SB Installation Guide Final
SB Installation Guide Final
SB Installation Guide Final
11-A-1077-01 Rev.2
Switchboards
Answers for industry.
Contents
Section 1.0 Introduction 1.1 Qualified person 1.2 Signal words 1.3 Dangerous procedures 1.4 Field service 1.5 General description 2.0 Safety precautions 3.0 Switchboard preparation 3.1 Receiving 3.2 Inspection 3.3 Shipping damage claims 3.4 Handling 3.5 Storage 4.0 Installation 4.1 Location 4.2 Foundation requirements 4.3 Positioning of sections 4.4 Anchoring, leveling and assembly 4.5 Joining shipping sections 4.6 Electrical connections 4.7 Through bus splice connections 4.8 Ground bus splice connections 4.9 Grounding and bonding 4.10 Busway connection 4.11 Switchboard busway flange connection 4.12 Conduit area 4.13 Cable pulling 4.14 Cable termination 4.15 Cable lashing requirements 4.16 Control wiring Pre-Energizing, inspection and testing 5.1 Inspection 5.2 Testing 5.3 Ground fault protection system 6.0 Ground fault inspection and testing 6.1 External ground fault 6.2 Internal ground fault 7.0 Energizing and operation, switchboard loading and maintenance 7.1 Placing equipment into service 8.0 Switchboard loading 9.0 Maintenance 9.1 Inspection and maintenance intervals 9.2 Recommended maintenance 9.3 Maintenance tasks 9.4 Cleaning insulation 10.0 Adverse conditions 10.1 Ambient temperatures 10.2 Short circuits 10.3 Arcing damage 10.4 Water damage 10.5 Corrosive atmospheres 11.0 Informational charts 11.1 Torque values 11.2 Wire bending requirements 11.3 Strap kits 11.4 Ground fault test record External 11.5 Ground fault test record Internal 12.0 Service bulletins 5.0 Page 2 2 2 2 2 2 3 3-5 3 3 3 4 4-5 5-10 5 5 5 5 6 6 6-7 8 8 8 8 9 9 9 9 10 10-12 10 11 11-12 12-13 12 12-13 13-14 13 14 14-15 14 14 14 15 16 16 16 16 16 16 16-19 16 17 17 18 19 20
THESE INSTRUCTIONS DO NOT PURPORT TO COVER ALL DETAILS OR VARIATIONS IN EQUIPMENT, NOR TO PROVIDE FOR EVERY POSSIBLE CONTINGENCY TO BE MET IN CONJUNCTION WITH INSTALLATION, OPERATION OR MAINTENANCE. SHOULD FURTHER INFORMATION BE DESIRED OR SHOULD PARTICULAR PROBLEMS ARISE WHICH ARE NOT COVERED SUFFICIENTLY FOR THE PURCHASERS PURPOSES, THE MATTER SHOULD BE REFERRED TO THE LOCAL SIEMENS SALES OFFICE. THE CONTENTS OF THIS INSTRUCTION MANUAL SHALL NOT BECOME PART OF OR MODIFY ANY PRIOR OR EXISTING AGREEMENT, COMMITMENT OR RELATIONSHIP. THE SALES CONTRACT CONTAINS THE ENTIRE OBLIGATION OF SIEMENS. THE WARRANTY CONTAINED IN THE CONTRACT BETWEEN THE PARTIES IS THE SOLE WARRANTY OF SIEMENS. ANY STATEMENTS CONTINUED HEREIN DO NOT CREATE NEW WARRANTIES OR MODIFY THE EXISTING WARRANTY.
Introduction
Section 1.0 Introduction The purpose of this manual is to assist the user in developing safe and efficient procedures for the installation, maintenance and operation of the equipment. For additional information, refer to NEMA Standards Publication PB2.1 General Instructions for Proper Handling, Installation, Operation, and Maintenance of Deadfront Distribution Switchboards rated 600 volts or less which is available from the NEMA web site (www.nema.org). Contact the nearest Siemens representative if any additional information is required. Siemens warrants that on the date of shipment all goods manufactured by Siemens are free of non-conformities in workmanship and materials. If within one year from date of initial operation, but not more than eighteen months from date of shipment by Siemens, of any item of the goods, purchaser discovers that such item was not as warranted above, and promptly notifies company in writing thereof, company shall remedy such defect by, at companys option, adjustment, repair or replacement of the item and any affected part of the goods. Refer to Standard Terms and Conditions of Sale for complete warranty terms. 1.1 Qualified person For the purpose of this manual a Qualified Person is one who has the skills and knowledge related to the construction and operation of electrical equipment and installations and has received safety training to recognize and avoid the hazards involved. In addition, this person has the following qualifications: 1.1.1. Training and authorization to energize, de-energize, clear, ground and tag circuits and equipment in accordance with established safety practices. 1.1.2. Training in the proper care and use of protective equipment such as rubber gloves, hard hat, safety glasses, face shields, flash clothing, etc., in accordance with established safety procedures. 1.1.3. Training in rendering first aid. 1.1.4. Knowledgeable of NEC requirements and other applicable codes, laws and standards 1.2 Signal words The signal words Danger, Warning and Caution used in this manual indicate the degree of hazard that may be encountered by the user. These words are defined as: 1.2.1. Danger Indicates an imminently hazardous situation which, if not avoided, will result in death or serious injury. 1.2.2. Warning Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury. 1.2.3. Caution Indicates a potentially hazardous situation which, if not avoided may result in minor or moderate injury. 1.3 Dangerous procedures In addition to other procedures described in this manual as dangerous, user personnel must adhere to the following warnings: 1.3.1. Danger! High Voltage. Qualified personnel only. Lock off all power to this equipment before working inside. Always work on de-energized equipment. Always
2 Switchboard Instruction and Installation Guide
de-energize equipment before performing any tests, maintenance or repair. 1.3.2. Warning! Always perform maintenance on the interrupting device after the closing mechanism(s) are discharged. 1.3.3. Caution! Always let an interlock device or safety mechanism perform its function without forcing or defeating the device. 1.3.4. Caution! Hydrocarbon spray propellants and hydrocarbon compounds will cause degradation of certain plastics. Contact your local Siemens representative before using these products to clean or lubricate components during installation or maintenance. 1.4 Field service Siemens Industrial Services can provide the following support services for switchboards. Call 1-800-241-4453 to obtain additional information and schedule an appointment. Start-up Commissioning Component and System Testing Maintenance (Scheduled and Preventative) Repair and Refurbishing On Site Operational Training 1.5 General description Siemens switchboards are designed and manufactured to perform efficiently under normal operating conditions. The instructions included in this manual are provided to aid in obtaining long and economical service from your switchboards. For proper operation and maintenance, this information should be distributed to the owners operators and engineers. These instructions cover the standard construction details of Siemens switchboards including auxiliary equipment and necessary accessories. Any special equipment furnished in accordance with purchase order requirements are covered by supplementary instruction books. The switchboards described in this manual are the deadfront type as defined in NFPA70 (NEC), UL891 and NEMA PB2. All parts, conductors, and insulation materials are designed and constructed to suit the voltage class of the equipment and are enclosed within grounded metal enclosures. The equipment furnished has been designed to operate in a system having the circuit capacity specified by the purchaser. If, for any reason, the equipment is later used in a different system, or if the short-circuit capacity of the system is increased, the momentary rating of the switchboards, the interrupting capacity of the protective devices and the bus capacity must be checked. Should the service be changed, the equipment must be checked to assure that the short circuit capacity, amperage and voltage class of the equipment meets or exceeds the requirement of the new system. Switchboards are free-standing units rated 6000 amperes or less at 600 volts AC or less. A typical switchboard will contain the service entrance section with main devices and distribution sections with branch devices. The sections contain disconnect devices, protective devices, auxiliary equipment, and any current transformers for metering, control, or ground fault protection.
