Project Execution Plan
Project Execution Plan
Project Execution Plan
Page 1 on 56
TABLE OF CONTENTS
CHAPITRE 1 : INTRODUCTION................................................................................................................... 4
GENERAL: .................................................................................................................................................. 4
ABBREVIATIONS: ..................................................................................................................................... 4
GOAL: .......................................................................................................................................................... 4
CONTEXT ................................................................................................................................................... 4
PROJECT PRESENTATION: ..................................................................................................................... 6
BRIEF DESCRIPTION OF THE PROJECT: ..............................................................................................7
SCOPE OF PROJECT WORK: ................................................................................................................... 8
PROJECT SCHEDULE: ..............................................................................................................................8
CHAPITRE 2 : PHASING OF THE PROJECT ........................................................................................... 11
PHASING WORKS ................................................................................................................................... 11
CHAPITRE 3 : PREPARATION ACTIVITIES ........................................................................................... 14
CONSTRUCTION SITE INSTALATION: ...............................................................................................14
LANDISCAPING AND IMPLEMENTATION:................................................................................ 14
SITE OFFICES ................................................................................................................................... 15
STORAGE AREA AND WORKSHOPS: .......................................................................................... 17
PREPARATORY WORK .......................................................................................................................... 21
TOPOGRAPHIC SURVEY: .............................................................................................................. 21
PROJECT POLYGONAL PLACEMENT ......................................................................................... 21
DELIMITATION OF EXISTING NETWORKS CROSSING: ......................................................... 21
STRIPPING OF TOPSOIL AND SHRUBS: ..................................................................................... 24
DEVIATION FROM PROVISIONAL TO FINAL NETWORKS .................................................... 26
WATER DISCHARGE CHANNEL: ......................................................................................................... 30
CHAPITRE 4 : PRELIMINARY ENGINEERING & PROCURMENT PHASE ..................................... 32
CIVIL ENGINEERING STUDY AND CALCULATIONS: .....................................................................32
PROCUREMENT PHASE: ....................................................................................................................... 34
PROCUREMENT OF ALL EQUIPMENTS AND EICA WORKS FOR BOTH INDUSTRIAL
LINE AND COMMON STRUCTURES ........................................................................................................... 34
PROCUREMENT OF ALL EQUIPMENTS AND EICA WORKS FOR BOTH URBAN LINE ..... 36
CHAPITRE 5 : INDUSTRIAL LINE CONSTRUCTION WORKS ........................................................... 37
PRELIMINARY ARRANGEMENTS: ...................................................................................................... 37
EARTHWORKS:................................................................................................................................ 37
FOUNDATIONS: ............................................................................................................................... 37
INSTALLATION OF PIPES AND UNDERGROUND INSTALLATIONS: ................................... 37
NEW CONSTRUCTIONS: ........................................................................................................................ 38
FORMWORK AND FORMWORK REMOVAL: ............................................................................. 38
Page 2 on 56
CONCRETE ....................................................................................................................................... 38
REINFORCEMENT: .......................................................................................................................... 38
REHABILITATION OF EXISTING STRUCTURES: ............................................................................. 39
CIVIL WORK PROGRAM FOR THE INDUSTRIAL LINE: .................................................................. 39
MECHANICAL WORK PROGRAM FOR THE INDUSTRIAL LINE: .................................................. 42
EICA WORK PROGRAM FOR THE INDUSTRIAL LINE: ...................................................................44
CHAPITRE 6 : URBAN LINE CONSTRUCTION WORKS ...................................................................... 46
CIVIL WORK PROGRAM FOR THE URBAN LINE: ............................................................................ 46
MECHANICAL WORK PROGRAM FOR THE URBAN LINE: ............................................................ 48
EICA WORK PROGRAM FOR THE INDUSTRIAL LINE: ...................................................................50
CHAPITRE 7 : DEMOLITION OF EXISTING STRUCTURES ............................................................... 52
CHAPITRE 8 : QUALITY CONTROL ......................................................................................................... 53
RESPONSIBILITIES: ................................................................................................................................ 53
QUALITY CONTROL PLAN (QCP) .......................................................................................................54
INSPECTIONS AND RECORDS ............................................................................................................. 54
CHAPITRE 9 : HEALTH SAFETY ENVIRONMENT ............................................................................... 55
RESPONSIBILITY: ...................................................................................................................................55
REPORTS / MEETINGS AND HSE ADVICE: ........................................................................................ 56
ENVIRONMENTAL CONTROL: ............................................................................................................ 56
Page 3 on 56
CHAPITRE 1 : INTRODUCTION
GENERAL:
The purpose of this document is to describe the plan of PASSAVANT ENERGY & ENVIRONMENT
for the execution of “THE REHABILITATION AND EXTENSION OF THE SUD MELIANE II WWTP”.
This project includes in the first phase, the rehabilitation and extension of the WWTP SUD
MELIANE II and in the second phase, the demolition of the WWTP SUD MELIANE I.
This document covers the PEE plan, for the implementation phasing of the Civil Engineering part of
this project.
