Schedule of Rate, Both Civil and Mechanical/Electrical With All Corrigendum and Addendum As On 03-Nov-2021
Schedule of Rate, Both Civil and Mechanical/Electrical With All Corrigendum and Addendum As On 03-Nov-2021
Schedule of Rate, Both Civil and Mechanical/Electrical With All Corrigendum and Addendum As On 03-Nov-2021
ORDER
The undersigned is directed by order of the Govemor to say that, the Governor is pleased to
accept the Schedule of Rates (Civil & Mechanical/Electrical) recommended by the Schedule Committee
formed vide Order No. PHE/IV/201 8/W- l 08/2020 dated 04.12.2020 at its meeting held on 04. 10.202 I .
2. This order issues in tandem with the approval of Secretary of this Department.
\ nooror^iko
to the Government of West Bengal
.
f Principal Accountant General (Audit), West Bengal.
2. Principal Accountant General (A&E), West Bengal (Express Budget Section)
3. Principal Accountant General (R.W & L.B.A), West Bengal.
4. Principal Accountant General (General & Social Sector), West Bengal.
5. Accountant General (Economic & Revenue Sector Audit), West Bengal.
6. Dy. Accountant General (A/Cs & VLC), Express-A.M.-I Section, Treasury Bldgs, Kol-l
7. Director of Treasuries & Accounts, West Bengal.
8. Special Secretary/ Joint Secretary, Finance Department (Group N), Nabanna.
9. Special Secretary/ Joint Secretary, Finance Deparfinent (Group F), Nabanna.
10. Special Secretary/ Joint Secretary, Finance Department (Group T), Nabanna.
I l. Sr. P.S. to Minister-in-Charge, PHE Department.
12. Sr. P.A to the Secretary, PFIE Department
13. P.A. to the Engineer-in-Chief, PHE Department.
14. P.A. to the Additional Secretary, PHE Department.
15. Financial Advisor, PHE. Department.
16. Chief Engineer (H.Qs), PHE Directorate
17. Chief Engineer (Planning & WQM), PHE Directorate
18. Chief Engineer (Western Zone\, PHE Directorate.
19. Chief Engineer (Northern Zone), PHE Directorate.
20. Chief Engineer, Northern Zone (MlE), PHE Directorate.
21. Chief Engineer(Southem Zone), PHE Directorate.
22. Project Director, PMU, Purulia, WBPWSP, PIIE Dte.
23. Chief Engineer & Project Director, WBDWSIP, PHE Dte.
24. File Copy.
o-\ rr\ 2t
Secretary (Technical)
to the Government of West Bengal
INDEX
Sl. No. Subject Page No.
1 Note Sheet I
2 1" Corrigendum & Addenda for Schedule of Rates of PHED Originally 2
Published on July 2019
J Supply, Delivery and Installation of Automatic Plunger Type 3
Chlorinator
4 Annexure-[ 4
Specification for Supply, Delivery and lnstallation of Automatic Plunger
Type Chlorinator having flow rate of 0-100 LPH and maximum pressure
of 10 kg/cm'?(should be included in tender document)
5 Supply, Delivery and Installation of Automatic Plunger Type 5
Chlorinator
6 Annexure-ll 6
Specification for Supply, Delivery and Installation of Automatic Plunger
Type Chlorinator having flow rate of 0-200 LPH and maximum pressure
of 12 kglcm' (should be included in tender document)
7 Repairing of Automatic Chlorinator by Supplying of different Spares 7
and other works at different WS Scheme
8 Annexure-lll 8
Specification for Repairing of Automatic Chlorinator by Supplying of
different Spares and other works at different W/S Scheme (should be
included in tender document
1
FileNo.DPHEll}l2o2l.cEPWoM(DPHE)-DPHE(ComputerNo.tt46754)
:eipt No : 19177 1212021 /O/oCEPWQM(DPHE)
NOTE SHEET
With a viewto prepare a common schedule of Rates (SOR) forfrequently used electro-mechanical works
under pHE Dte. like supply, installation of pumping machineries, electrical panels & others accessories,
which will be applicable for all Divisions under all circles of PHE Dte. in different district of West Bengal,
a Schedule Committee was formed for finalizing the Schedule of Rates in terms of G.O. No.
WestBengal pHE (Mechanical / Electrical) - July 2019 (vide G.O. No. PHE/L723llT-10l189 dated. 08-08-
2018). Rate for automatic plunger type chlorinator (Flow rate 0-100 LPH& 0-200 LPH), repairing of
automatic chlorinator by supplying of different spares at different W/S Schemewerenot included in the
SOR July 2019. Hence, schedule for automatic plunger type chlorinator (Flow rate 0-L00 LPH), repairing
-
of automatic chlorinator by supplying of different spares at different W/S Schemeare prepared'
Ratesfor the items already exists in the SOR of West Bengal PHE (Mechanical / Electrical) - July 2019
have also reviewed by this SOR Committee. After review, the rate for diaphragm-type Automatic
Chlorinator (0-2OO LPH) has been modified and incorporated as amendment in this SOR.
For items like i) Schedute of Rates for Wiring with PVC lnsulated & Urrsheatlted Copper Wires irr PVC
Rigid Conduit, ii) Schedule of Rates for Earthing lnstallation, iii) Schedule of Rates for lnstallation of
Lightning Conductor, iv) Schedule of Rates for Fixing of Approved Materials (Main Switch, Distribution
Boards, Fittings, Fans etc.), etc rates are taken from PWD Schedule of Rates (Electrical Works) Vol. I
November 2017.
ln order to arrive at the rate, the prevailing market rates of chlorinator and its spares have been
considered along with carrying & forwarding charges @ 5%& contractor's profit @ 10%. GST as
applicable will have to be added to the rate of any item of this SOR in order to arrive at the final rate of
that item for preparation of estimate of supply work or GSf @ 12% & Labour Cess @ 1.%oarelo be added
at the end of the estimate for any composite work.
P'il
*Boul,.hr Engineer, o1 lu 2l fuo*'t
Esecutjve H,r{gi*eei Plannrng Circle-I, Chief Engineer
wQNr,
Mech./Elec.) P.H.Engg. Dte. Qiech./Elec.), and
PIU, North 24-P arganas, and Convenor, SOR Southern Zone,
Committee
\{/BDWSIP, P.H.Engg. Dte. Committee P.H.Engg. Dte.
P,H.Engg. Dte.
Govt. of WestBengal. P.H.Engg. Dte. Gort. of West Bengal. Govt. of West Bengal.
Gort. of West Bengal.
File No. DPHE/16/2021'CEPWQM(DPHE)'DPHE
(Computer No' 446754 ) L
:ipt Nc 't g'17 7 1 212021 tO/oC E PWaM ( D PH E)
tuoplv. delivery and in*tallatien of DlqphRrm $rrne Futomatic chlorinator af diffefent c?pacitlqs.
2
File No. DPHE/16/2021 -CEPWOM(DPHE)-DPHE
(Gomputer No' 446754 ) 3
;eipt '. 19177 1212021 /O/oCEPWQM(DPHE)
3
eipt No :'19177 1212021 /O/oCEPWQM(DPHE)
FileNo.DPHEtl,l2o2l.cEPWQM(DPHE).DPHE(ComputerNo.446754) t
Annexur:e - I
Sl. No.
1) Supply & delivery of automatlc plunger type for feeding accurately
controlled dosage of chlorine solution lnto the water by connecbng metenng
PUrnP with
flow rate of water 0 100 LP},I with marimum sure of 0 kg cm- suitabie dosing
Pres 1,
Pump and other necessary ACCCS s ofles 0rl the delivery PiP e iine AS req urred. The PUrrIP
shall be coupled vdth Yz FIP motof having 3 phase power and 1 444 RPM 4'"/o) [Make
of Machine. As Pef attached vendor iist of PFIED]
2) Instailarion abovc of
Pump set
powef line by supplying of necess2r'Y \II1fe and confl.nuous carthing conneetcd lo auto
manual panel. Tlus includes the cosr ofrnaking necessary brick foundation base with neat
cement fi.nish by supplying all required materials and testing the endre set per direction
of EIC.
N.B. : 1) Test Certificate & Guarantee certificate of pump & motor needed.
2) All works should be carried out as per rerevant & ratest rS code.
4
File No. DPHE/16/2021'CEPWOM(DPHE)-DPHE (Computer No' 446754 ) E
:eipt : 19'177'l.212O21 /O/oCEPWQM(DPH E)
sr. o.
1)
and storage at site of
controlled plunger ri?e chLlorinator
dosing pumP.
5
File No. DPHE/16/2021-CEPWOM(DPHE)-DPHE (Computer No' 446754 ) 6
cei pt lilo : 19'177'1212021 /O/oCEPWQM(DPHE)
An4$r{trrq: tl
6
File No. DPHET16I2021'CEPWOM(DPHE)'DPHE
(Computer No' 446754 ) 1
ipt No : 19177 12t202'l IO/oCEPWQM(DPHE)
sl.
Rate
No.
1 of cirlcrrine machine as direction EIC. 1 no. 500.00
AS
1 no. 474.00
Slider
1 no. 2512.00
'V7orm
EN 1 no. 2541.00
Washing, cleaning unit
chiorine tank, PiPe &
speciaJs etc. by engaglng skilled personnel
once 1n il month rvith suppll' o (
fas movmg sp afes
Parts such as gland pacl<rng clamp, nu & bolt e tc. as
to the unit 1n condiuon. 1 times 394.00
4) of burnt out 0. HP ctrlonne Motor from work site to nearest work
shop for repairing.
1 item 400.00
s) Rervi*ding 0. HP motor surtable Srze coPPef
heat varnishing and all compiete AS direction.
Pef
1 item 2000.00
6) of repaired 0.5 HP chlorine from work shop io slte.
1 item 400.00
\ above dozing pumP part part 'llith newly supplied
materiais as exactly feqruired
Ifrom s1. No. (,) to (*n") includrng old
serviceable and tes AS direction of EIC. 1 item 1000,00
7
g
FileNo.oPHEt16t2o21-cEPWoM(DPHE)-DPHE(ComputerNo.446754)
ipt No : 19177 12t2021 IO/oCEPWQM(DPHE)
Annexure * lll
SPECIFICATION FOR REPAIRING OF AUTOMATIC CHLORINATOR BY SUPPTYING OF DIFFERENT SPARES
AND OTHER WORKS AT DIFFERENT WS SCHEME (should be included in tender document)
sl. Desctiption
No,
1 o machine as drrection o[
,\ o as below
l5mm dia braided hose
Tail mrn
15mm dia Gi
sc{ew
GM Gate 5
Mobrl
Starter Coil
Starter motof
15 mm dra. NRV
100 liter chlorine tenk
GI 15mm
SI. Indicator
15mm GI Tee
Gasket Set
Short
15mm dia flexible for chlonne solution
Worm Wheel chlorinc
Eccentric
Eccentric
Slider
Worm Shaft
3) Washrng, of machine urut including chlorine tank,
Plpe & specials etc. by engaglng
skilied personnel once month with supply of last movrng sPares
1n A
Parts such as gland packing, clamp,
nut & bolt etc. AS to the urut ln coodition.
4) o[ brrnt out 0.5 HP Motor from work site to nearest work shop for reparring.
s) Re*,inding of 0.5 HP motor with slze copPer \J/1fe heat and all
complete as per directioo.
6) repaired 0.5 Motor rvork shop to work site.