DANGER
Hazardous voltage. Will cause death or serious injury.
Keep out. Qualified personnel only. Disconnect and lock off all power before working on this equipment.
2.1. Only qualified persons familiar with the construction and operation of switchboards should perform work described in this set of instructions. Such work should be performed only after reading this complete set of instructions. 2.2. Follow safety related work practices, as described in NFPA 70E, at all times. 2.3. Hazardous voltages in electrical equipment can cause severe personal injury or death. Energizing a switchboard for the first time after initial installation or maintenance is potentially dangerous. Inspection and maintenance should be performed on switchboards and equipment to which power has been cut off, disconnected, and electrically isolated so that no accidental contact can be made with energized parts. 2.4. Some types of electrical equipment will cause harmonics in the electrical system which may result in overheating. Consider this condition when determining switchboard loading, as possible de-rating of equipment may be necessary. Section 3.0 - Switchboard preparation 3.1 Receiving Prior to shipment, each switchboard is inspected to ensure structural and electrical construction is in compliance with applicable specifications, codes, and standards. Depending on the size and number of sections, the switchboard is divided into shipping sections of one or more vertical sections and placed onto wooden skids. Each shipping section is packaged, securely blocked and braced for shipment. Whatever method of shipment, every precaution is taken to minimize the possibility of damage and to ensure its safe arrival. Relatively delicate instruments or devices may be included and the assembly must be handled carefully when unloading. When the equipment arrives at the destination, the packing list or marking tag(s) should be checked against the equipment actually received to make sure the shipment is correct and complete. Claims for shortages or incorrect material must be made in writing within 30 days after receipt of the shipment
Switchboard preparation
3.3.8. If practical, make further inspection for possible concealed damage while carrier inspector is on site. If inspection for concealed damage is not practical at the time the carrier is present, it must be done within 15 days of receipt of equipment. If concealed damage is found, the carrier must again be notified and inspection made prior to making any corrective action to repair. Also notify Siemens Sales Office immediately. 3.3.9. Obtain the original of the carrier inspection report and forward it along with a copy of the noted delivery receipt to the Siemens Sales Office. Approval must be obtained by Siemens from the carrier before any repair work can be performed. Before approval can be obtained, the documents requested must be in Siemens hands. The carrier inspection report and/or drivers signature on the delivery receipt does not constitute approval to repair. 3.4 Handling Each switchboard shipping section has provisions for attaching lifting equipment. The lift points are designed for use with a crane of adequate height and capacity. To estimate the maximum required crane capacity, multiply the number of sections to be lifted by 2,000 pounds. NOTE: 2,000 LBS IS AN AVERAGE WEIGHT. SOME SECTIONS MAY HAVE A WEIGHT OF GREATER THAN 2,000 LBS. PLEASE CALL THE SIEMENS SALES OFFICE TO VERIFY SECTION WEIGHTS. Switchboard sections may be moved by crane with lift cables attached to the lifting bars on the top of the switchboard. If crane facilities are unavailable, or if tight spaces prevent use of a crane, rollers under the skids may be used. Recommended lifting is by means of four cables connected to an overhead crane or by fork lift. 3.4.1 Lifting by means of an overhead crane Single section lifting The cables are connected to the lifting brackets, mounted at the top front and top rear mounting locations (See Fig. #1A). A crane with sufficient height should be used so the load angle (from horizontal) on the lifting cables will be a minimum of 45 degrees, when viewed from side of section. The lifting cables must have spreaders from side to side to prevent twisting the lifting brackets. Figure 1A For alternate handling means, please refer to the NEMA Standards Publication PB 2.1. 3.5. Storage 3.5.1 Indoor switchboards When switchboard is not to be installed immediately, it should be unpacked, inspected and stored in a clean dry location having adequate air circulation and uniform temperature to prevent condensation. If switchboard is to be stored for any length of time prior to installation, restore the packing for protection. If the packing material is removed, cover the switchboard to protect from dust, debris, and moisture. Indoor switchboards are neither weatherproof nor drip-proof. Therefore, it should be stored indoors. If it is to be kept either outdoors or in a humid, unheated area, provide an adequate covering to protect against weather and dirt, and place a heat 3.4.2 Multi-section lifting The method of lifting a multisection unit is similar to lifting single section. The cables need to be connected to all lifting brackets. The lifting cables must have correct spreader from side to side (See Fig #1B). A crane with sufficient height and lift is required. Figure 1B
3.4.3 Lifting by means of a forklift Forklift trucks should be used with care as improper lift points could cause damage to equipment. Balance the load carefully and use safety straps when handling with a forklift. Jacks may be used to lift switchboard sections which are properly supported by sturdy timbers. To prevent distortion of the enclosures, rollers and cribbing of equal height must be used in sufficient number to evenly distribute the load. Figure 2 shows a method of using a forklift on an indoor switchboard. Figure 2
Minimum
Front View
Side View
Installation
source of approximately 250 watts output within each vertical section to prevent condensation. Space heaters are not standard equipment on indoor switchboards. Remove any loose packaging or flammable materials inside the switchboard before energizing the heat source. Lubricate any moving parts such as hinges, shutters, etc., if storage is for an extensive period of time. 3.5.2 Storage Outdoor switchboards It is important that outdoor switchboards are stored exactly as described for indoor switchboards. When it is necessary to store outdoor switchboards in an area exposed to the weather or under humid conditions, they should be kept clean and dry as described above. Energize the self-contained space heaters (if provided) and make certain that louvers and vents are uncovered to allow air to circulate and cover shipping splits to protect from the elements. Refer to wiring diagram drawing for space heater circuit connections. Lubricate hinges, shutters, and other moving parts. Section 4.0 Installation The proper switchboard installation method depends on whether the units are shipped as one complete group (maximum of 84.0) or in two or more shipping sections.The general arrangement drawing supplied by the factory will indicate the shipping groups and their respective location within the lineup. Units must be assembled in accordance with the general arrangement drawing. 