ABBREVIATIONS:
GOAL:
The purpose of this document is to describe the PEE plan, methodologies, strategies and schedule
for project implementation. This plan identifies pre-construction activities and summarizes key
activities during project execution.
CONTEXT
The National Sanitation Office ONAS officially launched the rehabilitation and extension works of
the SUD Meliane wastewater treatment plant in Rades. This work is a part of the depollution
program for the Mediterranean, DEPOLMED, co-financed by the French Development Agency
FDA, the European Union EU and the European Investment Bank EIB.
Page 4 on 56
The objective of this DEPOLMED program is to contribute to the preservation of the quality of the
waters of the Tunisian coast by reducing water pollution. It plans to rehabilitate and extend the
following 4 purification stations:
Page 5 on 56
PROJECT PRESENTATION:
The planned demolition and reconstruction of the SM I module will be carried out on the current
site of the SUD Meliane station. The SUD Meliane WWTP is located in Rades, in the
governorate of Ben Arous.
Its location corresponds to a latitude of 36 ° 44'29.89 "N and a longitude of 10 ° 16'0.35" E. The
discharge of water purified by the WWTP is done directly at the level of the Oued Meliane, 4 km
upstream from the outlet in the small Gulf of Tunis.
The project site is limited by a close perimeter as follows:
- The national road N1
- The grappled water treatment plant
- The outlet for treated wastewater; Oued Meliane and Golf de Tunis
- The Olympic stadium and the forest of Rades
OLYMPIC STADIUM OF
RADES
RADES FOREST
NATIONAL ROAD N1
GRAPPLED STATION
GRAPPLED STATION
RADES WWTP
OUED MELIANE
Page 6 on 56
BRIEF DESCRIPTION OF THE PROJECT:
The SUD MELIANE purification center essentially consists of two WWTPs; SMI & SMII with a
total capacity equal to 75,700 m3 / d.
The project consists of the rehabilitation and extension of the SMII station to have a total
capacity of around 90,000 m3 / d which will be delivered by two separate treatment lines.
Page 7 on 56
SCOPE OF PROJECT WORK:
PROJECT SCHEDULE:
The baselines of the timeline for this project are 36 months. This period includes all the services of the
studies of the technical, specific design and execution of the rehabilitation and extension works of the
SUD MELIANE II wastewater treatment plant, the commissioning phase and the trial period phase.
This 36 months period will be distributed as follows:
- Civil engineering phase: 2022 for both lines industrial and urban.
- Construction work phase
- Commissioning phase
- Trial period phase
Page 8 on 56
For Civil engineering phase: 6 months starting from JANUARY 20, 2022 to JULY 20, 2022 for both lines
industrial and urban.
Regarding the other phases will be:
Page 9 on 56
Start Finish
JANUARY 20, 2022 CIVIL ENGINEERING PHASE DECEMBER 31,
2024
JANUARY 20, 2022
JULY 20, 2022
COMMISSIONING
PHASE IL
JULY 01,2023
SEPTEMBER 30, 2023
TRIAL PERIOD IL
OCTOBER 01, 2023
DECEMBER 31, 2023
COMMISSIONING
PHASE UL
JULY 01, 2024
SEPTEMBER 30, 2024
TRIAL PERIOD - UL
OCTOBER 02, 2024
DECEMBER 31, 2024
Page 10 on 56
CHAPITRE 2 : PHASING OF THE
PROJECT
The Work Schedule shows 4 distinct phases in order to not disrupt the operation of the existing SUD
Meliane I & II stations:
PHASING WORKS
Site facilities
Topographic and polygonal survey of the project
Inspection and surveying of existing structures (partial emptying)
Recognition of all underground networks (water, electricity, etc.)
Picketing, network marking
Network inspection and survey
Civil engineering calculations and dimensioning of structures
Preparatory earthworks
These works concern the construction of new structures on the industrial line as well as common ones with
the urban line which are necessary for the commissioning of this line.
This works covers different stages of construction;
Earthworks
Foundations
Superstructure (formwork, reinforcement and concreting)
Various networks (HDPE, GRP, PVC and Concrete)
Mechanical equipments installation & erection
EICA works installation
Page 11 on 56
As well as they cover the rehabilitation works of some existing structures of the SUD MELIANE II station.
The work program for this phase will be as follows and it will be detailed later in "Chapter 4:
Construction works of the industrial line"
These works concern the construction of the rest of the new works of the urban line.
As well as the rehabilitation of some existing structures of the SUD MELIANE II station.
The work program for this phase will be as follows and it will be detailed later in "Chapter 5:
Construction works of the urban line"
Page 12 on 56
PHASE4: Demolition of existing structures
Page 13 on 56
CHAPITRE 3 : PREPARATION ACTIVITIES
The location of site facilities is selected to ensure a minimum of disturbances during the construction
of permanent structures. For this purpose, the site installation was chosen considering the ease of
accessibility to the site without disturbing the operation of existing structures.
The site of installation of the chosen construction site consists of a part of the drying beds of the
SUD Meliane WWTP not currently used on the east side of the entrance to the WWTP.
The site installation and organization plan relating to the rehabilitation and extension of the SUD
Meliane II wastewater treatment plant contains the following elements:
- One equipment storage area by type: storage area for new equipment and another for
dismantled equipment.