7) Reassemble the above chlorine dozing
Pump Part by Part with newly supphed materials as exactly
tequired [from Sl. No. (r) to (xxtv) including old serviceable sPares and testlng complete
as Per
direction of EIC.
8
INDEX
Sl. No Description of Items Page No
SECTION – A : GENERAL
B.2 Different category of pipeline works for Water Supply projects. L-1 to L-24
B.3 Overhead Reservoir OH-1 to
OH-16
B.4 Iron Elimination Plant IEP- I
Annexures
I) Copy of PHED notification of formation of a committee for finalising the schedule of rates (both
Mech. & Civil) along with general template for tendering, all type of tender.
II) Template for general abstract of cost.
SECTION - A
GENERAL
A.1 INTRODUCTION:-
Most of the items in the schedule of rates for PHED have been framed as per the
specification as laid down in the relevant IS codes.
The rates of the items have been derived mostly from the CPWD’s analysis of rates &
current PWD schedule of rates & amendments.
Prices of major construction materials like stone materials, bricks, sand etc. have been
taken from recent PWD schedule of rates.
If not specifically indicated in the items, the rates appearing in this schedule are
inclusive of cost of all supply, carriage, handling, fitting, fixing, toll charges, ferry
charges etc. & all other incidental works, hire charges of tools & plants and all ancillary
materials but excluding of GST.
5% over head charges & 10% contractors profit have been considered along with the
aforesaid material cost, labour costs & other costs for arriving at the rate of different
item of this schedule.
The basic price of different items of work was arrived with the following considerations: -
i) For construction works where use of water is necessary, rates were framed
considering 1% sundries, 1% water charges, 5% overhead and 10% contractor’s
profit.
ii) For laying & other labour oriented items where no water is required, only 5%
overhead & 10% contractor’s profit has been considered.
iii) For supply of materials, such as valves, specials etc. only 10% contractor’s profit has
been considered.
iv) All the rates in the schedule are excluding GST and labour welfare Cess. After
framing estimates, GST and labour welfare Cess should be added as applicable as per
current norms (Please refer Annexure-II).
G-1
A.2 GENERAL GUIDELINES FOR WORK:-
A.2(a) Extras:-
(a) In riverine areas connected by river route and/or ferry crossing under Extra Rate
(b) In all other areas under Kakdwip PWD Sub-Division excluding the jurisdiction of
Kakdwip P.S. in riverine areas connected by river route and/or Ferry crossing. @ 10%
i) If repair works required inside running wards / cabins of hospitals are restricted by
hospital authority in writing for duration less than usual working hours an extra rate of
10% will be allowed.
ii) If for unavoidable circumstances works are to be done in emergency cases at night,
extra rate @10% will be applicable to items of night work only strictly under certificate
of Engineer- in-Charge.
iii) For works at Bhutni under Manikchawk P.S. in Malda District Extra 15% (Fifteen
per cent) over and above the rates provided in this schedule is allowed.
i) 20% for works in the following places (a) Hill area of Garubathan Block (b)
Kalimpong Municipal Area (c) Dow hill area of Kurseong Sub-Division (d) Miric Block
(e) Section from Mane Bhanjan to Phalut of Simana Sandakphu Phalut Road (f) Section
from Peshoke Khola to Lopchu Tea Garden of S. H. No. 12 (g) within 10 km. from
Mongpu under Takda Block (h) Ghoom Tiger Hill Road (i) Section Pankhabari Bazarto
the Starting of Kurseong Municipal Road of Garidhura- Kurseong Road (j) Kalimpong
Block 1/lI and Mongpo & Takda Block. k)Bijanbari Block l) Sukia Pokhri Block.
G-2
ii) 20% of works in the following places:- (a) Darjeeling Municipal area (b) Kurseong
Municipal area (excluding Dow Hill area) (c) Rangit (d) Health Centers at Singritam,
Pokhriabong, Lodhama, Takling, Gitdabling, Samathahar. Saimolbong & Sittong.
iii) The rates under sections stated above for Jalpaiguri district are to be enhanced by 15% for
works in Boxa Hills
iv) The rate of this schedule will be enhanced due to various circumstances as mentioned
below:- (a) By 10% (Ten percent) for works done within the Hilly region of Ajodhya in
the District of Purulia.
[Note:- A region will be treated as hills if the altitude is more than 200 meters from the
level of any adjoining area within 10 km radius.]
v) By 5 %( Five percent) for works done within the region of Khanakul-I & II Block under
the District of Hooghly.
i) All materials brought to site must have approval of Engineer in-Charge. Rejected
material must be removed by the contractor from the site within 24 hours of the issue of
orders to that effect. In case of non-compliance with such orders, the ‘Engineer-in-
Charge’ shall have the authority for removal of those rejected materials at the cost and
expenses of contractor and the contractor shall not be entitled to any loss or damage on
that account.
ii) The site must be cleared by the contractor from time to time by removing rubbish,
debris etc. as accumulated during the work and on completion the whole site must be
left in a clean and tidy condition to the satisfaction of Engineer-in-Charge or his
representative.
iii) Carriage of materials (unless specifically considered in the Rate Analysis) is the sole
responsibility of the contractor for which no extra payment should be made (unless in
exigency a few of those seem to be justified by the Engineer-in-Charge, when the same
are to be approved by the concerned Superintending Engineer).
G-3
iv) Both metallic and non-metallic pipes may be considered for pipe dia up to 300 mm, the
selection being guided by cost, accessibility, nature of soil, social behavior of the
beneficiaries and traffic load. The respective BIS code for different types of pipe
should also be consulted for this purpose.
v) For Saline areas use of UPVC / HDPE pipe is preferred.
vi) For Rocky areas use of HDPE / DI K7 and K9 pipe is preferred.
vii) For Zone – VI, HDPE (PE 100, PN10) pipe can be used as per direction of EIC.
G-4
Kolkata / N-24 Parganas /S-24 Parganas / Howrah /Hoogly / Nadia /Purba Midnapore
ZONE-I
Z-1
A.4 ZONE CONSIDERATIONS:-
ORIGINAL WORKS
SECTION – B.1
Note:
1)Rate only for pilot drilling will be @ 50%. of item rate.
2)Rate for reaming by 12 1/4 " dia. bit will be @ 14% of item rate.
3)Rate for reaming by 15 " dia. bit will be @ 16% of item rate.
4)Rate for reaming by 17.5 " dia. bit will be @ 20% of item rate.
Page : TW - 1
Section - B.1: RIG BORED TUBE WELL
Note:
1)Rate only for pilot drilling will be @ 50%. of item rate.
2)Rate for reaming by 12 1/4 " dia. bit will be @ 14% of item rate.
3)Rate for reaming by 15 " dia. bit will be @ 16% of item rate.
4)Rate for reaming by 17.5 " dia. bit will be @ 20% of item rate.
a) From 6 Mtr. to 60 Mtr. Mtr 796.50
b) From 60 Mtr. to 90 Mtr. Mtr 876.60
c) From 90 Mtr. to 120 Mtr. Mtr 963.90
d) From 120 Mtr. to 150 Mtr. Mtr 1,060.20
e) From 150 Mtr. to 180 Mtr. Mtr 1,166.40
f) From 180 Mtr. to 210 Mtr. Mtr 1,283.40
g) From 210 Mtr. to 240 Mtr. Mtr 1,412.10
h) From 240 Mtr. to 270 Mtr. Mtr 1,553.40
i) From 270 Mtr. to 300 Mtr. Mtr 1,709.10
j) From 300 Mtr. to 330 Mtr. Mtr 1,880.10
k) From 330 Mtr. to 360 Mtr. Mtr 2,068.20
l) From 360 Mtr. to 390 Mtr. Mtr 2,275.20
m) From 390 Mtr. to 420 Mtr. Mtr 2,502.90
n) From 420 Mtr. to 450 Mtr. Mtr 2,753.10
4 Lowering the tube well assembly (UPVC Casing pipe ,well pipe,
strainer along with UPVC accessories) vertically in a position with
proper lowering arrangement by applying necessary jointing LS 26,571.00
compound including labour cost for subsequent gravel packing and
machine operation cost etc.
5 Cost of Consumables for drilling rigs and machineries. LS 22,077.00
6 Development (Min. 8 Hr. continuous) of tube well by using suitable
air compressor (Min. Capacity: 600CFM & operating Pressure 14
Bar) followed by yield testing with BHT pump (Head :45 to
LS 56,908.00
50mtr.,Discharge :1100 to 1000 LPM and 25 BHP engine) all
complete including To & Fro Transportation cost and Cost of fuels,
lubricants & Labour etc.
7 Water sample collection and chemical test including Arsenic Test. LS 2,425.00
8 Transportation cost of drilling equipment and accessories rig
machine etc. including cost of fuel,Lubricant & loading unloading
the materials from store/stack yard /suppliers godown and LS 59,786.00
unloading /stacking the same at site.
(Upto 60.0 km distance)
Page : TW - 2
Section - B.1: RIG BORED TUBE WELL
Page : TW - 3
Section - B.1 : RIG BORED TUBE WELL
Page : TW - 5
Section - B.1 : RIG BORED TUBE WELL
Page : TW - 6
Section - B.1 : RIG BORED TUBE WELL
Page : TW - 7
SECTION – B.2
SCHEDULE OF RATES FOR DIFFERENT CATEGORY OF PIPE LINE WORKS FOR WATER SUPPLY PROJECTS
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
1 Carrying CI/DI pipes with specials and valves and lowering placing in
position and laying carefully inside the trenches in proper alignment and
gradient etc. including earth work in excavation of adequate width as per
specification having min. clear cover from top of pipe is 1.10mtr. below
existing ground level in any kind of soil including mixed with boulder,
road sub-grade and its flank,but excluding moorum and laterite and stone
etc.without damaging the exisiting telephone/electric cable etc.(in case of
damaged if any type of cable line during excecution , necessary
damaged charges as applicable by the respective authority will be borne
by the agency in his own cost) preparing the bottom surface for
continuous bedding of pipe line and laying pipes, fitting, fixing specials
and valves with bailing out water if any including carriage of pipes,
specials and valves from local deptt. store within 8KM and back filling the
trenches with excavated earth in layers to original condition as per
specification and direction of EIC. The surplus materials after execution
of work are to be return to the deptt. store.
N.B: i) Any deviation from required clear cover of 1.10mtr., due to site
adverse condition, prior permission is to be obtained from the EIC in
exceptional situation and payment will be made on prorate basis over the
rate of entire item
ii) No payment will be made without hydraulic test of the pipe line either
part or full
iii) The pipes, specials and valves , rubber gasket will be supplied deptt.
free of cost.