4.1. Location Find the designated area on the building plan where the switchboard will be installed. If this area is not specified, the location chosen for installation should provide working clearances complying with article 110.26 of the National Electrical Code (NEC). Front accessible switchboards require that field connections including mains, branches, ground, and neutral are accessible and maintainable from the front. Equipment drawings identify switchboards that require rear access. 4.2. Foundation requirements Extreme care should be taken in layout of foundation or floor. Refer to general arrangement drawing for exact location of anchor bolts, area for conduits, other limitations, and instructions. Foundations must be sufficiently strong to support the weight of the equipment. Conduit couplings should be stubbed flush with or below the finished floor level. (Refer to NEC 408.5) After the equipment has been lowered to the foundation and set in place, conduit extension sleeves may be screwed into couplings. Floors and sills must have a smooth level surface and be in the same plane. The surface of the foundation must not protrude above the grouted sills or bed plates at any point. Grouted sills or bed plates must be set true and level and be in an aligned position in the same plane to each other over the entire length. Outdoor equipment is usually installed on a concrete pad with a level and smooth surface. Outdoor equipment which has been assembled on formed base plates must be supported at each section. Adjacent units at each shipping split must be supported on a single support, and this must be taken into consideration when the foundation is designed and constructed. 4.3. Positioning of sections Positioning and connection of the switchboard sections at the installation site is done in the following manner. 4.3.1. Space to the front and rear should be sufficient for opening of doors, insertion and withdrawal of removable breakers, inspection, and maintenance. Service entrance equipment should be located as close as possible to the incoming service of the building. 4.3.2. Clean the mounting surface to remove all dirt and debris. Start with the left end shipping group and continue in sequence. Maneuver the section into the desired position using procedures described under Handling. Use care in locating sections over conduit areas and beware of any conduits which stub-up above floor level as these may block sliding the section in either direction. 4.3.3. Prepare for the connections across shipping splits before the equipment is moved into final position. Bus supports and bus joints should be removed using side, rear and front access options as required. Note the mounting position and orientation and save hardware for use in reinstallation. 4.3.4. Remove the shipping skid and stand the section in an upright position. Remove all packing material and the bottom floor plate if one is installed in the section. To protect the bottom channel, any sliding force must be carefully applied across the bottom 4 inches (100mm) of the side to fully distribute the sliding force. 4.3.5. All shipping sections must be leveled and aligned to each other in order to maintain proper alignment of the horizontal main through bus and splice bus connections. Bolt all section frames together and connect all through bus and ground bus at shipping breaks using the splice plate bus and hardware supplied. Tighten bolted connections in accordance with torque specifications indicated on the instruction label supplied. 4.4. Anchoring, leveling and assembly Indoor switchboard shipping groups are held in alignment by bolts holding the vertical sections to each other. The entire shipping group is to be anchored and leveled as a single element without loosening any hardware until entire shipping group is leveled and anchored. Supporting surfaces for the switchboard at each anchoring bolt location must be level and in the same plane. There must not be any projection above this plane within the area covered by the switchboard cubicles. Figure 3
Rear
Front
Typical bolt-down hole provisions for cubical bottom, each section.
Installation
If the floor or ground sill channels do not meet this requirement, it may be necessary to shim in the following manner. All anchor bolt locations in each cubicle must freely rest in firm contact with the mounting support surfaces. There must not be any projection or obstruction in other areas which may distort the cubicle. Do not force cubicle in firm contact by drawing down anchoring bolts as such drastic means will distort cubicles. Add 4 (100mm) square shims adjacent to anchor bolts until firm contact is achieved. Check each anchor bolt location (See Figure 3 and 4). 4.4.1. If side mounted lifting bars are supplied on shipping sections, it is necessary to remove the lifting bars. If top mounted lifting brackets are supplied on shipping sections, removal is optional. 4.4.2. Tighten anchor bolts or weld to sills. 4.4.3. If line-up consists of multiple groups, move the next group into position, with the rear of units in line and tight against the adjacent group. Do not bolt groups together at this time. Check that the cubicles are in firm contact with the foundation at each corner and anchor point and that bolt holes are in alignment. Add square shims as necessary. Tighten the anchor bolts. Now bolt groups together as described in Joining Shipping Sections. 4.4.4. Repeat Step 3 above until all shipping groups have been installed securely and in the correct order per the front elevation drawing supplied from the factory. Note: For seismic installation, refer to installation instructions furnished with the equipment. Figure 5
East Coast Standard Outdoor Type 3R Front West Coast Standard Outdoor Type 3R
4.6. Electrical connections Electrical connections within switchboards are made using either bus bar or cable. Bus bar is furnished for connections between the main bus, circuit breakers fusible devices and pads for cable terminations. Switchboards are designed to fully comply with standard electrical clearances. However, since cable and bus connections are being made in the field, care must be taken to ensure that all minimum clearances are maintained for electrical connections.
Between live parts of opposite polarity Through Air Over Surface 0-125V 1/2 3/4 126-250V 3/4 1 1/4 251-600V 1 2
Between live parts and grounded metal Through Air Over Surface
251-600V 1 1
4.7. Through bus splice connections When a switchboard group is split for shipping purposes, the cross bus and ground bus connections must be made when installing the equipment. To make these bolted connections, refer to Figures 6 through 12 and these instructions: Figure 4 4.5. Joining shipping sections The front panels and, if possible, the back plates should be removed so that adjacent shipping section frames can be bolted firmly together. Place 5/16-16 x 1.00 inch steel bolts through the holes in each front and rear corner post as shown in Figure 5. Torque the bolts to 12 ft lbs. 4.7.1. Access to the main bus from the cable termination area is achieved by removing the main bus compartment barrier which separates the main bus from the cable area. For some arrangements, it may be necessary to remove items between the main bus barriers and the rear of the unit in order to gain full access. After completion of the bus assembly and installation, these items should be reassembled in reverse sequence.
