate the environmental
impacts which, should inter-alia also include the impact due to change of land
use, due to loss of agricultural land and grazing land, if any, occupational health
impacts besides other impacts of the projects.
37) Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
38) Details of litigation pending against the project, if any, with direction /order
Page 49 of 73

passed by any Court of Law against the project should be given.


39) The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous page
numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the proposed
capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on the
website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought to
the attention of MoEF with reasons for such changes and permission should
be sought, as the TOR may also have to be altered. Post Public Hearing
changes in structure and content of the draft EIA/EMP (other than
modifications arising out of the P.H. process) will entail conducting the PH
again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.37 Acchi Bavri Soapstone & Dolomite Mine of M/s Mahesh Mantri, Nr. Village
Acchi Bavri, Distt. Rajsamand, Rajasthan (129.50 ha)-TOR (Consultant: Apex
Mintech Consultants)

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining Environmental Clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
proponent had submitted information in the prescribed format (Form-1) along with Pre-
Feasibility Report.
Page 50 of 73

The proposal is Acchi Bavri Soapstone & Dolomite Mine of M/s Mahesh Mantri, Nr.
Village Acchi Bavri, Distt. Rajsamand, Rajasthan (129.50 ha) – Capacity of Soapstone is
20,000 MTA & Dolomite 2,40,000 MTA (M.L. No. 5/98). No Forest Land is involved, Govt.
waste land is 27.02 ha, Pvt. Waste land is 70.48 ha and Grazing land is 32 ha. The mining
method is semi-mechanised opencast and the dimension of benches is 6m height and 9 m
width. Banas river is on Northern periphery. Water requirement is 13 KLD and source of
water is sump water (12KLD) and tube well (1KLD).

Issues presented before the Public have remained unchanged as also the
environmental background. Considering that the minerals being mined are environmentally
benign, the incremental impacts consequent on the proposed expansion are not going to be
materially different from the impacts placed before the Public on the previous occasion. The
Committee therefore feels that despite the proposed expansion of production, and also the
fact that last Public Hearing for Soapstone of 20,000 MTA & Dolomite 2,40,000 MTA was
held on 27-08-2008, the proposal deserves to be exempted from a repeat public
consultations in the instance case.

Based on the information furnished and presentation made, the Committee


prescribed the following TORs for undertaking detailed EIA study:-

1) Year-wise production details since 1994 onwards should be given clearly stating the
highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after the
EIA Notification, 1994 coming into force w.r.t., the highest production achieved prior
to 1994.
2) A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3) All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in the
name of the lessee.
4) All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5) Does the company have a well laid down Environment Policy approved by its Board
of Directors? If so, it may be detailed in the EIA report.
6) Does the Environment Policy prescribe for standard operating process/ procedures
to bring into focus any infringement / deviation / violation of the environmental or
forest norms / conditions? If so, it may be detailed in the EIA.
7) What is the hierarchical system or Administrative order of the company to deal with
the environmental issues and for ensuring compliance with the EC conditions.
Details of this system may be given.
8) Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9) The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should be
for the life of the mine / lease period.
10) Land use of the study area delineating forest area, agricultural land, grazing land,
Page 51 of 73

wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features should be indicated.
11) Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12) Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of the
mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13) A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be furnished
based on primary field survey clearly indicating the Schedule of the fauna present.
In case of any scheduled-I fauna found in the study area, the necessary plan for their
conservation should be prepared in consultation with State Forest and Wildlife
Department and details furnished. Necessary allocation of funds for implementing
the same should be made as part of the project cost.
14) Impact, if any, of change of land use should be given.
15) R&R plan / compensation details for the project affected people should be furnished.
While preparing the R&R plan, the National Rehabilitation & Resettlement Policy
should be kept in view. In respect of SCs / STs and other weaker sections, need
based sample survey, family-wise, should be undertaken to assess their requirement
and action programmes prepared accordingly integrating the sectoral programme of
line departments of the State Government.
16) One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be collected
and the AAQ data so collected presented date-wise in the EIA and EMP report. Site-
specific meteorological data should also be collected. The location of the monitoring
stations should be such as to represent whole of the study area and justified keeping
in view the pre-dominant downwind direction and location of sensitive receptors.
There should be at least one monitoring station within 500 m of the mine lease in
the pre-dominant downwind direction. The mineralogical composition of PM10
particularly for free silica should be given.
17) Air quality modelling should be carried out for prediction of impact of the project on
the air quality of the area. It should also take into account the impact of movement
of vehicles for transportation of mineral. The details of the model used and input
parameters used for modelling should be provided. The air quality contours may be
shown on a location map clearly indicating the location of the site, location of
sensitive receptors, if any and the habitation. The wind roses showing pre-
dominant wind direction may also be indicated on the map.
18) The water requirement for the project, its availability and source to be furnished. A
detailed water balance should also be provided. Fresh water requirement for the
project should be indicated.
19) Necessary clearance from the Competent Authority for drawl of requisite quantity of
water for the project should be provided.
20) Details of water conservation measures proposed to be adopted in the project
should be given.
21) Impact of the project on the water quality both surface and groundwater should be
Page 52 of 73

assessed and necessary safeguard measures, if any required should be provided.


22) Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary permission
from Central Ground Water Authority for working below ground water and for
pumping of ground water should also be obtained and copy furnished.
23) Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24) Details of rainwater harvesting proposed, if any, in the project should be provided.
25) Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for the
same.
26) Quantity of solid waste generation to be estimated and details for its disposal and
management should be provided. The quantity, volumes and methodology planned
for removal and utilisation (preferably concurrently) of top soil should be indicated.
Details of backfilling proposed, if any, should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be brought
out).
27) The reclamation plan, post mine land use and progressive greenbelt development
plan shall be prepared in tabular form (prescribed format) and submitted.
28) Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out, indicating
whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies such
as State Government) should be covered.
29) Details of the infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
30) Conceptual post mining land use and Reclamation and Rehabilitation of mined out
area (with plans and with adequate number of sections) should be given in the EIA
report.
31) Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32) Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33) Public health implication of the project and related activities for the population in
the impact zone should be systematically evaluated and the proposed remedial
measures should be detailed along with budgetary allocation.
34) Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for implementation.
35) Detailed environmental management plan to mitigate the environmental impacts
Page 53 of 73

which, should inter-alia also include the impact due to change of land use, due to
loss of agricultural land and grazing land, if any, occupational health impacts besides
other impacts of the projects.
36) Public hearing points raised and commitment of the project proponent on the same
along with time bound action plan to implement the same should be provided and
also incorporated in the final EIA/EMP Report of the Project.
37) Details of litigation pending against the project, if any, with direction /order passed
by any Court of Law against the project should be given.
38) The cost of the project (capital cost and recurring cost) as well as the cost towards
implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a) A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b) All documents may be properly referenced with index and continuous
page numbering.
c) Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d) Where the documents provided are in a language other than English, an
English translation should be provided.
e) The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f) Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g) While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on
the website of this Ministry should also be followed.
h) Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought
to the attention of MoEF with reasons for such changes and permission
should be sought, as the TOR may also have to be altered. Post Public
Hearing changes in structure and content of the draft EIA/EMP (other
than modifications arising out of the P.H. process) will entail conducting
the PH again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.
Page 54 of 73

2.38 Joruri & Jalahari Iron Ore Mines of M/s Kalinga Mining Corp., Village Jalahari &
Khandbandh, Distt. Keonjhar, Orissa (54.754 ha) (1.0 MTPA)-TOR (Consultant:
CREATIVE ENGINEERS & CONSULTANTS, CHENNAI).

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining Environmental Clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
Proponent has submitted information in the prescribed format (Form-1) along with Pre-
Feasibility Report.

The proposal of Kalinga Mining Corporation is for the operating Joruri Iron and
Manganese Ore Mines (54.754 ha.) located in village Jalahari and Khandbandh, Sub-division
Champua, district Keonjhar of Orissa since June 1953. Out of the total area of 54.754 ha,
6.313 ha is under village forest, 45.167Ha is under DLC forest and rest of 3.274 ha is non-
forest land. Present proposal is for enhancement of production of iron ore from 0.101 MTPA
to 1.0 MTPA (ROM) and manganese ore to 0.014 MTPA capacity during 3rd RML period.
Application for third renewal of the mining lease for the period from 22.06.2013 to
21.06.2033 (20 years) is made on 12-06-2012 one year prior to lease expiry over the entire
area of 54.754 ha. Approval of Mining Scheme has been obtained from IBM vide letter no
MS/OTF.MECH/56-ORI/BHU/2010-11. Mining Plan for the lease area of 54.754 ha for the
third RML period of 20 years is being prepared. Forest diversion proposal for third RML
period over 51.48 ha is submitted and is under process. Environmental Clearance for a
production of 1,01,346 TPA of iron ore and 13,687 TPA of Manganese Ore was obtained
from MOEF in December 2008. TOR for enhancement of production of iron ore from 0.101
MTPA to 0.5 MTPA and manganese ore from 0.014 MTPA to 0.1 MTPA was obtained from
MOEF vide letter no J-11015/277/2010-IA.II (M) dated 29th November 2010. However,
since the lease is due for renewal in 2013 and there is a proposal to enhance the iron ore
production to 1.0 MTPA (ROM), the management has decided to obtain fresh TOR for
increased production and Lease renewal. Baitarani river (About 3.0km, E), Dalko Nala (1.5
km, E), Kundra Nala (2.7 Km, West), Kakrapani (5.5Km, SW) Karo river (13.5 Km, NW) are
the surrounding rivers. No Ecologically sensitive area such as National park/Wild life
sanctuary/Biosphere reserve/tiger/Elephant reserve exists within 10 km of Buffer zone.
Karo Karampada elephant corridor is located at a distance of 18.3 km. Open cast
mechanized mining using drilling & blasting, raising of ore and waste by shovel dumper
combination is proposed.

Based on the information furnished and presentation made, the Committee


prescribed the following TORs for undertaking detailed EIA study:-

1. Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t. the highest production
achieved prior to 1994.
2. A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3. All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
Page 55 of 73

4. All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5. Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
6. Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7. What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
8. Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9. The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
10. Land use of the study area delineating forest area, agricultural land, grazing land,
wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features should be indicated.
11. Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13. A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
of funds for implementing the same should be made as part of the project cost.
14. Impact, if any, of change of land use should be given.
15. R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State Government.
16. One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location of
the monitoring stations should be such as to represent whole of the study area
and justified keeping in view the pre-dominant downwind direction and location
Page 56 of 73

of sensitive receptors. There should be at least one monitoring station within 500
m of the mine lease in the pre-dominant downwind direction. The mineralogical
composition of PM10 particularly for free silica should be given.
17. Air quality modeling should be carried out for prediction of impact of the project
on the air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
18. The water requirement for the project, its availability and source to be furnished.
A detailed water balance should also be provided. Fresh water requirement for
the project should be indicated.
19. Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
20. Details of water conservation measures proposed to be adopted in the project
should be given.
21. Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required should be
provided.
22. Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
23. Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24. Details of rainwater harvesting proposed, if any, in the project should be
provided.
25. Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
26. Quantity of solid waste generation to be estimated and details for its disposal and
management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
27. The reclamation plan, post mine land use and progressive greenbelt development
plan shall be prepared in tabular form (prescribed format) and submitted.
28. Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
Page 57 of 73

other agencies such as State Government) should be covered.