L-1
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
a) 80mm dia Mtr. ₹ 67.00 ₹ 67.00 ₹ 67.00 ₹ 67.00 ₹ 67.00 ₹ 67.00
b) 100mm dia. Mtr. ₹ 72.00 ₹ 72.00 ₹ 72.00 ₹ 72.00 ₹ 72.00 ₹ 72.00
c) 125mm dia. Mtr, ₹ 100.00 ₹ 100.00 ₹ 100.00 ₹ 100.00 ₹ 100.00 ₹ 100.00
d) 150mm dia. Mtr. ₹ 112.00 ₹ 112.00 ₹ 112.00 ₹ 112.00 ₹ 112.00 ₹ 112.00
e) 200mm dia. Mtr. ₹ 136.00 ₹ 136.00 ₹ 136.00 ₹ 136.00 ₹ 136.00 ₹ 136.00
f) 250mm dia. Mtr. ₹ 164.00 ₹ 164.00 ₹ 164.00 ₹ 164.00 ₹ 164.00 ₹ 164.00
g) 300mm dia. Mtr. ₹ 192.00 ₹ 192.00 ₹ 192.00 ₹ 192.00 ₹ 192.00 ₹ 192.00
h) 350mm dia. Mtr. ₹ 225.00 ₹ 225.00 ₹ 225.00 ₹ 225.00 ₹ 225.00 ₹ 225.00
i) 400mm dia. Mtr. ₹ 260.00 ₹ 260.00 ₹ 260.00 ₹ 260.00 ₹ 260.00 ₹ 260.00
j) 450mm dia. Mtr. ₹ 297.00 ₹ 297.00 ₹ 297.00 ₹ 297.00 ₹ 297.00 ₹ 297.00
k) 500mm dia. Mtr. ₹ 331.00 ₹ 331.00 ₹ 331.00 ₹ 331.00 ₹ 331.00 ₹ 331.00
l) 600mm dia. Mtr. ₹ 416.00 ₹ 416.00 ₹ 416.00 ₹ 416.00 ₹ 416.00 ₹ 416.00
m) 700mm dia. Mtr. ₹ 501.00 ₹ 501.00 ₹ 501.00 ₹ 501.00 ₹ 501.00 ₹ 501.00
n) 750mm dia. Mtr. ₹ 545.00 ₹ 545.00 ₹ 545.00 ₹ 545.00 ₹ 545.00 ₹ 545.00
o) 800mm dia. Mtr. ₹ 591.00 ₹ 591.00 ₹ 591.00 ₹ 591.00 ₹ 591.00 ₹ 591.00
p) 900mm dia. Mtr. ₹ 706.00 ₹ 706.00 ₹ 706.00 ₹ 706.00 ₹ 706.00 ₹ 706.00
q) 1000mm dia. Mtr. ₹ 828.00 ₹ 828.00 ₹ 828.00 ₹ 828.00 ₹ 828.00 ₹ 828.00
L-2
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
2 Supplying, laying, fiting, fixing and jointing of UPVC pipes conforming to
IS:4985-2000 with latest revision and amendments, if any, with
necessary UPVC/CI specials, CIDF sluice valves, as per relevant I.S.
specification including labour charges for earth work in excavation in any
kind of soil including mixed soil with boulder ,road sub-grade and its
flanks but excluding moorum and laterite or sand stonehard arock
including cutting of brick payment without damaging the existing
telephone/electrical cable line etc.(in case of damage of any type of
cable line during excavation, necessary damaged charges as applicable
by the respaective authority will be borne by the agency in his own cost.
Loading, unloading, carrying of pipes, specials, valves from the local
store to work site and lowering laying of pipes specials valves carefully in
trenches maintaining proper levels and alignment ,jointing the pipe and
specials including supplying of good quality/approved brand solvent
cement (as per IS:14182-1994 including cost of all fabricated PVC fitting
i.e. tees,bend, reducers, adopter etc.as per IS:101-1988 and making
flange joints including supplying required quantity of nuts, bolts and
rubber insertion (CIDF sluice valves will be supplied by the department
free of cost) as required at site by adopting suitable method so as to
facilate the maintenance of pipe line locally as per conventional method
including back filling the trenches with good earth obtained from
excavation of trenches including consolidation with watering in layer not
exceeding 150mm thk. with maintaining an average depth of
L-3
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
rd
ii) 3 party inspection of UPVC pipe & specials to be done by CEPET or
(India) SGS/NTH Kolkata or as per direction of EIC as per approved
vender list.
iii)No part payment at any stage on account of supply of materials shall
be entertained.
iv)Payment will be made on actual consumption of materials.
v)UPVC pipes for the works to be supplied as per approved vendor list
and as per direction & satisfaction of EIC. No pipes will be allowed
beyond recommendated vendor list.
vi)Submission of drawing of pipe line with statement of materials
consumed between node to node points against each R.A. & final bill.if
so.
vii) Any deviation from required clear cover of 1.10mtr.due to site
adverse condition, prior permission is to be obtained from EIC and
payment for such work will be made on prorate basis over the rate of
entire item.
L-7
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
3 Supplying HDPE (Materials grade PE-80) pipes conforming to IS 4984-
1995 with latest revision & amendments if any with necessary HDPE
specials (excluding cost of CIDF valves) including labour charges for
earth work in excavation in any kind of soil including mixed soil with
boulder,road sub-grade and aits flank but excluding moorum laterite or
sand stone / hard rock cutting with chisel required including cutting road
flank/ brick pavement etc. without damaging the exisiting
telephone/electrical cable line etc.(in case of damage of any type of
cable line by the agency at the time of execution necessary damage
charge as applicable by the respective authority will have to be brone by
the agency at his own cost)upto the depth (av.) so as to maintain
1.10m.earth cushion from top of the pipe upto G.L. including loading
unloading carrying lowering laying fitting fixing carefully pipes, valves and
specials with the all types of jointing materials in trenches maintaining
proper levels and alignment jointing the pipes and specials by butt
welding/ adopting suitable method (But weld jointing with help of
hydraulic tack and trimming machines, Hitter etc. for reaching at
necessary melting point of HDPE pipe so that joint can be monolithic) so
as to facilitate the maintenance of pipe line locally as per conventional
method in future.
L-11
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
4 Supplying HDPE (Materials grade PE-100) pipes conforming to IS 4984-
1995 with latest revision & amendments if any with necessary HDPE
specials (excluding cost of CIDF valves) including labour charges for
earth work in excavation in any kind of soil including mixed soil with
boulder,road sub-grade and aits flank but excluding moorum laterite or
sand stone / hard rock cutting with chisel required including cutting road
flank/ brick pavement etc. without damaging the exisiting
telephone/electrical cable line etc.(in case of damage of any type of
cable line by the agency at the time of execution necessary damage
charge as applicable by the respective authority will have to be brone by
the agency at his own cost)upto the depth (av.) so as to maintain
1.10m.earth cushion from top of the pipe upto G.L. including loading
unloading carrying lowering laying fitting fixing carefully pipes, valves and
specials with the all types of jointing materials in trenches maintaining
proper levels and alignment jointing the pipes and specials by butt
welding/ adopting suitable method (But weld jointing with help of
hydraulic tack and trimming machines, Hitter etc. for reaching at
necessary melting point of HDPE pipe so that joint can be monolithic) so
as to facilitate the maintenance of pipe line locally as per conventional
method in future.
L-16
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
7 Cutting DI pipe (all class & type) to required length with cutting device
etc. and grinding the cutting portion with file as per direction and
satisfaction of EIC.
a) 80mm.dia. to 125mm.dia pipe Each ₹ 109.00 ₹ 109.00 ₹ 109.00 ₹ 109.00 ₹ 109.00 ₹ 109.00
b) 150mm.dia.to 200mm.dia pipe Each. ₹ 141.00 ₹ 141.00 ₹ 141.00 ₹ 141.00 ₹ 141.00 ₹ 141.00
c) 250mm.dia.to 350mm.dia pipe Each. ₹ 263.00 ₹ 263.00 ₹ 263.00 ₹ 263.00 ₹ 263.00 ₹ 263.00
d) 400mm.dia.to 450mm.dia pipe Each. ₹ 385.00 ₹ 385.00 ₹ 385.00 ₹ 385.00 ₹ 385.00 ₹ 385.00
e) 500mm.dia.to 600mm.dia pipe Each. ₹ 436.00 ₹ 436.00 ₹ 436.00 ₹ 436.00 ₹ 436.00 ₹ 436.00
f) 700mm.dia.pipe Each ₹ 539.00 ₹ 539.00 ₹ 539.00 ₹ 539.00 ₹ 539.00 ₹ 539.00
g) 750mm.dia to 800mm.dia.pipe Each ₹ 706.00 ₹ 706.00 ₹ 706.00 ₹ 706.00 ₹ 706.00 ₹ 706.00
h) 900mm.dia to 1000mm.dia pipe Each ₹ 873.00 ₹ 873.00 ₹ 873.00 ₹ 873.00 ₹ 873.00 ₹ 873.00
8 Chamfering the spigot end of all type/class of DI pipe for proper using of
push joint by means of grinder set at site for proper joint etc. all complete
as per direction of EIC.
a) 75mm dia (OD) Mtr. ₹ 0.69 ₹ 0.69 ₹ 0.69 ₹ 0.69 ₹ 0.69 ₹ 0.69
b) 90mm dia (OD) ₹ 0.88 ₹ 0.88 ₹ 0.88 ₹ 0.88 ₹ 0.88 ₹ 0.88
Mtr.
c) 110mm dia (OD) Mtr. ₹ 1.08 ₹ 1.08 ₹ 1.08 ₹ 1.08 ₹ 1.08 ₹ 1.08
d) 125mm dia (OD) Mtr. ₹ 1.24 ₹ 1.24 ₹ 1.24 ₹ 1.24 ₹ 1.24 ₹ 1.24
e) 140mm dia (OD) Mtr. ₹ 1.44 ₹ 1.44 ₹ 1.44 ₹ 1.44 ₹ 1.44 ₹ 1.44
f) 160mm dia (OD) Mtr. ₹ 1.73 ₹ 1.73 ₹ 1.73 ₹ 1.73 ₹ 1.73 ₹ 1.73
g) 180mm dia (OD) Mtr. ₹ 2.05 ₹ 2.05 ₹ 2.05 ₹ 2.05 ₹ 2.05 ₹ 2.05
h) 200mm dia (OD) Mtr. ₹ 2.42 ₹ 2.42 ₹ 2.42 ₹ 2.42 ₹ 2.42 ₹ 2.42
i) 225mm dia (OD) Mtr. ₹ 2.93 ₹ 2.93 ₹ 2.93 ₹ 2.93 ₹ 2.93 ₹ 2.93
j) 250mm dia (OD) Mtr. ₹ 3.50 ₹ 3.50 ₹ 3.50 ₹ 3.50 ₹ 3.50 ₹ 3.50
k) 280mm dia (OD)
Mtr. ₹ 4.27 ₹ 4.27 ₹ 4.27 ₹ 4.27 ₹ 4.27 ₹ 4.27
l) 315mm dia (OD) Mtr. ₹ 5.28 ₹ 5.28 ₹ 5.28 ₹ 5.28 ₹ 5.28 ₹ 5.28
L-20
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
11 Submission of complete detailed drawing of distribution system, rising
main etc. after execution of work showing position of different types of
valves, fittings/specials sluice valve chamber with location, node to node
wise in the sanctioned drawing as completion drawing of the water
supply scheme as per direction and satisfaction of EIC. The list of dia
Mtr. ₹ 0.38 ₹ 0.38 ₹ 0.38 ₹ 0.38 ₹ 0.38 ₹ 0.38
wise fitting/specials, different pipes ;of valve used in the rising main
should be shown in the completion drawing (not separate) with verified
by SAE & AE in-charge of the scheme. The above drawing will be
submitted in 5 copies.