Installation
4.7.2. All surfaces must be free of dust, dirt or other foreign material. Do not use any abrasive cleaner on plated contact surfaces. Cleaning is normally not necessary and should not be done unless parts are badly tarnished. If cleaning is necessary, use a mild cleaner and thoroughly remove all residue. Keep cleaning agent off insulation. 4.7.3. Before assembling any bus bar joint, check that the bar is inserted through bus supports (when required). Observe the relationship of the bus bar and maintain this relationship when connecting bus bars. Spacers may be required in some bus joint connections. 4.7.4. Assemble all joints with the parts dry. Do not use grease or no-oxide product. 4.7.5. Use the hardware provided with the Splice Plate Kit. Using smaller or different grade hardware may result in over-heating of the connection. 4.7.6. Single Bolt Connections: Insert the bolt through the hole on the tie plate and the through bus. Next, place the large diameter Belleville washer on the 1/2-13 bolt. Hand tighten the nut and then torque to 50 ft. lbs. Duplicate for each set. 4.7.7. Four Bolt Connections: Position the (4) ,-16 carriage bolts in the slotted holes in the splice plate and the through bus. Hand tighten the ,-16 belleville washer nut and then torque to 20 ft lbs. Duplicate for each set.
SPLICE PLATES
HARDWARE GRADE 5 5 2 1) MAX. TORQUE 20 FT/LBS 50 FT/LBS 22FT/LBS
THRU BUS
WHEN MORE THAN ONE SPLICE PLATE IS PROVIDED PER PHASE INSTALL ON EACH SIDE OF THE THRU BUS.
11-A-1021-01 REV. 2
Hardware Grade Determinations Figure 10 (Straight tie plate Four hole to single hole)
Grade 2
1) Older
Grade 5
switchboards used Grade 2 hardware. See Hardware Grade Determination Detail for determining which type of bolt is installed in the gear. Also, refer to the torque table provided with the gear.
Installation
Figure 11 (Offset tie plate Four hole to single hole) 4.9.1.2. If required, the main bonding jumper between the neutral bus and the ground bus will be installed at the factory. Ensure that the bonding jumper is in place and properly labeled. 4.9.1.3.It is important that none of the grounding conductors are connected to load side of any neutral disconnecting link or any sensor used for ground fault protection. 4.9.1.4. When the system is a dual fed (double ended) and has ground fault protection, refer to switchboard front elevation drawing for proper grounding and handling. 4.9.2. For ungrounded systems used as service equipment, or as main switchboard on a separately derived system, follow the steps below: 4.9.2.1.Run a grounding electrode as described in part 4.9.1.1. above. 4.8 Ground bus splice connections Remove ground bus splice plate and rotate the bar into place. Align and secure the ground bus splice connection between shipping sections. Refer to Figure 13 for connection. Torque connections to 6 ft lbs. NOTE: Proper installation is essential for safe and proper operation of ground fault protection system (when provided). Figure 13 4.9.3. If the system is grounded at any point ahead of the switchboard, the grounded conductor must be run from that point and connected to the ground bus as described in paragraph 250.24(C) of the National Electric Code (NEC). This conductor is required even if the switchboard supplies only phase to phase loads. 4.9.4. For a switchboard not used as service equipment or as a main switchboard on a separately derived system: 4.9.4.1.Use equipment grounding conductors sized according to Table 250.122 of the National Electric Code to ground the switchboard frame and ground bus to the service ground, or by bonding to the raceway enclosing the main supply conductors in accordance with sections 250.118 and 250.120 of the National Electrical Code. 4.10 Busway connection Refer to the SENTRON Busway Storage, Installation and Maintenance Instructions Piece No. 31-9918-01 supplied with the Busway for installation of the busway runs. 4.11 Switchboard busway flange connection In some cases, the Sentron Busway standard stubs are shipped to the job site already factory connected to the switchboard. In applications where the flange stub is not installed from the factory, refer to the following instructions below: 4.11.1. From inside the switchboards, remove the bolts that fasten the switchboard bus to the busway flanges. 4.11.2. Remove the screws from the switchboard that are around the opening busway cutout. 4.11.3. Insert the busway flange end into the switchboard bus connectors in the switchboard and align the holes. NOTE: Top plate is not designed to support weight of busway. Busway must be supported by other means.
4.9. Grounding and bonding 4.9.1 For grounded systems used as service equipment or as a main switchboard on a separately derived system, follow the steps below: 4.9.1.1. Run a grounding electrode conductor from the grounding electrode at the installation site to the switchboard grounding electrode conductor terminal. Select the proper material and size the grounding conductor to comply with sections 250.62, 250.66, and 250.166 of the National Electric Code (NEC). Install the grounding electrode conductor as specified in section 250.64(B) of the National Electric Code (NEC). No ground conductors are allowed on load side of neutral disconnect link or ground fault sensor.
Installation
4.11.4. Insert the bolts at bus joint and torque to 20 ft lbs. Tighten bus joint connections, all phases, neutral and ground bars. 4.11.5. Insert the screws that attached the busway flange to the switchboard top plate or outer cover. 4.11.6.Verify busway flange phasing with switchboard phasing (i.e., ABCN, front to rear). Figure 14 to relieve this condition or place suitable protective material at the bearing point to protect the cable insulation. 4.13.5. Where cables enter or leave the switchboard, or pass through any metal which has magnetic properties, be certain to run all phase and the neutral conductors through the same opening. See 300.20 (A) of the National Electrical Code 4.13.6. Cables entering or exiting the switchboard should be in the same section in which they are terminated, except as noted in 408.3 of the National Electrical Code. See Article 300 of the National Electrical Code for proper wiring methods. 4.13.7. For Class 2 and Class 3 remote control, signaling and power-limited circuits separation requirements, see 725.136 of the National Electrical Code. 4.13.8. Conductors of size 1/0 AWG and larger may be run in parallel. When these conductors are run in parallel they should be of the same size, length and material to assure the equal division of current, as required by 310.4 of the National Electrical Code. 4.14 Cable termination 4.14.1. Strip a length of insulation from the end of the cable sufficient to fit into the full length of the lug barrel, being careful not to nick or ring the strands. Use a proper insulation stripping tool. 4.14.2. Thoroughly clean aluminum cable contact surfaces with a wire brush. 4.14.3. Apply an acceptable joint compound to the bare aluminum. 4.14.4. If compression type lugs are furnished on any switch or circuit breaker, or as the main incoming power lugs, unbolt and remove them. Insert the cable into the lug barrel and, using the recommended crimping tool, make the specified number of crimps. Wipe excess sealant from the connector and insulation. With the cables connected, remount the lugs onto the bus bars, switches, or circuit breakers. Torque the bolts per the chart on page 16. 4.14.5. Set screw type lugs may be furnished as main incoming lugs and are standard on all devices supplied by Siemens. Torque values for these lugs are marked on these units. Torque values for other switchboard lugs are marked on the switchboard. 4.15 Cable lashing requirements For conductor lashing instructions on switchboards marked 65kA, 100kA or 200kA short circuit current ratings, refer to the following instructions: 4.15.1. Switchboards with a single fusible main switch rated 4000A or less do not require lashing. 4.15.2. Switchboards with a single main molded case circuit breaker rated 4000A or less do not require lashing. When using a WL Circuit Breaker, lashing is required. 4.15.3. Switchboards with a single main fused circuit breaker rated 4000A and less do not require lashing.