- A storage area for the materials required for the construction of new hydraulic structures.
- A traffic plan showing the path that will be followed (machinery, vehicles, pedestrians) during the
transfer of materials or waste, without causing a traffic problem within the WWTP and or in the
surrounding area.
- Signs (vertical and horizontal signs) warning of the presence of a work zone and exit of
construction machinery, before a few tens of meters from the purification center and within it.
- A machine park lot area
- A vehicle park lot area
- A sanitary installation and any other protective measure.
- Site offices
Page 14 OF 56
Site offices
The offices are installed at the entrance of the site to ensure the staff a minimum of comfort and hygiene
during the work, to accommodate the various site meetings, suppliers and subcontractors. Also allow the
storage of tools and small equipment.
The main premises are the offices, meeting room, sanitary facilities, WC.
The number of rooms and their surface area depend on the type of site.
We consider three types of site:
Type 1 Site less than 15 days regardless of the number of workers, or from 15 days to 4
months up to 20 workers
The offices will be installed according to the site installation plans. They include:
Page 15 OF 56
Page 16 OF 56
Storage area and workshops:
The installation of a concrete plant on site is not to be expected, the supply will be directly by certified and
authorized concrete plants with a diameter of around 15 km.
Also, the SIP does not provide for a machine washing and maintenance station. In fact, these tasks will be
carried out in stations near the wastewater treatment plant.
The SIP, show the crane towers locations, we will have 4 crane towers for the two phases of the project.
- First phase: Crane towers location for the construction of the industrial line. (see attached SIP)
- Second phase: Crane towers location for the construction of the industrial line. (see attached SIP)
Page 17 OF 56
Page 18 OF 56
Page 19 OF 56
SITE OFFICES
Page 20 OF 56
PREPARATORY WORK
Topographic survey
The delimitation and the marking of existing networks crossing which
constitute an obstacle with the new structures
Project polygonal placement
Stripping topsoil and shrubs
Deviation from provisional networks to final networks.
Implementation of the new rejection channel
Topographic survey:
A topographic survey of the site will be carried out to specify the existing situation of the
site.
A contradictory verification of general dimensions on the drawings with the site
implementation, in particular compared to the limits of parcels, existing buildings and
location of networks in place.
The establishment of the base polygonal will be linked to the general leveling of Tunisia.
Level marks attached to the general markers will be placed near and in the right-of-way
of the stations. A drawing showing the location of these bench marks and their
dimensions will be provided.
In the preliminary phase, it is imperative to identify all the existing underground networks
and the intersections between them which may be subject of a constraint during the
execution.
Marking is mandatory before starting work. It identifies the location of the networks and
must be maintained along the duration of the work.
During the identification of the existing networks, it turned out that some network pipes do
not work as shown in the project’s general layout.
Page 21 on 56
Considering the following existing networks pipes as shown in the project’s general layout:
Network N°1 DN1000 : Arrival from lifting station SR2 to SMI (Industrial line)
Network N°2 DN1000 concrete : By pass to emergency basin
Network N°3 DN1000 concrete : Arrival from SMI to SMII
Network N°4 DN1000 concrete : By pass to emergency basin
Network N°5 DN800 concrete : By pass SMII from lifting station SR2
Network N°6 DN500 concrete :Discharge for purified water from the industrial
WWTP
Page 22 OF 56
Page 23 on 56
Stripping of topsoil and shrubs:
Earthworks will be carried out with suitable mechanical means. Earthworks include:
- Brush clearing, weeding and uprooting of shrubs over the entire area
where the new works will be carried out
Page 24 on 56
- Stripping topsoil at least 30 cm thick
Page 25 OF 56
Deviation from provisional to final networks
Page 26 OF 56
Page 27 on 56
After having defined and delimited the crossing of the existing networks, they must be
diverted since the station must be kept functional.
The lines will be replaced by others, always ensuring the same flow rate and the same
section of the pipes.
Note that Pipe N°5 and Pipe N°6 , stand in the way of the construction of some structures of
both line and industrial, the solution proposed by PEE is to,
Replace the Pipe N°6 by another one flowing purified water directly in the new
discharge water channel from the industrial WWTP
Replace the pipe N°5 by another fly PEHD pipe flowing pumped water from the
SR2 to the SMII.
Page 28 on 56
Page 29 on 56
WATER DISCHARGE CHANNEL:
The discharge channel is a reinforced concrete channel of dimensions (2.00m / 1.60m) going up to
more than 513 m in length from the water reception structure until reaching the discharge channel in
a pit with a slope of around 0.4%.
This channel intersects with existing networks and with new modifications.
- Intersection Canal / existing networks:
the Bypass line to the SUD MELIANE II station (Φ800 in concrete) coming from
the SR2 pumping station
The line for discharging purified water from an industrial wastewater treatment
plant (cluster water station)
Name Location
Intersection water discharge channel / • the
Bypass line to the SUD MELIANE II station
(Φ800 in concrete) coming from the SR2
pumping station
Intersection water discharge channel / sludge line (02) 3xDN 200 / I442 PSA 06
1000 GRP / Floats (11)
Intersection water discharge channel / DN1600 to I240
Intersection water discharge channel / I442 PSA 06 1000 GRP
water discharge channel / Wastewater intersection (DN2000 from U261),
Page 30 on 56
Name Location
For water discharge channel intersections with the new networks, their identification is used to
properly plan reservations for pipes crossing the channel.