Ref. Item 2(a), page-10, PWD SOR Vol-I cum ₹ 939.00 ₹ 939.00 ₹ 939.00 ₹ 939.00 ₹ 939.00 ₹ 939.00
14 Construction of different dia Sluice valve /Air valve /Washout chamber in
different sizes for village road where light traffic run and for main road
where heavy traffic run as deptt.approved drawing with 25cm thick brick
work (1:6) over cement concrete (4:2:1) over a single B/F soling
over150mm.thick sand filling in foundation including earth work in
excavation and disposal of excess earth from work site with RCC
(1:1.5:3) cover slab 100mm / 150mm thick slab on top of chamber with
1% reinforcement in RCC cover slab with necessary opening for
operation of valve all complete including cost of labour & materials as per
Departmental Dwg. [Reinforcement type:- Other manufactuerers not
specified]
L-22
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
18 Carriage of different type of departmental pipes from
Divisional/Sub-divisional store to the work site by truck including
loading, unloading, stacking etc. including cost of fuel, lubricant
and also cost of driver, helper etc. and all other taxes and charges
as applicable as per direction of EIC
a) Any distance upto 5 Km Trip ₹ 956.00 ₹ 956.00 ₹ 956.00 ₹ 956.00 ₹ 956.00 ₹ 956.00
b) Above 5 Km upto 10 Km Trip ₹ 1,360.00 ₹ 1,360.00 ₹ 1,360.00 ₹ 1,360.00 ₹ 1,360.00 ₹ 1,360.00
c) Above 10 Km upto 20 Km Trip ₹ 2,057.00 ₹ 2,057.00 ₹ 2,057.00 ₹ 2,057.00 ₹ 2,057.00 ₹ 2,057.00
d) Above 20 Km upto 30 Km Trip ₹ 2,658.00 ₹ 2,658.00 ₹ 2,658.00 ₹ 2,658.00 ₹ 2,658.00 ₹ 2,658.00
e) Above 30 Km upto 40 Km Trip ₹ 3,213.00 ₹ 3,213.00 ₹ 3,213.00 ₹ 3,213.00 ₹ 3,213.00 ₹ 3,213.00
f) Above 40 Km upto 50 Km Trip ₹ 3,754.00 ₹ 3,754.00 ₹ 3,754.00 ₹ 3,754.00 ₹ 3,754.00 ₹ 3,754.00
g) Above 50 Km (Extra cost per Km) Km ₹ 57.00 ₹ 57.00 ₹ 57.00 ₹ 57.00 ₹ 57.00 ₹ 57.00
19 Making barricading of excavation trenches of road width upto
15mtr. to avoid any accident by providing 75mm dia bamboo post
placed vertically & horizontally with the help of 6”size iron rail as
per direction and satisfaction of EIC. (Applicable where critical
situation arise and take up the work as per direction of EIC)
Mtr. ₹ 118.00 ₹ 118.00 ₹ 118.00 ₹ 118.00 ₹ 118.00 ₹ 118.00
L-23
Item
No. Rate (Rs.)
Description of items Unit
ZONE -I ZONE - II ZONE-III ZONE-IV ZONE-V ZONE-VI
20 Excavation of Trench as per drawing and laying,fixing and jointing
with detachable joints AC pressure pipes with necessary spaceals
and valves, cutting pipes to required size, if necessary in any kind
of soil (including mix soil with boulder, road sub-grade and its flank)
prepairing the bottom serface for continous bedding of pipe line in
proper alignment as per specification instuction with joint holes,
sluice valve, wash out valve etc. bailing out water where necessary
including carrage of all materials from local store within 25 Km.,
making a clear cover of 1.00 mtr.between top of the pipe in trench
and existing ground level and backfilling the depth of the trench in
layers as directed (useing excavated earth ) two original conditions
with progresive submission of drawings of pipe lines layed and with
a statement of materials consumed against each R.A and Final
Bill. N.B.
(i) Any deviation from required depth of 1.00 mtr over pipe line in
trench has to be got permitted by the EIC and payment will be
made on prorate basis over the rate of entair item, if executed with
permission of EIC. (ii) 25% payment
against this item will be withheld till hydraulic test of pipe line is not
done as provided separately.
L-24
SECTION – B.3
OVERHEAD RESERVOIR
OVERHEAD RESERVOIR
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
1 Cleaning compound premises of shrubs, plants, jungles etc. as per direction of E.I.C. sqm Refer respective Item of PWD SOR
2 Providing Bored Cast-in-situ R.C.C. pile in position as per specifications in all kinds of soil
including cost of boring using drilling mud to stabilize the bore and flushing the bore of excess
mud with freshly prepared drilling fluid by using pumps prior to placing concrete by tremie pipe
in one continuous operation and including the cost of all materials and labour for placing of
concrete and also including the cost of mobilization and hire charges of all equipment necessary
for boring, welding of reinforcement cage as necessary and lowering of reinforcement cage,
preparation and placing of concrete, including the cost of concrete but excluding the cost of
reinforcement and labour for bending binding etc. complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts and lead upto 1000 m. Work to be
executed as per IS: 2911 (Part II Sec 2).
(Using tripod, winches) / (Using Hydraulic Piling Rig)
ii) To obtain the complete rate the construction wing have to add cost of concrete volume for 1.0
mtr. Length of pile, multiplied by a factor,
[1+{Dummy length of Pile(Max 1.50mtr.)/Individual Length of Pile}]
iii) Rate for concrete may be adopted same as for bottom plug vide item no. 12.09(C) (IV).
iv) The cost of dismantling the length of the pile above cut off level is to be added.
OH -1
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
3 Plain / Reinforced Cement Concrete, in pile foundation with coarse aggregates of appropriate
nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of
approved quality, cement and water reducing admixtures, as necessary, including labour, cost
and carriage of all materials and including preparation of design mix, approval of the same by the
Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per
drawing and technical specification including the cost of necessary form work and staging
complete. ( PCC Grade M25 with providing 10 % extra cement and Using concrete mixer ) { Refer respective Item of PWD SOR
From durability consideration, the value of minimum cement content and maximum water cement
ratio to be considered in the mix design shall be 420 kg/cu.m. and 0.4 respectively. }
OH -2
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
5 Performing Lateral load test on two piles or two groups of piles by introducing a hydraulic jack
with gauge between two piles or pile groups under test by applying horizontal loads in
increments of about 20% of the estimated safe load at each stage and applying the next
increment after the rate of displacement is nearer to 0.1 mm. per 30 minutes till the total
displacement becomes, 12 mm at the cut-off level including the cost of arranging the entire set- Refer respective Item of PWD SOR
up, hire charges of all implements including at least two dial gauges, preparing the pile head if
necessary, and removal of all arrangement after completion etc. complete in all respect including
cost of carriage of all materials and as per IS specification and direction of Engineer-in-charge.
Each
6 Reinforcement for piling work including main bars, stirrups, binders etc. initial straightening and
removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct
shape. Cost of mobilization and welding of reinforcement cage as necessary and lowering of
reinforcement cage placing in proper position , including labour cost complete as per drawing Refer respective Item of PWD SOR
and direction.
a) HYSD bars (Tor steel) M.T
7 Earth work in excavation of foundation trenches ordrains, inallsorts of soil (including mixed soil
but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a
lead of 75m. as directed. The item includes necessary trimming the sides of trenches, levelling,
dressing and ramming the bottom, bailing out water as required complete.
OH -3
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
10 Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding
150mm. including watering and ramming etc. layer by layer complete. (Payment to be made on
the basis of measurement of finished quantity of work)
(c) With carried earth arranged by the contractor within a radius of 1km.including cost of carried
cum Refer respective Item of PWD SOR
earth.
(d) With carried earth arranged by the contractor within a radius of 3km.including cost of carried
earth. cum
(e) With carried earth arranged by the contractor within a radius exceeding 3km.but not
exceeding 5km. including cost of carried earth. cum
(f) With carried earth arranged by the contractor within a radius exceeding 5km.but not
exceeding 10km.including cost of carried earth. cum
11 Filling in foundation or plinth by silver sand in layers not exceeding 150mm as directed and
consolidating the same by thorough saturation with water, ramming complete including the cost cum Refer respective Item of PWD SOR
of supply of sand. (payment to be made on measurement of finished quantity)
12 Filling in foundation plinth by fine sand cum Refer respective Item of PWD SOR
13 Hire and labour charges for shoring work (including necessary close plank walling, framing,
Eucalyptus/ Jhoubulla piling, strutting etc) complete as per direction of the Engineer-in- charge
for foundation excavation (vertical surface are incontact with supported earth is to be measured.)
(This item should be executed on specific direction of the Enginner in charge).
a) Depth upto 1.5mtr. sqm
Refer respective Item of PWD SOR
b) For add. depth beyond 1.5m.upto 3m. sqm
14 Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper
level and filling joints with local sand. sqm Refer respective Item of PWD SOR
15 Ordinary Cement concrete (mix1:2:4) with graded stone chips (20mm nominal size) excluding
shuttering and reinforcement, if any, in ground floor as per relevant IS codes.
(a) Pakur variety OH -4 cum Refer respective Item of PWD SOR
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
16 Controlled Cement concrete with well graded stone chips (20mm graded nominal size) excluding
shuttering and reinforcement with complete design of concrete as per IS: 456 and relevant
special publications, submission of job mix formula after preliminary mix design after testing of
concrete cubes as per direction of Engineer- incharge. Consumption of cement will not be less
than 300Kg of cement with Super plasticiser per cubic meter of controlled concrete but actual
consumption will be determined on the basis of preliminary test and job mix foumula. In ground
floor and foundation.
M-25 grade : i) Pakur variety cum Refer respective Item of PWD SOR
17 Add extra over the rate of ground floor for basement and each additional floor above ground floor
i) Pakur variety (for Tank wall, Tank floor, top & bottom ring beam heal beam etc. above work)
OH -5
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
19 Hire and labour charges for shuttering for concrete work in ove rhead R.C.Reservoir on separate
R.C.frame including fitting, fixing and striking of fafter compeltion of work including staging upto sqm Refer respective Item of PWD SOR
4m using ply board or steel shuttering.
20 Extra for Staging beyond 4m [mode of measurement: Area of unsupported horizontal projection
(where staging beyond 4m is practically unavoidable)x mean height of staging] above initial 4m
cum Refer respective Item of PWD SOR
D= Outer dia of cell wall of tank, h= ht. of G.L. to bottom of Heal beam
A=0.785 x D² ; V=A x h
21 Reinforcement for reinforced concrete work in all sorts of structures including distribution bars,
stirrups, binder set initial straightening and removal of loose rust (ifnecessary), cutting to
requisite length, hooking and bending to correct shape, placing in proper position and binding
with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.
OH -6
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
a) 25mm.thick for wall and floor of tank Add extra @ 1.5% for each additional floor upto 4th .floor
th sqm Refer respective Item of PWD SOR
and @ 1.75% for each additional floor above 4 .floor for original item.
