III CONCRETING WORKS (NOTE: All weights are in KILOGRAMS and lengths are in METERS, otherwise specified)
L W D Volume bags/cu.m.
3.1.1.4 SLAB ON GRADE AREA 1 3.90 2.00 0.10 0.78 12.00 9.36 1.00 1.00 1.03 9.36 56.00 bag/s -
AREA 2 6.00 3.00 0.10 1.80 12.00 21.60 1.00 1.00 21.60
AREA 3 5.00 3.00 0.10 1.50 12.00 18.00 1.00 1.00 18.00
AREA 4 2.10 2.00 0.10 0.42 12.00 5.04 1.00 1.00 5.04
L W D Volume bags/cu.m.
3.1.1.5 SUSPENDED SLAB SECOND FLOOR AREA 1 5.00 3.90 0.10 1.95 12.00 23.40 1.00 1.00 1.03 23.40 63.00 bag/s -
SECOND FLOOR AREA 2 6.50 3.50 0.10 2.28 12.00 27.30 1.00 1.00 27.30
CANOPY 20CM FRONT 6.30 0.50 0.20 0.63 12.00 7.56 1.00 1.00 7.56
CANOPY 20CM RIGHT SIDE 2.90 0.30 0.20 0.17 12.00 2.09 1.00 1.00 2.09
B D H Volume bags/cu.m.
3.1.1.6 COLUMNS (GROUND FLOOR) C1 0.25 0.40 4.40 0.44 12.00 5.28 6.00 1.00 1.03 31.68 49.00 bag/s -
C2 0.25 0.40 4.40 0.44 12.00 5.28 3.00 1.00 15.84
B D H Volume bags/cu.m.
3.1.1.7 COLUMNS (SECOND FLOOR) C1 (A) 0.25 0.40 2.10 0.21 12.00 2.52 2.00 1.00 1.03 5.04 33.00 bag/s -
C2 (A) 0.25 0.40 2.10 0.21 12.00 2.52 1.00 1.00 2.52
C1 (B) 0.25 0.40 2.68 0.27 12.00 3.22 1.00 1.00 3.22
C2 (B) 0.25 0.40 2.68 0.27 12.00 3.22 1.00 1.00 3.22
C1 (C) 0.25 0.40 3.63 0.36 12.00 4.36 3.00 1.00 13.07
C2 (C) 0.25 0.40 3.63 0.36 12.00 4.36 1.00 1.00 4.36
L B D Volume bags/cu.m.
3.1.1.8 SECOND FLOOR BEAMS 2B1 11.25 0.30 0.45 1.52 12.00 18.23 1.00 1.00 1.03 18.23 72.00 bag/s -
2B2 4.60 0.25 0.45 0.52 12.00 6.21 1.00 1.00 6.21
2B3 13.20 0.20 0.40 1.06 12.00 12.67 1.00 1.00 12.67
2B4 30.44 0.20 0.40 2.44 12.00 29.22 1.00 1.00 29.22
2CB1 3.30 0.20 0.45 0.30 12.00 3.56 1.00 1.00 3.56
L B D Volume bags/cu.m.
3.1.1.9 ROOF BEAMS RB1 40.74 0.20 0.40 3.26 12.00 39.11 1.00 1.00 1.03 39.11 41.00 bag/s -
W L D Volume bags/cu.m.
3.1.1.11 COUNTERTOPS GROUND FLR COUNTERTOP 1 0.64 2.90 0.10 0.18 12.00 2.21 1.00 1.00 1.03 2.21 4.00 bag/s -
GROUND FLR COUNTERTOP 2 0.50 1.80 0.10 0.09 12.00 1.08 1.00 1.00 1.08
L W D Volume bags/cu.m.
3.1.1.12 CANOPY CANOPY (W2) 5.50 0.50 0.10 0.28 12.00 3.30 1.00 1.00 1.03 3.30 6.00 bag/s -
CANOPY (W3) 1.80 0.50 0.10 0.09 12.00 1.08 1.00 1.00 1.08
CANOPY (D2) 1.50 0.40 0.10 0.06 12.00 0.72 1.00 1.00 0.72
3.1.2 Washed Sand (S-1) L W D Volume cu.m./cu.m.
3.1.2.1 FOUNDATION FOOTINGS F1 1.90 1.70 0.30 0.97 0.50 0.48 1.00 1.00 1.03 0.48 3.47 m3 -
F2 1.80 1.65 0.30 0.89 0.50 0.45 1.00 1.00 0.45
F3 1.70 1.50 0.30 0.77 0.50 0.38 2.00 1.00 0.77
F4 1.60 1.45 0.30 0.70 0.50 0.35 3.00 1.00 1.04
F5 1.55 1.40 0.30 0.65 0.50 0.33 1.00 1.00 0.33
F6 1.50 1.35 0.30 0.61 0.50 0.30 1.00 1.00 0.30
L W D Volume cu.m./cu.m.
