TO DO LIST - 2022
Description
Monthly Stoppage Job List - Jan 2022
Work Instructions for area operators for additions of jobs at last page of log book.
Work Instructions for ensuring water flushing of AN line from 174 - 100 F during one day stoppage / longer
shutdown period.
JSA of internal cleaning of Slurry tanks.
SR is approved
Completed
Completed
In Progress
In Progress
TA-22 Pending
In Progress
Completed
Completed
Extra Jobs for 2022 Achievements
Sr. No. Description
1 Putting strict control and focus on Lime water recycling which will reduce lime slippage in drain channel by 10%,
throughout the year.
2 Rectification of hoods of VBF-A/C/D for improving work environment.
Achieve Level 3 In 1st party audit by creating awareness in more than 90% of employees by imparting at least 01
3 awareness session per month as per developed plan throughout the year. CAN Unit Nominate the OHIH
champion and issue training plan by end of Q-1.
5 Aligning the practices with UMM – 2021 and strengthen the systems at CAN Plant.
6 Hazards reporting to be improved through Hazard reporting cards. At least 250 hazards to be identified & rectified
till Q-4. (50 / each SIC)
7 Training of employees on FG AN safety standard at unit level. Arrange training session in each shift group (Total
04 sessions).
SR to be raised for study of utilization of 15-2112 for ammonia evaporation circuit to meet ammonia
8
requirement.
9 Revival of ammonia nozzles of CN pre-neutralizers as per design.
10 Study to be done for temperature improvement of Ammonia & Nitric acid feed to D/N reactor for concentration
improvement.
11 AN & Moisture content in wet lime to be reduced by 5-10% of current values.
12 Checklist against relevant work procedures to be developed till Q-3.
13 Cleaning of 15-2002 to be done on at least quarterly basis.
14 Study for re-routing the overflow lines of CN reactor - A & B.
15 Lime bin de-dusting filters revival.
16 Raise SR for Study of revival of ratio control loop on CN reactor – A & B.
17 SR to be raised for Study of provision of pH control loop on Pre-neutralizers (to control pH of CN feed to CN
reactor).
18 List of Steam circuit piping to be developed prone to corrosion due to acidic fumes in Q#1 especially AN
evaporation & Prilling section. 20% to be replaced in 2022.
19 Insulation health assessment of AN line to FFE’s to be carried out. During TA check the AN line through
boroscopy for any scaling observation.
Modification of Platform for Preventive Maintenance, Electric Motors dismantling / fitting and Oil replacement of
20 Agitators installed at AN Solution Tank 17-2009, Slurry Tanks 17-2004 & 2024 and Pre-Neutralizer Tanks 17-2003
& 17-2023 at 106 Floor.
21 Health assessment of wooden planks of VBF-A/B platform to be done in Q-1. Report to be prepared & share with
civil.
22 SR to be raised for installation of PG/PT on first stage AN separator to study the impact of system pressurization
on increased load of AN evaporation of 1st stage separator.
23 Liquid ammonia circuit of NH3 circuit of 15-1003 battery to be inspected.
24 Remote access of CAN & CN Recorders for better monitoring.
25 Up-gradation of Staff room & wash rooms at 113-F.
26 Revival of VBF-B.
27 Installation of cameras for plant vents monitoring.
Assigned to
MINUTES OF MEETING IN SPM OFFICE
DATED: 23-02-2022 (1200 - 1400 hrs)
Participants: Abdul Ghaffar, Hyder Ali, Sohail Sharif & Shehzad Afzal
Sr.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
20
21
22
MINUTES OF MEETING IN SPM OFFICE
DATED: 23-02-2022 (1200 - 1400 hrs)
Participants: Abdul Ghaffar, Hyder Ali, Sohail Sharif & Shehzad Afzal
Actions Detail
New cladding to be installed at locations where possible.
Alarms analysis to be shared, gaps to be highlighted. Priority to be shared.
Consumption for meals during One day stoppages TBD from separate budget head.
Pavement of plant areas to be done.
Alarms to be highlighted in PREP forum.
Carseal valves to be marked on P&ID.
Crictical valves to be made carseal.
Isolation Plans to be standardized (Charles Taylor Recommendation).
Cabinets for full face masks placement to be done from tools budget head.
Organogram to be updated.
Gap analysis of missing instrumentation to be done, to be compared with design.
Instrumentation loops requirement on heat maps to be provided.
Benchmark the analyzers installed at FFL plants of NP & CAN.
Operation of Parallel CN reactors.
Procedures development plan should be risk wise. (High risk to be prepared first. Then
Medium & Low)
List of critical MOC's to be discussed.
Highlight the best trade apprentice for early confirmation. Approval through IR.
Manning Data to be shared separately.
E
Target Resp.
Next Week
HA
HA
SS
SS
SS
SS/MUR
Next Week SS
3/4/2022
ND SS
3/4/2022 SS