This is why its installation will be done by moving back from the point of contact with septic
discharge channel towards the reception structure.
Before the realization of this channel, it is necessary to identify, mark and plan all the networks
passing above and below this structure in order to avoid any overlap problem during construction.
Page 31 OF 56
CHAPITRE 4 : PRELIMINARY ENGINEERING &
PROCURMENT PHASE
We ensure the completion of the required study drawings according to the specifications and
specifications of the project.
According to the provisional schedule of the project, the study work is subdivided into the following
steps:
- Study and civil engineering calculations of the industrial line
- Study and civil engineering calculations of the urban line
The stages of the civil engineering study phase encompass the following tasks:
The deadlines for preparing civil engineering studies are as follows for the industrial line:
Work program for the realization of the Estimated Start date of GC GC study end date
industrial line duration studies
Industrial and urban pre-treatment structures
38 DAYS JANUARY 20, 2022 MARCH 08, 2022
205-210-219-I221-I222-I225
Industrial Primary Settling tanks I230
34 DAYS JANUARY 20, 2022 MARCH 02, 2022
Page 32 OF 56
The deadlines for preparing civil engineering studies are as follows for the Urban line:
Work program for the Estimated Start date of GC GC study end date
construction of the Urban line duration studies
Urban primary settling tanks U230
31 DAYS April 08, 2022 MAY 19, 2022
Urban Secondary Clarifiers U260 29 DAYS April 29, 2022 JUNE 06, 2022
Urban auxiliary Structures U261-
U231-U294-U440-U442-U443-U444- 29 DAYS May 20, 2022 JUNE 24, 2022
U815
Rehabilitation of operating building
710 16 DAYS April 19, 2022 MAY 10, 2022
Page 33 OF 56
PROCUREMENT PHASE:
For the procurement PEE should submit the technical documents to ONAS, for review and
approval, ONAS on his part has 5 to 6 days to approve the documents.
After ONAS approval PEE precedes to purchasing and EX-works for each equipment.
Regarding the supply to site, we will have 2 delivery times, one for the industrial line’s
equipments and common structure equipments, which lasts 3 months starting from December
2022 to February 2023.
The supply to site, for the urban line’s equipments also lasts 3 months starting from December
2023 to February 2024.
- First volley: procurement of all equipments and EICA works for both
industrial line and common structures
- Second volley: procurement of all equipments and EICA works for the
urban line
Procurement of all equipments and EICA works for both industrial line and
common structures
Submission of
EQUIPMENT /EICA WORKS technical document Delivery to site date
to ONAS date
Aeration Blower FEBRUARY 21, 2022 DECEMBER 31, 2022
Biofilter FEBRUARY 26, 2022 DECEMBER 31, 2022
Annexes Pipes And Fittings MARCH 04, 2022 DECEMBER 31, 2022
Dismantling Pieces MARCH 10, 2022 DECEMBER 31, 2022
Bolts And Nuts MARCH 16,2022 DECEMBER 31, 2022
Sealings MARCH 22, 2022 DECEMBER 31, 2022
Stainless Steel Parts MARCH 29, 2022 DECEMBER 31, 2022
Pipes Climps DECEMBER 31, 2022
APRIL 04, 2022
Bucket Crane APRIL 11, 2022 DECEMBER 31, 2022
Valves FEBRUARY 21, 2022 FEBRUARY 22, 2023
Penstocks February 28, 2022 February 16, 2023
Grit Blower March 05, 2022 February 23,2023
Diesel Tank March 12, 2022 February 28, 2023
Aeration System March 18, 2022 February 23, 2023
Coarse & Fine Screens, Conveyers, Grit
March 24, 2022 February 17, 2023
Classifiers, Compactors
Page 34 OF 56
Submission of
EQUIPMENT /EICA WORKS technical document to Delivery to site date
ONAS date
Gasholder, Gas Flare, Gas Dryer,
May 13, 2022 February 14, 2023
Siloxane Filter
Digester Equipment February 21, 2022 February 21, 2023
Boiler With Heating Equipment February 26, 2022 February 15, 2023
Pipe Manometers And Thermometers March 04, 2022 February 21, 2023
Scrappers And Picket Fence April 18, 2022 February 28, 2023
Centrifuges And Belt Thickeners April 23, 2022 February 22, 2023
Page 35 OF 56
Procurement of all equipments and EICA works for both urban line
Submission of
EQUIPMENT /EICA WORKS technical document Delivery to site date
to ONAS date
Penstocks February 28, 2022 February 14, 2024
Grit Blower March 05, 2022 February 22,2024
Diesel Tank March 12, 2022 February 26, 2024
Aeration System March 18, 2022 February 22, 2024
Coarse & Fine Screens, Conveyers, Grit
March 24, 2022 February 15, 2024
Classifiers, Compactors
Gasholder, Gas Flare, Gas Dryer,
Siloxane Filter May 13, 2022 February 10, 2024
Digester Equipment
February 21, 2022 February 20, 2024
Boiler With Heating Equipment
February 26, 2022 February 13, 2024
Pipe Manometers And Thermometers March 04, 2022 February 20, 2024
Scrappers And Picket Fence April 18, 2022 February 26, 2024