29. Details of the infrastructure facilities to be provided for the mine workers should
be included in the EIA report.
30. Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
31. Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32. Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33. Public health implication of the project and related activities for the population in
the impact zone should be systematically evaluated and the proposed remedial
measures should be detailed along with budgetary allocation.
34. Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
35. Detailed environmental management plan to mitigate the environmental impacts
which, should inter-alia also include the impact due to change of land use, due to
loss of agricultural land and grazing land, if any, occupational health impacts
besides other impacts of the projects.
36. Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
37. Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
38. The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a. A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b. All documents may be properly referenced with index and continuous
page numbering.
c. Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d. Where the documents provided are in a language other than English, an
English translation should be provided.
e. The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f. Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g. While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on
Page 58 of 73

the website of this Ministry should also be followed.


h. Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought
to the attention of MoEF with reasons for such changes and permission
should be sought, as the TOR may also have to be altered. Post Public
Hearing changes in structure and content of the draft EIA/EMP (other
than modifications arising out of the P.H. process) will entail conducting
the PH again with the revised documentation.

The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage, clearly showing the land features of the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.39 Joruri Iron Ore Mines of M/s Kalinga Mining Corp., Village Jalahari, Distt.
Keonjhar, Orissa (27.170 ha) (0.5 MTPA)-TOR (Consultant: CREATIVE
ENGINEERS & CONSULTANTS, CHENNAI)

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining environmental clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
proponent has submitted information in the prescribed format (Form-1) along with Pre-
Feasibility Report.

The Proposal of M/s Kalinga Mining Corporation is for their operating Joruri Iron
Ore Mines (27.17 ha.) located in village Jalahari, Sub-division Champua, district Keonjhar of
Orissa since June 1953. Out of the total ML area of 27.17 ha, 9.39 ha. are non- forest land,
16.67 ha of DLC forest land and 1.11 ha. of non - forest land which is under sabik kisam
jungle. Present proposal is for enhancement of iron ore production to 0.50 MTPA (ROM)
during 3rd RML period. Application for 3rd renewal of mine lease was filed for the period of
20 years starting from 22-06-2013 as per the rule 22 of MCR, 1960 on 12-06-2012 i.e. one
year prior to expiry of existing lease period. Mining Plan for the lease area of 27.17 ha for
the third renewal of lease for 0.50 MTPA (ROM) capacity is being prepared under rule 24 of
MCR, 1960 for the next RML period for approval from IBM. Out of total 17.78 ha of forest
land, 11.881 ha is already broken up prior to 1980. Application to divert 17.78 ha of forest
land including 11.431 broken up forest land prior to 1980, safety zone of 3.163 ha for non -
forest use under F.C. act 1980 for third RML period is made. This TOR is applied towards
obtaining environmental clearance for production of 0.50 MTPA during renewal of mine
lease. Baitarani river is at 1.7 km east, Suna nadi is at 3 km from NW towards South, Dalko
Nala is at 0.7 km, Kakrapani is at 6.7Km, SW. Open cast mechanized mining using drilling &
blasting is being done. No Ecologically sensitive area such as National park/Wild life
sanctuary / Biosphere reserve / tiger / Elephant reserve within 10 km of Buffer zone. Karo
Karampada elephant corridor is located at a distance of 18.0 kms. Ore is transported to
mobile crusher ( 2 x 150 TPH) /screen plant (2 x 150 TPH) through dumpers to get the
final product of -5mm, 5-18mm, 18-40mm sized ore.
Page 59 of 73

Based on the information furnished and presentation made, the Committee


prescribed the following TORs for undertaking detailed EIA study:-

1. Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t. the highest production
achieved prior to 1994.
2. A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3. All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
4. All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5. Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
6. Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7. What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
8. Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9. The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
10. Land use of the study area delineating forest area, agricultural land, grazing land,
wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features should be indicated.
11. Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13. A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
Page 60 of 73

of funds for implementing the same should be made as part of the project cost.
14. Impact, if any, of change of land use should be given.
15. R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State Government.
16. One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location of
the monitoring stations should be such as to represent whole of the study area
and justified keeping in view the pre-dominant downwind direction and location
of sensitive receptors. There should be at least one monitoring station within 500
m of the mine lease in the pre-dominant downwind direction. The mineralogical
composition of PM10 particularly for free silica should be given.
17. Air quality modeling should be carried out for prediction of impact of the project
on the air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
18. The water requirement for the project, its availability and source to be furnished.
A detailed water balance should also be provided. Fresh water requirement for
the project should be indicated.
19. Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
20. Details of water conservation measures proposed to be adopted in the project
should be given.
21. Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required should be
provided.
22. Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
23. Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24. Details of rainwater harvesting proposed, if any, in the project should be
provided.
25. Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
26. Quantity of solid waste generation to be estimated and details for its disposal and
Page 61 of 73

