Method Statement For 11KV VCB Coupling To Existing VCB - Unimas

This document provides a method statement for coupling and testing new 11kV 1250A 25kA outgoing feeder vacuum circuit breaker (VCB) switchgear to existing 11kV VCB switchgear. The key steps include: 1) arranging a shutdown with the power supplier, 2) confirming all outgoing and incoming feeders on the existing switchgear are de-energized, 3) installing the new switchgear and connecting busbars, 4) performing contact resistance and insulation testing between the new and existing busbars, 5) conducting a high potential test, and 6) calibrating protection devices before returning the system to service.

Uploaded by

muhd faiz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
222 views4 pages

Method Statement For 11KV VCB Coupling To Existing VCB - Unimas

This document provides a method statement for coupling and testing new 11kV 1250A 25kA outgoing feeder vacuum circuit breaker (VCB) switchgear to existing 11kV VCB switchgear. The key steps include: 1) arranging a shutdown with the power supplier, 2) confirming all outgoing and incoming feeders on the existing switchgear are de-energized, 3) installing the new switchgear and connecting busbars, 4) performing contact resistance and insulation testing between the new and existing busbars, 5) conducting a high potential test, and 6) calibrating protection devices before returning the system to service.

Uploaded by

muhd faiz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

LIM AIK CHAI ELECTRICAL SDN BHD

SUBLOT 5, JALAN DEMAK LAUT 3, PHASE 1, DEMAK LAUT INDUSTRIAL


PARK, 93050 KUCHING, SARAWAK, P.O.BOX 3213, 93792
Tel: 082-433667, 433668& 433669 F a x : 082-433660
Email: [email protected]

METHOD STATEMENT

PROJEK PEMBINAAN DAN PENYIAPAN HOSPITAL PENGAJAR DAN


PUSAT KESIHATAN PRIMA (PKP), UNIVERSITI MALAYSIA SARAWAK
(UNIMAS), KOTA SAMARAHAN, SARAWAK (REKA DAN BINA)

METHOD STATEMENT FOR COUPLING AND TESTING (CONTACT


RESISTANCE AND INJECTION/PRESSURE/HIGH POTENTIAL) OF
NEW 2 NOS. 11KV 1250A 25kA OUTGOING FEEDER VCB
SWITCHGEAR TO SEB EXISTING 11KV VCB SWITCHGEAR

Method Statement Page | 1


Table of Contents:

1. Installation/Coupling and Testing of Electrical 11KV 1250A 25kA TAMCO Outgoing


Feeder VCB Switchgear to Existing 11kV SEB VCB Switchgear

2. Attachment Detail of Testing (Hi-Pot Test and Contact Resistance)

Method Statement Page | 2


1. INSTALLATION/COUPLING AND TESTING OF ELECTRICAL 11KV 1250A
25KA OUTGOING FEEDER VCB SWITCHGEAR INSTALLATION TO EXISTING
11KV VCB SWITCHGEAR

- Arrange shutdown with SESCO/SEB on the RELATED WORKS

- SESCO/SEB to shutdown on the POWER supply to the existing 11KV VCB


switchgear either partial shutdown on LEFT Hand Bus (MGL5) followed by Right
Hand Bus (MHL5) or TOTAL SHUTDOWN

- Upon Shutdown, SESCO/SEB to confirm all Outgoing Feeders, Incoming Feeders


and Bus Section at the Existing VCB are all de-energize by racking-out all the
related 11KV VCB truck (Feeders , Incomer & Bus Section Truck) and
ground/earth the outgoing and incoming feeders cable

- Authorized Competent SESCO/SEB Switching Personnel to issue Electrical Permit-


To-Work (EPTW) to contractor’s Competent Installation Personnel upon
confirming all 11KV VCB Busbar are de-energized/isolated

- Upon receiving the EPTW, use the High Voltage Detector to ensure that the LIVE
part of the existing 11KV VCB Busbar are de-energized/isolated

- LOCAL Earth MUST be APPLIED onto the Existing 11KV Busbar to double confirm
that there is no more any surge of VOLTAGE from any other places and to avoid
any mishap during installation

- Push the NEW 11KV VCB towards the EXISTING 11KV VCB and tighten the NEW &
Existing 11KV VCB by means of Bolt & Nuts given and bolt down the panel to the
Unistrut on the floor by means of Bolt & Spring Nuts (Make sure the leveling
MUST be straight and level of tolerance +-2mm as mentioned in the manufacturer
drawing)

- Upon completion of the above, install all the 3 Phases Busbar at the 11KV VCB
Busbar compartment by connecting the NEW VCB with the existing VCB as per
manufacturer requirement.

- Upon completion, clear and clean the Busbar compartment then install back all
the compartment cover

- Connect all internal / interlink control wiring between all new & existing panels
as per manufacturer shop drawings.

- Upon completion of the above, the competent tester are to perform Contact
Resistance Test on the newly installed Busbar connecting to the existing Busbar

- An Insulation-Resistance Test using 5KV insulation tester will be perform

Method Statement Page | 3


between the Newly Installed Busbar and the Existing Busbar before and after Hi-
PoT Test

- Hi-Pot Test will be perform between the Newly Installed busbar and the existing
busbar

- Upon completion of the above All LOCAL Earthing installed previously MUST be
REMOVE and our Competent Installation person will CANCEL OFF the EPTW and
handover to SESCO/SEB Authorized Competent & Authorized Personnel at site

- The Licensed and Competent Tester shall conduct all necessary calibration
settings or TRIP TEST on all the Protection Devices with SESCO Personnel
witnessing the work before shutdown to prevent any power downtime during
shutdown

- End of Works

- The HV Switchgear is ready for energizing

- Prepare and submit test report to SESCO via Consultant

Method Statement Page | 4