3.1.2.4 SLAB ON GRADE AREA 1 3.90 2.00 0.10 0.78 0.50 0.39 1.00 1.00 1.03 0.39 2.32 m3 -
AREA 2 6.00 3.00 0.10 1.80 0.50 0.90 1.00 1.00 0.90
AREA 3 5.00 3.00 0.10 1.50 0.50 0.75 1.00 1.00 0.75
AREA 4 2.10 2.00 0.10 0.42 0.50 0.21 1.00 1.00 0.21
L W D Volume cu.m./cu.m.
3.1.2.5 SUSPENDED SLAB SECOND FLOOR AREA 1 5.00 3.90 0.10 1.95 0.50 0.98 1.00 1.00 1.03 0.98 2.59 m3 -
SECOND FLOOR AREA 2 6.50 3.50 0.10 2.28 0.50 1.14 1.00 1.00 1.14
CANOPY 20CM FRONT 6.30 0.50 0.20 0.63 0.50 0.32 1.00 1.00 0.32
CANOPY 20CM RIGHT SIDE 2.90 0.30 0.20 0.17 0.50 0.09 1.00 1.00 0.09
B D H Volume cu.m./cu.m.
3.1.2.6 COLUMNS (GROUND FLOOR) C1 0.25 0.40 4.40 0.44 0.50 0.22 6.00 1.00 1.03 1.32 2.04 m3 -
C2 0.25 0.40 4.40 0.44 0.50 0.22 3.00 1.00 0.66
B D H Volume cu.m./cu.m.
3.1.2.7 COLUMNS (SECOND FLOOR) C1 (A) 0.25 0.40 2.10 0.21 0.50 0.11 2.00 1.00 1.03 0.21 1.35 m3 -
C2 (A) 0.25 0.40 2.10 0.21 0.50 0.11 1.00 1.00 0.11
C1 (B) 0.25 0.40 2.68 0.27 0.50 0.13 1.00 1.00 0.13
C2 (B) 0.25 0.40 2.68 0.27 0.50 0.13 1.00 1.00 0.13
C1 (C) 0.25 0.40 3.63 0.36 0.50 0.18 3.00 1.00 0.54
C2 (C) 0.25 0.40 3.63 0.36 0.50 0.18 1.00 1.00 0.18
L B D Volume cu.m./cu.m.
3.1.2.8 SECOND FLOOR BEAMS 2B1 11.25 0.30 0.45 1.52 0.50 0.76 1.00 1.00 1.03 0.76 3.00 m3 -
2B2 4.60 0.25 0.45 0.52 0.50 0.26 1.00 1.00 0.26
2B3 13.20 0.20 0.40 1.06 0.50 0.53 1.00 1.00 0.53
2B4 30.44 0.20 0.40 2.44 0.50 1.22 1.00 1.00 1.22
2CB1 3.30 0.20 0.45 0.30 0.50 0.15 1.00 1.00 0.15
L B D Volume cu.m./cu.m.
3.1.2.9 ROOF BEAMS RB1 40.74 0.20 0.40 3.26 0.50 1.63 1.00 1.00 1.03 1.63 1.68 m3 -
W L D Volume cu.m./cu.m.
3.1.2.11 COUNTERTOPS GROUND FLR COUNTERTOP 1 0.64 2.90 0.10 0.18 0.50 0.09 1.00 1.00 1.03 0.09 0.14 m3 -
GROUND FLR COUNTERTOP 2 0.50 1.80 0.10 0.09 0.50 0.05 1.00 1.00 0.05
L W D Volume cu.m./cu.m.
3.1.2.12 CANOPY CANOPY (W2) 5.50 0.50 0.10 0.28 0.50 0.14 1.00 1.00 1.03 0.14 0.21 m3 -
CANOPY (W3) 1.80 0.50 0.10 0.09 0.50 0.05 1.00 1.00 0.05
CANOPY (D2) 1.50 0.40 0.10 0.06 0.50 0.03 1.00 1.00 0.03
3.1.3 Gravel 3/4 L W D Volume cu.m./cu.m.
3.1.3.1 FOUNDATION FOOTINGS F1 1.90 1.70 0.30 0.97 1.00 0.97 1.00 1.00 1.03 0.97 6.94 m3 -
F2 1.80 1.65 0.30 0.89 1.00 0.89 1.00 1.00 0.89
F3 1.70 1.50 0.30 0.77 1.00 0.77 2.00 1.00 1.53
F4 1.60 1.45 0.30 0.70 1.00 0.70 3.00 1.00 2.09
F5 1.55 1.40 0.30 0.65 1.00 0.65 1.00 1.00 0.65
F6 1.50 1.35 0.30 0.61 1.00 0.61 1.00 1.00 0.61
L W D Volume cu.m./cu.m.