management should be provided. The quantity, volumes and methodology


planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
27. The reclamation plan, post mine land use and progressive greenbelt development
plan shall be prepared in tabular form (prescribed format) and submitted.
28. Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
29. Details of the infrastructure facilities to be provided for the mine workers should
be included in the EIA report.
30. Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
31. Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32. Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33. Public health implication of the project and related activities for the population in
the impact zone should be systematically evaluated and the proposed remedial
measures should be detailed along with budgetary allocation.
34. Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
35. Detailed environmental management plan to mitigate the environmental impacts
which, should inter-alia also include the impact due to change of land use, due to
loss of agricultural land and grazing land, if any, occupational health impacts
besides other impacts of the projects.
36. Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
37. Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
38. The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a. A note confirming compliance of the TOR, with cross referencing of the
Page 62 of 73

relevant sections / pages of the EIA report should be provided.


b. All documents may be properly referenced with index and continuous
page numbering.
c. Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d. Where the documents provided are in a language other than English, an
English translation should be provided.
e. The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f. Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g. While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on
the website of this Ministry should also be followed.
h. Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought
to the attention of MoEF with reasons for such changes and permission
should be sought, as the TOR may also have to be altered. Post Public
Hearing changes in structure and content of the draft EIA/EMP (other
than modifications arising out of the P.H. process) will entail conducting
the PH again with the revised documentation.

The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage, clearly showing the land features of the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

2.40 Guali Iron Ore Mines of M/s R.P. Sao (Ramesh Prasad Sao), Village Topadih,
Panduliposhi, Loidapada, Guali & Rugudih, Tehsil Barbil, Distt. Keonjhar,
Orissa (365.026 ha)-TOR

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for obtaining environmental clearance
in accordance with the provisions of the EIA Notification, 2006. For this purpose, the
proponent has submitted information in the prescribed format (Form-1) along with Pre-
Feasibility Report.

The proposal of Iron Ore Mines of M/s R.P. Sao (Ramesh Prasad Sao) at Village
Topadih, Panduliposhi, Loidapada, Guali & Rugudih, Tehsil Barbil, Distt. Keonjhar, Orissa
(365.026 ha). Mining lease originally granted in the year 27.06.1953. Application for third
renewal of the mining lease for the period 27.06.201. 3 to 26.06.2033 (20 years) applied on
25-04-2012 one year prior to lease expiry over the entire area of 365.026 Ha. Mining plan
for third RML period over the lease area of 365.026 Ha submitted to IBM for approval.
Environmental Clearance for 5.7 MTPA iron ore production obtained from MOEF vide letter
Page 63 of 73

No.J-11015/1155/2007-IA-II (M) dated the 22 June 2009. Out of 288.796 Ha forest area,
forest clearance for 42.471 Ha of already broken up area (prior to 1980), obtained from
MoEF vide letter. No F.No-8-96/96-FC dated 14th January 2005. Forest clearance for
additional 95.00 Ha area obtained from MOEF vide letter F.N-96/96(+P) dated 6th
September 2011 from MOEF. Thus the total diverted forest area at present is 137.417 Ha.
Lessee has now filed diversion proposal for entire forest area of 288.796 Ha on 22.06.2012
for renewal of mining lease, which includes 137.417 Ha diverted forest, 135.219 Ha virgin
forest and 16.160 Ha safety zone. NOC for withdrawal of ground water has been obtained
from CGWA vide letter. No .No-21-4 (93)/SER/ CGWA/ 2008-1730. Site-specific wildlife
conservation plan got approved from Principal Chief Controller of Forests (Wildlife), Orissa
vide Memo No.321 to 324 1 WL-C-FC-385/08 dt.17.01.09. Method of mining is open cast
and mechanized. Life of mine is 19 years.

During the presentation for TOR, the proponent mentioned the Project has obtained
EC on 22nd June 2009 after Public Hearing. The conditions stipulated are being complied
with by the Project. The present proposal for TOR is for renewal of the EC for next lease
period without any change in production, lease area and pollution load etc. The renewal of
the lease is due on 26th June 2013. It was requested by the proponent to allow exemption
from Public Hearing. It was noted that considering the nature of the public hearing and the
action plan, the proponent deserves to be exempted from the public consultations.

Based on the information furnished and presentation made, the Committee


prescribed the following TORs for undertaking detailed EIA study:-

1. Year-wise production details since 1994 onwards should be given clearly stating
the highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after
the EIA Notification, 1994 coming into force w.r.t. the highest production
achieved prior to 1994.
2. A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3. All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in
the name of the lessee.
4. All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5. Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
6. Does the Environment Policy prescribe for standard operating process/
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the EIA.
7. What is the hierarchical system or Administrative order of the company to deal
with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
8. Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9. The study area will comprise of 10 km zone around the mine lease from lease
Page 64 of 73