Centrifuges And Belt Thickeners April 23, 2022 February 20, 2024
Polymer Dosing Station APRIL 29, 2022 FEBRUARY 13, 2024
Compressor For Airlift Pump MAY 10, 2022 FEBRUARY 23, 2024
Gas Booster Blower MAY 17, 2022 FEBRUARY 16, 2024
Gas Analyzer MAY 23, 2022 FEBRUARY 23, 2024
Gas Detection System MAY 30, 2022 FEBRUARY 23, 2024
Centrifugal Pumps And Mixers MARCH 29, 2022 FEBRUARY 26, 2024
Eccentric Screw Pumps APRIL 04, 2022 FEBRUARY 24, 2024
Desulphurization APRIL 11, 2022 FEBRUARY 24, 2024
CHP Unit APRIL 16, 2022 FEBRUARY 13, 2024
EICA Works MAY 31, 2022 FEBRUARY 19, 2024
Other (SmalL Equipment) JULY 07, 2022 FEBRUARY 20, 2024
Other (Big Equipment) JULY 15, 2022 FEBRUARY 24, 2023
Containers (tertiary plant) JULY 21, 2022 FEBRUARY 24, 2024
DISC FILTER JULY 28, 2022 FEBRUARY 26, 2024
UV DISINFECTION JULY 28, 2022 FEBRUARY 26, 2024
Page 36 OF 56
CHAPITRE 5 : INDUSTRIAL LINE
CONSTRUCTION WORKS
Considering the constraint of maintaining two functional SM I and SM II stations during the
construction period, the work program is to begin the construction of the entire industrial line
including the rehabilitation works and common structures necessary for its operation, with
some works of the urban line after switching to the construction of urban line.
After commissioning of the Industrial line, flows will be balanced on this line and work on the
urban line can begin.
The stages of carrying out work on the industrial line are as follows:
PRELIMINARY ARRANGEMENTS:
Earthworks:
The earthworks concern the earthworks necessary for the construction of reinforced concrete
structures and those necessary for the construction of underground networks and roads.
The earthwork methodology as well as the techniques and tools envisaged are the subject of
an execution procedure "earthworks execution procedure"
Foundations:
The foundations are defined according to the nature of the soil in place while respecting
the recommendations of the geotechnical study.
We will have two types of foundations to make according to the geotechnical investigation
carried out:
- Shallow foundations
- Deep foundations for I420 & U420 digesters only
These two types of foundations are subject to two execution procedures: "shallow foundation
execution procedure" & "deep foundation execution procedure"
The installation of pipes and installations concerns the installation of all the drainage, sludge
and wastewater pipes before the construction of the final roads.
We distinguish the following types of pipes:
- GRP pipe
- PVC pipe
- Concrete pipe
- HDPE PIPE
Page 37 OF 56
This phase includes the earthworks in the trenches, the excavation shielding, as well as the
temporary plugging of existing networks.
This installations steps and methods are detailed after in an execution procedure “execution
procedure of pipes & undergrounds installations “
NEW CONSTRUCTIONS:
Any type of formwork to be used must be clean and well cleaned of dust before concreting and
maintained during each use. The formwork must be perfectly waterproof and not dripping.
In the case of using a sliding formwork, an installation procedure will be provided to the client
for approval.
For the formwork removal, it must be done carefully without impact. The various elements will
be stripped in an order to not resulting a dangerous stresses for the works.
In the case of a sliding formwork, the method of execution; installation of reinforcements,
formwork for the holes and sealing to be reserved in the walls will be well described in an
execution procedure to be approved by the customer called "sliding formwork execution
procedure".
Concrete
The concrete to be used will be a ready-mixed concrete delivered on site to a nearby certified
concrete plant within a radius of 15Km maximum.
Concrete formulations will comply with the requirements set according to the exposure classes
to which the concrete will be subjected.
Reinforcement:
The reinforcements will be shaped in such a way as to present exactly the lengths and shapes
provided for in the working drawings and delivered to the site for installation.
At the time of their installation, the reinforcements must be clean, free from loose rust, no
traces of earth, paint, grease or any harmful matter.
The correct installation of the reinforcement and the necessary amount of shims between the
reinforcement and the formwork as well as the final concrete layer will be carefully reviewed
before placing the concrete.
For concrete and reinforcement, the technique and methodology will be more detailed in a
procedure note "procedure for the execution of reinforced concrete"
Page 38 OF 56
REHABILITATION OF EXISTING STRUCTURES:
Indeed, this work must disturb the operation of the existing lines as little as possible while
guaranteeing the same quality and quantity of treatment of the existing Meliane I and Meliane
II stations.