23 Plaster (toe wall, floor, ceilingetc.) with sand and cement mortar including rounding of for
chamfering corners as directed and raking out joints including throating, no singanddrip course,
scaffolding / staging where necessary (Groundfloor). [Excluding cost of chipping over concrete
surface]
I) With (1:4) cement mortar external surface(a) 20mm thick sqm Refer respective Item of PWD SOR
Extra for each addl. floor over the rate of ground floor as above.
i) 4mtr. to 8mtr. sqm
ii) 8mtr. to 12mtr. sqm
iii)12mtr. to 16mtr. sqm
Refer respective Item of PWD SOR
iv)16mtr. to 20mtr. sqm
v) 20mtr. to 24mtr. sqm
vi)24mtr. to 28mtr.. sqm
II) with (1:3) cement mortar Internal surface (a) 15mm thick sqm Refer respective Item of PWD SOR
Extra for each addl. floor over the rate of ground floor as above.
i) 4mtr. to 8mtr. sqm
ii) 8mtr. to 12mtr. sqm
iii)12mtr. to 16mtr. sqm
Refer respective Item of PWD SOR
iv)16mtr. to 20mtr. sqm
v) 20mtr. to 24mtr. sqm
vi)24mtr. to 28mtr. sqm
24 Neat cement punning about 1.5mm.thick sqm Refer respective Item of PWD SOR
25 Expansion joint in floor,roof wall etc. formed with V strips made of 22.50cm wide strips of
24gauge aluminium sheets with anchor am projecting on each side(and end turned) embedded
in adjacent cement concrete , including shaping and finishing the edges on either side of the
joint(Including the cost of bituminous filler if any) complete as per direction. Mtr. Refer respective Item of PWD SOR
OH -7
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
26 Applying 2 (two) coats of bonding agent with synthetic multi funtional rubber emulsion having
adhesive and water proofing properties by making with water in proportion ( 1 bonding agent : 4
water : 6 cement) as per manufacturer's specification. sqm
27 Extra rate for using water proofing and plastering admixture @ 0.2%by weight of cement ( or at
manufacturer's specified rate for concrete of various grades). /Kg
28 Apply exterior grade Acrylic primer of approved quality
Ground floor, Two coats upto 4mtr. from G.L. sqm
Add extra for each adding floor over the rate for ground Refer respective Item of PWD SOR
i) 4mtr. to 8mtr. sqm
ii) 8mtr. to 12mtr. sqm
iii)12mtr. to 16mtr. sqm
Refer respective Item of PWD SOR
iv)16mtr. to 20mtr. sqm
v) 20mtr. to 24mtr. sqm
vi) 24mtr. to 28mtr. sqm
29 Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per
manufacturer's specification and as per direction of EIC to be applied over acrylic primer as
required. The rate includes cost of material, labour, scaffolding and allincidental charges but
excluding the cost of primer. (two coat)
a) Premium 100% Acrylic emulsion upto 4mtr. sqm Refer respective Item of PWD SOR
Add extra for each adding floor over the rate for ground
i) 4mtr. to 8mtr. sqm
ii) 8mtr. to 12mtr. sqm
iii)12mtr. to 16mtr. sqm
Refer respective Item of PWD SOR
iv)16mtr. to 20mtr. sqm
v) 20mtr. to 24mtr. sqm
vi) 24mtr. to 28mtr. sqm
30 Bitumen paint on roof domes including scraping & polishing as per drawing and direction
including cost of paint. i)Two coats (for top of roof Refer respective Item of PWD SOR
sqm
OH -8
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
nd
a) Upto 2 Lift (upto 8.0mtr. from G.L) Kg. ₹ 78.99 ₹ 78.99 ₹ 78.99 ₹ 78.99 ₹ 78.99
b) from 8mtr. to 12mtr. @ 1.5%extra of (a) Kg. ₹ 80.17 ₹ 80.17 ₹ 80.17 ₹ 80.17 ₹ 80.17
c) from 12mtr. to 16mtr. @ 1.5%extra of (b) Kg. ₹ 81.37 ₹ 81.37 ₹ 81.37 ₹ 81.37 ₹ 81.37
d) from 16mtr. to 20mtr. @ 1.5%extra of (c) Kg. ₹ 82.59 ₹ 82.59 ₹ 82.59 ₹ 82.59 ₹ 82.59
e) from 20mtr. to 24mtr. @ 1.5%extra of (d) Kg. ₹ 83.83 ₹ 83.83 ₹ 83.83 ₹ 83.83 ₹ 83.83
f) from 24mtr. to 28mtr. @ 1.5%extra of (e) Kg. ₹ 85.09 ₹ 85.09 ₹ 85.09 ₹ 85.09 ₹ 85.09
35 Supplying at site hoisting, fitting, fixing erecting and building in position where necessary
450mm.wide ladder as per design consisting of 2nos. M.S.Plate of 8mm.thick with necessary
base plate 60mm wide; and 16mm.dia M.S.round or square bar as steeps placed @ 300 c/c
including fabrication, welding drilling etc. as per drawing and direction and finished with two
coats of synthetic enamel painting over a coat of red lead primer etc. all complete as per
;direction of the EIC
Mtr. ₹ 1,067.00 ₹ 1,067.00 ₹ 1,067.00 ₹ 1,067.00 ₹ 1,067.00
OH -9
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
36 Supplying & labour for mixing of super plasticizer of approved make brand sika/cico conforming
to IS-2645-1975 & IS-9130-1979 to be need in mortar admixture @ 0.20% by wt. of cement (i.e
100ml per 50kg of cement) for improving workability, reducing shrinkage and improvement of
water tightness of the concrete.
/Kg. ₹ 139.00 ₹ 139.00 ₹ 139.00 ₹ 139.00 ₹ 139.00
37 Supplying, fitting, fixing 900 mm high G.I. pipe railing for R.C.C stair cat ladder walk way
fabrication,erection,welding of 40 mm G.I (NON TATA medium) pipe place at top of railing and
2 nos 25 mm dia. G.I pipe (NON TATA medium) placed equally in between railing top & floor,
vertical post of railling are 40 mm dia. G.I pipe (NON TATA medium) placed at 900 mm c/c . The
each end of the vertical post is join by the 62 mm (25 mm X 6 mm X 0.062 m long) MS flat and
150 mm length (propes pipes) are grouted in concrete base of stair, walk way etc. All complete
with supplying of all materials including hoisting up to the any height complete with 2 coats of
painting with super gloss (Hi gloss) in any shade except white and black over a coat of primer
complete as per direction of E.I.C. Analysis of rate enclosed in seperate sheets. ( Analysis
Rate )
Mtr. ₹ 1,804.00 ₹ 1,804.00 ₹ 1,804.00 ₹ 1,804.00 ₹ 1,804.00
38 Bituminous filer of approved type in excavation joint between the shell wall & roof including
finishing the top surface as per ;drawing, specification and direction of EIC cum ₹ 54,737.00 ₹ 54,737.00 ₹ 54,737.00 ₹ 54,737.00 ₹ 54,737.00
39 Supplying hoisting, fitting fixing approved type water level indicator with copper float, guide
pulley, wire boards etc. as per standard specification and direction and satisfaction of EIC
Each ₹ 64,271.00 ₹ 64,271.00 ₹ 64,271.00 ₹ 64,271.00 ₹ 64,271.00
40 Supplying fitting and fixing in position reinforced cement polymer concrete manhole cover with
matching frame as per IS-12592 (MD)
a) 5MT load bearing capacity round manhole cover parovided with two nos. lifter hook with
machining frame of size 550mm x 65mm(cover) and 650mm x 125mm(frame) opening 470mm
and WT. 90KG. approx. Each ₹ 3,013.00 ₹ 3,013.00 ₹ 3,013.00 ₹ 3,013.00 ₹ 3,013.00
41 Band moulding (Horizontal/vertical) rectangular section made with cement plaster(1:4) complete
OH -10
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
42 (A)Earthing with 50mm.dia G.I. pipe3.64mm.thick x 3mtr. (10”-0”) long and l;1 x 4SWG G.I. (Hot
dip)wire 4mtr. long 13mm. dia x 80mm.long G.I.Bolts, double nuts , washer including S&F
15mm.dia G.I.pipe protection (1mtr. long) to be filled with bitumen partly below ground level to an
av. Depth of 3.65m below G.L. and restoring the surface duly rammed as per IEE rule
47 Construction of masonry drain 300 mm X 250 mm inner section with 1st class 250 mm th. Brick
work in cement mortar(1:4) over a layer of single brick flat soling , sand filling 100mm th. and 100
mm th. weak cement concrete(6:3:1) with graded stone ballast pakur variety (40mm size)
including earth work in excavation , 15mm th. Cement plaster(4:1) and neat cement punning all
rounding the drain etc. all complete as per approved design , drawing and direction of the
Engineer in-charge. ( Ref. Deptt. Dwg)
Mtr. Refer respective Item of PWD SOR
48 Fitting, fixing Duck foot bend including construction of cement concrete(4:2:1) base with
approved grade stone chips and including excavation of earth & filling etc. all complete in all
respect as per direction of EIC.
a) 400mm.dia (Base size 450mmx450mmx600mm.deep) Each. ₹ 950.00 ₹ 950.00 ₹ 950.00 ₹ 950.00 ₹ 950.00
b) 300mm.dia (Base size 350mmx350mmx500mm.deep) Each. ₹ 527.00 ₹ 527.00 ₹ 527.00 ₹ 527.00 ₹ 527.00
c) 250mm.dia (Base size 300mmx300mmx450mm.deep) Each. ₹ 367.00 ₹ 367.00 ₹ 367.00 ₹ 367.00 ₹ 367.00
d) 200mm.dia (Base size 250mmx250mmx400mm.deep) Each. ₹ 261.00 ₹ 261.00 ₹ 261.00 ₹ 261.00 ₹ 261.00
e) 150mm.dia (Base size 200mmx200mmx350mm.deep) Each. ₹ 168.00 ₹ 168.00 ₹ 168.00 ₹ 168.00 ₹ 168.00
49 Supplying mosquito proof net made of polythene (NETLON) size 75cm. X 75cm. for ventilator
including fitting, fixing in the best sal wood frame of 8cm. X 5cm. cross section with necessary
wooden batten fixing the assembly with necessary MS clamp in RCC wall at the lantern.
Sqm. ₹ 1,681.00 ₹ 1,681.00 ₹ 1,681.00 ₹ 1,681.00 ₹ 1,681.00
50 Supplying fitting and fixing door made with IRC febric mesh of 75mm x50mmx4.5mmx2.7mm on
50mm x 50mm x 6mm angle iron frames all round and one 37.5mm x 6mm M.S. flat bar over the
netting all round welded to angle iron frame and providing locking arrangements if necessary and
with two coats of synthetic enamel paint(Other than Hi-gloss) fitted and fixed with clamps or
haskal doomney etc. complete at the lantern of R.C.C. over head reservoir.