Switchboard Instruction and Installation Guide 9
4.12 Conduit area All conduits and stubs must be located to avoid cable interference with structural members and live bus. Conduit shall not be more than 3 inches above bottom of enclosure (NEC 408.5). Deep switchboard frames may need to have side-to-side frame support removed. Install conduit properly, with appropriate hubs or sleeves and ring connectors to protect cables and prevent water from entering and accumulating in the switchboard. Bond all metallic conduit and stubs to the switchboard with electrical connections sized according to 250.122 of the National Electric Code. Before pulling cable, verify that their size, temperature rating, and conductor insulation comply with the switchboard markings. (Ref NEC 110.14(C)). NOTES: 1) If bottom plates are furnished, holes for any conduit entering the bottom of the switchboard must be made by the customer. After making the holes, reinstall the bottom plate. 2) Top plate is not designed to support weight for conduit. Conduit must be supported by other means. 4.13 Cable pulling Siemens switchboards are constructed according to NEMA standards for cable arrangements. It is important that all cables enter the switchboard in the conduit area shown on the front elevation drawing and per the instructions shown below: 4.13.1. Use only cable sizes suitable for a proper fit with the corresponding lugs. 4.13.2. Pull the proper number of line side and load side cables as per the load served. 4.13.3. Position the cables inside the switchboard so that they are not subject to physical damage. 4.13.4. Maintain the maximum possible bending radii and proper clearance to bus bars and grounded parts. If any cables are lying or bearing on structural members, support them
Wires can be easily traced on a wiring diagram furnished for the switchboard. Each device is illustrated and each terminal on each device is identified. The wire list adjacent to each device on the diagram indicates the device and terminal number to which each wire is connected at the next connection point. All control wiring installed by the factory is neatly bundled and secured to the cubicle side plate or wiring pan. Make all field connections in a similar manner. Check that all parts and components clear any additional wiring installed. All field wiring is to be routed behind the cable retainer which is removable for installation purposes. Use plastic or nylon ties to secure all field installed wire to the cubicle structure. SECTION 5.0 Pre-Energizing, inspection and testing Before the equipment is energized, it must be thoroughly inspected and tested. Correct any deviations and re-inspect equipment before energizing. Siemens Industrial Services can provide the following support services for switchboards. Call 1-800-241-4453 to obtain additional information and schedule an appointment. Start-up Commissioning Component and System Testing Maintenance (Scheduled and Preventative) Repair and Refurbishing On Site Operational Training 5.1 Inspection Check the following points: 5.1.1. Visually inspect switchboard for any damage that may have affected bus bar supports, device mountings or reduced electrical clearances within the switchboard (minimum clearance values are listed on Page 6). 5.1.2. Electrical disconnecting contacts, machine parts, shutter, etc., checked for lubrication and operation. 5.1.3. Blocking, supports and other temporary ties removed from breakers, instruments, relays, etc. 5.1.4. Check torque of all accessible bus bar connections, including factory and field installed connections. Access to connections may require temporary removal of certain barriers. (Torque values are listed on Page 16.) 5.1.5. Proper fuses correctly installed. 5.1.6. Manually operate all devices (circuit breakers, switches, etc.) Check for alignment and proper operation. 5.1.7. Operate all electrically operated devices (circuit breakers, switches, meters, relays, etc.). An auxiliary power source may be required. 5.1.8. Temporary wiring jumpers (used on the secondaries of current transformers tied to external devices, as shown on wiring diagrams) removed. 5.1.9. Check current transformer shorting terminal block screw position.
100kA
Lashing Instructions to 100,000A Maximum
To comply with UL short circuit withstand ratings the adjacent & N connections shall be lashed per the instructions provided below. Wrap line cables together with nominal 3/8 nylon rope or rope having a minimum tensile strength of 2000 pounds. From switchboard entrance to the point that the cables lace together, wrap each run of cable with 1 turn every 3 inches. Where cables lace into terminals, support must be added to the cables per the diagram.This should be installed 6 from the terminals and every 9 beyond that point. Crimp Connectors - Refer to instructions on connector for proper crimping tool and quantity of crimps required.The lashing shall be as described above.
11-1001-01 REV. 6
200kA
Lashing Instructions to 200,000A Maximum
To comply with UL short circuit withstand ratings the adjacent & N connections shall be lashed per the instructions provided below. Crimp Connectors - Refer to instructions on connector for proper crimping tool and quantity of crimps required. Wrap line cables together with nominal 1/2 nylon rope or rope having a minimum tensile strength of 3000 pounds. Where cables lace into line terminals support must be added to cable per the diagram provided.This should be installed every 6 from line terminals and every 6 above that point. Note: Cable support must be re-installed over lug barrels after cable termination.
Cable Support Supplied by Siemens
11-1006-01 REV. 3
4.16 Control wiring Control wiring is carefully installed and checked at the factory. Inter-group wiring at shipping splits can be readily connected by referring to wire markings. These wires are of sufficient length to be routed to their termination point after cubicles are bolted together. Terminals for these leads are furnished by others to suit the available crimping tools. When required, terminal block hardware is furnished with the switchboard. All wiring diagrams needed for installation are furnished in advance.
10
withstand test values specified for each voltage rating of switchboard. When performing dielectric tests, the voltage should be raised to the test value in discrete steps and held for a period of one minute. In accordance with ANSI C37.20.02 Clause 5.5, Field Dielectric Tests are also recommended when new units are added to an existing installation, or after major field modifications. The equipment should be put in good condition prior to the field test. It is not expected that equipment shall be subjected to these tests after it has been stored for long periods of time or has accumulated a large amount of dust, moisture, or other contaminants without being first restored to good condition.
DANGER
Hazardous voltage. Will cause death or serious injury.
Keep out. Qualified personnel only. Disconnect and lock off all power before working on this equipment.