For the aeration basins a successive rehabilitation of the basins of the industrial line and that
of the urban line will be carried out, with consecutive hydraulic isolation of one basin after
another, will allow the maintain the operation of the station
The phasing principle is to switch all the incoming flow of wastewater to the urban line aeration
basin, make the necessary stoppings and drain the basin and after the rehabilitation
intervention.
Switching the treatment of wastewater to the future urban line, the rehabilitation of other
existing works of the industrial line no longer pose a problem.
The rehabilitation interventions will be detailed in a procedure "rehabilitation works
execution procedure"
The following table summarizes the estimated times for carrying out civil works, the start date
and the end date.
Page 39 OF 56
Work program for the realization of the Estimated
CW start date CW end date
industrial line duration
Secondary settling tanks I260
Secondary industrial settling tank I260.2 299 DAYS MARCH 30, 2022 APRIL 07, 2023
Secondary industrial settling tank I260.3
Secondary industrial settling tank I260.4
Auxiliary structures 216-600 & Discharge
channel
Industrial & Urban Entrance Flow meter
216 215 DAYS APRIL 11, 2022 JANUARRY 04, 2023
Odor treatment unit for common
pretreatment 600
Common discharge water channel
Operating buildings 711-713
New common operating building 711
312 DAYS APRIL 12, 2022 MAY 08, 2023
Common workshop 713
Page 40 OF 56
Work program for the realization of the Estimated
CW start date CW end date
industrial line duration
I420 industrial digesters
Industrial digester I420.1 251 DAYS MAY 17, 2022 MARCH 24, 2023
Industrial Digester I420.2
Industrial sludge treatment and cogeneration
works I464-I460-I540-I452
Industrial dewatering and thickening
building I460
210 DAYS JUNE 03, 2022 FEBRUARY 20, 2023
Mechanical sludge thickening and industrial
thickened secondary sludge pump I464
Industrial cogeneration I540
Industrial supernatants pump station I452
Rehabilitation of industrial structures
I240-I255
Industrial aeration basin I240 240 DAYS JUNE 22, 2022 APRIL 15, 2023
Industrial Biological Treatment Suppressor
Building I255
Rehabilitation of industrial structures I431-
I432-445-I447
Industrial Primary Sludge Gravity Thickener
I431
SEPTEMBER 05,
Industrial digested sludge storage I432 185 DAYS APRIL 19, 2023
2022
Common digested sludge pumping station
445
Industrial Thickened Primary Sludge
Pumping Station I447
Industrial hydraulic networks FEBRUARY 16,
106 DAYS JUNE 30, 2023
2023
Industrial roads laying out
100 DAYS MARCH 27, 2023 AUGUST 03, 2023
Page 41 OF 56
MECHANICAL WORK PROGRAM FOR THE INDUSTRIAL LINE:
Work program for the realization of the Estimated
MW start date MW end date
industrial line duration
Pretreatment structures 205-210-219-I221-I222-
I225
Raw sewage connection for common tanker
trucks 205
Urban & industrial reception and distribution
FEBRUARY 23,
structure 210 27 DAYS MARCH 29, 2023
2023
Industrial & urban bastard pit 219
Industrial primary settling tank I230.1 30 DAYS MARCH 31, 2023 MAY 10, 2023
Industrial primary settling tank I230.2
Secondary settling tanks I260
Secondary industrial settling tank I260.1
Secondary industrial settling tank I260.2 35 DAYS MARCH 27, 2023 MAY 11, 2023
Secondary industrial settling tank I260.3
Secondary industrial settling tank I260.4
Auxiliary structures 216-600 & Discharge
channel
Industrial & Urban Entrance Flow meter
216 67 DAYS JANUARY 04, 2023 MARCH 28, 2023
Odor treatment unit for common
pretreatment 600
Common discharge water channel
Operating buildings 711-713
New common operating building 711 18 DAYS MAY 08, 2023 MAY 30, 2023
Common workshop 713
Auxiliary Industrial structures I261-I231-I293-
I440-I442-I443-I444-I815
Industrial secondary distribution-clarifier
chamber I261
Distribution chamber-clarifier Industrial
primers I231
Industrial Outlet Flow meter Chamber I293
Industrial primary sludge pumping station 30 DAYS MARCH 25, 2023 MAY 04, 2023
I440
Return sludge and industrial excess sludge
pumping station I442
Return sludge and industrial excess sludge
pumping station I443
Industrial Floating Pump Station I444
Page 42 OF 56
Work program for the realization of the Estimated
MW start date MW end date
industrial line duration
Auxiliary Industrial structures 601-I425-I503-
I510-I550
Odor treatment unit for common mud line
601
Industrial Digester Equipment Building I425 FEBRUARY 27,
35 DAYS APRIL 12, 2023
2023
Industrial desulphurization I503
Page 43 OF 56
EICA WORK PROGRAM FOR THE INDUSTRIAL LINE:
Work program for the realization of the Estimated EICA Work start
EICA Work end date
industrial line duration date
Pretreatment structures 205-210-219-I221-I222-
I225
Raw sewage connection for common tanker
trucks 205
Urban & industrial reception and distribution
structure 210 60 days MARCH 29, 2023 JUNE 13, 2023
Industrial & urban bastard pit 219
Industrial primary settling tank I230.1 41 DAYS MAY 10, 2023 JUNE 30, 2023
Industrial primary settling tank I230.2
Secondary settling tanks I260
Secondary industrial settling tank I260.1
Secondary industrial settling tank I260.2 40 DAYS MAY 11, 2023 JUNE 30, 2023
Secondary industrial settling tank I260.3