periphery and the data contained in the EIA such as waste generation etc should
be for the life of the mine / lease period.
10. Land use of the study area delineating forest area, agricultural land, grazing land,
wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features should be indicated.
11. Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of
the mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13. A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora
and fauna, duly authenticated, separately for core and buffer zone should be
furnished based on primary field survey clearly indicating the Schedule of the
fauna present. In case of any scheduled-I fauna found in the study area, the
necessary plan for their conservation should be prepared in consultation with
State Forest and Wildlife Department and details furnished. Necessary allocation
of funds for implementing the same should be made as part of the project cost.
14. Impact, if any, of change of land use should be given.
15. R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken
to assess their requirement and action programmes prepared accordingly
integrating the sectoral programme of line departments of the State Government.
16. One season (non-monsoon) primary baseline data on ambient air quality (PM10,
SO2 and NOx), water quality, noise level, soil and flora and fauna shall be
collected and the AAQ data so collected presented date-wise in the EIA and EMP
report. Site-specific meteorological data should also be collected. The location of
the monitoring stations should be such as to represent whole of the study area
and justified keeping in view the pre-dominant downwind direction and location
of sensitive receptors. There should be at least one monitoring station within 500
m of the mine lease in the pre-dominant downwind direction. The mineralogical
composition of PM10 particularly for free silica should be given.
17. Air quality modeling should be carried out for prediction of impact of the project
on the air quality of the area. It should also take into account the impact of
movement of vehicles for transportation of mineral. The details of the model
used and input parameters used for modeling should be provided. The air
quality contours may be shown on a location map clearly indicating the location
of the site, location of sensitive receptors, if any and the habitation. The wind
roses showing pre-dominant wind direction may also be indicated on the map.
18. The water requirement for the project, its availability and source to be furnished.
A detailed water balance should also be provided. Fresh water requirement for
the project should be indicated.
19. Necessary clearance from the Competent Authority for drawl of requisite
quantity of water for the project should be provided.
Page 65 of 73

20. Details of water conservation measures proposed to be adopted in the project


should be given.
21. Impact of the project on the water quality both surface and groundwater should
be assessed and necessary safeguard measures, if any required should be
provided.
22. Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary
permission from Central Ground Water Authority for working below ground
water and for pumping of ground water should also be obtained and copy
furnished.
23. Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24. Details of rainwater harvesting proposed, if any, in the project should be
provided.
25. Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for
the same.
26. Quantity of solid waste generation to be estimated and details for its disposal and
management should be provided. The quantity, volumes and methodology
planned for removal and utilisation (preferably concurrently) of top soil should
be indicated. Details of backfilling proposed, if any, should also be given. It may
be clearly indicated that out of the total waste generated during the mine life,
how much quantity would be backfilled and how much quantity would be
disposed off in the form of external dump (number of dumps, their height,
terraces etc. to be brought out).
27. The reclamation plan, post mine land use and progressive greenbelt
development plan shall be prepared in tabular form (prescribed format) and
submitted.
28. Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out,
indicating whether it is capable of handling the increased load. Arrangement for
improving the infrastructure, if contemplated (including action to be taken by
other agencies such as State Government) should be covered.
29. Details of the infrastructure facilities to be provided for the mine workers should
be included in the EIA report.
30. Conceptual post mining land use and Reclamation and Rehabilitation of mined
out area (with plans and with adequate number of sections) should be given in
the EIA report.
31. Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32. Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
Page 66 of 73

33. Public health implication of the project and related activities for the population
in the impact zone should be systematically evaluated and the proposed remedial
measures should be detailed along with budgetary allocation.
34. Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for
implementation.
35. Detailed environmental management plan to mitigate the environmental impacts
which, should inter-alia also include the impact due to change of land use, due to
loss of agricultural land and grazing land, if any, occupational health impacts
besides other impacts of the projects.
36. Public hearing points raised and commitment of the project proponent on the
same along with time bound action plan to implement the same should be
provided and also incorporated in the final EIA/EMP Report of the Project.
37. Details of litigation pending against the project, if any, with direction /order
passed by any Court of Law against the project should be given.
38. The cost of the project (capital cost and recurring cost) as well as the cost
towards implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a. A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b. All documents may be properly referenced with index and continuous
page numbering.
c. Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d. Where the documents provided are in a language other than English, an
English translation should be provided.
e. The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f. Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
g. While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on
the website of this Ministry should also be followed.
h. Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought
to the attention of MoEF with reasons for such changes and permission
should be sought, as the TOR may also have to be altered. Post Public
Hearing changes in structure and content of the draft EIA/EMP (other
than modifications arising out of the P.H. process) will entail conducting
the PH again with the revised documentation.

The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage, clearly showing the land features of the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
Page 67 of 73

take further necessary action for obtaining environmental clearance in accordance with the
procedure prescribed under the EIA Notification, 2006.

2.41 Kumbhajari Decorative Stone Mines of M/s Ajax Petro, Village Kumbhajhari,
Distt. Ganjam, Orissa (13.638 ha)-TOR

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.42 Dakhinpur Decorative Stone Mines of M/s Ajax Petro, Village Dakhinpur, Distt.
Ganjam, Orissa (8.964 ha)-TOR.

The consideration of the proposal was deferred as the project proponent did not
attend the meeting.

2.43 Iron ore mine of M/s Urumunda Iron Ore Mines located at kasipur,
Keonjhar,Orissa- EC – Reconsideration. (Consultant: Envomin Consultant (Pvt.)
Ltd.)