NEC Section 230.95 requires ground fault protection on all service disconnects rated 1000 amperes and larger in switchboards when fed by a solidly grounded wye system of more than 150 volts to ground. When provided, all ground fault protection equipment for the switchboard is tested before shipment from the factory. The ground fault protection system, when provided, must be tested when first installed in accordance with NEC Section 230.95 paragraph C . There are exceptions to this rule: Ground fault protection is not required on fire pumps or continuous industrial loads where a non-orderly shutdown would cause additional hazard. Health care facilities, such as hospitals require additional levels of ground fault protection. These requirements are described in NEC Article 517. Sections 215.10 and 240.13 of the NEC require ground fault protection on all 1000 ampere and larger devices, breakers, and switches, applied in a system as described above, unless there is ground fault protection upstream. Many utilities use a grounded Wye secondary transformer and bring a connection from the grounded mid-point to the service section ground bar. When this is the case, ground fault protection is required.
5.2.3
Voltage transformers, control power transformers, surge arresters, surge protective devices and surge capacitors must be disconnected during these tests.
NOTE: The dielectric test voltage is given as a reference only for those using dielectric tests to verify the integrity of connected cable installations without disconnecting the cables from the switchboard. It represents values believed to be appropriate and approximately equivalent to the corresponding power frequency
11
Reset the relay, and the disconnect device. System is now back to normal. To test the ground fault relay and sensor only (the sensor will trip the relay in this test).
Load
Disconnect Device
#1
Sensor (GFS)
Check for control power, LED should be illuminated. Press and hold the shunt trip bypass switch on the relay. Press the push to test switch. The ground fault relay will trip. Reset the relay, then release the shunt trip bypass switch. System is now back to normal. Note: Test Report form found on page 19 of this manual can be used to record ground fault field testing. 6.2 Internal ground fault The procedures below are for SJD6, SHJD6, SCJD6, SLD6, SHLD6, SCLD6, SMD6, SHMD6, SCMD6, SND6, SHND6, SCND6, SPD6, SHPD6, DG, FG, JG, LG, MG, NG, PG, WL fixed mount and WL drawout. 6.2.1 General Siemens VL, Sensitrip III and WL circuit breakers may be equipped with integral ground fault protection. The National Electrical Code requires that these devices be performance tested when first installed (230.95(C)). The following instructions are intended to guide the installer in meeting this requirement for Sensitrip III circuit breakers. Use the Guide for Primary Injection Testing WL Circuit Breakers P/N 11-C-9036-00 for WL circuit breakers and Ground Fault Test Procedure P/N 806946A00 for VL circuit breakers which are both available at www.usa.siemens.com/circuitbreakers General instructions 6.2.1.1. The interconnected system shall be evaluated when initially installed by qualified personnel. It is also suggested this be done periodically thereafter. 6.2.1.2. The proper location of the sensors around the bus of the circuit to be protected shall be determined. This can be done visually, with knowledge of which bus is involved.
To GFR
From Sensor To Control Power Source
Fig. #1
GFS #1, is the standard location GFS #2, alternate location for GFS
WARNING: The following should be performed only by qualified personnel as defined in NEC article 100. The ground fault sensor (GFS), ground fault relay (GFR), must be installed as in Figure 15. Note: Test report and test record forms found on Page 18 and 19 of this manual can be used to record ground fault field testing. 6.0 Ground fault inspection and testing Siemens Industrial Services can provide the following support services for switchboards. Call 1-800-241-4453 to obtain additional information and schedule an appointment. Start-up Commissioning Component and System Testing Maintenance (Scheduled and Preventative) Repair and Refurbishing On Site Operational Training 6.1 External ground fault 6.1.1. Disconnect main power source. 6.1.2. Remove the neutral disconnect link. Make sure the neutral is grounded only by the main bonding jumper, which must be on the line side of the sensor. 6.1.3. Close all branch devices. 6.1.4. Using a megger type meter, measure the resistance of the load phase and neutral to ground. This is to ensure
12 Switchboard Instruction and Installation Guide
Note: Test report form found on page 18 can be used to record ground fault field testing.
DANGER
Hazardous voltage. Will cause death or serious injury.
Keep out. Qualified personnel only. Disconnect and lock off all power before working on this equipment.
Warning: Never pass test current through an unterminated Neutral Sensor. Permanent sensor damage may occur if operated in this manner. 6.2.1.8.2. 3 Phase/4 Wire Using Figure 17, individually test breaker poles A, B and C in conjunction with the proper Neutral Sensor for proper Ground Fault operation. Each of the circuit breakers front panel controls should be set to the highest setting. Using a low-voltage current source, apply 125 percent of the ground fault setting to one pole of the circuit breaker. The circuit breaker must not trip. Reduce the test current to zero.
FAILURE TO PROPERLY MAINTAIN EQUIPMENT CAN RESULT IN DEATH, SERIOUS INJURY OR PRODUCT FAILURE. THE INSTRUCTIONS CONTAINED HEREIN SHOULD BE CAREFULLY REVIEWED, UNDERSTOOD AND FOLLOWED. THE FOLLOWING MAINTENANCE PROCEDURES MUST BE PERFORMED REGULARLY. SECTION 7.0 - Energizing and operation WARNING: HAZARDOUS VOLTAGES IN ELECTRICAL EQUIPMENT CAN CAUSE SEVERE PERSONAL INJURY OR DEATH. ENERGIZING A SWITCHBOARD FOR THE FIRST TIME AFTER INITIAL INSTALLATION OR MAINTENANCE IS POTENTIALLY DANGEROUS. 7.1 Placing equipment into service Only qualified persons familiar with the construction and operation of switchboards should perform work described in this set of instructions. Such work should be performed only after reading this complete set of instructions.
Switchboard Instruction and Installation Guide 13
DANGER
Hazardous voltage. Will cause death or serious injury.
Keep out. Qualified personnel only. Disconnect and lock off all power before working on this equipment.