Secondary industrial settling tank I260.4
Auxiliary structures 216-600 & Discharge
channel
Industrial & Urban Entrance Flow meter
216 30 DAYS MARCH 28, 2023 MAY 06,2023
Odor treatment unit for common
pretreatment 600
Common discharge water channel
Operating buildings 711-713
New common operating building 711 15 DAYS MAY 30, 2023 JUNE 16, 2023
Common workshop 713
Auxiliary Industrial structures I261-I231-I293-
I440-I442-I443-I444-I815
Industrial secondary distribution-clarifier
chamber I261
Distribution chamber-clarifier Industrial
primers I231
Industrial Outlet Flow meter Chamber I293
Industrial primary sludge pumping station 46 DAYS MAY 04, 2023 JUNE 30, 2023
I440
Return sludge and industrial excess sludge
pumping station I442
Return sludge and industrial excess sludge
pumping station I443
Industrial Floating Pump Station I444
Page 44 OF 56
Work program for the realization of the Estimated EICA Work start
EICA Work end date
industrial line duration date
Auxiliary Industrial structures 601-I425-I503-
I510-I550
Odor treatment unit for common mud line
601
Industrial Digester Equipment Building I425
50 DAYS APRIL 12, 2023 JUNE 16, 2023
Industrial desulphurization I503
Page 45 OF 56
CHAPITRE 6 : URBAN LINE CONSTRUCTION
WORKS
Work on the remaining works of the urban line begins after finishing those of the industrial line,
following the same strategy for the construction of new structures and the rehabilitation of
existing structures.
The construction steps for this line are the same as for the industrial line.
For rehabilitation works, once the industrial line is operational, the wastewater flow to be
treated will be divided between the SUD MELIANE I treatment plant and the new industrial line
during the rehabilitation intervention.
The precautions and network stoppings necessary for this phase will be planned in advance.
The following table summarizes the estimated times for carrying out civil works, the start date
and the end date.
Urban primary settling tank U230.1 332 DAYS JANUARY 06? 2023 FEBRUARY 22, 2024
Urban primary settling tank U230.2
Page 46 OF 56
Work program for the realization of the Estimated
CW start date CW end date
Urban line duration
Auxiliary urban structures U261-U231-U294-
U440-U442-U443-U444-U815
Urban secondary distribution-clarifier
chamber U261
Urban Distribution chamber-clarifier
primers U231
Urban Outlet Flow meter Chamber U294
Urban primary sludge pumping station 312 DAYS JANUARY 31, 2023 FEBRUARY 22, 2024
U440
Return sludge and Urban excess sludge
pumping station U442
Return sludge and Urban excess sludge
pumping station U443
Urban Floating Pump Station U444
Urban Electrical Room U815
Urban Secondary settling tanks U260
Secondary Urban settling tank U260.1
FEBRUARY 15,
Secondary Urban settling tank U260.2 325 DAYS MARCH 25, 2024
2023
Secondary Urban settling tank U260.3
Secondary Urban settling tank U260.4
Urban digesters U420
Urban digester U420.1 310 DAYS MARCH 04, 2023 MARCH 25, 2024
Urban Digester U420.2
Rehabilitation building 710
284 DAYS APRIL 19, 2023 APRIL 06, 2024
Exploitation building 710
Rehabilitation of Urban structures U431-U432
Urban Primary Sludge Gravity Thickener
220 DAYS MAY 23, 2023 FEBRUARY 19, 2024
U431
Urban digested sludge storage U432
Tertiary treatment plant U271-U293-U277-
U816-U214-U448-801
Common transformer & MV building 801
Tertiary filter U271
Outlet flow meter chamber U293
UV Disinfection U277 220 DAYS MAY 26, 2023 FEBRUARY 22, 2024
Electrical room U816
Service water intake and transfer pumping
U214
Dirty water pumping station for washing
filters U448
Rehabilitation of urban structures
I240-I255
Urban aeration basin I240 190 DAYS JULY 04, 2023 FEBRUARY 21, 2024
Urban Biological Treatment Suppressor
Building I255
Urban hydraulic networks 141 DAYS JANUARY 05, 2024 JULY 01, 2024
Urban roads laying out NOVEMBER 29,
200 DAYS MARCH 26, 2024
2024
Page 47 OF 56
MECHANICAL WORK PROGRAM FOR THE URBAN LINE:
Page 48 OF 56
Work program for the realization of the Estimated MW start date MW end date
urban line duration
Urban Secondary settling tanks U260
Page 49 OF 56
EICA WORK PROGRAM FOR THE INDUSTRIAL LINE:
Work program for the realization of the Estimated EICA Work start EICA Work end date
urban line duration date
Auxiliary Urban structures U425-U503-U510-
U550
Urban Digester Equipment Building U425
Urban desulphurization I503
52 days April 08, 2024 June 14, 2024
Treatment and storage of Urban biogas
I510
Urban flare I550
Urban primary settling tank U230.1 52 days April 16,2024 June 20, 2024
Urban primary sludge pumping station 52days April 12, 2024 June 15, 2024
U440
Return sludge and Urban excess sludge
pumping station U442
Return sludge and Urban excess sludge
pumping station U443
Urban Floating Pump Station U444
Page 50 OF 56
Work program for the realization of the Estimated EICA Work start EICA Work end date
urban line duration date
Urban Secondary settling tanks U260
Page 51 OF 56
CHAPITRE 7 : DEMOLITION OF EXISTING
STRUCTURES
The last phase of the project will be the demolition of the existing structures. In accordance with the
Specifications, the decommissioned structures of the existing SMI station will be demolished and the
sites redeveloped. This also concerns certain abandoned SMII structures.