The proposal is for renewal of mine lease, which became due on 29.12.2011 and
enhancement of production of iron ore from 30,000 TPA to 1,80,000 TPA. A Crushing,
Screening and Beneficiation Plant of 60,000 TPA is also part of the Project. The mine is
reported to be closed presently. TORs for this project were prescribed on 18.1.2010. Public
Hearing has been held on 30.6.2010. Mine lease area is 82.03 ha, which includes 54.63 ha of
forestland. It is a violation case as the proponent has increased production without
obtaining requisite prior environment clearance. Mine working will be opencast semi
mechanized involving drilling and blasting. Ultimate working depth will be 585 m AMSL.
Groundwater table during post monsoon is reported 575.5 m AMSL. Mine working will not
intersect groundwater table. It was stated by the Proponent that they are proposing to take
necessary measures by involving other mine owners in the area. Based on the presentation
made and discussions held, the Committee decided that the proponent will come for
obtaining environmental clearance beyond 2011. Now, the Proponent has ensured that the
necessary safeguard measures are in place and their effectiveness is demonstrated by
supporting data on ambient air quality in the area. The mining plan for renewal of Mining
Lease has been reapproved on 28.04.2011 by IBM, Bhubaneswar vide letter no.
MP/OTF.MECH/39-ORI/BHU/ 2010-11.

Based on the presentation made and discussions held, the Committee recommended
the project for environmental clearance.

2.44 Capacity Expansion of Mining and Mineral Separation Unit of M/s Indian Rare
Earths Ltd. Located at P.O-Matikhalo, Chatrapur (Ganjam), Orissa (Consultant:
Bhagvathi Ana Labs Ltd. Hyderabad)

The proposal was earlier considered by the Expert Appraisal Committee during its
meeting held on November 28-30, 2011 wherein the Committee had sought additional
information/clarifications on various related issues. Based on the additional
information/clarifications submitted by the proponent, the proposal was considered
further.
Page 68 of 73

The proposal is for enhancement of production of heavy mineral raw sand from
25,00,000 TPA to 75,00,000 TPA which will be processed in the mineral separation plant for
producing ilmenite along with other associated heavy minerals. The mine lease area is
2,464.054 ha which includes 157.7 ha of forestland. Application has been made for
obtaining forestry clearance ,copy of which has been submitted. No national park/sanctuary
is reported within 10 km of mine lease, however, nesting sites of Olive Ridley Turtles are
reported within 5.5 km from the approved mine site and 2.16 km from mine lease
boundary. The proponent stated that no mining will be carried out within 5km of the
nesting site. NOC has been granted by Principal Chief Conservator of Forests & Chief
Wildlife Warden vide letter No.3536/WL(C)(SSP)-149/2012 dated 11th May 2012 for
carrying out mining in north sector with respect to Capacity Expansion of Mining & Mineral
Separation Units (CEMMU). The distance of mine lease boundary from the Rushikulya River
Bank varies from 50 m to 1500 m. TORs for this project were prescribed on 20.10.2009.
Public Hearing has been held on 29.03.2011. The issues raised during public hearing were
also considered and discussed during the meeting. It was reported that there is no court
case pending against the project. The compliance status of the earlier EC conditions was
also presented and discussed.

Based on the presentation made and discussion held, the Committee recommended
the project for environmental clearance subject to Compliance with the conditions laid
down by Odisha State Coastal Zone Management Authority. No mining shall be carried out
in “NO GO ZONE / NO OPERATION ZONE” as stipulated in the conditions in the NOC letter
granted by Principal Chief Conservator of Forests & Chief Wildlife Warden.

2.45 Donkhera Dolmite & Baryte of M/s Satveer Singh at Mohindergarh, Haryana-
TOR (Consultant: Perfact EnviroSolutions Pvt. Ltd.)

The proposal was considered by the Committee to determine the Terms of


Reference (TOR) for undertaking detailed EIA study for the purpose of obtaining
environmental clearance in accordance with the provisions of the EIA Notification, 2006.
For this purpose, the proponent had submitted information in the prescribed format (Form-
1) along with Pre-Feasibility Report.

The proposal of Donkhera Dolmite & Baryte at Mohindergarh, Haryana is for the
production of Dolomite of 2.2 MTPA. The lease area is 24.3 ha, which is a barren land. Date
of grant of lease is 21-08-2001 and the same is valid for 20 years. Krishnawati or Kasaunti
river is at 2.0 Km E and Meena ka Nangal PF is adjacent. Ecologically sensitive area such as
National park/Wild life sanctuary / Biosphere reserve / tiger / Elephant reserve are not
present within 10 km of Buffer zone. The Proponent has submitted a letter from DFO,
Mohindergarh stating that the area is not covered under Section 4 and 5 of Punjab Land
Preservation Act. It was also reported by the proponent that there is no court case pending
against the project. The mining method will be opencast semi mechanized including drilling
and blasting.

Based on the information furnished and presentation made, the Committee prescribed
the following TORs for undertaking detailed EIA study:-

1. Year-wise production details since 1994 onwards should be given clearly stating the
highest production achieved in any one year prior to 1994. It may also be
categorically informed whether there had been any increase in production after the
Page 69 of 73