14
Maintenance
9.3 Maintenance tasks 9.3.1. Before any maintenance is performed on a switchboard that has been energized for at least 3 hours, it is recommended, just prior to inspection, a simple hand test be performed. This test should consist of placing your hand on the front and side of the equipment enclosure, the deadfront surfaces of circuit breakers, switches, interior trims, doors for at least 3 seconds. If you cannot maintain contact with the surfaces due to the extreme temperatures, this may be an indication of trouble and immediate investigation is required. Warning: Switchboards contain voltages that may cause severe injury or death. Power to the switch board should be turned off, disconnected and electrically isolated so that accidental contact cannot be made with energized parts during inspection and maintenance, unless otherwise specified. 9.3.2. Before starting work on the equipment, the following should be completed on any equipment that will affect the area of the work: A. Disable remote control and automatic transfer schemes. B. De-energize all direct and back feed power and control sources, test and ground C. Disconnect all voltage and control power transformers. D. Open all disconnects. 9.3.3. Include the following items in your procedure: A. Check general condition of switchboard installation. B. Inspect interior for accumulation of dust, dirt or any foreign matter. Vacuum the interior to remove any dirt or dust deposits. Do not use an air hose as pressurized air may blow dust into critical electrical contact areas. C. Check the interior carefully for moisture, condensation buildup, or signs of any previous wetness. Inspect all conduit entrances and cracks and seal off any leaks to eliminate moisture. Clean air filters by washing in a mild household detergent. D. Examine indicating lamps and replace as required. E. Check terminal blocks contacts for loose connections. F. Check instrument and control switches and inspect their contacts. G. Check for proper condition of instrument transformers. Replace burned out fuses, if any. Check primary and secondary connections. H. Remove dust from all de-energized insulators. I. Inspect bus bars and connections for proper condition. If bus bars are overheating, check for poor or loose connections or for overload. J. Examine fuse clip contact pressure and contact means. If signs of over-heating or looseness, contact sales for replacement. K. Look for and replace deteriorated insulated material where sealing compound has melted. DANGEROUS VOLTAGES ARE PRESENT IN THE EQUIPMENT WHICH CAN CAUSE DEATH, SERIOUS INJURY OR PROPERTY DAMAGE. ALWAYS DE-ENERGIZE AND GROUND THE EQUIPMENT BEFORE MAINTENANCE. MAINTENANCE SHOULD BE PREFORMED ONLY BY QUALIFIED PERSONNEL. THE USE OF UNAUTHORIZED PARTS IN THE REPAIR OF THE EQUIPMENT, TAMPERING BY UNQUALIFIED PERSONNEL, WILL RESULT IN DANGEROUS CONDITIONS WHICH CAN CAUSE DEATH, SERIOUS INJURY OR EQUIPMENT DAMAGE. FOLLOW ALL SAFETY INSTRUCTIONS CONTAINED HEREIN. 9.4 Cleaning insulation Most of the plastics and synthetics used in insulation systems are attacked by solvents containing aromatics or halogenated hydrocarbons which may cause crazing and deformation of the material reducing the dielectric strength. ISOPROPYL ALCOHOL IS THE ONLY RECOMMENDED SOLVENT CLEANER.
Switchboard Instruction and Installation Guide 15
L. Examine all safety interlocks to insure they are functional and in proper working order. M. Carefully inspect all devices for any worn, cracked, or missing parts. Manually open and close devices several times to insure they are in proper working order. Perform maintenance of interrupting devices as out lined in the device instruction manual. Do not open sealed breaker or trip unit as calibration may be disturbed. Return to factory for any replacement. For reference, see NEMA AB4. N. Check space heaters and thermostat (if equipped) for proper operation. O. Maintain other auxiliary equipment per their respective instruction book requirements. P. Lubricate mechanisms, contacts, and other moving components. Do not lubricate parts of molded case circuit breakers. Q. Inspect painted surfaces and touch up as needed. R. Check for signs of rodent or insect nesting inside the switchboard. S. Replace, reassemble, re-insulate, return all items to proper operating conditions and remove grounds prior to energization. T. Ensure satisfactory operation of relays and instruments as per instruction books furnished separately. Do not leave device covers off longer than necessary. When a cover has been broken, cover the device temporarily and replace broken glass as soon as possible. U. Test ground fault protection system (if furnished). V. Conduct an electrical insulation resistance test to ensure that the switchboard is free of short circuit and ground. 9.3.4. THIS CHECKLIST DOES NOT REPRESENT AN EXHAUSTIVE SURVEY OF MAINTENANCE STEPS NECESSARY TO ENSURE SAFE OPERATION OF THE EQUIPMENT. PARTICULAR APPLICATIONS MAY REQUIRE FURTHER PROCEDURES. SHOULD FURTHER PROCEDURES BE DESIRED OR SHOULD PARTICULAR PROBLEMS ARISE WHICH ARE NOT COVERED SUFFICIENTLY FOR THE PURCHASER'S PURPOSES, THE MATTER SHOULD BE REFEREED TO THE LOCAL SALES OFFICE.
mixed with other lubricants, as they may interact and lose essential properties. Siemens Electrical Contact Lubricant, Part No. 15-172-791-214 may be used for other applications. Other exposed components can be protected with a coat of glyptol or other corrosion-resistant coating. When old grease becomes dirty, wipe the part clean and apply new grease immediately. Section 11.0 - Informational charts 11.1 Torque values
Informational charts
11.2 Wire bending requirements Wire Bending space at terminals shall be measured in a straight line from the end of the lug or wire connector (in the direction that the wire leaves the terminal) to the wall, barrier, or obstruction. For reference, see NEMA 312.6 (A) and (B). For removable and lay-in-wire terminals intended for only one wire, bending space shall be permitted to be reduced by the number of inches shown in parenthesis. For use with SB1, SB2 and SB3 Switchboards includes copper straps, cover plates and necessary hardware for switchboards. 11.3 Strap kits 11.3.1 Connecting strap kits Circuit breaker For use with SB1, SB2 and SB3 Switchboards includes copper straps, cover plates and necessary hardware for switchboards.
Strap kit catalog number SBLBD SEBD SNBD 6E62 6CLE2 SDGD 6QJ2 6F62 6CLF1 SFGD 6JJ61 6JJ62 6CL J1 6SJL1 6SCJ1 SJG2D SJG1D 6LL61 6CLL1 6SLL1 6SCL1 SLGD SLM1D SMND SSMND MG1D SMND SSMND NG1D Height (inches) 3.75 3.75 3.75 3.75 3.75 5 5 5 5 5 8.75 8.75 8.75 8.75 8.75 6.25 6.25 8.75 8.75 8.75 8.75 6.25 8.75 10 10 8.75 10 10 10
11.3.2 Filler plates For use with SB1, SB2, and SB3 Switchboards.
Breaker frame BQ, BQH, HBQ, E2, E4, E6, HE4, HE6, E2-A, E-4A, E6-A, HE4-A OR HE6-A and ED2, ED4, ED6, HED4, HED6 NEB, HEB Filler plate catalog number QF3 EBF1
Note: When a front filler plate is not completely filled with breakers, the openings in the unused space must be closed with 1-pole filler plates from table. 11.3.3 Connecting strap kits Vacu-Break and HCP For use with SB1, SB2 and SB3 Switchboards. Includes copper straps and necessary hardware for switchboards.