OH -12
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
51 Providing water thirable non-toxic expoxy coating (techoxy or equivalent brand of approved
quality)2(two)finished coats over 2(two)of primer of same brand to the ceiling of roof dome
including supply of requisite coating materials, cleaning of the substrate properly to make it free
from dirt, paint, oil and grease, sludge, blister, loose plaster, fungus, moss and all other
undesirable particles using wire brush, sand papers etc. including mending good all damages all
complete as per direction of EIC & his satisfaction.
sqm ₹ 299.00 ₹ 299.00 ₹ 299.00 ₹ 299.00 ₹ 299.00
52 Labour for chipping of concrete surface before taking up plastering work. sqm Refer respective Item of PWD SOR
PIPING ARRANGEMENT
53 Making flange joint to CIDF pipe, specials, valves etc.with supply of necessary nuts and bolts,
rubber insertion of 6kg/m2 (3mm gauge) and materials required including dewatering if any tools
and plants, labour cost etc. as per specification and direction of EIC (Nut and bolts shall be of
TATA/GKW make) for
i)300mm.dia. Each ₹ 849.00 ₹ 849.00 ₹ 849.00 ₹ 849.00 ₹ 849.00
ii)250mm.dia. Each ₹ 693.00 ₹ 693.00 ₹ 693.00 ₹ 693.00 ₹ 693.00
iii)200mm.dia. Each ₹ 508.00 ₹ 508.00 ₹ 508.00 ₹ 508.00 ₹ 508.00
iv)150mm.dia. Each ₹ 431.00 ₹ 431.00 ₹ 431.00 ₹ 431.00 ₹ 431.00
v)100mm.dia. Each ₹ 399.00 ₹ 399.00 ₹ 399.00 ₹ 399.00 ₹ 399.00
vi)80mm.dia. Each ₹ 239.00 ₹ 239.00 ₹ 239.00 ₹ 239.00 ₹ 239.00
54 Hoisting,fitting,fixing of C.I. bell mouth with puddle collar in RCC work as per drawing
specification and direction of EIC all complete.
a) 300mm.dia. Each ₹ 151.00 ₹ 151.00 ₹ 151.00 ₹ 151.00 ₹ 151.00
b) 250mm.dia. Each ₹ 113.00 ₹ 113.00 ₹ 113.00 ₹ 113.00 ₹ 113.00
c) 200mm.dia. Each ₹ 90.00 ₹ 90.00 ₹ 90.00 ₹ 90.00 ₹ 90.00
d) 150mm.dia. Each ₹ 75.00 ₹ 75.00 ₹ 75.00 ₹ 75.00 ₹ 75.00
e) 100mm.dia. Each ₹ 65.00 ₹ 65.00 ₹ 65.00 ₹ 65.00 ₹ 65.00
55 Hoisting, erection ,placing connecting with pipes and specials CIDF pipes, specials) securing
with building specials providing stays, clamps as required including cost of staging platform for
the work etc.all complete in all respects as per drawing and direction of EIC.
OH -13
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
N.B: For OHR use CIDF class B pipe for inlet, outlet, overflow and washout.
(B) CIDF Duck foot bend as per I.S. 1538 1976 with latest revision. Kg ₹ 61.00 ₹ 61.00 ₹ 61.00 ₹ 61.00 ₹ 61.00
(C) CIDF Bell mouth pes. with puddle collar as per ISI 1538-1976 with latest revision Kg ₹ 61.00 ₹ 61.00 ₹ 61.00 ₹ 61.00 ₹ 61.00
(D) C.I.D.F 90˚ Bend as per I.S.1538 (Part-XXI)-1976 with latest amended Kg ₹ 61.00 ₹ 61.00 ₹ 61.00 ₹ 61.00 ₹ 61.00
59 Supply and delivery of CIDF sluice valve (Special type) PW-1.00 of different dia make with CI
double flanged non rusting spindle sluice valves conforming to IS 14846 -2000 with latest
emended having body dome/bonnet and cover of C.I.Gr-F.G 210mtr. spindle of IS-6603 G.R-
12/Gr-13 non-magnetic, nuts seat rings are of Gunonetal as per IS:318 LTB-2 flanges and drilled
to IS:1538 Part IV & VI valves are suitable for max. working pressure of 10kg/cm2(seat test) and
body tested to 15kg/cm2.
N.B: The above item should be procured from the reputed manufactures as per deptt. approved
vender list
i) 300mm.dia. Each ₹ 29,700.00 ₹ 29,700.00 ₹ 29,700.00 ₹ 29,700.00 ₹ 29,700.00
ii)250mm.dia. Each ₹ 24,420.00 ₹ 24,420.00 ₹ 24,420.00 ₹ 24,420.00 ₹ 24,420.00
iii)200mm.dia. Each ₹ 16,632.00 ₹ 16,632.00 ₹ 16,632.00 ₹ 16,632.00 ₹ 16,632.00
iv)150mm.dia. Each ₹ 9,174.00 ₹ 9,174.00 ₹ 9,174.00 ₹ 9,174.00 ₹ 9,174.00
v) 100 mm dia. Each ₹ 6,138.00 ₹ 6,138.00 ₹ 6,138.00 ₹ 6,138.00 ₹ 6,138.00
60 Removal of rubbish, earth etc. from the working site and disposal of the same beyond the
compound, inconformity with the Municipal/Corporation Rules for such disposal, loading in to
truck and cleaning the site inall respect as per direction of Engineer in charge
Cum Refer respective Item of PWD SOR
61 Commissioning the R.C.C. over head reservoir by operating of all category of sluice valves ,
testing of hoisted pipe joints including repairing the leakage(s) if detected , including making
inter connections,flange jointing/lead jointing with the newly laid rising main and distribution main
all complete as per direction of the EIC. Each ₹ 6,000.00 ₹ 6,000.00 ₹ 6,000.00 ₹ 6,000.00 ₹ 6,000.00
OH -15
Rate (Rs.)
Item
Description of item Unit
No. ZONE - I ZONE - II ZONE - III ZONE - IV ZONE - V
62 Soil Investigation studies for all disturbed & un-disturbed soil in different areas for selection of
nature of foundation of structural works including supplying, preparation & submission of report
in six copies giving relevant information, data, site plan borelog and water table, test results,
calculations discussion suggestion and recommendation in respect of suitable foundation etc
including determination of silt factor, calculation of water ways and complete design of Item. Refer respective Item of PWD SOR
foundation including analysis of bearing capacities and settlements in bound and presentable
form complete as per direction of EIC.
OH -16
SECTION – B.4
Item Rate
Description of Items Unit
No. (Rs.)
1 Supplying, Fabrication, Erection on suitable RCC
foundation and Commissioning with 3 (three) months Trial
Run (including cost of routine testing of water sample for
performance evaluation) of pressure type Iron removal
plant as per design norms of the P.H.E. Dte. with necessary
accessories viz. MS fabricated shell with minimum 10 mm
thick MS plate with 2 (two) coats of anticorrosive paint &
minimum 12 mm thick MS media supporting plate fitted
with required no. of pot strainer, MS fabricated oxidation
chamber with minimum 10 mm thick plate with necessary
pipe connection, valves, Gauges & other instruments as
required as per departmental approved design & drawing
including cost of filter media, Air Compressor & Air blower
with motor, starter, main switch etc. of required capacity &
approved specification including power connection from
main line etc. all complete.
Rate excludes the cost of Concrete Platform & drain, and
the cost of Blower Room
For more than 50 cum/hr, twin unit of equal size in parallel
shall be adopted.
i) 5 cum/hr 1 612400.00
ii) 10 cum/hr 1 732100.00
iii) 15 cum/hr 1 788100.00
iv) 20 cum/hr 1 862800.00
v) 25 cum/hr 1 940300.00
vi) 30 cum/hr 1 1027900.00
vii) 35 cum/hr 1 1084400.00
viii) 40 cum/hr 1 1144300.00
ix) 45 cum/hr 1 1196200.00
x) 50 cum/hr 1 1312700.00
IEP-1
SECTION – B.5
1 Construction of Arsenic-cum-Iron Removal Plant (AIRP) to reduce Arsenic concentration to 10 ppb (0.01 mg/l) and Iron
to 100 ppb (0.1 mg/l) from influent concentration upto 500 ppb (0.5 mg/l) and 3000 ppb (3 mg/1) respectively (single /
multi-stage) based on oxidation followed by chemical co-precipitation, filtration etc. and departmental
process/hydraulic design consisting of inlet arrangement, oxidation chamber (30 minute detention time), flash mixer,
flocculation and sedimentation unit, filtration unit with Back washing arrangement (including the cost of 2 years
polishing media where applicable) with air and water, back wash water tank of suitable capacity, and staging
height, air compressors, blower etc, with or without activated alumina chamber all with pneumatic valve and
control arrangements, clear water reservoir (30 minute detention time), Solid-liquid sludge separation bed with 100%
recirculation facility, including the cost of all mechanical and electrical items (but excluding the cost of Raw water inlet
pumps and clear water pumps), all accessories & RCC sludge storage tank etc, chemical house-cum-store, administrative
building (with minimum 100 m2 plinth area), allied pipeline, integration of total plant etc. all complete showing all
necessary arrangements, structural & hydraulic detail based on departmental drawing and specification with trial run for a
period of 3 (three) months after completion of the works and 3 months maintenance after successful trial run
including the cost of chemicals but excluding the cost of electricity charges.
Type-1 - Fully Gravity System with RG Filter — with baffled flocculator,plain sedimentation tank, rapid gravity filter, with or
A without gravity type activated alumina chamber all complete as per departmental drawing no. PC I/AIRP/Type-1/Sheet- 1 & 2.
Each
A
B Type-2- Fully Gravity System with Mechanised Clariflocculator -- With mechanized clariflocculator, rapid gravity filter, s
with or without gravity type activated alumina chamber all complete as per departmental drawing no.PC- I/AIRP/Type-
P
Each
2/Sheet-1 & 2.
e
Type-3- Partial Gravity System With RG Filter and Pressurized Upflow Polishing Unit — with mechanized clariflocculator, r
C C
rapid gravity filter, with or without pressurized up-flow activated alumina chamber all complete as per departmental C Each
drawing no. PC-I/AIRP/Type-3/Sheet-1 & 2. h
a
r
Type-4- Partial Gravity System with Pressure Filter and Pressurized Upflow Polishing Unit — with mechanized t
D clariflocculator, pressure filter, with or without pressurized up-flow activated alumina chamber all complete as per Each
departmental drawing no. PC-I/AIRP/Type-4/Sheet-1 & 2.
AC-1
RATE CHART
ZONE I
WITH ACTIVATED ALUMINA POLISHING UNIT WITHOUT ACTIVATED ALUMINA POLISHING UNIT
CAPACITY UNIT TYPE -1 TYPE-2 TYPE-3 TYPE-4 TYPE -1 TYPE-2 TYPE-3 TYPE-4
70 Cum/Hr 1 Unit 155 143 144 142 119 107 108 106
AC-2
RATE CHART
ZONE II
WITH ACTIVATED ALUMINA POLISHING UNIT WITHOUT ACTIVATED ALUMINA POLISHING UNIT
CAPACITY UNIT TYPE -1 TYPE-2 TYPE-3 TYPE-4 TYPE -1 TYPE-2 TYPE-3 TYPE-4
70 Cum/Hr 1 Unit 154 142 143 142 118 107 107 106
AC-3
RATE CHART
ZONE IV
WITH ACTIVATED ALUMINA POLISHING UNIT WITHOUT ACTIVATED ALUMINA POLISHING UNIT
CAPACITY UNIT TYPE -1 TYPE-2 TYPE-3 TYPE-4 TYPE -1 TYPE-2 TYPE-3 TYPE-4
70 Cum/Hr 1 Unit 153 142 143 141 118 106 107 105
AC-4
SECTION - C
MAINTENANCE WORK
Schedule of Rates for Maintenance related works of Water Supply Scheme.
Sl.
No.
Description Of Item Rate Unit
PART - A
1 Opening & closing of all the different dia Sluice Valves (80 rum dia to 350 mm dial on different places along the alignment of the rising main and distribution main at different places
over the command area daily as and when required for regulating the supply of water and distributing' water all over the command area smoothly including changing and restoration of
gland packing of sluice valve, air valve if required including opening the cap / plug of wash out point or opening the sluice valves including de-jointing flange joints (80 mm to 350
387.00 Each per day.
mm dial including repairing works and cleaning the pipeline or changing of gate, spindle or liner etc. of sluice valves all complete, restoration works to be done including earth work in
the excavation bailing out of water, re-filling the excavated earth, taking out of RCC slab or slab cover and refaxing true to position etc. all complete as per the specification and
direction of EIC.