EIA Notification, 1994 coming into force w.r.t. the highest production achieved prior
to 1994.
2. A copy of the document in support of the fact that the proponent is the rightful
lessee of the mine should be given.
3. All documents including approved mine plan, EIA and public hearing should be
compatible with one another in terms of the mine lease area, production levels,
waste generation and its management and mining technology and should be in the
name of the lessee.
4. All corner coordinates of the mine lease area superimposed on High Resolution
Imagery/toposheet should be provided.
5. Does the company have a well laid down Environment Policy approved by its Board
of Directors? If so, it may be detailed in the EIA report.
6. Does the Environment Policy prescribe for standard operating process/ procedures
to bring into focus any infringement / deviation / violation of the environmental or
forest norms / conditions? If so, it may be detailed in the EIA.
7. What is the hierarchical system or Administrative order of the company to deal with
the environmental issues and for ensuring compliance with the EC conditions.
Details of this system may be given.
8. Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
9. The study area will comprise of 10 km zone around the mine lease from lease
periphery and the data contained in the EIA such as waste generation etc should be
for the life of the mine / lease period.
10. Land use of the study area delineating forest area, agricultural land, grazing land,
wildlife sanctuary and national park, migratory routes of fauna, water bodies,
human settlements and other ecological features should be indicated.
11. Land use plan of the mine lease area should be prepared to encompass pre-
operational, operational and post operational phases and submitted.
12. Location of National Parks, Sanctuaries, Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves (existing as well as proposed), if any, within 10 km of the
mine lease should be clearly indicated supported by a location map duly
authenticated by Chief Wildlife Warden. Necessary clearance, if any, as may be
applicable to such projects due to proximity of the ecologically sensitive areas as
mentioned above should be obtained from the State Wildlife Department/ Chief
Wildlife Warden under the Wildlife (Protection) Act, 1972 and copy furnished.
13. A detailed biological study for the study area [core zone and buffer zone (10 km
radius of the periphery of the mine lease)] shall be carried out. Details of flora and
fauna, duly authenticated, separately for core and buffer zone should be furnished
based on primary field survey clearly indicating the Schedule of the fauna present.
In case of any scheduled-I fauna found in the study area, the necessary plan for their
conservation should be prepared in consultation with State Forest and Wildlife
Department and details furnished. Necessary allocation of funds for implementing
the same should be made as part of the project cost.
14. Impact, if any, of change of land use should be given.
15. R&R plan / compensation details for the project affected people should be
furnished. While preparing the R&R plan, the National Rehabilitation &
Resettlement Policy should be kept in view. In respect of SCs / STs and other
weaker sections, need based sample survey, family-wise, should be undertaken to
Page 70 of 73

assess their requirement and action programmes prepared accordingly integrating


the sectoral programme of line departments of the State Government.
16. One season (non-monsoon) primary baseline data on ambient air quality (PM10, SO2
and NOx), water quality, noise level, soil and flora and fauna shall be collected and
the AAQ data so collected presented date-wise in the EIA and EMP report. Site-
specific meteorological data should also be collected. The location of the monitoring
stations should be such as to represent whole of the study area and justified keeping
in view the pre-dominant downwind direction and location of sensitive receptors.
There should be at least one monitoring station within 500 m of the mine lease in
the pre-dominant downwind direction. The mineralogical composition of PM10
particularly for free silica should be given.
17. Air quality modelling should be carried out for prediction of impact of the project on
the air quality of the area. It should also take into account the impact of movement
of vehicles for transportation of mineral. The details of the model used and input
parameters used for modelling should be provided. The air quality contours may be
shown on a location map clearly indicating the location of the site, location of
sensitive receptors, if any and the habitation. The wind roses showing pre-
dominant wind direction may also be indicated on the map.
18. The water requirement for the project, its availability and source to be furnished. A
detailed water balance should also be provided. Fresh water requirement for the
project should be indicated.
19. Necessary clearance from the Competent Authority for drawl of requisite quantity of
water for the project should be provided.
20. Details of water conservation measures proposed to be adopted in the project
should be given.
21. Impact of the project on the water quality both surface and groundwater should be
assessed and necessary safeguard measures, if any required should be provided.
22. Based on actual monitored data, it may clearly be shown whether working will
intersect groundwater. Necessary data and documentation in this regard may be
provided. In case the working will intersect groundwater table, a detailed hydro
geological study should be undertaken and report furnished. Necessary permission
from Central Ground Water Authority for working below ground water and for
pumping of ground water should also be obtained and copy furnished.
23. Details of any stream, seasonal or otherwise, passing through lease area and
modification / diversion proposed, if any and the impact of the same on the
hydrology should be brought out.
24. Details of rainwater harvesting proposed, if any, in the project should be provided.
25. Information on site elevation, working depth, groundwater table etc. should be
provided both in AMSL and bgl. A schematic diagram may also be provided for the
same.
26. Quantity of solid waste generation to be estimated and details for its disposal and
management should be provided. The quantity, volumes and methodology planned
for removal and utilisation (preferably concurrently) of top soil should be indicated.
Details of backfilling proposed, if any, should also be given. It may be clearly
indicated that out of the total waste generated during the mine life, how much
quantity would be backfilled and how much quantity would be disposed off in the
form of external dump (number of dumps, their height, terraces etc. to be brought
out).
27. The reclamation plan, post mine land use and progressive greenbelt development
plan shall be prepared in tabular form (prescribed format) and submitted.
Page 71 of 73