Ampere rating Unit height (inches) Catalog number
Breaker type BL, BLH, HBL, BQD NEB, HEB NGB ED2, ED4, ED6, HED4, HED6, HHED6 CED6 ND, HD, LD QJ2, QJH2, QH2-H FD6, FXD6, HFD6, HFXD6, HHFD6, HHFXD6 CFD6 NF, HF, LF JXD2, JD6, JXD6, HJD6, HJXD6, HHJD6, HHJXD6, Single Branch JXD2, JD6, JXD6, HJD6, HJXD6, HHJD6, HHJXD6 Double Branch CJD6 SJD6, SHJD6 SCJD6 NJ, HJ, LJ NJ, HJ, LJ LD6, LXD6, HLD6, HLXD6 HHLD6, HHLXD6 CLD6 SLD6, SHLD6 SCLD6 NL, HL, LL LMD6, LMXD6, HLMD6, HLMXD6 MD6, MXD6, HMD6, HMXD6, CMD6 SMD6, SHMD6, SCMD6 NM, HM, LM ND6, NXD6, HND6, HNXD6, CND6 SND6, SHND6, SCND6 NN, HN, LN
Mounting D D D D D D D D S D S D S S S D S S S S S S S S S S S S S
30-30 30-60 60-60 60-100 100-100 100 200 200-200 400-600 800-1200 (HCP)
5, 7 5, 7 5, 7 7 7 7 7, 10 10 15 16
VB657
11.3.4 Blank plates Circuit breaker and Vacu-Break For use with SB1, SB2, and SB3 Switchboards.
Height (inches) 1 2 3 5 10 Catalog number 6FPB01 6FPB02 6FPB03 6FPB05 6FPB10
17
Informational charts
11.4 Ground fault test record Internal Performance test report Ground fault protection
Job: ______________________________________________________________________________________________________________ Location: ______________________________________________________ Date of Test: ___________________________________________ Circuit: ________________________________________________________________________________________________________________ Switchboard: _________________________________________________________________________Single/Double End _________________ Disconnect Device: _____________________________________________________________________________________________________ GF Protective Device: ___________________________________________________________________________________________________ GF Sensor: _____________________________________________________________________________________________________________ Test Equipment: (Describe on back or attach a page.) Test Setup and Method: (Describe on back or attach a page.) A. Inspection 1. Wiring and conductors 2. Connections and wire clamping 3. Bonding, splice bussing and grounding 4. Sensor mounting and wiring 5. Control circuit overcurrent protection 6. Other: ___________________________________________________________________________________________________________ B. Insulation resistance 1. Neutral-to-ground 2. Neutral-to-enclosure 3. Enclosure and grd. bus-to-ground 4. Grounded service conductor-to-ground 5. Other: ___________________________________________________________________________________________________________ C. Operation test 1. GF protective device setting: _______________A, _____________________sec. Time Curve: _________________________________ 2. Control Power: ____________________________________________________________________________________________________ 3. Test Current: (a) __________________________________A, x ______________________ turns = ___________________________At or (b) Test set signal: ____________________________________________________________________________________________ or (c) Primary Current: _______________________________A 4. Trip operation 5. Time Delay: one second or less 6. Test button, lamp, indicator operation 7. Other: ___________________________________________________________________________________________________________ D. Label affixed E. Equipment restored to operational condition GFP settings (as left) _________________________________________________________________________________________________ Tested by: ___________________________________________________________ (1) This test record to be retained by those in charge of the building electrical installation. (2) Make the report available to the authority having jurisdiction. Dwg. No. 1S-7732 Rev. 1
18
Informational charts
11.5 Ground fault test record External Performance test report Ground fault protection Job: ________________________________________________________________________________________________________________ Location: ______________________________________________________ Date of Test: _____________________________________________ Circuit: __________________________________________________________________________________________________________________ Switchboard: _________________________________________________________________________Single/Double End ___________________ Disconnect Device: _______________________________________________________________________________________________________ GF Protective Device: ______________________________________________________________________________________________________ GF Sensor: _______________________________________________________________________________________________________________ Test Equipment: (Describe on back or attach a page.) Test Setup and Method: (Describe on back or attach a page.) Ground fault testing Warning: The following should be performed only by qualified personnel as defined in N.E.C. Article 100. The ground fault sensor (GFS), ground fault relay (GFR), must be installed as in Fig. 1.
#2
Sensor (GFS) Main Power Source
Disconnect Device
#1
Sensor (GFS)
To GFR
From Sensor To Control Power Source
Fig. #1
1. Disconnect Main Power Source. 2. Remove the neutral disconnect link. Make sure the neutral is grounded only by the main bonding jumper, which must be on the line side of the sensor. 3. Close all branch devices. 4. Using a megger type meter, measure the resistance of the load phase and neutral to ground. This is to ensure that no ground connections exist in the system. Resistance readings of (1) Megohm or greater are preferred. 5. Re-install the neutral disconnect link. 6. Open all branch devices.
GFS #1, is the standard location GFS #2, alternate location for GFS
7. Connect the main power source. 8. To Test The Entire System. a. Check for control power. (LED should be illuminated). b. Press the push to test switch on the relay. c. The trip indicator should go to the tripped position and the disconnect device should operate. d. Release the push to test switch and return the trip indicator to the reset position. e. Reset or close the disconnect device for normal operation of the switchboard. 9. This test meets the requirements of the National Electrical Code Section 230.95 (C).
Test record
Date By Amp setting Time setting Notes
Load
19
Service bulletins
Section 12.0 - Service bulletins For service bulletins reference the technical information at: www.usa.siemens.com/circuitbreakers Reference information NFPA7O (NEC) NFPA 70 E NEMA PB2 NEMA PB2.1 NEMA PB2.2 NEMA AB4 UL891
20
Siemens Industry, Inc. Building Technologies Division 5400 Triangle Parkway Norcross, GA 30092 1-800-964-4114 [email protected] www.usa.siemens.com/switchboards
Subject to change without prior notice. Order No: SWIM-00100-0310 All rights reserved. Printed in USA 2010 Siemens Industry, Inc.
The information provided in this brochure contains merely general descriptions or characteristics of performance which in case of actual use do not always apply as described or which may change as a result of further development of the products. An obligation to provide the respective characteristics shall only exist if expressly agreed in the terms of contract. All product designations may be trademarks or product names of Siemens AG or supplier companies whose use by third parties for their own purposes could violate the rights of the owners.