# Please see the special clause against this item in Tender Document
PART - B
2 Labour charges for repairing the bursting/damage/leakage of 80 mm. dia, to 200 mm. dia. A.C. Pipeline with detachable joints including earth work in excavation tracing out the actual
position of burst/leak, cutting pipe of required length, refitting the same with new pipes and old/new detachable joints after chiseling and shaping the pipe, bailing out water from the
trenches and refilling the trenches to its original condition all complete as per direction of E.I.C. (Extra A.C. Pipes and detachable joints with rubber ring, nuts and bolls etc. will be
supplied from the scheme store, Surplus and unserviceable pipes and specials will have to be returned to the same store. The rates are inclusive of carriage to site of work and back
carriage of materials to and from scheme store as mentioned above.)
i) 80mm to 125 mm dia 496.00 Each
ii) 150mm to 200 mm dia 552.00 Each
3 Extra repairing charges over item no 2 for changing of gland packing of sluice valve/air valve with supplying of gland packing grease etc. bailing out of water including removing the
top cover slab of vaIve chamber and refixing the same after completion of work as per direction of EIC.
a) 80 mm dia. to 125 mm dia. 230.00 Each
b) 150 mm dia. to 250 mm dia. 322.00 Each
c) 300 mm dia to 350 mm dia. 488.00 Each
4 Repairing of flange joint after dismantling the joints, removing the unserviceable rubber insertion and supply new rubber insertion and supply upto 50 % of new nuts and bolts all
complete including necessary earth work dewatering & supply of washer etc. all complete as per direction of EIC
a) 80 mm dia. to 100 mm dia. 311.00 Each
b) 125 mm dia. to 200 mm dia. 545.00 Each
c) 250 mm dia to 350 mm dia. 744.00 Each
d) 400 mm dia to 500 mm dia. 888.00 Each
e) 600 mm dia to 700 mm dia. 1269.00 Each
5 Repairing of air valves by changing the ball with changing the requisite nuts and bolts and rubber insertion all complete as per direction of EIC. 260.00 Each
6 Making barricading for protecting the trench to avoid any accident including making arrangement of road light during the night. 962.00 Each location
M-1
Sl.
No.
Description Of Item Rate Unit
7 Renewing lead joint to CI pipes and specials and spun yam 'including reusing 60% of old and using 40% new lead of approved quality new span yam and caulking the same properly
including labour charges for dismantling the existing damaged portion complete as per direction of EIC. Approved quality lead, spun yarn, fuel and other materials will be supplied by
the agency including necessary earth work in exacavation & back filling in same trenches (Lead if supplied by the department will be recovered @ 145/- per kg) NB:-This item
will be executed as per specific direction of EIC
a) 80 mm dia. to 150 mm dia. 1080.00 Each
b) 200 mm dia. to 250 mm dia. 1412.00 Each
c) 300 mm dia to 350 mm dia. 2214.00 Each
d) 400 mm dia. with supply of 10.80 Kg lead & 750 gms yarn to each. 2254.00 Each
e) 450 mm dia. with supply of 12.20 Kg lead & 950 gms yarn to each. 2545.00 Each
f) 500 mm dia. with supply of 15.00 Kg lead & 1.00 Kg. yarn to each. 2957.00 Each
g) 600 mm dia. with supply of 19.00 Kg lead & 1.20 Kg. yarn to each. 3831.00 Each
h) 700 mm dia. with supply of 22.00 Kg lead & 1.35 Kg. yarn to each. 4337.00 Each
8 (i) Carrying charges of materials M.S. Rod, D.I. Pipe, G.I. Pipe, TW materials, C.I.Dt. Joints, A.C. Coupling, Brass Strainer, H.D.P. Strainer, A.C. Pressure Pipes, M.S. Pipes etc. by
road from different stack yard to any places within West Bengal including loading (upto a lead of 20 mtr. from loading point), packing, unloading and stacking charges etc. complete
as per direction.
a) For distance 0 Km. to 5 Km. 44.42 MT/Km.
b) For distance (above) 5 Km.to 10 Km. [Subject to minimum of Rs. 222.10/MT] 24.87 MT/Km.
c) For distance (above) 10 Km.to 15 Km. [Subject to minimum of Rs. 248.70/MT] 23.20 MT/Km.
d) For distance (above) 15 Km.to 25 Km. [Subject to minimum of Rs. 348.00/MT] 19.84 MT/Km.
e) For distance (above) 25 Km.to 50 Km. [Subject to minimum of Rs. 496.00/MT] 15.68 MT/Km.
f) For distance (above) 50 Km.to 100 Km. [Subject to minimum of Rs. 784.00/MT] 14.07 MT/Km.
g) For distance (above) 100 Km.to 125 Km. [Subject to minimum of Rs. 1407.00/MT] 13.14 MT/Km.
h) For distance (above) 125 Km.to 150 Km. [Subject to minimum of Rs. 1642.00/MT] 10.99 MT/Km.
i) For distance (above) 150 Km.to 200 Km. [Subject to minimum of Rs. 1648.00/MT] 8.53 MT/Km.
(ii) Carriage of pipe and specials from Depttl. Store including loading and unloading and stacking at store of any PWSS. ( By Van or other means ) 638.00 Trip
9 Cleaning silt (every month) from the over head reservoir, cleaning washing and disinfecting the same with bleaching powder, including machinery, tools and plants as per direction of
EIC complete (Bleaching powder will be supplied by the agency).
a) Upto 1.50 lakh gallon capacity OHR. 2408.00 /Occ
b) Above 1.50 lakh gallon and upto 2.5 lakh gallon capacity OHR 2852.00 /Occ
10 Withdrawing and relaying of DI/CI pipes / AC pipe after excavation of earth and with the help of chain pully derrick etc. by dismantling & jointing by rubber gasket joint or lead joint
or flange joint and stacking the withdrawn pipes and specials at site store /road flank, godown etc. all complete in the excavated same trench & as per direction of EIC.
M-2
Sl.
No.
Description Of Item Rate Unit
a) 80 mm to 125 mm AC/DI/CI Pipe 210.00 /Mtr.
b) 150 mm dia to 200 mm AC/DI/CI Pipe 213.00 /Mtr.
c) 250 mm dia to 350 mm dia DI/CI Pipe 281.00 /Mtr.
12 Dismantling existing ferule with fitting and refixing the same after cleaning and washing of pipe line upto stand post. 394.00 Each
13 Labour charges for repairing of UPVC pipe by using UPVC socket and solvent cement including earth work in excavation with dewatering and necessary tracing out the actual
position of brusting / leakage, cutting the pipe to required length in the trenches and replacing the same with new pipe (as per required length) including fitting fixing after roughing
the UPVC surface & supplying and applying solvent cement, back filling the trenches with excavated earth upto the same as per direction of EIC all complete (UPVC pipes and
specials, solvent cement to be supplied by the Agency). Unserviceable broken withdrawn surplus materials are to be deposited to the Deptt. store.
M-3
Sl.
No.
Description Of Item Rate Unit
20 Taking out of old and damaged valve of any type from the existing line after dismantling of Flange Joint or Socket Joint and fitting, fixing of New Valve. ( Cost of dismantling of joint
and renewing the same to be added with this item to complete the job in all respect )
i) 80 mm to 100 mm dia 250.00 Each
ii) 125 mm to 150 mm dia 280.00 Each
iii) 200 mm to 250 mm dia 500.00 Each
iv) 300 mm to 350 mm dia 844.00 Each
21 Charges for day to day conveyance towards reporting related to operation and maintenance of smooth water supply from the scheme including cost of Tele-communication charges etc.
30.00 per day
all complete whatsoever required for the purpose as per direction and satisfaction of the E.I.C.
22 Supplying Bleaching Powder of approved brand (DCM/Modi/Kanoria) including all charges and free delivery at site.
50.00 Kg.
23 Supplying Alum bar of approved brand including all charges and free delivery at site. 50.00 Kg.
24 Supplying of UPVC Coupler 6Kg., class – III conforming to IS : 4985 – 2000 with latest revision and amendments ( This item is applicable for maintenance/ repairing work of pipe
line only).
a) 63 mm dia ( OD ) 35.00 Each
b) 75 mm dia ( OD ) 48.00 Each
c) 90 mm dia ( OD ) 67.00 Each
d) 110 mm dia ( OD ) 99.00 Each
e) 140 mm dia ( OD ) 185.60 Each
f) 160 mm dia ( OD ) 347.50 Each
25 Supplying bolts with nuts matching with different dia. C.I. detachable joint as per IS : 8794 -1988 with latest amendment.
119.00 Kg.
a) 10 to 25 mm dia.
26 Supplying rubber ring matching with different dia. C.I. detachable joint as per IS : 8794 -1988 with latest amendment.
a) For 80mm dia. 4.80 Each
b) For 100mm dia. 5.45 Each
c) For 125mm dia. 6.25 Each
d) For 150mm dia. 7.00 Each
e) For 200 mm dia. 8.50 Each
M-4
SECTION – D
T-1
T-2
D.2
IE-1
SECTION – E
INSPECTION
Dimensional, Visual, Physical & Chemical Properties
Sl. Parameter Instrument Sampling size & Manufacturer Third
No. frequency Party/
Departmen
t
1 Visual Appearance -- Every pipe Perform Witness
Qu-1
INSPECTION
Mechanical Properties
Sl. Parameter Instrument Sampling size & Manufacturer Third
No. frequency Party/
Departmen
t
9 Hydraulic charecteristics As per Review Report Review
a) Type Test IS:4985/2000 Report
Annex –
Hydraulic testing D, CL.-2.1.3
machine & End As per Perform Witness
fittings IS:4985/2000
b) Acceptance test CL. –
D.1.10, Table-17
Calibration Certificate of all measuring & testing equipments will be provided for review.
Qu-2
SEC:-E.2
QH-1
SECTION – F
RESOURCE PROCUREMENT
LIST OF DEPARTMENTAL MATERIALS SUPPLIED
BY
THE RESOURCES DIVISION, PHED.
R-1
SECTION – G
SUPPORTING DRAWINGS
SCHEDULE OF DRAWINGS
To
The Chief Engineer
(Ail)
(All) Circle
Corrigendum No.-I & Addendum No.-I along with general specifications of materials to be used for
house connection of the schedule of rates of P.H.E. Dte. (Both Civil & Mechanical) has been given
in the departmental web site (with effect from 0210712020).
O
O F a: [ji 3:i=i=s
- =
IF
oo
= 5E-.=5s,rao
=
f-.
i=r- Pco=d6'!1 6* = w
p
s c 4 4-= f
=6'-=-:its I
I
r=+=1+=e
=q=
g,E
(].r
lh
\A
#.J 3 $ r- L\)
\$
.t
-Q6=:.-o(,
6;=='==---
$ a-=. =a6 = a'
€9.=4E+;o
Eo p ii d-= 3 5
cr3
..\
\>
+
T (D
= P QI Pl io: ?
>: () r =.+ s2 (D o
(D
a)
vLs
+
P
lA 0 .=-
^L C) -= o a .li I
a"p Ln=.8 -il
(D GJC) -
D.\
I'z =
o fr \n
E=.
=
--v:t)- +
o
-.1
F t
--=1o=€E a-f
s.sHE=a o
an
?
E
u^-rr.-O
44 (D -
F =fr+q
-JUJ=A :.-
g3i;B BlBilA
= LAJ
!t'
eEd
ra Ealos+3
== i.-
3e ; il.i 5 E I1l
p
I E E 9H P: =
6"==*e5+ (n
lt tl
-
F-q
(.o
. ^:3=
'Ti x :
io_(oa I $=
= O--
(D
rna
4
/!
o
r C.q
+-'o o
q==HloEo-
=
g€
i6 so-(b:L(,
sp6.