28. Impact on local transport infrastructure due to the project should be indicated.
Projected increase in truck traffic as a result of the project in the present road
network (including those outside the project area) should be worked out, indicating
whether it is capable of handling the increased load. Arrangement for improving the
infrastructure, if contemplated (including action to be taken by other agencies such
as State Government) should be covered.
29. Details of the infrastructure facilities to be provided for the mine workers should be
included in the EIA report.
30. Conceptual post mining land use and Reclamation and Rehabilitation of mined out
area (with plans and with adequate number of sections) should be given in the EIA
report.
31. Phase-wise plan of greenbelt development, plantation and compensatory
afforestation should be charted clearly indicating the area to be covered under
plantation and the species to be planted. The details of plantation already done
should be given.
32. Occupational health impact of project should be anticipated and preventive
measures initiated. Details in this regard should be provided. Details of pre-
placement medical examination and periodical medical examination schedules
should be incorporated in the EMP.
33. Public health implication of the project and related activities for the population in
the impact zone should be systematically evaluated and the proposed remedial
measures should be detailed along with budgetary allocation.
34. Measures of socio economic significance and influence to the local community
proposed to be provided by project proponent should be indicated. As far as
possible, quantitative dimensions may be given with time frame for implementation.
35. Detailed environmental management plan to mitigate the environmental impacts
which, should inter-alia also include the impact due to change of land use, due to
loss of agricultural land and grazing land, if any, occupational health impacts besides
other impacts of the projects.
36. Public hearing points raised and commitment of the project proponent on the same
along with time bound action plan to implement the same should be provided and
also incorporated in the final EIA/EMP Report of the Project.
37. Details of litigation pending against the project, if any, with direction /order passed
by any Court of Law against the project should be given.
38. The cost of the project (capital cost and recurring cost) as well as the cost towards
implementation of EMP should clearly be spelt out.

Besides the above, the below mentioned general points should also be followed:-
a. A note confirming compliance of the TOR, with cross referencing of the
relevant sections / pages of the EIA report should be provided.
b. All documents may be properly referenced with index and continuous
page numbering.
c. Where data are presented in the report especially in tables, the period in
which the data were collected and the sources should be indicated.
d. Where the documents provided are in a language other than English, an
English translation should be provided.
e. The Questionnaire for environmental appraisal of mining projects as
prescribed by the Ministry shall also be filled and submitted.
f. Approved mine plan along with copy of the approval letter for the
proposed capacity should also be submitted.
Page 72 of 73

g. While preparing the EIA report, the instructions for the proponents and
instructions for the consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August, 2009, which are available on
the website of this Ministry should also be followed.
h. Changes, if any made in the basic scope and project parameters (as
submitted in Form-I and the F.R for securing the TOR) should be brought
to the attention of MoEF with reasons for such changes and permission
should be sought, as the TOR may also have to be altered. Post Public
Hearing changes in structure and content of the draft EIA/EMP (other
than modifications arising out of the P.H. process) will entail conducting
the PH again with the revised documentation.
The EIA report should also include (i) surface plan of the area indicating contours of
main topographic features, drainage and mining area, (ii) geological maps and sections and
(iii) sections of the mine pit and external dumps, if any, clearly showing the land features of
the adjoining area.

After preparing the draft EIA (as per the generic structure prescribed in Appendix-
III of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.

*****************
Page 73 of 73

Annexure
List of Participants

1. Shri M.S. Nagar - Chairman


2. Dr. S. Subramaniyam - Vice Chairman
3. Prof. C.K. Varshney - Member
4. Shri K.S. Anandan - Member
5. Dr. T.K. Joshi - Member
6. Shri Mihir Moitra - Member
7. Dr. L. Ajay Kumar - Member
8. Dr. S.K. Peshin - Member
9. Shri Vinay Mahajan - Member
10. Shri Rajesh Srivastava - Member
11. Dr. B.K. Mishra - Member
12. Shri Ranjan Sahai - Member
13. Dr. Saroj, Director - Member Secretary
14. Shri Om Prakash, Dy. Director, MoEF
15. Shri Neeraj Khatri, Dy. Director, MoEF
16. Representative of M/s Prachi Mines
17. Representative of M/s Tata Steel Ltd.
18. Representative of M/s UltraTech Cement Ltd.
19. Representative of M/s Gogte Minerals
20. Representative of M/s Nilesh Mines Corp.
21. Representative of M/s Hindustan Copper Ltd.
22. Representative of M/s Singhbhum Mineral Co.
23. Representative of M/s Sri Om Prakash Jaiswal
24. Representative of M/s Anand Kumar Singh
25. Representative of M/s Aaress Grits
26. Representative of M/s Sri Shripal
27. Representative of M/s Associated Soapstone Distributing Co. Pvt. Ltd.
28. Representative of M/s Archana Hi Tech Automation System Pvt. Ltd.
29. Representative of M/s Adhunik Cement Ltd.
30. Representative of M/s Hindustan Construction Company
31. Representative of M/s GHCL
32. Representative of M/s Kajla Stone Crusher
33. Representative of M/s Ullikallu Dolomite Mine Pvt.ltd.
34. Representative of M/s Associated Soapstone Distributing Co. Pvt. Ltd.
35. Representative of M/s Sh. Laxmi Chand Goyal
36. Representative of M/s Mohunta Mining & Mfg. Co. Pvt. Ltd.
37. Representative of M/s Leela Devi
38. Representative of M/s Mohd. Sher Khan
39. Representative of M/s Rungta Sons (P) Ltd.,
40. Representative of M/s Harish Clays
41. Representative of M/s Mahesh Mantri,
42. Representative of M/s Kalinga Mining Corp.,
43. Representative of M/s R.P. Sao
44. Representative of M/s Urumunda Iron Ore Mines
45. Representative of M/s Indian Rare Earths Ltd
46. Representative of M/s Satveer Singh
*******************

You might also like