3.1.3.4 SLAB ON GRADE AREA 1 3.90 2.00 0.10 0.78 1.00 0.78 1.00 1.00 1.03 0.78 4.64 m3 -
AREA 2 6.00 3.00 0.10 1.80 1.00 1.80 1.00 1.00 1.80
AREA 3 5.00 3.00 0.10 1.50 1.00 1.50 1.00 1.00 1.50
AREA 4 2.10 2.00 0.10 0.42 1.00 0.42 1.00 1.00 0.42
L W D Volume cu.m./cu.m.
3.1.3.5 SUSPENDED SLAB SECOND FLOOR AREA 1 5.00 3.90 0.10 1.95 1.00 1.95 1.00 1.00 1.03 1.95 5.18 m3 -
SECOND FLOOR AREA 2 6.50 3.50 0.10 2.28 1.00 2.28 1.00 1.00 2.28
CANOPY 20CM FRONT 6.30 0.50 0.20 0.63 1.00 0.63 1.00 1.00 0.63
CANOPY 20CM RIGHT SIDE 2.90 0.30 0.20 0.17 1.00 0.17 1.00 1.00 0.17
B D H Volume cu.m./cu.m.
3.1.3.6 COLUMNS (GROUND FLOOR) C1 0.25 0.40 4.40 0.44 1.00 0.44 6.00 1.00 1.03 2.64 4.08 m3 -
C2 0.25 0.40 4.40 0.44 1.00 0.44 3.00 1.00 1.32
B D H Volume cu.m./cu.m.
3.1.3.7 COLUMNS (SECOND FLOOR) C1 (A) 0.25 0.40 2.10 0.21 1.00 0.21 2.00 1.00 1.03 0.42 2.70 m3 -
C2 (A) 0.25 0.40 2.10 0.21 1.00 0.21 1.00 1.00 0.21
C1 (B) 0.25 0.40 2.68 0.27 1.00 0.27 1.00 1.00 0.27
C2 (B) 0.25 0.40 2.68 0.27 1.00 0.27 1.00 1.00 0.27
C1 (C) 0.25 0.40 3.63 0.36 1.00 0.36 3.00 1.00 1.09
C2 (C) 0.25 0.40 3.63 0.36 1.00 0.36 1.00 1.00 0.36
L B D Volume cu.m./cu.m.
3.1.3.8 SECOND FLOOR BEAMS 2B1 11.25 0.30 0.45 1.52 1.00 1.52 1.00 1.00 1.03 1.52 6.00 m3 -
2B2 4.60 0.25 0.45 0.52 1.00 0.52 1.00 1.00 0.52
2B3 13.20 0.20 0.40 1.06 1.00 1.06 1.00 1.00 1.06
2B4 30.44 0.20 0.40 2.44 1.00 2.44 1.00 1.00 2.44
2CB1 3.30 0.20 0.45 0.30 1.00 0.30 1.00 1.00 0.30
L B D Volume cu.m./cu.m.
3.1.3.9 ROOF BEAMS RB1 40.74 0.20 0.40 3.26 1.00 3.26 1.00 1.00 1.03 3.26 3.36 m3 -
W L D Volume cu.m./cu.m.
3.1.3.11 COUNTERTOPS GROUND FLR COUNTERTOP 1 0.64 2.90 0.10 0.18 1.00 0.18 1.00 1.00 1.03 0.18 0.28 m3 -
GROUND FLR COUNTERTOP 2 0.50 1.80 0.10 0.09 1.00 0.09 1.00 1.00 0.09
- - - -
L W D Volume cu.m./cu.m.
3.1.3.12 CANOPY CANOPY (W2) 5.50 0.50 0.10 0.28 1.00 0.28 1.00 1.00 1.03 0.28 0.44 m3 -
CANOPY (W3) 1.80 0.50 0.10 0.09 1.00 0.09 1.00 1.00 0.09
CANOPY (D2) 1.50 0.40 0.10 0.06 1.00 0.06 1.00 1.00 0.06
L W D Volume cu.m./cu.m.
3.1.3.13 GRAVEL BED F1 1.90 1.70 0.10 0.32 1.00 0.32 1.00 1.00 1.03 0.32 7.12 m3 -
F2 1.80 1.65 0.10 0.30 1.00 0.30 1.00 1.00 0.30
F3 1.70 1.50 0.10 0.26 1.00 0.26 2.00 1.00 0.51
F4 1.60 1.45 0.10 0.23 1.00 0.23 3.00 1.00 0.70
F5 1.55 1.40 0.10 0.22 1.00 0.22 1.00 1.00 0.22
F6 1.50 1.35 0.10 0.20 1.00 0.20 1.00 1.00 0.20
AREA 1 3.90 2.00 0.10 0.78 1.00 0.78 1.00 1.00 0.78
AREA 2 6.00 3.00 0.10 1.80 1.00 1.80 1.00 1.00 1.80
AREA 3 5.00 3.00 0.10 1.50 1.00 1.50 1.00 1.00 1.50
SEPTIC TANK 3.45 1.70 0.10 0.59 1.00 0.59 1.00 1.00 0.59
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
-
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
-
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
PhP -