-no N
@
(4
t-
fr,1
.\c-
r)
L1l
7.
-
I E qe'a 3B
q (oo-
- rC
Fi7
H d .'t.>
,P
= 1 /,
rn?
Th I
m G
o)
c) o
=- =
-
N
^))
N) o
z.
a-r
b-, m ,/)
5
so
x
(n
O
o Y
^u
N
o -
-@ z. N)
O
m or-
s !v
!D
b
o
'n
-a
I
AI N
o n
oi
U
F-
N) z. (D
m i
O
(,
(, v? -+
L
b
O t
/*o
N F
^lt o
z. \)
-@
(o m
P
o
o
A) N
o
z.
"co
(, m
9r'
O
o
o
5 p 3
o
N & a c- p u =
a P
z
C
C
a c =
='
e C C - oc ='
I
:.
c c j D
= ?.
= o =' 3 = =
+ c ot lc= + ? p ='
.JC
o o p
= a p = D
a a
C a a =
l!
C
N p L 7
C
- o= = : C
C
C
a
p
1.^9
a a
= a p = =' - 2 I
= a p =.
!
a
- =g /,
fic ='
fii i I I-.
D -- c s p a g, Fl c6
z
f,
p a
= p
VI c U a L - - - u- t^i
p a' z \s
d: $ a -aa
;'-o
D
C
:.
a
D
=
1
G
C
a
-a- c\
\)
k) @
a 9. =.
I r ,>
n'_.
= -
G
I -
0!
U,
a
q. )s
D
.$ a
2.
!
D =
G
i= !
!
o
J
a-
a
= E
IA 0 - a
9 o ao. c U \..r)
a a - p o
\N a a -a o
r ,
a G p
c c) + o
D
Fo 7
!
a
, a D
-.
a
a
i
= = al
a G 1
E 0.
o c -
=. I
D D
p D
F a
=
G
a
d
d
=
D
c
=
c-
-l
[--
F
I
! D =
c o
a rJ)
a =
qo
a
I
- o C
=
c
c e =
= =' t
-a
a
5
=_
a
E
= J
:/ -
.z
t. o C a p a
= a =
=o J.
= a : ar't o
t-
N
1
='
a
a
a
6
?a ==-
'; tl
a\)
o 7
---7
/=
a J
: a
p
a
I I
:-7
= = =. -trz
:ll =
p ? o
a
), =
= - - a
-r:
- IF -. =
=
a
T
a
!-r
p
='
a a'
-
=.
- -D U'
--
c -.
='
- -
rIa a =
=' a-
oc U
- C
= 55 h a -at
!
a
OE
D
= \.=' o
'n
c + T
p a
o a
a
?. =. T
a I.T
a a = =
c
(,
oq
D U
=' a
o a
o - o
a o)
I 5 o
o 9.
s - ?. t-
=
c =
c o
o P
=
R"
o
o F I
= o e X o
o
arc
a
:''
a
a
=
v +
=' = I
0c
- As
\J
lJ
I\D rl
C)
1\
>+
>t
GENERAL SPECIFICATIONS OF MATERIALS TO BE USED FOR
Ferrule
Gun Metal Confirming to lS 269211994(reaffirmed 2005) lSl Marked.
s+ r^J g
Trc,\,f 3c,!"-Jrr.!,.-
rn^"'"^^ tt<<
N{enroNo.:- gL1- 5g29l8rfnlr313 Date:- cL',)7-)-,a't-->
ADDENDUM No.-1
Section -8.6: SMALL TUBE WELL USING WATER-IET METHOD, SCI{EDULE OF RATES
(cIVrL woRKS), JULY 201.9
Item Rate
Description of Items Unit
No. (Rs.)
1 Labour for boring tube well of required diameter by water jet
system through any type of soil strata including hire and labour
charges for boring pipes, scaffolding, tools and plants as necessary
and taking out them and lowering pipes, strainers, blank pipe etc.
and fitting and fixing the same complete including other
incidental works as per direction of Engineer-in-charge. The tube
well should have a rninimum 50mm gap in between the outside of
the tube well pipe and the bore.
)L
Page:STW-1
(cIVrL woRKS), JULv 2019
Item Rate
Description of Items Unit
No. (R..)
7 Supp11, of PVC pipes & fittings Scheclule 80 (n-redium clutv)
conforming to ASTMD - 7785 and threadecl to match u.ith GI Pipes
as per IS :7239 (Palt - I).
A) PVC pipes
a) 40rnm dia Mtr < 207.00
b) 50rnm dia Mh. <282.00
c) 100mm dia Mtr < 874.00
B) Reducing Socket (mm X mrn)
a) 100 x 40 Each { 202.00
b) 100 x 50 Each < 171.00
B Supplying high density polythene strainer of approved make with
adapter conforming to I.S. specifications.
a) 40mrn dia Mtr < 376.00
b) 50mm dia Mtr < 532.00
9 Supplying PVC strainer of approved make with adapter
conforming to I.S.12818 specifications.
a) 40mrn dia Mtr r 293.00
b) 50mm dia Mtr < 367.00
10 Supplying, fitttng and fixing steel cutter piece upto 450 mrn long
with sockets.
a) 40mm dia Mtr < 124.00
b) 50mrn dia Mtr < 189.00
11 Supply and delivery of MS TW Specials (Clamp, Cap, Bail plug,
Lrgs, Ring etc.) LS < 1,200.00
72 Supply and delively of India Mark-II hand pump set Set <13,624.00
\^Its- L
(qvprqt S,J^"-!r^Qe
q9'-^"^: +l-==-
Page:STW-2
?
N 7i rD
)
J
z
*E$a + [g *iElFqaBAlFr ig+tnBfi iE :.
q
I
Fi $rl +iETi$E:srgEiigi$:EEEf
i
f.4
.D
l..r5
isiErBt;
ch
a
,[ t31
\^1
eI =F B
-
*gi iF*xe=a*:EEFEiE
Fd
r:(1
C
gp+iri=s +: IeiEai1 o
in
-l,
i *iIi$
,\3
U
o
)ul t^9-
s g; *iFe*=iiiE3*'gfit*u-iT +=
g gF i6+iEfgr*iE*+;Ei:IEBil3
rssg$i[;iriiaen;*+Fli;iig e U
U
rn
z
ts
o N dE
+ ri
N zrn z
I
't
N
zln
I U
!')
.t
o
I
N r\
p
zln I
I
D
D.)
o + I
N r l.o
NJ
z
Lll
b
I
N
z
Lll
4I
N
z
LI]
I
U
f"
7i
J c :'. v{ p<
C-t
=, C- =:
--/.- !. ='=:
= -v a.= =. to)-
c =|<
= = a |-- =
IC D = C,'
c- '/
,tr
-aq =
b
a,
a ;>
G
=
=
-o
!
G+ a
C
=
IJ . =
O UJ D=
;u. =- q C
C
FJ =
-;' ,=.
= o
V L
a-
C
0. = tz_
_et
= = = =
-:, c-<
=A G
!='
@
o-
= C = = = F ;,
c-
a C
o
o p o=. c
a
a
a
=' a U U E' -,= =
-. U q !
a
IIL :
=.
=
G
!
o
3. i.: z -o..t
o
= c=.
a
= ^= T = - o
e- a
p =
o g-.
o -lf
€a -F'
c .= a
C
!)
= .D
AA th
(; <.a q a
a o =
t1 -, 1 =
? 6= I a ajt - =
o
a
- =-c
=c
a
o- - r_t
F6
= =' =
o
a- {.).t :l
a'-'
oa G
-o E.
!
+
=' o D a*
0a
0a
c --' o o-
o
aa 9. a
o C = h E
o a = -o c -O o
o
q !, --a
c+, n z' G =
-o oo UA
ti
a
o
a a GC_ o- _o F' o
-+) -o o- o -tr
o a a=' t-!
cd @ ;
;' (D
a = (D o
o-c G c
q)
(D
a p
o
=
a I
o-
lJ
,)' E'
o o-
6
& = F' c
a =. @ ='-
a P o-
o
o ='@ +O
::1 o
Ia a o
io
C - o
o e C. ..
-t=
=. c
.D o=. Cr.
0. !J 5F'
=
c- o
a
a = o
C :n -El
-o o- o
c-* -a
I+
tt
.D 0a p t)c -n
9. o = oi -o"'
=^1
(D
la -l
d
a o o
=
o =='
O-@ -
? ? 7 ? e
H :r B -
d
NJ
)v )tl N
o )+1 )14
P H ts P
NJ P
O
5
@
O
!
F
u) zrn
b
o b
o o b
b O I
N
)t A )t )q
H P P P z
P 5 o
!
F
tll
O 90
UJ
b o o b
I
o o o
N
.)* )l )!1 )11
P
L
(! P
P
P
5
@
P
o
!
F (JJ
z
P Lrl
o o b
b I
F) 9J
iJ O O O o
N ch
)t4 )ll )q )t
P
P
o
P
5
P
o
{
P
F
L^J
z
Lll
90
o o b
b I
o o o
qo gl
-o
@' N
o
) o
(o
o,
zln
I
\
Memo No.1 L\2g 8o/ft I \3 Dare I q-f lz'[ 2 -o 2't
If
ADDENDU]\I NO. - 2
WBPHED SCHEDULE OF RATES (CryIL WORKS), JULY,2O19
Manufactures must proride tfrira party inspection report from PHE authorised
Laboratory.
Materials grade of stainless steel made with SS316
a) 5 LPM discharge @ 0.5 bar pressure. Each 157 00
b) 1-0 LPM discharge @ 0.5 bar pressure. Each 166.00
& Ch ngineer
Planning Circle-|, PHE Dte. Planning & WQM, PHE Dte,
CORRIGENDUM N
WBPHED SCHEDULE OF RATES (CrVIL WORKS), IULY,2019
SOR OF FHTC (FUNCTIONAL HOUSEHOLD TAP CONN
Item
Description of item Unit Rate (Rs.)
No.
1 For New FHTC
1.1 Providing FHTC from the existing CIIDIIuPVCIHDPE/Gl/AC distribution pipeline by
installing 10 mm NB Gun-metal Ferrule conforming to lS 2692:1989 with latest
amendments on the said pipeline with supply, fitting & flxing of all other accessories like
saddle piece of required size to fit the existing distribution pipeline, specials, nut & bolts,
rubber sheet, washers etc and supply & laying of 15mm NB PVC (schedule 80)/20mm OD
HDPE (PE100, PN16)/20mm OD PPR-C (Class - SDR7.4 / PN16) pipe (average 15m length)
with all necessary specials l-.0 metre below the ground connecting the ferrule/flow
control valve including cutting trenches in all sorts of soil and filling up trenches as per
direction of the Engineer-in-charge and upto a point just inside the premises of the
household or as directed by ElC. Supply and installation of a 15mm dia. alloy iron Bib
Cock (tested to 2L Kglcm2) above 1.0 Mtr. from ground, an alloy Stop Cock of 15 mm
dia. with brass spindle (tested to 21 Kg/cm2) to be fitted in a position as directed by
E.l.C. G.l pipe of TATA make (medium duly) of 2 metre length with all necessary specials
/PPR-C pipe and upto 1.0 m above ground
Chairman, tee
& Superintending Engineer
Planning Circle-1, PHE Dte. Planning & WQM, PHE Dte.