Demolition concerns all structures located above ground level and up to 0.5 m below ground level,
followed by upgrading by backfill to fill at ground level.
This work concerns the following structures:
Page 52 OF 56
CHAPITRE 8 : QUALITY CONTROL
All stages of construction will be inspected according to the associated Quality Control Plans
(PCQ).
The inspection methodology will be well detailed in the Project Quality Plan (PQP).
RESPONSIBILITIES:
QA / QC manager:
He is responsible for:
Review all quality documentation and approve as necessary.
Plan, establish and maintain effective project quality management systems to guide
and provide feedback on project performance.
Compliance monitoring of all inspection and testing activities.
Assist and approve inspection points when specified in the QCP
Provide guidance and advice on all inspection and testing activities
Management and monitoring of non-conformities and corrective actions,
Plan, organize and attend the audit
Check compliance with quality requirements by the project organization
Knowledge of the activities of QC inspectors.
Follow-up of Client complaints.
Track and obtain “original” inspection and test documentation.
QA / QC inspectors
They will be in charge of:
Monitoring of control operations, according to the QCP
Application of quality control standards and requirements as defined with the Client
and also with the project specifications
Development of the "Final documentation Dossier "
Page 53 OF 56
QUALITY CONTROL PLAN (QCP)
A quality control plan covering the activities of material and equipment supply, prefabrication
and construction will be applied in order to ensure compliance with all contractual
requirements specified during the execution of the project.
Inspection and testing must be performed in accordance with the project documentation and project
requirements.
Preparation, collection and archiving of all quality records proving that the inspection has been
carried out. These records should clearly indicate necessary information of the item inspected.
QC records should include at least the following information:
Article under test
Type of control, inspection and test
Person performing the test
Instrument identification number (if applicable)
Possible illustrative drawings or sketches of the item being checked and the location
where the non-destructive testing was carried out
Reference document for requirements
Test result
All controls and tests are recorded at each level of their performance.
All inspections and tests must be recorded in the appropriate inspection reports.
A traceability register of inspection reports will be generated.
The final checks and tests validate all the checks and self-checks previously carried out.
Page 54 OF 56
CHAPITRE 9 : HEALTH SAFETY ENVIRONMENT
HSE requirements must be strictly observed and maintained by the HSE organization at the
construction site.
The project team should organize an HSE committee made up of the project manager, the
HSE advisor and the construction manager.
The HSE committee must:
Monitor and ensure the proper functioning of the HSE program.
Lead, coordinate and guide HSE activities.
Promulgate the dissemination of policies, objectives, rules and / or regulations.
Research, detect and identify risky conditions.
Carry out a thorough investigation of all accidents and review the recommendations to
avoid any recurrence of the accident.
RESPONSIBILITY:
Project Manager
He must:
Have primary responsibility for ensuring the security of the site.
Establish a realistic HSE policy and HSE objectives for the site.
Promote the implementation of the HSE plan, regulations and rules and an HSE
training plan, etc.
Organize and chair the HSE committee.
HSE manager :
He must:
Organize a weekly meeting of the HSE committee.
Coordinate HSE activities
Review and approve the HSE Construction program and procedures,
Advise and recommend the necessary corrective actions.
Director of construction:
He must:
Be responsible for all HSE activities including fire prevention during the construction
period.
Organize the HSE committee.
Submit a work program including HSE measures for the work to the field HSE advisor
before the start of the work.
Establish, implement and maintain the HSE program through the HSE supervisor and
workers.
Page 55 OF 56
Independent audits to ensure compliance with the established HSE program and
perform
Determine the effectiveness of individual elements of the program.
Any accident must be immediately reported orally to the supervisor in the cases described
below and will be followed by a written report.
ALL fatal injuries.
ALL injuries requiring first aid.
ALL fires.
ALL releases or spills of hazardous materials.
A written accident report should detail the circumstances and include the results of the
accident investigation and analysis. This report describes the accident classification, cause,
time, date, location, etc.
ENVIRONMENTAL CONTROL:
The construction team is responsible for the environmental control specified for the job site,
including all equipment and machinery used.
Do not throw used oil or liquid wastes directly into the ground, pit or storm drains. Dispose of
these materials only in properly labeled containers.
Page 56 OF 56